21.197 REVISED National Grid Petition for Installation of Underground Conduit on Damon Road
April 6, 2021
City Council
Town of Northampton
To Whom It May Concern:
Enclosed please find the revised petition of NATIONAL GRID covering the installation of underground
facilities.
If you have any questions regarding this permit, please contact:
Daniel Lopez-Velez 774-235-2603
If this petition meets with your approval, please return an executed copy to:
National Grid: Lisa Ayres; 1101 Turnpike Street; North Andover, MA 01845
(978)725-1418
Very truly yours,
Jim Kehrer/lla
Jim Kehrer
Name: Distribution Design Supervisor
Supervisor, Distribution Design
Enclosures
Questions contact – Daniel Lopez-Velez 774-235-2603
Petition of the Massachusetts Electric Company d/b/a NATIONAL GRID
Of NORTH ANDOVER, MASSACHUSETTS
For Electric Conduit Location:
To the City Council of Northampton, Massachusetts
Respectfully represents the Massachusetts Electric Company d/b/a NATIONAL GRID of
North Andover, Massachusetts, that it desires to construct a line of underground electric conduits,
including the necessary sustaining and protecting fixtures, under and across the public way or ways
hereinafter named.
Wherefore it prays that after due notice and hearing as provided by law, it be granted
permission to excavate the public highways and to run and maintain underground electric conduits,
together with such sustaining and protecting fixtures as it may find necessary for the transmission
of electricity, said underground conduits to be located substantially in accordance with the plan
filed herewith marked – Damon Rd. - Northampton, Massachusetts.
The following are the streets and highways referred to: 23303524
Damon Rd. - beginning at a point approximately 213 feet northeast of the centerline of the
intersection of Industrial Dr. and Damon Rd. and continuing approximately 377 feet in a northeast
direction, National Grid to install MH 1 Damon Rd., install MH 2 Damon Rd., install 45' of 2-5"
Conduit from P7-25 Damon Rd to MH 1 Damon Rd., install ~377' of 6-5" Conduit from MH 1 to
MH 2 Damon Rd., and install ~37' of 2-5" Conduit from P7-50 Damon Rd to MH 2 Damon Rd.
Location approximately as shown on plan attached.
Massachusetts Electric Company d/b/a
NATIONAL GRID Jim Kehrer/lla
BY _____________________________________
Engineering Department
Dated: April 6, 2021
ORDERED:
Notice having been given and public hearing held, as provided by law, that the
Massachusetts Electric Company d/b/a NATIONAL GRID be and it is hereby granted permission
to excavate the public highways and to run and maintain underground electric conduits, together
with such sustaining and protecting fixtures as said company may deem necessary, in the public
way or ways hereinafter referred to, and to make the necessary house connections along said
extensions, as requested in petition with said company dated the 6th day of April 2021.
Said underground electric conduits shall be located substantially in accordance with the
plan filed herewith marked – Damon Rd. - Northampton, Massachusetts 23303524
The following are the public ways or part of ways along which the underground electric
conduits above referred to may be laid:
Damon Rd. - beginning at a point approximately 213 feet northeast of the centerline of the
intersection of Industrial Dr. and Damon Rd. and continuing approximately 377 feet in a northeast
direction, National Grid to install MH 1 Damon Rd., install MH 2 Damon Rd., install 45' of 2-5"
Conduit from P7-25 Damon Rd to MH 1 Damon Rd., install ~377' of 6-5" Conduit from MH 1 to
MH 2 Damon Rd., and install ~37' of 2-5" Conduit from P7-50 Damon Rd to MH 2 Damon Rd.
I hereby certify that the foregoing order was adopted at a meeting of the …………………………
………………………………………………………………………………………………………
………………, held on the ……………………..… day of …………………………., 20 ………..
………………………………………………, …………………………., 20 ………..
Received and entered in the records of location orders of the City/Town of
Book ………………………. Page …………………………..
Attest:
………………………………
………….. hereby certify that on ………………………………20….., at ……….. o’clock, ….M
at ………………………………………………., a public hearing was held on the petition of
Massachusetts Electric Company d/b/a NATIONAL GRID for permission to construct the
underground electric conduits described in the order herewith recorded, and that I mailed at least
seven days before said hearing a written notice of the time and place of said hearing to each of the
owners of real estate (as determined by the last preceding assessment for taxation) along the ways
or parts of ways upon which the Company is permitted to construct the underground electric
conduits under said order. And that thereupon said order was duly adopted.
………………………………………………...
………………………………………………...
………………………………………………...
ORDERED:
Notice having been given and public hearing held, as provided by law, that the
Massachusetts Electric Company d/b/a NATIONAL GRID be and it is hereby granted permission
to excavate the public highways and to run and maintain underground electric conduits, together
with such sustaining and protecting fixtures as said company may deem necessary, in the public
way or ways hereinafter referred to, and to make the necessary house connections along said
extensions, as requested in petition with said company dated the 6th day of April 2021.
Said underground electric conduits shall be located substantially in accordance with the
plan filed herewith marked – Damon Rd. - Northampton, Massachusetts 23303524
The following are the public ways or part of ways along which the underground electric
conduits above referred to may be laid:
Damon Rd. - beginning at a point approximately 213 feet northeast of the centerline of the
intersection of Industrial Dr. and Damon Rd. and continuing approximately 377 feet in a northeast
direction, National Grid to install MH 1 Damon Rd., install MH 2 Damon Rd., install 45' of 2-5"
Conduit from P7-25 Damon Rd to MH 1 Damon Rd., install ~377' of 6-5" Conduit from MH 1 to
MH 2 Damon Rd., and install ~37' of 2-5" Conduit from P7-50 Damon Rd to MH 2 Damon Rd.
I hereby certify that the foregoing order was adopted at a meeting of the …………………………
………………………………………………………………………………………………………
………………, held on the ……………………..… day of …………………………., 20 ………..
………………………………………………, …………………………., 20 ………..
Received and entered in the records of location orders of the City/Town of
Book ………………………. Page …………………………..
Attest:
………………………………
………….. hereby certify that on ………………………………20….., at ……….. o’clock, ….M
at ………………………………………………., a public hearing was held on the petition of
Massachusetts Electric Company d/b/a NATIONAL GRID for permission to construct the
underground electric conduits described in the order herewith recorded, and that I mailed at least
seven days before said hearing a written notice of the time and place of said hearing to each of the
owners of real estate (as determined by the last preceding assessment for taxation) along the ways
or parts of ways upon which the Company is permitted to construct the underground electric
conduits under said order. And that thereupon said order was duly adopted.
………………………………………………...
………………………………………………...
………………………………………………...