Permit ProcessReview
Applicant delivers DPW and Fire copies
24 days before board meeting: OPD warns applicant
20 days before board meeting: DPW Go/NO Go
17 days before board meeting: OPD Go/NO Go
16 days before: Advertisement
OPD/DPW Staff meeting
10 days before: DPW comments
7 days before: Staff report
Public Hearing
Decision vote
Decision write-up
20 Day Appeal Period
Applicant Records
Applicant addresses conditions
Building Permit issued
Review
Staff initial review
To DPW and Fire
24 days before board meeting:
OPD warns applicant
17 days before board meeting:
OPDGo/NO Go Decision
16 days before: Advertisement
OPD/DPW Staff meeting
7 days before: Staff report
DPW comments
Public Hearing
Decision vote
Decision write-up
20 Day Appeal Period
Applicant records
Applicant addresses conditions
Building Permit issued
Application
30 days before Board meeting
Forms on-line
Separate form for each permit
Complete on-line
Print & Submit Paper
OPD later scans
On web in 90 days
Applications
Combined application (IF possible)Nested loops to reduce # questions
All attachments PDF
Plans
Drainage
Traffic
Other infrastructure analysis
Acknowledge benefits of PRIOR review
On-Line OR EMail Submittals
CAN include Zoning Application
Fees on-line (Google checkout or PayPal)
Required Major Projects
Recommended Other Projects
Fewer paper copies when electronic
OPD Staff Pre-application review & DPW Staff Pre-application review
Optional
Recommended
Zoning Application
Building Commissioner
Ad-hoc Technical Review
OPD with staff & board representatives
Optional for major projects
Recommended!!!