2. 18-09Nth Quarterly Report 06_30_2020-WF 1Status Code: 1. On Schedule; 2. Suspended; 3. Delayed; 4. Cancelled; 5. Completed 2Cost Code: 1. Cost Unchanged; 2. Cost Overrun; 3. Cost Underrun UPDATED – FY2019 MEMA MITIGATION PROGRAM QUARTERLY REPORT    Contact Name:       Wayne Feiden                                     Contact Email:   wfeiden@northamptonma.gov             Project Name:     Hazard Mitigation Plan Update                      Applicant:        City of Northampton                        Period From:     April 1, 2020     To:   June 30, 2020      Project #      Summary of Overall Scope Status  Code1  Approved  Completion  Date  Actual  Completion  Date  Cost  Code2  PDMC 18‐09Nth Update the Hazard Mitigation Plan for the Town 1 6/30/2021  1   Tasks/Accomplishments From Work Schedule     If more room is needed please attach another sheet to this document  Task Start  Date  Task  Duration   (In Months)  Estimated  Task End  Date  Percent  Complete  Grant Award and Contracting 11/1/19 1.5 12/15/19 100%  Select and Hire a Vendor 12/15/19 2 2/15/20 100%  Convene Local Hazard Mitigation Planning Committee 2/15/20 1.5 4/1/20 100%  Update Hazard Profiles 4/1/20 3 7/1/20 100%  Update Critical Facility Inventory 4/1/20 3 7/1/20 100%  Update Hazard Vulnerability 5/1/20 4 9/1/20 100%  Update Mitigation Goals 9/1/20 3 12/1/20 100%  Update Actions 10/1/20 2 12/1/20 100%  Plan review, Evaluation, and Implementation 12/1/20 2 2/1/21 100%  Plan Maintenance 1/1/21 1 3/1/21 100%  Public Review of Draft 2/1/21 2 4/1/21  100%    Review and Approval 4/1/21 3 6/30/21 0%                                                   Total Percentage of Project Complete 95%    *WE HAVE EXPENDED FUNDS DURING THIS FISCAL YEAR, THAT MEET OR EXCEED THE THRESHOLD(S) REQUIRED BY THE SINGLE AUDIT ACT OF  1996 AND WILL CONDUCT ALL REQUIRED AUDITS.   Yes No    1. Please describe significant activities and developments that have occurred, which show performance during this  quarter, including a comparison of actual accomplishments to the objectives established in the application. [Maximum  Characters allowed 700]                                  2. Do you anticipate completion of work within the performance period?  Yes No     If not, please describe any problems, delays or adverse conditions that will impair the ability to meet the stated objectives in the  application.                              Do you anticipate:  3. Cost underrun/overrun?    Yes No        4. Request for change in Scope?    Yes No        5. Request for extension of performance period? Yes No        If you answer yes to any of the above, please provide comments in the section below.   Should additional funds become available, this form will be used to track and evaluate if costs are eligible for consideration.   This form will also be used to evaluate any requests for change in scope, or performance period extension.      We have completed public engagement, vulnerability assessment, goal setting, drafting of mitigation actions, drafting action plan, and completed the draft plan ready for improvement. We are ahead of schedule because we are committed to completing the plan by the time our current plan expires. The draft plan is ready for MEMA/FEMA review and then City Council adoption.