5.Northampton Shared Use & Sidewalk Ramps Project Bid Cost Estimate_03042020ITEM  NUMBER ITEM DESCRIPTION BID UNIT  BID UNIT PRICE  ENGINEER'S ESTIMATED  QUANTITY1 COST 102.51 INDIVIDUAL TREE PROTECTION EA $375.00 3 $1,125.00 120.1 UNCLASSIFIED EXCAVATION CY $45.00 63 $2,835.00 129.2 OLD PAVEMENT EXCAVATION SY $35.00 77 $2,684.50 151 GRAVEL BORROW CY $95.00 54 $5,130.00 170 FINE GRADING AND COMPACTING SY $6.00 260 $1,560.00 181.1 HEALTH AND SAFETY PLAN LS/RAMP $385.00 7 $2,695.00 181.2 IMPLEMENTATION OF HEALTH AND SAFETY PLAN HR $180.00 7 $1,260.00 220 DRAINAGE STRUCTURE ADJUSTED EA $500.00 4 $2,000.00 440 CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL LB $0.40 280 $112.00 443 WATER FOR ROADWAY DUST CONTROL MGL $50.00 7 $350.00 452 ASPHALT EMULSION FOR TACK COAT GAL $60.00 15 $900.00 464.5 HOT POURED RUBBERIZED ASPHALT SEALER FT $4.50 323 $1,453.50 472 HOT MIX ASPHALT FOR MISCELLANEOUS WORK TON $290.00 28 $8,120.00 482.3 SAWCUTTING ASPHALT PAVEMENT FT $3.00 323 $969.00 482.4 SAWCUTTING PORTLAND CEMENT CONCRETE FT $12.00 55 $660.00 506 GRANITE CURB TYPE VB ‐ STRAIGHT FT $70.00 116 $8,120.00 506.1 GRANITE CURB TYPE VB ‐ CURVED FT $80.00 41 $3,280.00 509 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ STRAIGHT FT $70.00 75 $5,250.00 509.1 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ CURVED FT $80.00 51 $4,080.00 511.1 GRANITE EDGING TYPE SB‐STRAIGHT FT $35.00 0 $0.00 580 CURB REMOVED AND RESET FT $50.00 0 $0.00 582 CURB CORNER REMOVED AND RESET EA $400.00 0 $0.00 590 CURB REMOVED AND STACKED FT $20.00 153 $3,060.00 592 CURB CORNER REMOVED AND STACKED EA $100.00 0 $0.00 632.4 INDIVIDUAL POST REMOVED AND DISCARDED  EA $56.00 10 $560.00 657 TEMPORARY FENCE FT $10.00 690 $6,900.00 697 SEDIMENTATION FENCE FT $6.00 308 $1,848.00 697.1 SILT SACK EA $175.00 7 $1,225.00 701 CEMENT CONCRETE SIDEWALK SY $70.00 22 $1,512.00 701.2 CEMENT CONCRETE RAMP/ DRIVEWAY /PATH SY $125.00 109 $13,675.00 748 MOBILIZATION LS/RAMP $600.00 7 $4,200.00 751 LOAM BORROW CY $60.00 10 $600.00 752 TOP SOIL REHANDLED AND SPREAD CY $60.00 10 $600.00 765 SEEDING SY $5.00 46 $230.00 832 WARNING REGULATORY SIGNS SF $13.00 162 $2,099.50 841.3 SUPPORT FOR GUIDE SIGN EA $140.00 17 $2,380.00 850.31 PORTABLE BREAKAWAY BARRICADES TYPE III EA $140.00 2 $280.00 851.1 TRAFFIC CONES FOR TRAFFIC MANAGEMENT DAY $0.50 320 $160.00 852 SAFETY SIGNING FOR TRAFFIC MANAGEMENT SF $10.00 913 $9,130.00 854.1 PAVEMENT MARKING REMOVAL SF $2.00 441 $882.00 859 REFLECTORIZED DRUM DRUM ‐ DAY $0.25 320 $80.00 864.04 PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC) SF $10.00 165 $1,650.00 865.1 CROSSWALKS AND STOP LINES REFLECTORIZED WHITE (THERMOPLASTIC) SF $5.00 804 $4,020.00 874.2 TRAFFIC SIGN REMOVED AND RESET EA $200.00 16 $3,200.00 999.003 TRUNCATED DOME TACTILE INDICATOR  SF $35.00 112 $3,920.00 999.1 TRAFFIC POLICE  HR $51.00 112 $5,712.00 999.3 CONSTRUCTION STAKINGS & SURVEY LS/RAMP $400.00 7 $2,800.00 999.4 TEMPORARY ACCESSIBLE ROUTE LS/RAMP $2,500.00 7 $17,500.00 999.5 CONCRETE COLD PLANE / GRIND SF $40.00 47 $1,880.00 1  Whole Number Values Shown TOTAL ITEMS $142,687.50 10% CONTINGENCIES & INCIDENTAL ITEMS $14,268.75 TOTAL COST ESTIMATE $156,957.00 ENGINEER'S COST ESTIMATE FOR BASE BID (RAMPS 10,11,22,23,24,31,32)  Shared Use and Sidewalk Ramps Project ITEM  NUMBER ITEM DESCRIPTION BID UNIT  BID UNIT PRICE  ENGINEER'S ESTIMATED  QUANTITY1 COST 102.51 INDIVIDUAL TREE PROTECTION EA $375.00 1 $375.00 120.1 UNCLASSIFIED EXCAVATION CY $45.00 23 $1,035.00 129.2 OLD PAVEMENT EXCAVATION SY $35.00 22 $773.50 151 GRAVEL BORROW CY $95.00 17 $1,615.00 170 FINE GRADING AND COMPACTING SY $6.00 96 $576.00 181.1 HEALTH AND SAFETY PLAN LS/RAMP $385.00 2 $770.00 181.2 IMPLEMENTATION OF HEALTH AND SAFETY PLAN HR $180.00 2 $360.00 220 DRAINAGE STRUCTURE ADJUSTED EA $500.00 0 $0.00 440 CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL LB $0.40 80 $32.00 443 WATER FOR ROADWAY DUST CONTROL MGL $50.00 2 $100.00 452 ASPHALT EMULSION FOR TACK COAT GAL $60.00 5 $300.00 464.5 HOT POURED RUBBERIZED ASPHALT SEALER FT $4.50 122 $549.00 472 HOT MIX ASPHALT FOR MISCELLANEOUS WORK TON $290.00 11 $3,190.00 482.3 SAWCUTTING ASPHALT PAVEMENT FT $3.00 122 $366.00 482.4 SAWCUTTING PORTLAND CEMENT CONCRETE FT $12.00 0 $0.00 506 GRANITE CURB TYPE VB ‐ STRAIGHT FT $70.00 24 $1,680.00 506.1 GRANITE CURB TYPE VB ‐ CURVED FT $80.00 25 $2,000.00 509 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ STRAIGHT FT $70.00 20 $1,400.00 509.1 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ CURVED FT $80.00 0 $0.00 511.1 GRANITE EDGING TYPE SB‐STRAIGHT FT $35.00 0 $0.00 580 CURB REMOVED AND RESET FT $50.00 0 $0.00 582 CURB CORNER REMOVED AND RESET EA $400.00 0 $0.00 590 CURB REMOVED AND STACKED FT $20.00 0 $0.00 592 CURB CORNER REMOVED AND STACKED EA $100.00 0 $0.00 632.4 INDIVIDUAL POST REMOVED AND DISCARDED  EA $56.00 0 $0.00 657 TEMPORARY FENCE FT $10.00 180 $1,800.00 697 SEDIMENTATION FENCE FT $6.00 160 $960.00 697.1 SILT SACK EA $175.00 1 $175.00 701 CEMENT CONCRETE SIDEWALK SY $70.00 11 $749.00 701.2 CEMENT CONCRETE RAMP/ DRIVEWAY /PATH SY $125.00 40 $5,037.50 748 MOBILIZATION LS/RAMP $600.00 2 $1,200.00 751 LOAM BORROW CY $60.00 6 $360.00 752 TOP SOIL REHANDLED AND SPREAD CY $60.00 7 $420.00 765 SEEDING SY $5.00 37 $185.00 832 WARNING REGULATORY SIGNS SF $13.00 71 $923.00 841.3 SUPPORT FOR GUIDE SIGN EA $140.00 6 $840.00 850.31 PORTABLE BREAKAWAY BARRICADES TYPE III EA $140.00 2 $280.00 851.1 TRAFFIC CONES FOR TRAFFIC MANAGEMENT DAY $0.50 80 $40.00 852 SAFETY SIGNING FOR TRAFFIC MANAGEMENT SF $10.00 237 $2,370.00 854.1 PAVEMENT MARKING REMOVAL SF $2.00 136 $272.00 859 REFLECTORIZED DRUM DRUM ‐ DAY $0.25 80 $20.00 864.04 PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC) SF $10.00 118 $1,180.00 865.1 CROSSWALKS AND STOP LINES REFLECTORIZED WHITE (THERMOPLASTIC) SF $5.00 404 $2,020.00 874.2 TRAFFIC SIGN REMOVED AND RESET EA $200.00 6 $1,200.00 999.003 TRUNCATED DOME TACTILE INDICATOR  SF $35.00 70 $2,450.00 999.1 TRAFFIC POLICE  HR $51.00 32 $1,632.00 999.3 CONSTRUCTION STAKINGS & SURVEY LS/RAMP $400.00 2 $800.00 999.4 TEMPORARY ACCESSIBLE ROUTE LS/RAMP $2,500.00 2 $5,000.00 999.5 CONCRETE COLD PLANE / GRIND SF $40.00 0 $0.00 1  Whole Number Values Shown TOTAL ITEMS $45,035.00 5% CONTINGENCIES & INCIDENTAL ITEMS $2,251.75 TOTAL COST ESTIMATE $47,287.00 ENGINEER'S COST ESTIMATE FOR ALTERNATE 1 BID (RAMPS 12 & 13) Shared Use and Sidewalk Ramps Project ITEM  NUMBER ITEM DESCRIPTION BID UNIT  BID UNIT PRICE  ENGINEER'S ESTIMATED  QUANTITY1 COST 102.51 INDIVIDUAL TREE PROTECTION EA $375.00 1 $375.00 120.1 UNCLASSIFIED EXCAVATION CY $45.00 8 $360.00 129.2 OLD PAVEMENT EXCAVATION SY $35.00 8 $276.50 151 GRAVEL BORROW CY $95.00 6 $570.00 170 FINE GRADING AND COMPACTING SY $6.00 31 $186.00 181.1 HEALTH AND SAFETY PLAN LS/RAMP $385.00 1 $385.00 181.2 IMPLEMENTATION OF HEALTH AND SAFETY PLAN HR $180.00 1 $180.00 220 DRAINAGE STRUCTURE ADJUSTED EA $500.00 0 $0.00 440 CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL LB $0.40 40 $16.00 443 WATER FOR ROADWAY DUST CONTROL MGL $50.00 1 $50.00 452 ASPHALT EMULSION FOR TACK COAT GAL $60.00 2 $120.00 464.5 HOT POURED RUBBERIZED ASPHALT SEALER FT $4.50 53 $238.50 472 HOT MIX ASPHALT FOR MISCELLANEOUS WORK TON $290.00 2 $580.00 482.3 SAWCUTTING ASPHALT PAVEMENT FT $3.00 53 $159.00 482.4 SAWCUTTING PORTLAND CEMENT CONCRETE FT $12.00 0 $0.00 506 GRANITE CURB TYPE VB ‐ STRAIGHT FT $70.00 18 $1,260.00 506.1 GRANITE CURB TYPE VB ‐ CURVED FT $80.00 3 $240.00 509 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ STRAIGHT FT $70.00 0 $0.00 509.1 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ CURVED FT $80.00 0 $0.00 511.1 GRANITE EDGING TYPE SB‐STRAIGHT FT $35.00 24 $840.00 580 CURB REMOVED AND RESET FT $50.00 0 $0.00 582 CURB CORNER REMOVED AND RESET EA $400.00 0 $0.00 590 CURB REMOVED AND STACKED FT $20.00 32 $640.00 592 CURB CORNER REMOVED AND STACKED EA $100.00 0 $0.00 632.4 INDIVIDUAL POST REMOVED AND DISCARDED  EA $56.00 0 $0.00 657 TEMPORARY FENCE FT $10.00 140 $1,400.00 697 SEDIMENTATION FENCE FT $6.00 48 $288.00 697.1 SILT SACK EA $175.00 1 $175.00 701 CEMENT CONCRETE SIDEWALK SY $70.00 0 $0.00 701.2 CEMENT CONCRETE RAMP/ DRIVEWAY /PATH SY $125.00 22 $2,687.50 748 MOBILIZATION LS/RAMP $600.00 1 $600.00 751 LOAM BORROW CY $60.00 1 $60.00 752 TOP SOIL REHANDLED AND SPREAD CY $60.00 6 $360.00 765 SEEDING SY $5.00 16 $80.00 832 WARNING REGULATORY SIGNS SF $13.00 41 $533.00 841.3 SUPPORT FOR GUIDE SIGN EA $140.00 4 $560.00 850.31 PORTABLE BREAKAWAY BARRICADES TYPE III EA $140.00 0 $0.00 851.1 TRAFFIC CONES FOR TRAFFIC MANAGEMENT DAY $0.50 280 $140.00 852 SAFETY SIGNING FOR TRAFFIC MANAGEMENT SF $10.00 162 $1,615.00 854.1 PAVEMENT MARKING REMOVAL SF $2.00 200 $400.00 859 REFLECTORIZED DRUM DRUM ‐ DAY $0.25 280 $70.00 864.04 PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC) SF $10.00 11 $110.00 865.1 CROSSWALKS AND STOP LINES REFLECTORIZED WHITE (THERMOPLASTIC) SF $5.00 354 $1,770.00 874.2 TRAFFIC SIGN REMOVED AND RESET EA $200.00 4 $800.00 999.003 TRUNCATED DOME TACTILE INDICATOR  SF $35.00 50 $1,750.00 999.1 TRAFFIC POLICE  HR $51.00 16 $816.00 999.3 CONSTRUCTION STAKINGS & SURVEY LS/RAMP $400.00 1 $400.00 999.4 TEMPORARY ACCESSIBLE ROUTE LS/RAMP $2,500.00 1 $2,500.00 999.5 CONCRETE COLD PLANE / GRIND SF $40.00 0 $0.00 1  Whole Number Values Shown TOTAL ITEMS $23,590.50 5% CONTINGENCIES & INCIDENTAL ITEMS $1,179.53 TOTAL COST ESTIMATE $24,771.00 ENGINEER'S COST ESTIMATE FOR ALTERNATE 2 BID (RAMPS 25A & 25B)  Shared Use and Sidewalk Ramps Project ITEM  NUMBER ITEM DESCRIPTION BID UNIT  BID UNIT PRICE  ENGINEER'S ESTIMATED  QUANTITY1 COST 102.51 INDIVIDUAL TREE PROTECTION EA $375.00 1 $375.00 120.1 UNCLASSIFIED EXCAVATION CY $45.00 8 $855.00 129.2 OLD PAVEMENT EXCAVATION SY $35.00 8 $882.00 151 GRAVEL BORROW CY $95.00 6 $1,710.00 170 FINE GRADING AND COMPACTING SY $6.00 31 $432.00 181.1 HEALTH AND SAFETY PLAN LS/RAMP $385.00 1 $1,155.00 181.2 IMPLEMENTATION OF HEALTH AND SAFETY PLAN HR $180.00 1 $540.00 220 DRAINAGE STRUCTURE ADJUSTED EA $500.00 0 $0.00 440 CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL LB $0.40 40 $48.00 443 WATER FOR ROADWAY DUST CONTROL MGL $50.00 1 $150.00 452 ASPHALT EMULSION FOR TACK COAT GAL $60.00 2 $300.00 464.5 HOT POURED RUBBERIZED ASPHALT SEALER FT $4.50 53 $504.00 472 HOT MIX ASPHALT FOR MISCELLANEOUS WORK TON $290.00 2 $2,610.00 482.3 SAWCUTTING ASPHALT PAVEMENT FT $3.00 53 $336.00 482.4 SAWCUTTING PORTLAND CEMENT CONCRETE FT $12.00 0 $60.00 506 GRANITE CURB TYPE VB ‐ STRAIGHT FT $70.00 79 $5,530.00 506.1 GRANITE CURB TYPE VB ‐ CURVED FT $80.00 33 $2,640.00 509 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ STRAIGHT FT $70.00 0 $0.00 509.1 GRANITE TRANSITION CURB FOR WHEELCHAIR RAMPS ‐ CURVED FT $80.00 12 $960.00 511.1 GRANITE EDGING TYPE SB‐STRAIGHT FT $35.00 0 $0.00 580 CURB REMOVED AND RESET FT $50.00 0 $0.00 582 CURB CORNER REMOVED AND RESET EA $400.00 0 $0.00 590 CURB REMOVED AND STACKED FT $20.00 0 $0.00 592 CURB CORNER REMOVED AND STACKED EA $100.00 0 $0.00 632.4 INDIVIDUAL POST REMOVED AND DISCARDED  EA $56.00 0 $0.00 657 TEMPORARY FENCE FT $10.00 410 $4,100.00 697 SEDIMENTATION FENCE FT $6.00 126 $756.00 697.1 SILT SACK EA $175.00 4 $700.00 701 CEMENT CONCRETE SIDEWALK SY $70.00 0 $0.00 701.2 CEMENT CONCRETE RAMP/ DRIVEWAY /PATH SY $125.00 29 $3,600.00 748 MOBILIZATION LS/RAMP $600.00 3 $1,800.00 751 LOAM BORROW CY $60.00 0 $0.00 752 TOP SOIL REHANDLED AND SPREAD CY $60.00 14 $840.00 765 SEEDING SY $5.00 40 $200.00 832 WARNING REGULATORY SIGNS SF $13.00 77 $994.50 841.3 SUPPORT FOR GUIDE SIGN EA $140.00 9 $1,260.00 850.31 PORTABLE BREAKAWAY BARRICADES TYPE III EA $140.00 0 $0.00 851.1 TRAFFIC CONES FOR TRAFFIC MANAGEMENT DAY $0.50 131 $65.50 852 SAFETY SIGNING FOR TRAFFIC MANAGEMENT SF $10.00 340 $3,395.00 854.1 PAVEMENT MARKING REMOVAL SF $2.00 179 $358.00 859 REFLECTORIZED DRUM DRUM ‐ DAY $0.25 131 $32.75 864.04 PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC) SF $10.00 33 $330.00 865.1 CROSSWALKS AND STOP LINES REFLECTORIZED WHITE (THERMOPLASTIC) SF $5.00 336 $1,680.00 874.2 TRAFFIC SIGN REMOVED AND RESET EA $200.00 0 $0.00 999.003 TRUNCATED DOME TACTILE INDICATOR  SF $35.00 48 $1,680.00 999.1 TRAFFIC POLICE  HR $51.00 48 $2,448.00 999.3 CONSTRUCTION STAKINGS & SURVEY LS/RAMP $400.00 3 $1,200.00 999.4 TEMPORARY ACCESSIBLE ROUTE LS/RAMP $2,500.00 3 $7,500.00 999.5 CONCRETE COLD PLANE / GRIND SF $40.00 0 $0.00 1  Whole Number Values Shown TOTAL ITEMS $52,026.75 5% CONTINGENCIES & INCIDENTAL ITEMS $2,601.34 TOTAL COST ESTIMATE $54,629.00 ENGINEER'S COST ESTIMATE FOR ALTERNATE 3 BID (RAMPS 28,29,30)  Shared Use and Sidewalk Ramps Project