2012 CPA Annual Report (CPA #51 - Nton DPW - Hotel Bridge)2 messages
John Frey <jfrey@northamptonma.gov>
Wed, Jan 9, 2013 at 1:10 PM
To: Ned Huntley <nhuntley@northamptonma.gov>
Hello Ned,
Please send me a summary of your 2012 CPA activity regarding the Hotel Bridge Feasibility Study. Please include...
-timeline and narrative for completed work to date
-report of funds spent to date
-timeline and narrative for remaining work
-report of expected funds to be spent (we show a remaining balance of $28,028.19).
FYI, the fund is set to expire June 28, 2014. Please keep that in mind while planning for the remainder of the project.
Thanks,
John Frey
Office of Planning and Development
City of Northampton
413-587-1072
jfrey@northamptonma.gov
Edward S. Huntley, P.E. <nhuntley@northamptonma.gov>
Thu, Jan 17, 2013 at 12:17 PM
To: John Frey <jfrey@northamptonma.gov>
Hi JohnI got an email from a member of the Leeds Civic group the other day which brought his project to the to the front of the pile again. DPW is in receipt of a draft report
from Stantec, the engineering consultant hired for the bridge evaluation. The contract was for $33,758 in which $6,971.81 has been expended.Work performed to dateBridge Inspection
has been completed and a preliminary structural analysis has started. I am hoping to complete the all the remaining work and public meetings this calender year. Ned