Construction Project Estimate_1-28-2022Project Preliminary Design Estimate 103.TREE REMOVED - DIAMETER UNDER 24 INCHES EA $1,800.000 30.000 $54,000.00 102.55 ARBORIST HR *$300.000 64.000 $19,200.00 105.STUMP REMOVED EA $750.000 38.000 $28,500.00 104.TREE REMOVED - DIAMETER 24 INCHES AND OVER EA $4,500.000 5.000 $22,500.00 102.521 TREE AND PLANT PROTECTION FENCE FT *$15.000 310.000 $4,650.00 101.CLEARING AND GRUBBING A $5,000.000 1.000 $5,000.00 102.511 TREE PROTECTION – ARMORING & PRUNING EA *$350.000 20.000 $7,000.00 102.1 TREE TRIMMING FT $30.000 100.000 $3,000.00 120.EARTH EXCAVATION CY $34.000 10400.000 $353,600.00 145.DRAINAGE STRUCTURE ABANDONED EA $700.000 26.000 $18,200.00 141.1 TEST PIT FOR EXPLORATION CY $110.000 400.000 $44,000.00 121.CLASS A ROCK EXCAVATION CY $75.000 40.000 $3,000.00 144.CLASS B ROCK EXCAVATION CY $156.000 33.000 $5,148.00 142.CLASS B TRENCH EXCAVATION CY $36.000 700.000 $25,200.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Friday, January 28, 2022Measure System:E Description:NORTHAMPTON- DOWNTOWN COMPLETE STREETS CORRIDOR AND INTERSECTION IMPROVEMENTS ON MAIN STREET (ROUTE 9) Date: District:2 Extended Description: This is a complete street project consisting of right-of-way to right-of-way altering of Main Street (Route 9)and intersecting streets in downtown Northampton, from Market Street to Bedford Terrace. This project includes improvements to sidewalks, a new separated bike lane, installation of street furniture/tree belt, new curbing, pavement, pavement markings, crosswalks, and signage, along with adjustments at crossings and signalized intersections to be more bicycle and pedestrian friendly and to improve the functioning of intersections and the roadway. Project:609286 Project Preliminary Design Estimate 220.5 DRAINAGE STRUCTURE REMODELED EA $800.000 2.000 $1,600.00 220.7 SANITARY STRUCTURE ADJUSTED EA $425.000 3.000 $1,275.00 222.31 FRAME AND GRATE MUNICIPAL STANDARD EA *$1,000.000 56.000 $56,000.00 220.DRAINAGE STRUCTURE ADJUSTED EA $450.000 111.000 $49,950.00 220.2 DRAINAGE STRUCTURE REBUILT FT $500.000 15.000 $7,500.00 220.3 DRAINAGE STRUCTURE CHANGE IN TYPE EA $1,000.000 5.000 $5,000.00 222.32 FRAME AND COVER MUNICIPAL STANDARD EA *$100.000 32.000 $3,200.00 151.01 GRAVEL BORROW - TYPE C CY $31.000 720.000 $22,320.00 151.2 GRAVEL BORROW FOR BACKFILLING STRUCTURES AND PIPES CY $50.000 2000.000 $100,000.00 153.CONTROLLED DENSITY FILL - EXCAVATABLE CY *$175.000 1600.000 $280,000.00 210.SANITARY SEWER MANHOLE EA *$10,000.00 0 7.000 $70,000.00 146.DRAINAGE STRUCTURE REMOVED EA $750.000 10.000 $7,500.00 151.GRAVEL BORROW CY $40.000 5250.000 $210,000.00 201.CATCH BASIN EA $4,500.000 72.000 $324,000.00 202.MANHOLE EA $5,000.000 24.000 $120,000.00 204.GUTTER INLET EA $2,500.000 5.000 $12,500.00 154.SAND BORROW CY $50.000 240.000 $12,000.00 156.CRUSHED STONE TON $52.000 765.000 $39,780.00 170.FINE GRADING AND COMPACTING - SUBGRADE AREA SY $15.000 13000.000 $195,000.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 241.36 36 INCH REINFORCED CONCRETE PIPE FT $250.000 70.000 $17,500.00 227.4 MASONRY PLUG SF $120.000 70.000 $8,400.00 227.31 REMOVAL OF DRAINAGE PIPE SEDIMENT FT $10.000 670.000 $6,700.00 238.06 6 INCH DUCTILE IRON PIPE FT $110.000 1000.000 $110,000.00 238.04 4 INCH DUCTILE IRON PIPE - WATER FT *$100.000 50.000 $5,000.00 223.1 FRAME AND GRATE (OR COVER) REMOVED AND STACKED EA *$100.000 45.000 $4,500.00 241.24 24 INCH REINFORCED CONCRETE PIPE FT $155.000 50.000 $7,750.00 227.3 REMOVAL OF DRAINAGE STRUCTURE SEDIMENT CY $255.000 70.000 $17,850.00 224.12 12 INCH HOOD EA $500.000 47.000 $23,500.00 241.12 12 INCH REINFORCED CONCRETE PIPE FT $100.000 2270.000 $227,000.00 238.18 18 INCH DUCTILE IRON PIPE FT $185.000 130.000 $24,050.00 241.18 18 INCH REINFORCED CONCRETE PIPE FT $120.000 630.000 $75,600.00 241.15 15 INCH REINFORCED CONCRETE PIPE FT $110.000 450.000 $49,500.00 238.10 10 INCH DUCTILE IRON PIPE FT $115.000 30.000 $3,450.00 238.08 8 INCH DUCTILE IRON PIPE - WATER FT *$110.000 600.000 $66,000.00 238.16 16 INCH DUCTILE IRON PIPE FT $180.000 3050.000 $549,000.00 238.12 12 INCH DUCTILE IRON PIPE FT $160.000 140.000 750.000 $142,400.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 358.GATE BOX ADJUSTED EA $270.000 29.000 $7,830.00 363.1 1 INCH CORPORATION COCK EA $270.000 27.000 $7,290.00 350.16 16 INCH GATE AND GATE BOX EA $6,000.000 16.000 $96,000.00 350.12 12 INCH GATE AND GATE BOX EA $3,500.000 6.000 $21,000.00 376.HYDRANT EA $6,000.000 19.000 $114,000.00 384.CURB STOP EA $400.000 27.000 $10,800.00 250.12 12 INCH POLYVINYLCHLOR IDE SANITARY SEWER PIPE FT *$120.000 400.000 $48,000.00 271.12 12 INCH AND UNDER PIPE REMOVED AND STACKED FT *$40.000 560.000 $22,400.00 250.08 8 INCH POLYVINYL CHLORIDE SANITARY SEWER PIPE FT *$130.000 350.000 $45,500.00 350.08 8 INCH GATE AND GATE BOX EA $2,500.000 7.000 $17,500.00 250.06 6 INCH POLYVINYL CHLORIDE SANITARY SEWER PIPE FT *$150.000 75.000 $11,250.00 271.18 18 INCH PIPE REMOVED AND STACKED FT *$50.000 50.000 $2,500.00 347.1 1 INCH COPPER TUBING TYPE K FT $70.000 1000.000 $70,000.00 350.06 6 INCH GATE AND GATE BOX EA $2,200.000 25.000 $55,000.00 309.DUCTILE IRON FITTINGS FOR WATER PIPE LB $10.000 18000.000 $180,000.00 271.36 36 INCH PIPE REMOVED AND STACKED FT *$80.000 70.000 $5,600.00 291.1 STORMWATER LANDSCAPE AREAS LS *$125,000.0 00 1.000 $125,000.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 431.HIGH EARLY STRENGTH CEMENT CONCRETE BASE COURSE SY $78.000 520.000 $40,560.00 440.CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL LB $0.400 56700.000 $22,680.00 443.WATER FOR ROADWAY DUST CONTROL MGL $57.000 29.000 $1,653.00 415.2 PAVEMENT FINE MILLING SY $7.500 14340.000 $107,550.00 472.TEMPORARY ASPHALT PATCHING TON $210.000 1452.000 $304,920.00 390.TEMPORARY WATER BY-PASS SYSTEM LS *$100,000.0 00 1.000 $100,000.00 402.DENSE GRADED CRUSHED STONE FOR SUB-BASE CY $75.000 1540.000 $115,500.00 450.22 SUPERPAVE SURFACE COURSE – 9.5 (SSC – 9.5) TON $140.000 490.000 $68,600.00 451.HMA FOR PATCHING TON $210.000 1270.000 $266,700.00 452.ASPHALT EMULSION FOR TACK COAT GAL $8.000 2590.000 $20,720.00 453.HMA JOINT ADHESIVE FT $1.000 31475.000 $31,475.00 450.42 SUPERPAVE BASE COURSE - 37.5 (SBC - 37.5) TON $140.000 1715.000 $240,100.00 450.23 SUPERPAVE SURFACE COURSE - 12.5 (SSC - 12.5) TON $140.000 2160.000 $302,400.00 450.31 SUPERPAVE INTERMEDIATE COURSE - 12.5 (SIC -12.5) TON $175.000 355.000 $62,125.00 450.32 SUPERPAVE INTERMEDIATE COURSE - 19.0 (SIC - 19.0) TON $135.000 2480.000 $334,800.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 706.8 PERMEABLE PAVER SY *$417.000 950.000 $396,150.00 706.9 COBBLE PAVER SY *$200.000 520.000 $104,000.00 706.7 CONCRETE UNIT PAVER SY *$375.000 670.000 $251,250.00 701.2 CEMENT CONCRETE PEDESTRIAN CURB RAMP SY $110.000 690.000 $75,900.00 702.HOT MIX ASPHALT SIDEWALK OR DRIVEWAY TON $230.000 297.000 $68,310.00 707.1 PARK BENCH EA *$3,000.000 40.000 $120,000.00 707.19 GRANITE BENCH $*$4,500.000 24.000 $108,000.00 504.1 GRANITE CURB TYPE VA4 - CURVED FT $65.000 1495.000 $97,175.00 509.GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - STRAIGHT FT $60.000 820.000 $49,200.00 504.GRANITE CURB TYPE VA4 - STRAIGHT FT $50.000 13000.000 $650,000.00 701.1 CEMENT CONCRETE SIDEWALK AT DRIVEWAYS SY $80.000 150.000 $12,000.00 482.3 SAWCUTTING ASPHALT PAVEMENT FT $10.000 940.000 $9,400.00 697.1 SILT SACK EA *$180.000 107.000 $19,260.00 701.CEMENT CONCRETE SIDEWALK SY $75.000 7640.000 $573,000.00 594.CURB REMOVED AND DISCARDED FT $7.000 6025.000 $42,175.00 509.1 GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - CURVED FT $70.000 110.000 $7,700.00 516.GRANITE CURB CORNER TYPE A EA $350.000 54.000 $18,900.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 816.03 TRAFFIC SIGNAL RECONSTRUCTION LOCATION NO. 3 LS $357,225.0 80 1.000 $357,225.08 816.02 TRAFFIC SIGNAL RECONSTRUCTION LOCATION NO. 2 LS $264,420.0 80 1.000 $264,420.08 745.2 PEDESTRIAN BUS SHELTER REMOVED AND STACKED LS *$8,000.000 1.000 $8,000.00 745.PEDESTRIAN BUS SHELTER EA *$17,000.00 0 2.000 $34,000.00 751.LOAM FOR ROADSIDES CY $55.000 209.000 $11,495.00 748.MOBILIZATION LS $419,884.9 80 1.000 $419,884.98 707.2 TRASH RECEPTACLE EA *$2,000.000 30.000 $60,000.00 816.01 TRAFFIC SIGNAL RECONSTRUCTION LOCATION NO. 1 LS $218,656.4 00 1.000 $218,656.40 740.ENGINEERS FIELD OFFICE AND EQUIPMENT (TYPE A) MO *$3,000.000 20.000 $60,000.00 707.9 BICYCLE RACK EA *$1,800.000 70.000 $126,000.00 751.7 COMPOST BLANKET CY *$12.000 667.000 $8,004.00 796.8 PERENNIAL EA *$24.000 3840.000 $92,160.00 784 CANOPY TREE - 2.5-3 INCH CALIPER EA *$3,500.000 66.000 $231,000.00 811.37 ELECTRIC HANDHOLE ADJUSTED EA $350.000 11.000 $3,850.00 811.36 ELECTRIC MANHOLE ADJUSTED EA $375.000 1.000 $375.00 756.NPDES STORMWATER POLLUTION PREVENTION PLAN LS *$10,000.00 0 1.000 $10,000.00 751.8 STRUCTURAL SOIL TON *$6,682.000 107.000 $714,974.00 767.7 FLEXIPAVE SF *$20.000 3820.000 $76,400.00 765.SEEDING SY $3.500 210.000 $735.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 852.12 TEMPORARY PEDESTRIAN RAMP EA *$250.000 45.000 $11,250.00 856.ARROW BOARD DAY $10.000 550.000 $5,500.00 852.SAFETY SIGNING FOR TRAFFIC MANAGEMENT SF $25.000 380.000 $9,500.00 852.11 TEMPORARY PEDESTRIAN BARRICADE FT *$12.000 7500.000 $90,000.00 864.04 PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC ) SF $8.000 1070.000 $8,560.00 856.12 PORTABLE CHANGEABLE MESSAGE SIGN DAY $25.000 580.000 $14,500.00 859.REFLECTORIZED DRUM DAY $2.000 27500.000 $55,000.00 820.14 ROADWAY LIGHTING LS *$1,549,300 .000 1.000 $1,549,300.00 820.15 PEDESTRIAN LIGHTING LS *$315,700.0 00 1.000 $315,700.00 850.41 ROADWAY FLAGGER HR $62.000 4380.000 $271,560.00 816.04 TRAFFIC SIGNAL RECONSTRUCTION LOCATION NO. 4 LS *$200,988.9 50 1.000 $200,988.95 832.WARNING- REGULATORY AND ROUTE MARKER - ALUMINUM PANEL (TYPE A) SF $15.000 505.000 $7,575.00 847.1 SIGN SUP (N/GUIDE)+RTE MKR W/1 BRKWAY POST ASSEMBLY - STEEL EA $160.000 80.000 $12,800.00 823.71 HIGHWAY LIGHTING POLE AND LUMINAIRE REMOVED AND STACKED EA *$800.000 33.000 $26,400.00 823.72 REMOVE CONCRETE FOUNDATION FOR ROADWAY LIGHTING EA *$1,500.000 33.000 $49,500.00 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total Project Preliminary Design Estimate 866.124 24 INCH REFLECTORIZED WHITE LANE (THERMOPLASTIC ) FT *$8.000 2450.000 $19,600.00 877.1 SIGN POST REMOVED AND DISCARDED EA *$50.000 105.000 $5,250.00 874.2 TRAFFIC SIGN REMOVED AND RESET EA *$117.000 105.000 $12,285.00 867.106 6 INCH REFLECTORIZED YELLOW LINE (THERMOPLASTIC ) FT $1.250 4020.000 $5,025.00 866.106 6 INCH REFLECTORIZED WHITE LINE (THERMOPLASTIC ) FT $1.250 7950.000 $9,937.50 864.1 GREEN FRICTION SURFACE (THERMOPLASTIC ) SF *$20.000 2400.000 $48,000.00 866.112 12 INCH REFLECTORIZED WHITE LINE (THERMOPLASTIC ) FT $3.600 540.000 $1,944.00 864.2 RAINBOW FRICTION SURFACE (THERMOPLASTIC ) SF *$20.000 200.000 $4,000.00 864.15 RED FRICTION SURFACE (THERMOPLASTIC ) SF *$20.000 3700.000 $74,000.00 Total Amount $12,675,480.99 $1,740,570.00 $14,416,050.99 Item #Description Units Type Unit Price FA - Hwy Safety Improvement Prgm (HSIP) NORTHAMPTON - Other - Municipality (Non-Participating) Total