Loading...
GEOTECHICAL-OTO Crafts Ave-2022 June J1843-23-01 June 24, 2022 City of Northampton c/o Ms. Dorrie Brooks Jones Whitsett Architects 308 Main Street Greenfield, Massachusetts 01301 Re: Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Avenue Northampton, Massachusetts Dear Ms. Brooks: O’Reilly, Talbot & Okun Associates, Inc. (OTO) is pleased to provide this letter report summarizing our geotechnical engineering recommendations for the proposed building at Crafts Avenue in Northampton, Massachusetts. A Site Locus is provided as Figure 1. A Site Sketch is provided as Figure 2. Our geotechnical recommendations are based upon subsurface conditions observed in two soil borings. Our services consisted of the full-time observation of the borings, review of the logs and soil samples, engineering analyses, and preparation of this report. This report is subject to the attached limitations. PROJECT DESCRIPTION Existing Conditions The Site is located off Crafts Avenue in Northampton, Massachusetts. It is bounded to the north and west by commercial and municipal buildings, to the south by Roundhouse Plaza, and to the east by Crafts Avenue. The location of the Site is shown on Figure 1. The northern portion of the Site contains an existing parking area (upper lot) for Northampton municipal offices. A separate parking area (lower lot) for the Northampton Building Department is located in the southern portion of the Site. Topography in both the upper lot and lower lot is generally flat, near elevation 148 and 128 feet, respectively 1. Topographic relief between the two parking lots is provided by a pair of retaining walls, a shrub covered slope, and an integrated stairwell (portions of which also act to retain soil). A landscaped slope is also present along the eastern portion of the Site, between the upper lot and Crafts Ave. The existing parking lots, retaining walls, and nearby buildings are shown on Figure 2. 1 Elevations were determined using the “Massachusetts Elevation Finder”, which is based upon Lidar data. Accessed via: https://massgis.maps.arcgis.com/apps/webappviewer/index.html?id=3144242832214194945076cc18d78372 Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 2 Proposed Construction Preliminary project plans call for the construction of a five-story, approximately 3,200 square foot (footprint) building. The approximate location of the building is shown on Figure 2. The structure will be a multi-story structure. We anticipate that the building will have a constant bottom floor level even with the existing ground surface in the lower lot, near elevation 128 feet. Therefore, a cut of approximately 22 feet will be required to establish the bottom floor subgrade in the northern part of the building. The lower two levels will be steel framed and the upper three levels will be wood framed. The existing retaining walls will be demolished to prepare the Site for construction, and the proposed building will be built into the existing slope. Therefore, the lower-level walls in the northern half of the building will effectively be basement walls and will need to be designed to resist lateral earth pressures. We expect structural loads to be supported on both isolated column and continuous strip footings. Maximum unfactored structural loads, as currently estimated are on the order of 130 kips for column loads and approximately 13 kips per linear foot for bearing walls. The recommendations provided in this report should be reviewed and revised as necessary if finals load differ. SUBSURFACE EXPLORATIONS AND TESTING Subsurface investigations consisted of two soil borings performed within the footprint of the proposed building. Boring CA-1 was performed in the upper lot to a depth of 34 feet, and boring CA-2 was performed in the lower lot to a depth of 19 feet. Boring locations are shown on Figure 2. The borings were performed on May 19, 2019, by Seaboard Drilling of Chicopee, Massachusetts. Borings were performed using a Mobile B-53 truck mounted drill rig and drive and wash (CA-1) or hollow stem (CA-2) drilling techniques. Boring logs are attached. Soil samples were collected continuously from the ground surface to a depth of four feet below ground surface, at a depth of five feet, and every five feet thereafter. Soil samples were collected using a two-inch diameter split spoon sampler, driven 24 inches with a 140-pound automatic hammer falling 30 inches (American Society for Testing and Materials Test Method D1586 “Standard Test Method for Penetration Test and Split-Barrel Sampling of Soils”). The number of blows required to drive the sampler each six inches was recorded. The standard penetration resistance, or N-value, is the number of blows required to drive the sampler the middle 12 inches. Soil properties, such as strength and density, are related to the N-value. The field N-values are corrected to a standard 60% hammer efficiency, known as N60, to account for differing hammer efficiencies for each hammer type and drill rig. The N-values presented on the boring logs are field values, which are not adjusted for hammer efficiency. However, the adjusted N60 values were used in our engineering calculations and analysis. An O’Reilly, Talbot & Okun Associates, Inc. (OTO) engineer observed and logged the borings. Samples were classified according to a modified version of the Burmister Soil Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 3 Classification System. After drilling, bore holes were backfilled with soil cuttings and patched with asphalt. Field Strength Testing Field strength testing was performed on selected samples of the silt and clay using pocket torvane (E-285 Pocket Vane Shear Tester) and pocket penetrometer devices. These field measurements are intended to provide a rough measure of the strength of fine-grained soils. The pocket penetrometer provides a measure of the unconfined compressive strength of soil by failing the clay by “punching”. The torvane device provides an estimate of the undrained shear strength of fine-grained soils by failing the silt and/or clay in a rotational shearing mode. Theoretically, the unconfined compressive strength is twice the undrained shear strength. A total of five pocket penetrometer and torvane tests (each) were completed in the field. Pocket torvane and pocket penetrometer results are presented on the attached boring logs and discussed below. Photo-Ionization Detector (PID) Screening The headspace of each soil sample collected from the borings was screened using a MiniRAE Lite Photo-Ionization Detector (PID). PID screening provides an assessment of volatile organic content of the samples. PID readings are provided on the attached boring logs and discussed below. Grain Size Analysis One composite soil sample, collected from cuttings in the upper five feet of boring CA-1, was submitted for grain size analysis (sieve only) to Allied Testing Laboratories of Springfield, Massachusetts. This test was performed to evaluate the suitability of on-Site soils for use as engineered fill. Results are discussed below. SUBSURFACE CONDITIONS The subsurface profile described below was interpreted based upon conditions encountered in the soil borings. Subsurface conditions generally consisted of a surface layer of pavement with granular base underlain by non-engineered fill, native fine-grained soils, and bedrock. Soil Conditions Asphalt or Concrete Pavement: Each boring was performed in an existing paved parking area. Four inches of asphalt with approximately six inches of granular base course was present at boring location CA-1. The base consisted of medium to coarse sand with little gravel and trace amounts of silt. Five to six inches of concrete was present at boring location CA-2 with little to no granular base course. Non-Engineered Fill: Approximately 15.5 feet and 5.5 feet of non-engineered fill was encountered in borings CA-1 and CA-2, respectively. The fill generally consisted of loose to medium dense, fine to coarse sand with varying amounts of gravel and debris (brick, Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 4 concrete, wood, coal, ash). However, the bottom one to two feet of the fill contained significant amounts (greater than 25% by volume) of debris at both boring locations. This fill is not a suitable bearing layer. The fill extended to an approximate elevation of 132.5 feet in boring CA-1 and 122.5 feet in boring CA-2. Therefore, the base of the fill appears to be above the bottom level subgrade in the northern part of the building and about five feet below subgrade level in the southern portion. Varved Silt and Clay: The fill layer was directly underlain by varved silt and clay. Geologically, the Site is located near the western shore of former Lake Hitchcock, which was a large post-glacial lake that formerly covered much of the Connecticut River Valley. Sediments consisting of thin, interbedded lenses of silt and clay (collectively known as varved clay) were deposited at the bottom of the lake. Glacial Till: Glacial till appears to directly underlie the varved silt and clay level. Boring CA-1 encountered refusal on what may be glacial till at a depth of approximately 34 feet below ground surface (elevation 114 feet.) Boring CA-2 encountered glacial till at a depth 18 feet (elevation 110 feet). Glacial till is a very dense, heterogeneous mixture of silt, clay, sand, and gravel that is generally present immediately above bedrock throughout New England. Given its density, glacial till should be relatively incompressible under the anticipated foundation loads and would be a good bearing surface to support the anticipated building. However, since the top of the glacial till unit is about 15 feet below the bottom level it is unlikely that it could be used as a bearing surface for a shallow foundation system. Bedrock: Auger refusal was encountered in both borings on what might be bedrock. Refusal was encountered in boring CA-1 at a depth of 34.1 feet below ground surface (elevation 113.9 feet) and in boring CA-2 at 19.2 feet elevation (elevation 108.8 feet). Groundwater Conditions Groundwater was encountered boring CA-2 at a depth of eight feet below ground surface, corresponding to an approximate elevation of 120 feet, or about eight feet below the anticipated bottom slab level. The depth to groundwater could not be determined in boring CA-1 due to the method of drilling employed. Results of Unconfined Compressive and Shear Strength Testing The unconfined compressive strength of the clay stratum was estimated in the field using a pocket penetrometer and the undrained shear strength was estimated using an E-285 Pocket Vane Shear Tester. These field measurements are intended to provide a rough measure of the engineering properties of the fine-grained soils. Vane Shear measurements of shear strength ranged from approximately 1,500 to 4,500 pounds per square foot (psf) in the soft varved silt and clay portion. Pocket penetrometer measurements of unconfined compression strength ranged from approximately 500 to 2,500 psf. Pocket vane shear and penetrometer test results are presented on the attached boring logs. Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 5 Environmental Field Screening The headspace of each soil sample was screened using a photoionization detector (PID). PID screening provides an assessment of volatile organic compounds (VOCs) of the samples. PID readings taken from samples of native Site soils and the fill at boring location CA-2 were generally below the instrument detection limits. However, PID readings taken from samples of the non-engineered fill at boring location CA-1 ranged from 1.3 to 23 parts per million (ppm). The 23 ppm reading is above typical background levels and indicative of the presence of VOCs. This fill material may have originated at a former coal gasification plant that was located near the Site. Therefore, the fill may be regulated under the Massachusetts Contingency Plan (MCP). The owner should carry a contingency for further testing, removal, and disposal costs associated with managing regulated soils. PID readings are presented on the boring logs. Grain Size Distribution The sample collected from the upper five feet of boring CA-1 was classified as a fine gravel and fine to coarse sand with trace amounts of coarse gravel and silt. This appears to be suitable for use as Sand and Gravel and Granular Fill. SIGNIFICANT GEOTECHNICAL ISSUES The significant geotechnical issues for the proposed construction addressed in this report include the following: the presence of non-engineered fill within the footprint of the proposed building; foundation bearing capacity and settlement; seismic design considerations; pavement design; and the suitability of on-Site materials for use as engineered fill. PRELIMINARY DESIGN RECOMMENDATIONS The following recommendations are provided for the construction assumed in this report and refer to the 9th Edition of the Massachusetts State Building Code (MSBC). We note that the 9th Edition of the MSBC includes amendments to the 2015 International Building Code (IBC). Non-Engineered Fill and Demolition of Existing Structures Non-engineered fill was encountered in the upper 5 to 16 feet with significant amounts of debris (greater than 25% by volume) in the bottom portion of the fill layer. A description of the fill soils is provided above. The non-engineered fill soils were likely placed to achieve final grades during construction of the existing upper and lower parking lots. This fill is an unsuitable bearing material for the proposed building due to the variability of the composition and density of this material. We recommend that the contractor remove the non-engineered fill from beneath the footprint of the new building. We note that the fill appears to extend below proposed footing and slab subgrade levels in the southern portion of the building. It may be possible to reuse some of the excavated material, provided over-sized and deleterious materials Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 6 (debris) are removed. Additional information regarding the reuse of on-Site granular material is presented below. We understand that the existing staircase may be demolished to prepare the Site for the new construction. Any foundation walls or slabs, or utilities that are located within the footprint of the proposed building should be removed in their entirety. These excavations may extend below the planned slab and footing levels. Any excavations resulting from the removal of existing foundations and/or slabs, should be backfilled with compacted engineered fill, consistent with the recommendations provided below and in the Earthwork Considerations section. Abandoned buried utilities containing asbestos (such as electrical conduit insulation or transite pipe) are commonly found during construction excavations. Furthermore, former structures (pipes, conduits, foundations walls) may contain or be covered with materials containing asbestos. Such materials should be handled in accordance with MassDEP’s asbestos regulations (310 CMR 7.15). We recommend that suspect materials be managed appropriately and tested by a Department of Labor Standards (DLS) certified asbestos inspector prior to disturbances. Excavations resulting from the removal of non-engineered fill, foundations, slabs, and/or other structures should be backfilled with compacted engineered fill. Recommendations for backfill gradation and compaction requirements are provided below. Foundation Recommendations The proposed building can be founded on either a thick concrete mat or normal spread footing foundation. The structural mat would cover the entire lower level, while spread footings would be located under footings and load bearing walls. Both alternatives would likely bear on 12-inches of compacted Crushed Stone over the native soils. A maximum allowable bearing pressure of 2,000 pounds per square foot may be used for the design of both foundation systems. Both systems have relative advantages and disadvantages. The normal spread footing foundation system would involve less concrete and reinforcing steel. The concrete mat would be more rigid which would limit the potential for differential settlement. In addition, the installation of waterproofing would be easier for a mat foundation system. The varved silt and clay layer is soft and could compress under the anticipated building loads, potentially causing the building to undergo unacceptable settlement. The actual building loads are not unknown at this time, and we cannot provide a detailed estimate of potential settlement. However, up to three inches of total differential settlement is possible for a five-story building. We recommend that a rigorous settlement evaluation be conducted during final design. We note that the soft soils present below subgrade level could be improved using aggregate piers. The piers would likely extend to the base of the soft varved silt and clay layer (at an elevation of about 110 feet). Exterior footings (or the exterior edge of a mat foundation) should be embedded a minimum of 48 inches below the lowest adjacent grade for frost protection. Interior footings Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 7 should bear at least two feet below the surrounding floor slab. Strip footings, beneath the load bearing walls, should be at least 18 inches wide. Isolated column footings should be at least 24 inches wide. All other applicable requirements of the Massachusetts State Building Code (MSBC) should be followed. The structural mat or spread footings should not be placed on frozen soils and should be free of loose or disturbed materials. Any boulders or cobbles larger than four inches in diameter should be removed from within one foot of the bottom of the footings and replaced with Crushed Stone or Sand and Gravel fill. The foundation subgrades should be densified immediately prior to placement of footing concrete with at least three passes with a vibrating plate compactor. If pumping of the subgrade occurs, vibratory compaction should be stopped, and OTO contacted to provide additional recommendations. If loose materials are present in the excavations, they shall be recompacted to form a firm, dense bearing surface. Concrete Slabs We recommend that concrete floor slabs bear on at least 12 inches of compacted Crushed Stone to provide uniform support and a capillary moisture break. The subgrade should also be free of large boulders or cobbles, if encountered. The engineered fill beneath the concrete slabs should meet the grain size distribution characteristics outlined in Table 1. The subgrade within the footprint of the proposed building should be stripped of topsoil, asphalt, and any non-engineered fill. Prior to the placement of any engineered fill, we recommend that the building footprint be thoroughly densified to treat any loose areas present. If non-engineered fill, soft, or disturbed areas are present, these materials should be removed and recompacted or replaced with compacted, Sand and Gravel or Crushed Stone. Fill supporting slabs should be placed in accordance with the recommendations presented on Sheet 1. Groundwater and Surface Water Control The near surface varved silt and clay present at the Site inhibits the vertical infiltration of stormwater and may result in layers of perched groundwater during periods of wet weather. Therefore, we recommend that the building include perimeter drainage to control groundwater and surface water infiltration. The perimeter drainage system can consist of perforated PVC pipe, installed in a Crushed Stone trench, and wrapped in a non-woven geotextile fabric. Furthermore, we recommend that a Crushed Stone drainage layer be included beneath the first-floor slab. The Crushed Stone drainage layer and perimeter drain should be hydraulically connected to allow the water to flow away from the foundation via gravity. A typical detail of the underdrain system is shown on Sheet 2. Clean-outs should be provided in the sub-slab and/or perimeter drainage system, to allow for future maintenance. Since the bottom levels will be occupied, we recommend that water proofing be provided below the slab, water-stops be included, and at a minimum, the basement walls be damp- proofed. We recommend that complete (membrane) waterproofing be strongly considered Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 8 by the architect. As we discussed above, the use of a mat foundation system simplifies the installation of the waterproofing system. It should be noted that temporary groundwater control may be required during construction to provide for the installation of the mat/footings, drainage layers and utilities. It should be possible to dewater excavations by trenching or using sump pumps. Furthermore, the contractor should establish and maintain proper drainage of soils during construction. The native Site soils are susceptible to moisture, due to the high percentage of fines within the soil mass. If these soils become wet during construction, they will become soft and easily disturbed. Seismic Considerations Earthquake loadings must be considered under requirements in Section 1613 and 1806 of the 9th Edition (October 2017) of the Massachusetts State Building Code (MSBC). The 9th Edition of the MSBC is based upon the International Building Code 2015 (IBC) with Massachusetts amendments. Note that the IBC refers to ASCE-7 (2010), Minimum Design Loads for Buildings and Other Structures. Site Class and Earthquake Design Factors Section 1613 of the IBC covers lateral forces imposed on structures from earthquake shaking and requires that every structure be designed and constructed to resist the effects of earthquake motions in accordance with ASCE-7. Lateral forces are dependent on the type and properties of soils present beneath the Site, along with the geographic location. Per Table 1604.11, the maximum considered earthquake spectral response acceleration at short periods (Ss) and at 1-sec (S1) was determined to be 0.171 and 0.066, respectively, for Northampton, Massachusetts. Soil properties are represented through Site Classification. Procedures for the Site- specific determination of Site Classification are provided in Chapter 20 of ASCE-7. At this Site, we evaluated Site Classification using one of the parameters allowed, Standard Penetration Resistance (N-value). The Site Class was determined to be Class D based upon soil data collected. Furthermore, the Site coefficients Fa and Fv were determined according to Tables 1613.3.3(1) and 1613.3.3(2) of the IBC (2015), using both the Ss and S1 values and the Site Class. For this Site, Fa and Fv were determined to be 1.6 and 2.4, respectively. Retaining and basement walls should be designed to resist dynamic lateral earth forces in accordance with Section 1610.2 of the MSBC. The seismic earth forces as defined in Section 1610.2 should be applied as an inverted triangle over the height of the wall and added to the static lateral pressures. For purposes of the calculation, a total unit weight of 125 pounds per cubic foot should be used for the backfill against the retaining wall. Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 9 Liquefaction Section 1806.4 relates to the liquefaction potential of the underlying soils. The liquefaction potential was evaluated for saturated Site soils, using Figure 1806.4c of the MSBC. However, based upon the observed density and composition of the native Site soils, it is unlikely that liquefaction-induced settlement would occur under the design earthquake. In addition, loose granular layers below the maximum depth explored are not anticipated. Lateral Earth Pressures Static lateral earth pressures will be imposed on basement and retaining walls. These walls should be designed for unbalanced loading conditions. We anticipate that the walls will be structurally braced, and not free to deflect, and recommend that an equivalent fluid pressure of 55 pounds per cubic foot (pcf) be used. In addition, basement walls should not be backfilled until the first-floor slab is installed. If basement walls are unbraced, they need to be designed to resist overturning, sliding, and bearing capacity failure. For unbraced walls, we recommend an equivalent fluid pressure of 35 pcf. A coefficient of friction of 0.34 is recommended to evaluate frictional resistance to sliding along the base of the wall and footings. These values apply to unsaturated soil conditions. The soil against the outside of basement and retaining walls should not be over- compacted, since this would greatly increase lateral loads against the walls. The recommended degree of compaction for engineered fill and compaction means and methods are presented on Sheet 1. We note that these are general guidelines and if it is determined that a location falls into two or more categories, as presented in Table 1-1, the design team should be notified to determine appropriate compaction efforts and/or methods. Exterior Slabs Exterior concrete slabs, such as those at entryways and sidewalks adjacent to the building should be designed to mitigate differential frost movement between adjacent slabs, doorways, and pavements. To address this concern, we recommend that concrete slabs at entryways be underlain by four feet of non-frost susceptible Sand and Gravel fill. Where exterior slabs butt against hard surfaces, we recommend that for the area beyond the edges of the slab, the bottom of Sand and Gravel fill should transition gradually upward at a slope of 3H:1V or flatter (zone of influence). A typical detail showing an entryway fill area is shown on Sheet 2. Earthwork Considerations We anticipate that earthwork for this project will include the following: removal and replacement of non-engineered fill; excavations for footings; placement of compacted engineered fill beneath the building, floor slab, and pavements (as needed); and the treatment of the existing soils to address any localized loose areas that may be present. Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 10 Engineered Fill Recommendations Three types of engineered fill types are recommended: • Sand and Gravel for use immediately below sidewalks and as backfill following demolition of structures and removal of non-engineered fill • Crushed Stone for use immediately below footings and floor slabs, and in drainage systems • Granular Fill for use as miscellaneous fill Grain size distribution requirements are presented in Table 1. On-Site soils may be suitable for reuse as engineered fill (Sand and Gravel and Granular Fill), if free from deleterious and/or oversized material. If the contractor elects to use the on-Site material as fill, we recommend that a representative sample be collected, and a grain size distribution analysis is performed to obtain approval by the engineer. Please note that the Sand and Gravel specification is approximately that for Mass Highway M1.03.0, Type B Gravel Borrow. Table 1 Grain Size Distribution Requirements Size Sand and Gravel Granular Fill Crushed Stone Percent Finer by Weight 3 inch 100 100 --- 1 inch --- --- 100 ¾ inch --- --- 90-100 ½ inch 50-85 --- 10-50 ⅜ inch --- --- 0-20 No. 4 40-75 --- 0-5 No. 10 --- 30-90 --- No. 40 10-35 10-70 --- No. 200 0-10 0-15 --- Compaction Recommendations Fill, debris, topsoil, and organic soils should be removed from beneath the building footprint and should not be reused as fill beneath structures. As was discussed above, debris fill may be present below proposed footing elevations in the southern portion of the proposed building. To avoid point loads any cobbles or boulders larger than four inches in diameter, encountered at the subgrade should also be removed. The resulting excavations should be backfilled with compacted Sand and Gravel or Crushed Stone fill. Prior to the placement of any engineered fill, we recommend that the entire building footprint be thoroughly proof compacted. Proof compaction should be accomplished by a minimum of six passes with a 6,000-pound vibratory roller. To facilitate compaction, the Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 11 moisture content of the on-Site material should be maintained at or near the optimum moisture content as determined by ASTM D1557. Compacted fill should be placed in lifts ranging in thickness between 6 and 12 inches depending on the size and type of equipment. Recommended degrees of compaction and compaction means and methods are presented on Sheet 1. Compaction within five feet of foundation or retaining walls should be performed using a hand-operated roller or vibratory plate compactor. Placement and compaction of engineered fill should proceed on both sides of foundation (frost) walls so that the difference in top of fill on either side does not exceed two feet. Retaining walls should be designed for unbalanced loading conditions and the engineered fill within ten feet of the wall should be compacted using hand-operated plate or drum rollers weighing 250 pounds or less. Sloping and Earth Support In areas of excavations, soil may become unstable when excavations extend deeper than four feet. Any groundwater or surface water runoff encountered during the excavations will need to be controlled be controlled via trenching and sumps to keep the excavation stable and dry. Sloping may be necessary to protect personnel, adjacent buildings, and to provide stability. The soils encountered in the upper 10 feet are estimated to be Type C soils for slope stability purposes. The maximum allowable slope for excavations of Class C soils is 1.5H:1V (34°). We recommend that a geotechnical engineer be on-Site to observe actual soil conditions during the construction, if appropriate. We note that protective systems for any excavation exceeding 20 feet in depth must be designed by a registered professional engineer. All excavations should conform to current OSHA requirements. Based upon the preliminary building location it does not appear that it will be necessary to protect any of the adjacent buildings. However, a temporary earth support system may be required along Crafts Avenue. in the northeastern portion of the Site. The design and engineering of the temporary earth support systems should be the responsibility of the contractor. Prior to construction, we recommend that the contractor evaluate the need for a temporary earth support system to protect the existing building, foundation, and personnel during construction. FINAL DESIGN AND CONSTRUCTION PHASE SERVICES It is recommended that O’Reilly, Talbot & Okun Associates, Inc. (OTO) be retained during final design to further evaluate: • Building settlement • Foundation type (mat vs. spread footing foundation) • The need for under slab drainage and/or waterproofing • Temporary earth system requirements Preliminary Geotechnical Engineering Recommendations 208 Main Street at Crafts Ave Northampton, Massachusetts June 24, 2022 12 O:\J1800\1843 Jones Whitsett Architects Inc\23-01 208 Main Street at Crafts Avenue, Northampton - Geotech\Report\OTO Crafts Ave Geotech Report 2022 June.docx During final design, we should also be retained to prepare and/or review appropriate specification sections and drawings, if necessary. During construction phases, we recommend that OTO be retained to provide engineering support and to document subgrade conditions and preparation. We appreciated the opportunity to be of service on this project. If you have any questions, please do not hesitate to contact the undersigned. Sincerely yours, O'Reilly, Talbot & Okun Associates, Inc. Dustin A. Humphrey, P.E. Michael J. Talbot, P.E. Project Manager Principal Attachments: Limitations, Site Locus, Site Sketch, Sheets, Boring Logs, Laboratory Data LIMITATIONS 1. The observations presented in this report were made under the conditions described herein. The conclusions presented in this report were based solely upon the services described in the report and not on scientific tasks or procedures beyond the scope of the project or the time and budgetary constraints imposed by the client. The work described in this report was carried out in accordance with the Statement of Terms and Conditions attached to our proposal. 2. The analysis and recommendations submitted in this report are based in part upon the data obtained from widely spaced subsurface explorations. The nature and extent of variations between these explorations may not become evident until construction. If variations then appear evident, it may be necessary to reevaluate the recommendations of this report. 3. The generalized soil profile described in the text is intended to convey trends in subsurface conditions. The boundaries between strata are approximate and idealized and have been developed by interpretations of widely spaced explorations and samples; actual soil transitions are probably more erratic. For specific information, refer to the boring logs. 4. In the event that any changes in the nature, design or location of the proposed structures are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed and conclusions of this report modified or verified in writing by O'Reilly, Talbot & Okun Associates Inc. It is recommended that we be retained to provide a general review of final plans and specifications. 5. Our report was prepared for the exclusive benefit of our client. Reliance upon the report and its conclusions is not made to third parties or future property owners. PROJECT No. FIGURE No. 293 Bridge Street, Suite 500 Springfield, MA 01103 413.788.6222 O'Reilly, Talbot & Okun E N G I N E E R I N G A S S O C I A T E S www.OTO-ENV.com 208 MAIN STREET AT CRAFTS AVE NORTHAMPTON, MASSACHUSETTS SITE LOCUSO:\J1800\1843 Jones Whitsett Architects Inc\23-01 208 Main Street at Crafts Avenue, Northampton - Geotech\Boring Logs, Figures, Calculations\WorkingJ1843-23-01 1 Topographic Map Quadrant: EASTHAMPTON, MA Map Version: 1964 Current As Of: 1979 Date: MAY 2022 1:25,000 SCALE NATIONAL GEODETIC VERTICAL DATUM 1929 10 FOOT CONTOUR INTERVAL 0 1000 FEET 0 0.5 1.0 MILES 0 0.5 1 KILOMETERS SITE PROJECT NO. FIGURE NO.293 Bridge Street, Suite 500 Springfield, MA 01103 413.788.6222O'Reilly, Talbot & OkunE N G I N E E R I N G A S S O C I A T E Swww.OTO-ENV.com208 MAIN AT CRAFTS AVENORTHAMPTON, MASSACHUSETTSSITE SKETCHO:\J1800\1843 Jones Whitsett Architects Inc\23-01 208 Main Street at Crafts Avenue, Northampton - Geotech\Boring Logs, Figures, CalculationsJ1843-23-01 2 DESIGNED BY: DAH DRAWN BY: JE CHECKED BY: DAH DATE: 06/10/2022 REV. DATE: LEGEND: APPROXIMATE SOIL BORING LOCATION PERFORMED BY SEABOARD DRILLING ON 5/19/2022, OBSERVED BY OTO NOTES: 1. BASE MAP GENERATED BY REFERRING TO MASS MAPPER (MASS GIS), ACCESSED ON JUNE 10, 2022 2. SAMPLE LOCATIONS ARE SHOWN ACCORDING TO TAPED MEASUREMENTS TAKEN FROM EXISTING SITE FEATURES 3. ALL DATA IS TO BE CONSIDERED ACCURATE ONLY TO THE DEGREE IMPLIED BY THE METHODS USED IN THE DEVELOPMENT OF THIS PLAN CA-1 220 MAIN ST 210 MAIN ST 210 MAIN ST UPPER PARKING LOT MAIN STREET CRAFTS AVENUECA-2 LOWER PARKING LOT SCALE IN FEET 1" = 50' 0'25'50'100' EXISTING RETAINING WALL/STAIRCASE APPROXIMATE FOOTPRINT OF PROPOSED BUILDING PROJECT No. SHEET No. 293 Bridge Street, Suite 500 Springfield, MA 01103 413.788.6222 O'Reilly, Talbot & Okun E N G I N E E R I N G A S S O C I A T E S www.OTO-ENV.com Westfield Intermodal Transit Center Elm and Arnold Streets Westfield, Massachusetts N O’Reilly, Talbot & Okun [ A S S O C I A T E S ] ENGINEERING SITE C 2003 National Geographic Holdings, Inc. Topographic Map Quadrant: West Springfield, MA Map Version: 1977 Current as of: 1979 Table 1-1 Degree of Compaction Recommendations Location Minimum Compaction Below Structures (Foundations and Slabs) 95% Below Pavements/Sidewalks/Exterior Slabs 95% Against Basement Walls/Retaining Walls 92% Utility Trenches 95% General Landscaped Areas 90% Notes. 1. Percentage of the maximum dry density as determined by Modified Proctor ASTM D1557, Method C. 2. When location falls into two or more categories, the engineer should be notified to determine appropriate compaction efforts and/or methods. 3. Crushed stone should be compacted in lifts of 12 inches to form a dense matrix using either traditional compaction methods (vibratory plate and/or roller) or tamping with an excavator bucket in deep excavations. It is generally not necessary to perform laboratory or field density testing on crushed stone. Table 1-2 General Guidelines for Compaction Means and Methods Compaction Method Maximum Stone Size (Inches Diameter) Maximum Lift Thickness (Inches) Minimum Number of Passes Below Structures & Pavement Non- Critical Areas Below Structures & Pavement Non- Critical Areas Hand-operated Vibratory Plate and confined spaces 3 6 8 6 4 Hand-operated vibratory drum roller (less than 1000 pounds) 3 6 8 6 4 Hand-operated vibratory drum roller (at least 1,000 pounds) 6 8 10 6 4 Light vibratory drum roller (minimum 3000 pounds) 6 10 14 6 4 Heavy vibratory drum roller (minimum 6000 pounds) 6 12 18 6 4 Note: The contractor should reduce or stop drum vibration if pumping of the subgrade is observed. GENERAL COMPACTION GUIDELINESO:\J1800\1843 Jones Whitsett Architects Inc\23-01 208 Main Street at Crafts Avenue, Northampton - Geotech\Boring Logs, Figures, Calculations\WorkingDESIGNED BY: ALS DRAWN BY: DAH CHECKED BY: MJT DATE: 11/09/2016 REV. DATE: 5/24/2022 J1843-23-01 1 208 MAIN STREET AT CRAFTS AVE NORTHAMPTON, MASSACHUSETTS PROJECT No. SHEET No. 293 Bridge Street, Suite 500 Springfield, MA 01103 413.788.6222 O'Reilly, Talbot & Okun E N G I N E E R I N G A S S O C I A T E S www.OTO-ENV.com TYPICAL FOUNDATION SECTIONO:\J1800\1843 Jones Whitsett Architects Inc\23-01 208 Main Street at Crafts Avenue, Northampton - Geotech\Boring Logs, Figures, Calculations\WorkingDESIGNED BY: ALS DRAWN BY: DAH CHECKED BY: MJT DATE: 11/9/2016 REV. DATE: 5/24/2022 J1843-23-01 2 NOTES: 1. NOT FOR CONSTRUCTION, FOR ILLUSTRATION PURPOSES ONLY 2. FOR ADDITIONAL INFORMATION, REFER TO OTO's GEOTECHNICAL REPORT DATED JUNE 2022 3. UNPAVED AREAS SHALL INCLUDE LOAM CAP AND SHOULD BE GRADED TO DIRECT SURFACE FLOW AWAY FROM BUILDING 4. PERMEABLE BACKFILL SHALL BE USED IN AREAS WITH UNDERDRAIN SYSTEMS BASE/SUBBASE TYPICAL FOUNDATION SECTION SLAB ON GRADE FOOTING WITH ENTRANCE SLAB 1 3 FLOOR SLAB PREPARED SUBGRADE SAND AND GRAVEL FILLGRANULAR FILL SAND AND GRAVEL SEE NOTES 3 AND 4 PERIMETER DRAINAGE SYSTEM TO BE DESIGNED BY OTHERS CRUSHED STONE UPON NON-WOVEN GEOTEXTILE FABRIC (AS NEEDED)CRUSHED STONE TRENCH PERFORATED PIPE 4' (MIN) NON-WOVEN GEOTEXTILE FABRIC PAVEMENT SECTIONENTRANCE SLAB SLOPING PER OSHA STANDARDS 208 MAIN STREET AT CRAFTS AVE NORTHAMPTON, MASSACHUSETTS FIRST FLOOR SLAB TYPICAL FOUNDATION SECTION BASEMENT FOUNDATION WITH GROUND LEVEL ENTRANCE SLAB SAND AND GRAVEL FILL FLOOR SLAB PREPARED SUBGRADE BASEMENT LEVEL ENTRANCE SLAB SLOPING PER OSHA STANDARDS BASE/SUBBASE SEE NOTES 3 AND 44' (MIN) 1 3 PAVEMENT SECTION WATERPROOFING BARRIER WATERPROOFING/ VAPOR BARRIER CRUSHED STONE UPON NON-WOVEN GEOTEXTILE FABRIC (AS NEEDED)CRUSHED STONE TRENCH PERFORATED PIPE NON-WOVEN GEOTEXTILE FABRIC BLOWS/FOOT (SPT N-Value) 0-4 Very soft 4-10 Soft 10-30 Medium Stiff 30-50 Stiff >50 Very stiff Hard MATERIAL FRACTION SMALLEST Coarse DIAMETER Fine None SILT Coarse 1/4" (pencil)Clayey SILT Medium 1/8"SILT & CLAY Fine 1/16"CLAY & SILT SILT/CLAY see adjacent table 1/32"Silty CLAY COBBLES 1/64"CLAY BOULDERS TERM % OF TOTAL and 35-50% some 20-35% little 10-20% trace 1-10% PID: Soil screened for volatile organic compounds (VOCs) using a photoionization detector (PID) referenced to benzene in air. Readings in parts per million by volume. Torvane: Undrained shear strength is estimated using an E285 Pocket Torvane (TV). Values in tons/ft2. Penetrometer: Unconfined compressive strength is estimated using a Pocket Penetrometer (PP). Values in tons/ft2. SUMMARY OF THE BURMISTER SOIL CLASSIFICATION SYSTEM (MODIFIED) RELATIVE DENSITY (of non-plastic soils) OR CONSISTENCY (of plastic soils) STANDARD PENETRATION TEST (SPT) 1/4" to 3/4"GRAVEL 15-30 >30 MATERIAL: (major constituent identified in CAPITAL letters) COHESIONLESS SOILS COHESIVE SOILS 8-15 1/16" to 1/4" Method: Samples were collected in accordance with ASTM D1586, using a 2" diameter split spoon sampler driven 24 inches. If samples were collected using direct push methodology (Geoprobe), SPTs were not performed and relative density/consistency were not reported. N-Value: The number of blows with a 140 lb. hammer required to drive the sampler the middle 12 inches. WOR: Weight Of Rod (depth dependent) WOH: Weight Of Hammer (140 lbs.) *Based upon uncorrected field N-values RQD: Rock Quality Designation is determined by measuring total length of pieces of core 4" or greater and dividing by the total length of the run, expressed as %. 100-90% excellent; 90-75% good; 75-50% fair; 50-25% poor; 25-0% very poor. COMMON FIELD MEASUREMENTS Wetted sample is rolled in hands to smallest possible diameter before breaking. Very High Cannot distinguish individual particles SAND 3" to 6" in diameter > 6" in diameter Note: Boulders and cobbles are observed in test pits and/or auger cuttings. ORGANIC SILT: Typically gray to dark gray, often has strong H2S odor. May contain shells or shell fragments. Light weight. Fibrous PEAT: Light weight, spongy, mostly visible organic matter, water squeezed readily from sample. Typically near top of layer. Fine grained PEAT: Light weight, spongy, little visible organic matter, water squeezed from sample. Typically below fibrous peat. DEBRIS: Detailed contents described in parentheses (wood, glass, ash, crushed brick, metal, etc.) BEDROCK: Underlying rock beneath loose soil, can be weathered (easily crushed) or competent (difficult to crush). Fill: Material used to raise ground, can be engineered or non-engineered. Varved clay: Fine-grained, post-glacial lake sediments characterized by alternating layers (or varves) of silt, sand and clay. ADDITIONAL CONSTITUENTS BORING LOGS COMMON TERMS Glacial till: Very dense/hard, heterogeneous mixture of sand, silt, clay, sub-angular gravel. Deposited at base of glaciers, which covered all of New England. IDENTITY High Non-plastic Slight PLASTICITY Finest visible & distinguishable particles 3/4" to 3" Low Medium GRAIN SIZE RANGE 1/64" to 1/16" Dense Very dense COHESIVE SOILSCOHESIONLESS SOILS BLOWS/FOOT CONSISTENCY(SPT N-Value) <2 2-4 4-8 RELATIVE DENSITY Very loose Loose Medium dense Page 1 of 2 34.1 148.0 Jeff 8 Joe 0 Roller Bit with Wash N (2 3/8" O.D.) FIRST (ft)N/A 2" O.D. Split Spoon LAST (ft)--Automatic TIME (hr)--140 lb / 30" DEPTH (ft)ELEV. 10/24 S-1 PID = 0.2 ASPHALT 1 (0-2')BASE COURSE FILL 19/24 S-2 PID = 5.5 (2-4') 16/24 S-3 PID = 7.5 (5-7') 12/24 S-4 PID = 1.3 (10-12') 2 18/24 S-5 PID = 23.0 15.5 132.5 (15-17')SILT AND CLAY 24/24 S-6 PID = 0.0 (20-22')TV = 0.75 3 PP = 0.50 4 0/24 S-7 -- (25-27') 1. Soil screened in field using MiniRAE Lite photoionization detector (PID) referenced to benzene in air. Readings in parts per million (PPM) by volume. 2. Auger grinding on wood at 13 feet below ground surface. 3. Undrained shear strength estimated in field using E285 Pocket Torvane (TV). Values in tons/ft2. 4. Unconfined compressive strength estimated in field using Pocket Penetrometer (PP). Values in tons/ft2. 5. Auger grinding at 34 feet below ground surface. 25' 1/1/2/2 CA-1 Remarks:PROJECT NO. 1843-23-01 LOG OF BORING NO RECOVERY 2/1/2/2 Top 2.5": Very loose, gray, medium to coarse SAND, little gravel, trace silt, trace debris (coal, ash; piece of 2" gray brown clay and silt; FILL) Next 0.5": DEBRIS (100% light brown wood) Bottom 15": Soft, blue to dark gray, varved SILT and CLAY, trace fine sand, trace medium sand, trace debris (slag; 1" varves) 20' 1/1/2/2 Soft, gray brown to red brown, varved SILT and CLAY (1" varves) 10' 3/7/6/3 Top 8": Medium dense, brown gray, medium to coarse SAND, little gravel, little silt, trace fine sand (FILL) Bottom 4": Medium dense, light gray, fine to coarse SAND, trace gravel, trace silt, trace fine sand (FILL) 15' 6/5/5/6 5/5/4/4 Medium dense, light gray, medium to coarse SAND, some gravel, trace silt, trace fine sand, damp (FILL) 5' HAMMER TYPE TYPE Top 4": ASPHALT Loose, brown, fine GRAVEL and fine to coarse SAND, trace silt, dry (BASE) N/A HAMMER WGT/DROP SIZE N/A DEPTH (ft)/ SAMPLES SAMPLES SAMPLE DESCRIPTION (MODIFIED BURMISTER) REMARKS/ WELL CONSTRUCTION PENETR. RESIST. (bl / 6 in) REC. (in) TYPE/ NO. FIELD TEST DATA PROFILE BORING LOCATION Upper parking lot SAMPLER ROCK CORING INFORMATION ENGINEER/SCIENTIST Caren Irgang WATER LEVEL ROD TYPE HAMMER DROP 30" FINISH DATE 5/19/2022 UNDISTURBED SAMPLES BIT TYPE HAMMER WGT 300 lb LOG OF BORING PROJECT 208 Main Street at Crafts Ave CONTRACTOR Seaboard Environmental Drilling START DATE 5/19/2022 DISTURBED SAMPLES HELPER CASE DIAMETER 4" JOB NUMBER 1843-23-01 FINAL DEPTH (ft)DRILLING EQUIPMENT B-53 Truck Mounted Rig LOCATION Northampton, MA SURFACE ELEV (ft)FOREMAN CASING CA-1 5/8/9/9 Medium dense, light gray, medium to coarse SAND, trace silt, trace fine sand, trace fine gravel, damp (FILL) Page 2 of 2 DEPTH (ft)ELEV. 13/24 S-8 PID = 0.1 SILT AND CLAY (27-29')TV = 1.00 (Continued) PP = 0.50 13/24 S-9 PID = 0.1 (30-32')TV = 1.25 PP = 0.25 0/0.5 S-10 --34.1 113.9 5 (34') Loose, red brown, fine SAND and SILT, little medium sand, trace fine gravel, trace coarse sand 3/3/3/3 50 for 0.5"NO RECOVERY (Fractured rock fragments in spoon) LOG OF BORING REC. (in) TYPE/ NO. PROFILE CA-1 Job No.1843-23-01 SAMPLES REMARKS/ WELL CONSTRUCTION DEPTH (ft)/ SAMPLES SAMPLE DESCRIPTION (MODIFIED BURMISTER) PENETR. RESIST. (bl / 6 in) FIELD TEST DATA Medium stiff, red brown, varved SILT and CLAY (1" varves) Auger refusal at 34.1'35' 30' 60' 55' 50' 45' 40' 1/2/4/4 Page 1 of 2 19.2 128.0 Jeff 6 Joe 0 Hollow Stem Auger A (1 5/8" O.D.) FIRST (ft)8.0 2" O.D. Split Spoon LAST (ft)N/A Automatic TIME (hr)N/A 140 lb / 30" DEPTH (ft)ELEV. 14/24 S-1 PID = 0.0 CONCRETE 1 (0-2')FILL 13/24 S-2 PID = 0.0 (2-4') 2 4/24 S-3 PID = 0.0 5.5 122.5 (5-7')SILT AND CLAY 120.0≡ 20/24 S-4 PID = 0.0 (10-12')TV = 2.25 3 PP = 1.25 4 12/24 S-5 PID = 0.0 (15-17')TV = 1.25 PP = 1.25 18.0 110.0 GLACIAL TILL 5 1/2 S-6 -- (19-19.2')19.2 108.8 Auger refusal at 19.2' 1. Soil screened in field using MiniRAE Lite photoionization detector (PID) referenced to benzene in air. Readings in parts per million (PPM) by volume. 2. From cuttings: Dark gray sand, gravel, and debris from 4 to 5 feet (end of non-engineered fill at 5 feet). 3. Undrained shear strength estimated in field using E285 Pocket Torvane (TV). Values in tons/ft2. 4. Unconfined compressive strength estimated in field using Pocket Penetrometer (PP). Values in tons/ft2. 5. Auger grinding at 18 feet below ground surface. LOG OF BORING CA-2 PROJECT 208 Main Street at Crafts Ave CONTRACTOR Seaboard Environmental Drilling Very dense, red brown, fine SAND and SILT, trace fine gravel (fractured rock fragments in spoon; TILL) START DATE 5/19/2022 DISTURBED SAMPLES HELPER CASE DIAMETER N/A JOB NUMBER 1843-23-01 FINAL DEPTH (ft)DRILLING EQUIPMENT B-53 Truck Mounted Rig LOCATION Northampton, MA SURFACE ELEV (ft)FOREMAN CASING ENGINEER/SCIENTIST Caren Irgang WATER LEVEL ROD TYPE HAMMER DROP 30" FINISH DATE 5/19/2022 UNDISTURBED SAMPLES BIT TYPE HAMMER WGT 140 lb REMARKS/ WELL CONSTRUCTION PENETR. RESIST. (bl / 6 in) REC. (in) TYPE/ NO. FIELD TEST DATA PROFILE BORING LOCATION Center area of lower parking lot SAMPLER ROCK CORING INFORMATION HAMMER TYPE TYPE N/A HAMMER WGT/DROP SIZE N/A 4/5/3/3 Top 7": Loose, gray brown, DEBRIS (30% varved silt and clay pieces, 25% brick, 25% concrete, 20% coal, ash), damp Bottom 6": Loose, light to dark brown, fine to coarse SAND, some debris (brick, concrete), little fine gravel, damp 3/4/8/7 5.5": CONCRETE Medium dense, orange brown, fine to medium SAND, little gravel, little silt, little to some debris (coal, ash), damp (gray with little silt at 4"; 2" layer of brown fine to medium sand at 6"; brown at 8"; FILL) DEPTH (ft)/ SAMPLES SAMPLES SAMPLE DESCRIPTION (MODIFIED BURMISTER) 5' 2/2/3/3 Loose, gray brown, varved CLAY and SILT, damp 10' 3/3/4/4 Medium stiff, gray brown, varved SILT and CLAY, wet (1/2"-1/4" varves, 1/4" silt and 1/8" clay) 15' 2/2/2/3 Top 4": Medium stiff, gray brown, varved SILT and CLAY, wet Bottom 8": Loose, red brown, fine SAND and SILT, trace fine gravel, wet (1/2"-1/4" varves, 1/4" silt and 1/8" clay) 20' 50 for 2" 25' CA-2 Remarks:PROJECT NO. 1843-23-01 LOG OF BORING