GFN Revised CPA budget 12.2.24Pavilion for the Grow Food Northampton Community Farm
Budget update
December 2nd,2024
Changes from the previous budget
We received bids for the project since the last CPC meeting and they came in higher than
anticipated (bids attached below).The low bid is $346,429.Approximately $130,000 is for the
timber frame structure and the rest is for sitework and other construction costs.
This is in line with or less than the costs of similar,recently built pavilions in our area.The
timberframe of the ‘Airnasium’at the Hampshire YMCA cost $178,950 and with the sitework,the
total project cost was close to $1 million.The town of Hatfield spent $215,000 on the timber
frame for a 26’x26’pavilion,not including site work and construction costs.
The revised budget below clarifies what funds are secured and what are pending.In addition to
CPA funds,we have one pending grant of $20,000,and one grant for $50,000 that was recently
denied.We also changed our request for CPA funds to be used only for the pavilion itself,and
not staff time or trees,given the higher-than-anticipated bid.
Are quotes from the bidding process guaranteed for a certain period of time?
Yes.If we proceed and sign a contract with either bidder the quote will be fixed and guaranteed.
If we don’t proceed and sign a contract,by December 22nd in the case of one of the bidders,we
will have to redo the bidding process.
1
Grow Food Northampton Budget
**UPDATED December 2nd,2024**
Project Sources
Description Status Amount
HUD Community Projects Funding Secured $231,629
Foundation Grant Denied 50,000
Foundation Grant Pending 20,000
CPA Funding Pending 202,000
Project Sources Total $453,629
Project Uses
Description CPA request
Funding
from other
sources Total budget Completed?
Architectural:schematic design $7,000 $7,000 Completed
Architectural:construction documents and
administration 12,000 12,000 Completed
Structural Engineering 5,000 5,000 Completed
Civil Engineering 4,200 4,200 Completed
Implementation staff and project administration 65,000 65,000 Partial
"Pick-your-own"orchard fruit trees 14,000 14,000
Yet to be
completed
Pavilion General Contracting,Site work,
Construction 202,000 144,429 346,429
Yet to be
completed
Project Uses Total $202,000 $251,629 $453,629
Source of funds percentage 45%55%100%
2
MSArchitects, LLC MarcSternickArchitect.com MSternick@MSArchitects.Design
Grow Food Pavilion - Bid Tabulation
Bid Due Date: 11/22/24 at 2pm
Requests for Bids was issued to:
1 D.A. Sullivan Sons, Inc.
82 North St, Northampton, MA 01060
2 Keiter Builders
1 Interstate Drive, West Springfield, MA 01089
3 Thayer Industries
P.O. Box 60322, Florence ma. 01062
Bids Received on 11/22/24 at 2pm:
BIDS
BASE BID
Alternate
#1
Alternate
#2
Alternate
#3
Total - Base Bid =
All Alternates
Keiter Builders $374,744.00 $1,565.00 ($22,780.00) ($7,100.00) $346,429.00
Thayer