604207 March 2009 363mh Cost Estimate100%_Final revisedMANHAN RAIL TRAIL NORTHAMPTON EASTHAMPTON, MA. MHD Project #604207 Project #363 Contract #2 3/3/2009 CONSTRUCTION COST ESTIMATE PS&E PHASE 100% Design UNIT TOTAL ITEM # ITEM QTY UNIT COST COST 101 CLEARING AND GRUBBING 2 HA $39,766.76 $79,533.52 120.1 UNCLASSIFIED EXCAVATION 4,000 CM $30.15 $120,600.00 129.5 TRACK EXCAVATION 100 M $87.33 $8,733.00 140. BRIDGE EXCAVATION 75 CM $44.35 $3,326.25 141 CLASS A TRENCH EXCAVATION 50 CM $30.45 $1,522.50 141. 1 TEST PIT FOR EXPLORATION 100 CM $73.59 $7,359.00 142 CLASS B TRENCH EXCAVATION 50 CM $40.88 $2,044.00 144 CLASS B ROCK EXCAVATION 11 CM $105.00 $1,155.00 150 ORDINARY BORROW 1,770 CM $29.34 $51,931.80 151 GRAVEL BORROW 5,000 0 CM $39.28 $196,400.00 170 FINE GRADING AND COMPACTING - SUBGRADE AREAS 18,030 SM $2.10 $37,863.00 180.1 HEALTH AND SAFETY PLAN 1 LS $4,056.35 $4,056.35 180.2 IMPLEMENTATION OF HEALTH AND SAFETY PLAN 100 HR $84.28 $8,428.00 180.3 PERSONNEL PROTECTION LEVEL "C" UPGRADE 75 HR $31.50 $2,362.50 180.4 MONITORING, HANDLING & STOCKPILING OF CONTAMINATED SOI 200 CM $51.12 $10,224.00 180.5 LICENSED SITE PROFESSIONAL (LSP) SERVICES 100 HOUR $131.25 $13,125.00 180.6 SOIL TESTING 20 EA $183.75 $3,675.00 181.1 DISPOSAL OPTIONS FOR CONTAMINATED SOILS 200 MG $70.39 $14,078.00 184.1 DISPOSAL OF TREATED WOOD PRODUCTS 100 MG $255.08 $25,508.00 242.06 600 MILLIMETER REINFORCED CONCRETE PIPE FLARED END 1 EA $1,125.00 $1,125.00 302.03 300 MM DUCTILE IRON WATER PIPE (RUBBER GASKET) 090M $293.39 $26,405.10 309 DUCTILE IRON FITTINGS FOR WATER PIPE 0 250 KG $11.30 $2,825.00 402 DENSE GRADED CRUSHED STONE FOR SUB-BASE 230 45 CM $76.08 $20,922.00 420 HOT MIX ASPHALT BASE COURSE 100 25 MG $114.64 $14,330.00 440 CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL 14,100 KG $0.83 $11,703.00 443 WATER FOR ROADWAY DUST CONTROL 295 KL $20.87 $6,156.65 460 HOT MIX ASPHALT 2,700 40 MG $104.09 $285,206.60 464.5 HOT POURED RUBBERIZED ASPHALT SEALER 40 M $3.57 $142.80 472 HOT MIX ASPHALT FOR MISCELLANEOUS WORK 100 MG $173.69 $17,369.00 482.3 SAWING ASPHALT PAVEMENT 60 M $8.87 $532.20 602 GUARDRAIL POST - STEEL 70 EA $66.60 $4,662.00 603.1 STEEL OFFSET BRACKET - W BEAM 70 EA $14.50 $1,015.00 604 W BEAM GUARD PANEL 12 EA $168.67 $2,024.04 620.1 STEEL W-BEAM HIGHWAY GUARD (SINGLE FACED) 90 M $92.36 $8,312.40 620.4 STEEL W BEAM HIGHWAY GUARD BURIED END (SINGLE FACED) 2 EA $1,087.48 $2,174.96 627.1 STEEL W BEAM TERMINAL SECTION (SINGLE FACED) 2 EA $53.55 $107.10 635.1 HIGHWAY GUARD REMOVED AND DISCARDED 62 M $10.19 $631.78 645.018 1.83 M CHAIN LINK FENCE (PIPE TOP RAIL) (LINE POST OPTION) 55 M $97.33 $5,353.15NON-PAMS Transportation Systems, Inc.1 MANHAN RAIL TRAIL NORTHAMPTON EASTHAMPTON, MA. MHD Project #604207 Project #363 Contract #2 3/3/2009 CONSTRUCTION COST ESTIMATE PS&E PHASE 100% Design UNIT TOTAL ITEM # ITEM QTY UNIT COST COSTNON-PA655.01 BICYCLE RAIL 2,590 M $52.50 $135,975.00 661 METAL PIPE GATE 2 EA $2,000.00 $4,000.00 665 CHAIN LINK FENCE REMOVED AND STACKED 130 M $22.58 $2,935.40 670.1 REMOVE AND RESET WOOD GATE & BOLLARDS 1 LS $2,625.00 $2,625.00 697 SEDIMENTATION FENCE 4,300 M $11.55 $49,665.00 707.8 STEEL BOLLARD 13 EA $1,010.35 $13,134.55 711 BOUND REMOVED AND RESET 5 EA $291.15 $1,455.75 740 ENGINEERS FIELD OFFICE AND EQUIPMENT-TYPE A 20 MO $2,443.77 $48,875.40 748 MOBILIZATION 1 LS $107,849.00 $107,849.00 751 LOAM BORROW 1,700 CM $49.69 $84,473.00 756 NPDES STORM WATER POLLUTION PREVENTION PLAN 1 LS $5,250.00 $5,250.00 765.11 TEMPORARY AND PERMANENT SEEDING 16,500 SM $1.84 $30,360.00 767.3 STRAW MULCH 8 MG $585.49 $4,683.92 767.8 BALES OF HAY FOR EROSION CONTROL 4,500 EA $10.50 $47,250.00 832.1 WARNING-REGULATORY AND ROUTE MARKER-ALUM. PANEL (TYP 9 SM $115.50 $1,039.50 847.1 SIGN SUP(N/GD)+RTE MKR W/1 BRKWY POST ASSEM-STL. 32 EA $105.00 $3,360.00 851 SAFETY CONTROLS FOR CONSTRUCTION OPERATIONS 20 UD $157.50 $3,150.00 852 SAFETY SIGNING FOR CONSTRUCTION OPERATIONS 13 SM $190.75 $2,479.75 861.10 100mm. REFLECTORIZED YELLOW LINE (PAINTED) 1,300 M $1.73 $2,249.00 865.1 CROSS WALKS AND STOP LINES REFL. WHITE (THERMOPLASTIC) 30 SM $21.00 $630.00 866.1 100mm. REFLECTORIZED WHITE LINE (THERMOPLASTIC) 80 M $1.60 $128.00 877.2 SIGN POST REMOVED & STACKED 5 EA $52.50 $262.50 952 STEEL SHEETING 89,000 KG $5.56 $494,840.00 983.1 RIPRAP 850 MG $63.00 $53,550.00 995.01 BRIDGE STRUCTURE, BRIDGE NO. E-05-028 (APT) 1 LS $321,819.75 $321,819.75 995.02 BRIDGE STRUCTURE, BRIDGE NO. E-05-027 (APN) 1 LS $44,759.57 $44,759.57 995.03 BRIDGE STRUCTURE, BRIDGE NO. N-19-001 (65T) 1 LS $1,269,683.10 $1,269,683.10 996.1 MECHANICALLY STABILIZED EARTH WALL 225 SM $442.79 $99,628.10 996.11 MSE WALL MANUFACTURER'S REPRESENTATIVE 40 DAY $630.00 $25,200.00 SUBTOTAL $3,864,233.99 CONTINGENCIES 0%$0.00 TOTAL ENGINEERS OFFICE CONSTRUCTION ESTIMATE $3,864,230.00 MS Transportation Systems, Inc.2