44-014-002 (3) BP-2022-0182
254OLD WILSON RD COMMONWEALTH OF MASSACHUSETTS
Map:Block:Lot:
44-014-002 CITY OF NORTHAMPTON
Permit: Ails Renovations
Repair
PERSONS CONTRACTING WITH UNREGI TERED CONTRACTORS
DO NOT HAVE ACCESS TO THE GUARAI ITY FUND (MGL c.142A)
BUILDING PERMIT
Permit# BP-2022-0182 PERMISSION IS HEREBY GRANTED TO:
Project# ANTENNAS Contractor: License:
Est.Cost: 35000 HEIDREA COMM !CATIONS LLC 109212
Const.Class: Exp.Date:04/I7/202
BROADBENT, ERICSSON & SUSAN LEIGH
Use Group: Owner: MACR ' MAIL: SBA COMMUNICATIONS CORP
Lot Size(sq.ft.)
Zoning: SC t/rp/icaot: HEIDR 'A COMMUNICATIONS LLC
Applicant Address Phone: Insurance:
1 WILLIAMS WAY W('-14220923
BELLINGHAM, MA 02019
ISSUED ON:03/01/2022
TO PERFORM THE FOLLOWING WORK:
ALTERATIONS TO EQUIPMENT AT CE1.1. SITE
POST THIS CART)SO IT IS VISIBLE FROM THE STREET
Inspector of Plumbing Inspector of Wiring D.P.W. Building Inspector
Underground: See%ice: Meter: Footings:
Rough: Rough: House# Foundation:
Gas: Final: Final: Rough Frame:
Rough: Fire Department Driveway Final: Fireplace/Chimney:
Final: oil: Insulation:
Smoke: Final: O y /a3 j 3411/
THIS PERMIT MAY BE REVOKED BY THE CITY OF NORTHAMPTON UPON VIOLATION OF
ANY OF ITS RULES AND REGULATIONS.
Signature: I i )2 TAR
, . ir .
Fees Paid: S2-15.00
212 Main Street, Phone(413)587-1240,Fax-(4l 3)51i 7-1272
Office of the Building Commissioner
Final Construction Control Document
!/, To be submitted at completion of construction by a
\ i Registered Design Professional
Ifor work per the ninth edition of the
Massachusetts State Building Code,780 CMR, Section 107
Project Title: Verizon Wireless—Pine Grove MA(Site ID:468256—Fuze ID: 16649744)(Permit No.:BP-2022-0182)
Property Address: 254 Old Wilson Road,Northampton,MA 01060 Date: 04/19/2023
Project: Check(x)one or both as applicable: ❑ New construction ® Existing Construction
Project description: Alteration of an existing wireless communications facility including modification of tower mounted
RF equipment,mounting hardware,feedlines and ground level equipment within an existing fenced compound,
(excluding equipment shelter interior)as shown in the construction drawings prepared by ProTerra Design Group,LLC
revised through 12/29/2021,(RevO).
I Jesse M.Moreno MA Registration Number: 47315 Expiration date: 06/30/2024,am a registered design
professional, and I have prepared or directly supervised the preparation of all design plans,computations and
specifications concerning':
❑ Entire Project(Site Plan) ❑ Architectural ❑ Structural ❑ Mechanical
❑ Fire Protection ❑ Electrical ® Other: Telecommunications Alteration
for the above named project. I,or my designee,have performed the necessary professional services,in accordance with the
Professional Standard of Care, and was present at the construction site on a regular and periodic basis. To the best of my
knowledge, information, and belief the work proceeded in accordance with the requirements of 780 CMR and the design
documents approved as part of the building permit and that I or my designee:
1. Have reviewed,for conformance to this code and the design concept,shop drawings,samples and other submittals
by the contractor in accordance with the requirements of the construction documents.Such review shall not diminish
or relieve the contractor of its submittal and other responsibilities.
2. Have performed the duties for registered design professionals in 780 CMR Chapter 17,as applicable.
3. Have been present at intervals appropriate to the stage of construction to become generally familiar with the
progress and quality of the work and to determine if the work was performed in a manner consistent with the
construction documents and this code.The contractor is responsible for the performance of the work in accordance
with the contract documents and shall be exclusively responsible for its construction means, methods, sequences
and procedures,and for construction safety.
Nothing in this document relieves the contractor of its responsibility regarding the provisions of 780 CMR 107.
Enter in the space to the right a"wet"or
electronic signature and seal: Ivys
1,
JESSEMORE M. G
MORENO �/►
I \ CIVIL
" LL. 7315
S ?
1
Phone number: (413)320-491 ��� ti3
Email:_jmoreno( proterra-design.com
Building Official Use Only
Building Official Name: Permit No.: Date:
Version O1 Ol 2018
1 1
PrtsTerra FIELD INSPECTION REPORT
INSPECTION DATE December 29, 2022 ' JOB NO. 17-017
DESIGN GROUP, LLC REPORT ISSUE DATE REVISON COMMENTS
January 31, 2023 0 Field Inspection Report
PREPARED BY:
ProTerra Design Group, LLC
4 Bay Road
Building A; Suite 200 PROJECT
Hadley, MA 01035 Verizon equipment upgrade on existing water tank
Building Permit#: BP-2022-0182
SUBMITTED TO: Site ID:468256
Jonathan Flagg Fuze ID: 16649744
Building Department Site Name: Pine Grove MA
Municipal Building Site Address: 254 Old Wilson Road
212 Main St. Northampton, MA 01060
Northampton, MA 01060 CONTRACTOR EQUIPMENT OWNER
Heidrea Communications, LLC Verizon
PRESENT AT SITE ORGANIZATION
Tupac Branche ProTerra Design Group, LLC
Pursuant to the Massachusetts State Building Code, 780 CMR 9`h edition (IBC 2015 with amendments) the
following report documents a visual inspection from ground level of completed construction for general
conformance with the construction drawings prepared by ProTerra Design Group, LLC issued December 29, 2021
(Revl)for the above referenced project.
1) Twelve (12) existing panel antennas have been removed per plan.
2) Six (6) proposed antennas have been installed on side-by-side mounts in general conformance with
the construction drawings, (typical of 2 per sector,total of 6). It was noted during review that there
were open (unused) brackets in the middle position of the new antennas. Verizon issued additional
brackets for this site and the contractor returned to install them where needed.
3) Three (3) new Verizon MT6407-77A panel antennas, (1 per sector) installed as shown in the
construction drawings.
4) Three (3) new CBRS RRHs with clip-on antenna were installed per plans, (1 per sector total of 3).
5) Nine (9) existing RRHs were removed as described in plans.
6) Three(3) 700/850 RRHs and three (3) AWS/PCS RRHs, (6 RRHs total)were installed to the back side of
the antenna mounting pipes as shown in the construction drawings.
7) Two (2) surge suppressors remained in position as specified in plans.
8) A Post Modification Inspection, (PMI) review has been completed by Maser Consulting/Colliers
Engineering and Design dated December 30, 2022 which found in their opinion, that the equipment
installation and any required mount modifications have been satisfactorily completed.
Site ID:468256 Page 1 of 3 Field Inspection Report
Site Name: Pine Grove MA December 29, 2022
The comments in this field report are a record of observations made on site. If there are any errors or omissions
please notify ProTerra Design Group, LLC in writing or all comments and all parties shall consider this report factual
and acceptable.
COPIES TO: File
SUBMITTED:_ -'Jf ��
Peter Nute, Project Engineer
REVIEWED: /
/1I
Jess ,Moreno, P.E. Managing Partner
i
1
Site ID:468256 Page 2 of 3 Field Inspection Report
Site Name: Pine Grove MA December 29, 2022
t ,
0 RU
14
.$ �,.U1
1..!mi V ...*" ., X
tiling. i all � �
1 ' Will
$. I.�((1
� , Olt
I
. \:- .„--- A P ' ''''441 . .J. • ,
H. )'!: if ,
i
Dual-mounted antennas Typical CBRS with clip-on antenna Verizon MT6407-77A panel antenna
(prior to installing the middle bracket)
i !k
I'' :414:: 771:
111
1fL
I
r#1� r:
} � hi
�,
t 1 ;
hitt
.bT .
I At ct'; `J r
4
Middle bracket installed on dual-mounted antennas Typical RRHs installed on back of antenna mount pipes
1.
iiirpo
1,
A
Ole
ll
' 4 `.`• d
♦ ) \ \� -
• ,.. - I Ill; 1
' •,:t, •., \ ':
4
`.1 e, , 1,
It 1
Overall Verizon antenna array(bottom array) Overall Verizon antenna array
Site ID:468256 Page 3 of 3 Field Inspection Report
Site Name: Pine Grove MA December 29, 2022
verizori1
c,llicr, &Desig nnh
Colliers Engineering & Design
160 Federal Street, 11th Floor
Boston, MA 02110
617.330.8000
peter.albano@collierseng.com
Antenna Mount Post-Modification Inspection Report
PM!
SMART Tool Project#: 10126640
Colliers Engineering & Design Project#: 21781171A
December 30, 2022
Site Information Site ID: 468256-VZW/PINE GROVE MA
Site Name: PINE GROVE MA
Carrier Name: Verizon Wireless
Address: 254 Old Wilson Road
Northampton, Massachusetts 01060
Hampshire County
Latitude: 42.295472°
Longitude: -72.667389°
Structure Information Tower Type: 170-Ft Monopole
Mount Type: 13.58-Ft Platform
FUZE ID # 16649744
Inspection Result: Pass
Report Prepared By: Frank Centone
Mount Post-Modification Inspection Report December 30, 2022
(1) 13.58-Ft Platform Site ID: 468256-VZW/PINE GROVE MA
Page 12
Executive Summary:
The objective of this re ort is to confirm that the proposed mount modification has been completed in
accordance with the aunt modification documents referenced below. Colliers Engineering &Design
did not visit the site and was not present during construction.
Based on our review of the provided modification photos and documents, it is our opinion that the modification
has been completed in accordance with the proposed mount modification documents.
Protect Closeout Documents:
Document Type Remarks
Proposed Mount Modification Maser Consulting Project#:21781171A, Dated January 6, 2022
Signed PMI Requirements Checklist Provided by Heidrea Communications LLC.,
Dated December 21, 2022
Contractor As-Built Drawings Not Provided
Modification Photos Provided by Heidrea Communications LLC.,
Dated December 21, 2022
Material Packing List/Invoice Not Provided
* Documents & Photos Required from Contractor.
Post-Modification Inspection Summary:
Modifications:
Antenna:
• Install (6) MX06FRO860-03 antenna, (2) per sector
• Install (3) MT6407-77A antenna, (1) per sector
• Install (3)XXDWMM-12.5-65 antenna, (1) per sector
• Install (3) RF4439d-25A radio, (1) per sector
• Install (3) RF4440d-13A radio, (1) per sector
Steel:
• Replace the position 3 mount pipe in all sectors with a P2.5 STD
• Install new MSK3 pipe to pipe kits on the position 1 mount pipe of Alpha sector and the position
3 mount pipe of Beta sector
• All existing pipe to pipe connections to be removed
Deviations:
Antenna:
• Dual mounted panel antennas installed in position 4 instead of position 3 of Beta sector
-Approved
• Radio installed in position 2 of Gamma sector instead of position 4-Approved
Steel:
• MSK3 pipe to pipe kits not installed—Approved
• Existing mount pipes relocated - Approved
Comments: Deviations are approved and will not affect the results of this analysis
Mount Desktop — Post Modification Inspection (PMI) Report Requirements
Documents & Photos Required from Contractor— Passing Mount Analysis
Passing Mount Analysis requires a PMI due to a modification in loading.
Electronic pdf version of this can be downloaded at https://pmi.vzwsmart.com.
For additional questions and support, please reach out to pmisupport@colliersengineering.com
PSLC #: 468256 SMART Project #: 10126340 Fuze Project ID: 16649744
Purpose—to provide SMART Tool structural vendor the proper documentation in order to complete
the required Mount Desktop review of the Post Modification Inspection Report.
• Contractor is responsible for making certain the photos provided as noted below provide
confirmation that the installation was completed in accordance with this Passing Mount
Analysis.
• Contractor shall relay any data that can impact the performance of the mount, this includes
safety issues.
Base Requirements:
• If installation will cause damage to the structure, the climbing facility, or safety climb if present
or any installed system, SMART Tool vendor to be notified prior to install. Any special photos
outside of the standard requirements will be indicated on the drawings.
• Provide "as built mount drawings" showing contractor's name, contact information, preparer's
signature, and date. Any deviations from the drawings (Proposed modification) shall be shown.
NOTE: If loading is different than what is conveyed in the passing mount analysis (MA) contact
the SMART Tool vendor immediately.
• Each photo should be time and date stamped
• Photos should be high resolution.
• Contractor shall ensure that the safety climb wire rope is supported and not adversely
impacted by the install of the modification components. This may involve the install of wire
rope guides, or other items to protect the wire rope. If there is conflict, contact the SMART Tool
engineer for recommendations.
• The PMI can be accessed at the following portal: https://pmi.vzwsmart.com
Photo Requirements:
• Photos taken at around level
o Photo of Gate Signs showing the tower owner, site name, and number.
o Overall tower structure after installation.
o Photos of the mount after installation; if the mounts are at different rad elevations,
pictures must be provided for all elevations that equipment was installed.
• Photos taken at Mount Elevation
o Photos showing the safety climb wire rope above and below the mount prior to
installation.
o Photos showing the climbing facility and safety climb if present.
o Photos showing each individual sector after installation. Each entire sector shall be in
one photo to show the interconnection of members.