136 Chestnut 2020-02-18Switches: Single Pole, Weather Proof, 3-Way, 4-Way
Switches: Dimmer, Timer
Audio Video: Control Panel, Switch
Wall Jacks: CAT5, CAT5 + TV, TV/Cable
Door Chime, Door Bell Button
Smoke Detectors: Ceiling Mounted, Wall Mounted
Speakers: Ceiling Mounted, Wall Mounted
WALL KEY
= EXISTING 2x6 INTERIOR WALL
= EXISTING 2x6 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
AND 2x6 INTERIOR WALL
= DEMO 2x8 INTERIOR WALL WITH BRICK
3 3/4" UP
3" UP
REMOVE &
DISCARD VENT
EXISTING
SHELVES
TO REMAIN
SOFFIT TO
REMAIN
REMOVE &
DISCARD
BRICK FLOOR
REMOVE & DISCARD
CHIMNEY FROM FLOOR TO
JUST BELOW ROOF PLANE
Specifications
Division 1: General Requirements
1.Contractor will obtain all necessary permits for construction, except that owner shall be responsible for water, sewer, electric, and
cable fees, if any.
2.Contract excludes approvals by zoning board of appeals, planning board and/or conservation commission.
3.Contract excludes architectural oversight.
4.Any other requirements from town not explicitly included in the plans or specs are not included in this contract.
5.Site survey is not included
6.Contractor has not tested for lead, asbestos, radon, and other hazardous materials and contract does not include any remediation or
abatement work.
7.All owner-supplied items are not under warranty by Integrity or Integrity’s sub-contractors and suppliers. Any owner-supplied items
that arrive damaged, late or incomplete may cause delays to the schedule and Integrity will not be held liable for such delays or costs.
8.All construction debris will be placed in an onsite dumpster provided by contractor and removed by contractor at contractor’s
expense.
9.Contractor shall promptly remove all construction equipment and materials from site at conclusion of construction.
10.All utilities used during construction are the owner’s responsibility.
11.Wherever contractor drawing or specification states, “match existing,” such language shall mean “match existing as closely as
possible from currently available stock items purchased locally”.
12.All dimensions are framing to framing unless otherwise specified.
13.All existing structural components to remain unless otherwise specified.
14.Appliances, furniture, etc. shown on plans are to be supplied by owner.
15.No winter conditions are included.
16.Contract includes both on-site and in-office job coordination
17.Required insurances include General Liability and Worker's Compensation
18.Use drop cloths and floor protection to protect flooring from front door to first-floor bath. Replace as necessary.
19.Contractor to supply temporary sanitary facilities on site for workers' use
20.All work is limited to first-floor bath and den unless otherwise noted
Demo. Specifications
Divisions 2-3: Site Work, Concrete
1.None
Division 4: Masonry
1.Remove & discard chimney from floor to just below
roof plane
Division 5: Metals
1.None
Division 6: Wood & Plastics
1.Remove & discard walls per plan
2.Remove & discard floor sheathing where new floor
is to be built
3.Enlarge existing opening for window in wall
Division 7: Thermal & Moisture Protection
Exterior Trim And Siding
1.Remove & discard siding in new window location
Insulation
1.Insulation in new window location to remain
Division 8: Doors & Windows
Doors
1.Remove & discard (2) doors per plan
Windows
1.Remove & discard (1) window per plan
Division 9: Finishes
Wall And Ceiling Finishes
1.Remove & discard brick on (2) walls
Flooring
1.Remove & discard brick flooring
Tile
1.Remove & discard bathroom finish flooring
Interior Trim And Carpentry
1.Remove & discard casing at (2) removed doors
2.Remove & discard baseboard in bath #1 only and at
new built-in locations in den
Division 10: Specialties
1.None
Division 11: Equipment
1.None
Division 12: Furnishings
1.Existing shelves to remain
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Remove & discard sink, faucet, toilet, and toilet seat
2.Cap existing pipe in wall if possible
Heating
1.Remove & discard vent per plan
2.Remove & discard existing bath heat register
Division 16: Electrical
1.See Electrical Plan For SpecificationsPIPE TO REMAIN; CAPIN WALL IF POSSIBLEREMOVE &
DISCARD
BRICK WALLS
Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE1INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INSCONTRACT AGREED BY:
____________________________________________________________________________
BRIAN BALDI - OWNER OF 136 CHESTNUT ST, FLORENCE, MA 01062
____________________________________________________________________________
LESLEY YALEN - OWNER OF 136 CHESTNUT ST, FLORENCE, MA 01062
____________________________________________________________________________
OWNER FOR INTEGRITY DEVELOPMENT & CONSTRUCTION, INC.
BALDI / YALEN
RESI DENCE
136 CHESTNUT ST, FLORENCE, MA 01062
INDEX
A-1
A-2
A-3
A-4
A-5
E-1
E-2
TITLE PAGE
EXISTING FIRST FLOOR PLAN
PROPOSED FIRST FLOOR PLAN
PROPOSED ELEVATIONS AND SCHEDULES
PROPOSED BOOKCASE ELEVATIONS & SECTIONS
EXISTING ELECTRIC PLAN
PROPOSED ELECTRIC PLAN
REMOVE &
DISCARD TO REMAINREMOVE & DISCARDREMOVE & DISCARDTO REMAINTO REMAIN
16'-1 1/4"1'-7 1/4"2'-1"6'21'-3"3'-6 3/4"12'-3"9'-11"WALL KEY
= EXISTING 2x6 INTERIOR WALL
= EXISTING 2x6 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
AND 2x6 INTERIOR WALL
= DEMO 2x8 INTERIOR WALL WITH BRICK
3 3/4" UP
3" UP
REMOVE &
DISCARD VENT
EXISTING
SHELVES
TO REMAIN
SOFFIT TO
REMAIN
REMOVE &
DISCARD
BRICK FLOOR
REMOVE & DISCARD
CHIMNEY FROM FLOOR TO
JUST BELOW ROOF PLANE
DEN
Specifications
Division 1: General Requirements
1.Contractor will obtain all necessary permits for construction, except that owner shall be responsible for water, sewer, electric, and
cable fees, if any.
2.Contract excludes approvals by zoning board of appeals, planning board and/or conservation commission.
3.Contract excludes architectural oversight.
4.Any other requirements from town not explicitly included in the plans or specs are not included in this contract.
5.Site survey is not included
6.Contractor has not tested for lead, asbestos, radon, and other hazardous materials and contract does not include any remediation or
abatement work.
7.All owner-supplied items are not under warranty by Integrity or Integrity’s sub-contractors and suppliers. Any owner-supplied items
that arrive damaged, late or incomplete may cause delays to the schedule and Integrity will not be held liable for such delays or costs.
8.All construction debris will be placed in an onsite dumpster provided by contractor and removed by contractor at contractor’s
expense.
9.Contractor shall promptly remove all construction equipment and materials from site at conclusion of construction.
10.All utilities used during construction are the owner’s responsibility.
11.Wherever contractor drawing or specification states, “match existing,” such language shall mean “match existing as closely as
possible from currently available stock items purchased locally”.
12.All dimensions are framing to framing unless otherwise specified.
13.All existing structural components to remain unless otherwise specified.
14.Appliances, furniture, etc. shown on plans are to be supplied by owner.
15.No winter conditions are included.
16.Contract includes both on-site and in-office job coordination
17.Required insurances include General Liability and Worker's Compensation
18.Use drop cloths and floor protection to protect flooring from front door to first-floor bath. Replace as necessary.
19.Contractor to supply temporary sanitary facilities on site for workers' use
20.All work is limited to first-floor bath and den unless otherwise noted
Demo. Specifications
Divisions 2-3: Site Work, Concrete
1.None
Division 4: Masonry
1.Remove & discard chimney from floor to just below
roof plane
Division 5: Metals
1.None
Division 6: Wood & Plastics
1.Remove & discard walls per plan
2.Remove & discard floor sheathing where new floor
is to be built
3.Enlarge existing opening for window in wall
Division 7: Thermal & Moisture Protection
Exterior Trim And Siding
1.Remove & discard siding in new window location
Insulation
1.Insulation in new window location to remain
Division 8: Doors & Windows
Doors
1.Remove & discard (2) doors per plan
Windows
1.Remove & discard (1) window per plan
Division 9: Finishes
Wall And Ceiling Finishes
1.Remove & discard brick on (2) walls
Flooring
1.Remove & discard brick flooring
Tile
1.Remove & discard bathroom finish flooring
Interior Trim And Carpentry
1.Remove & discard casing at (2) removed doors
2.Remove & discard baseboard in bath #1 only and at
new built-in locations in den
Division 10: Specialties
1.None
Division 11: Equipment
1.None
Division 12: Furnishings
1.Existing shelves to remain
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Remove & discard sink, faucet, toilet, and toilet seat
2.Cap existing pipe in wall if possible
Heating
1.Remove & discard vent per plan
2.Remove & discard existing bath heat register
Division 16: Electrical
1.See Electrical Plan For SpecificationsPIPE TO REMAIN; CAPIN WALL IF POSSIBLEBATH #1
REMOVE &
DISCARD
BRICK WALLS
SUNROOMWALL KEY
= EXISTING 2x6 INTERIOR WALL
= EXISTING 2x6 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
= EXISTING 2x8 EXTERIOR WALL WITH BRICK
AND 2x6 INTERIOR WALL
= DEMO 2x8 INTERIOR WALL WITH BRICK
3 3/4" UP
3" UP
REMOVE &
DISCARD VENT
EXISTINGSHELVESTO REMAINSOFFIT TOREMAIN REMOVE &DISCARDBRICK FLOORREMOVE & DISCARDCHIMNEY FROM FLOOR TOJUST BELOW ROOF PLANE
Specifications
Division 1: General Requirements
1.Contractor will obtain all necessary permits for construction, except that owner shall be responsible for water, sewer, electric, and
cable fees, if any.
2.Contract excludes approvals by zoning board of appeals, planning board and/or conservation commission.
3.Contract excludes architectural oversight.
4.Any other requirements from town not explicitly included in the plans or specs are not included in this contract.
5.Site survey is not included
6.Contractor has not tested for lead, asbestos, radon, and other hazardous materials and contract does not include any remediation or
abatement work.
7.All owner-supplied items are not under warranty by Integrity or Integrity’s sub-contractors and suppliers. Any owner-supplied items
that arrive damaged, late or incomplete may cause delays to the schedule and Integrity will not be held liable for such delays or costs.
8.All construction debris will be placed in an onsite dumpster provided by contractor and removed by contractor at contractor’s
expense.
9.Contractor shall promptly remove all construction equipment and materials from site at conclusion of construction.
10.All utilities used during construction are the owner’s responsibility.
11.Wherever contractor drawing or specification states, “match existing,” such language shall mean “match existing as closely as
possible from currently available stock items purchased locally”.
12.All dimensions are framing to framing unless otherwise specified.
13.All existing structural components to remain unless otherwise specified.
14.Appliances, furniture, etc. shown on plans are to be supplied by owner.
15.No winter conditions are included.
16.Contract includes both on-site and in-office job coordination
17.Required insurances include General Liability and Worker's Compensation
18.Use drop cloths and floor protection to protect flooring from front door to first-floor bath. Replace as necessary.
19.Contractor to supply temporary sanitary facilities on site for workers' use
20.All work is limited to first-floor bath and den unless otherwise noted
Demo. Specifications
Divisions 2-3: Site Work, Concrete
1.None
Division 4: Masonry
1.Remove & discard chimney from floor to just below
roof plane
Division 5: Metals
1.None
Division 6: Wood & Plastics
1.Remove & discard walls per plan
2.Remove & discard floor sheathing where new floor
is to be built
3.Enlarge existing opening for window in wall
Division 7: Thermal & Moisture Protection
Exterior Trim And Siding
1.Remove & discard siding in new window location
Insulation
1.Insulation in new window location to remain
Division 8: Doors & Windows
Doors
1.Remove & discard (2) doors per plan
Windows
1.Remove & discard (1) window per plan
Division 9: Finishes
Wall And Ceiling Finishes
1.Remove & discard brick on (2) walls
Flooring
1.Remove & discard brick flooring
Tile
1.Remove & discard bathroom finish flooring
Interior Trim And Carpentry
1.Remove & discard casing at (2) removed doors
2.Remove & discard baseboard in bath #1 only and at
new built-in locations in den
Division 10: Specialties
1.None
Division 11: Equipment
1.None
Division 12: Furnishings
1.Existing shelves to remain
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Remove & discard sink, faucet, toilet, and toilet seat
2.Cap existing pipe in wall if possible
Heating
1.Remove & discard vent per plan
2.Remove & discard existing bath heat register
Division 16: Electrical
1.See Electrical Plan For SpecificationsPIPE TO REMAIN; CAPIN WALL IF POSSIBLEREMOVE &DISCARDBRICK WALLS WALL KEY= EXISTING 2x6 INTERIOR WALL= EXISTING 2x6 EXTERIOR WALL= EXISTING 2x8 EXTERIOR WALL= EXISTING 2x8 EXTERIOR WALL WITH BRICK= EXISTING 2x8 EXTERIOR WALL WITH BRICK AND 2x6 INTERIOR WALL= DEMO 2x8 INTERIOR WALL WITH BRICK3 3/4" UP3" UPREMOVE &DISCARD VENTEXISTINGSHELVESTO REMAINSOFFIT TOREMAIN REMOVE &DISCARDBRICK FLOORREMOVE & DISCARDCHIMNEY FROM FLOOR TOJUST BELOW ROOF PLANE SpecificationsDivision 1: General Requirements1.Contractor will obtain all necessary permits for construction, except that owner shall be responsible for water, sewer, electric, andcable fees, if any.2.Contract excludes approvals by zoning board of appeals, planning board and/or conservation commission.3.Contract excludes architectural oversight.
4.Any other requirements from town not explicitly included in the plans or specs are not included in this contract.
5.Site survey is not included
6.Contractor has not tested for lead, asbestos, radon, and other hazardous materials and contract does not include any remediation or
abatement work.
7.All owner-supplied items are not under warranty by Integrity or Integrity’s sub-contractors and suppliers. Any owner-supplied items
that arrive damaged, late or incomplete may cause delays to the schedule and Integrity will not be held liable for such delays or costs.
8.All construction debris will be placed in an onsite dumpster provided by contractor and removed by contractor at contractor’s
expense.
9.Contractor shall promptly remove all construction equipment and materials from site at conclusion of construction.
10.All utilities used during construction are the owner’s responsibility.
11.Wherever contractor drawing or specification states, “match existing,” such language shall mean “match existing as closely as
possible from currently available stock items purchased locally”.
12.All dimensions are framing to framing unless otherwise specified.
13.All existing structural components to remain unless otherwise specified.
14.Appliances, furniture, etc. shown on plans are to be supplied by owner.
15.No winter conditions are included.
16.Contract includes both on-site and in-office job coordination
17.Required insurances include General Liability and Worker's Compensation
18.Use drop cloths and floor protection to protect flooring from front door to first-floor bath. Replace as necessary.
19.Contractor to supply temporary sanitary facilities on site for workers' use
20.All work is limited to first-floor bath and den unless otherwise noted
Demo. Specifications
Divisions 2-3: Site Work, Concrete
1.None
Division 4: Masonry
1.Remove & discard chimney from floor to just below
roof plane
Division 5: Metals
1.None
Division 6: Wood & Plastics
1.Remove & discard walls per plan
2.Remove & discard floor sheathing where new floor
is to be built
3.Enlarge existing opening for window in wall
Division 7: Thermal & Moisture Protection
Exterior Trim And Siding
1.Remove & discard siding in new window location
Insulation
1.Insulation in new window location to remain
Division 8: Doors & Windows
Doors
1.Remove & discard (2) doors per plan
Windows
1.Remove & discard (1) window per plan
Division 9: Finishes
Wall And Ceiling Finishes
1.Remove & discard brick on (2) walls
Flooring
1.Remove & discard brick flooring
Tile
1.Remove & discard bathroom finish flooring
Interior Trim And Carpentry
1.Remove & discard casing at (2) removed doors
2.Remove & discard baseboard in bath #1 only and at
new built-in locations in den
Division 10: Specialties
1.None
Division 11: Equipment
1.None
Division 12: Furnishings
1.Existing shelves to remain
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Remove & discard sink, faucet, toilet, and toilet seat
2.Cap existing pipe in wall if possible
Heating
1.Remove & discard vent per plan
2.Remove & discard existing bath heat register
Division 16: Electrical
1.See Electrical Plan For SpecificationsPIPE TO REMAIN; CAPIN WALL IF POSSIBLEREMOVE &DISCARDBRICK WALLS
Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE2INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INS1
A-02
1
A-02
EXISTING FIRST FLOOR PLAN
1/2" = 1'-0"
D01 - 2668 TO REMAIND02 - 3066ITGL 4824TO REMAINTO REMAIN
SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS:
1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FOR
CONSTRUCTION, EXCEPT THAT OWNER SHALL BE
RESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLE
FEES, IF ANY.
2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OF
APPEALS, PLANNING BOARD AND/OR CONSERVATION
COMMISSION.
3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT.
4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLY
INCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED IN
THIS CONTRACT.
5.SITE SURVEY IS NOT INCLUDED
6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHER
HAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDE
ANY REMEDIATION OR ABATEMENT WORK.
7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BY
INTEGRITY OR INTEGRITY’S SUB-CONTRACTORS AND
SUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVE
DAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TO
THE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLE
FOR SUCH DELAYS.
8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITE
DUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BY
CONTRACTOR AT CONTRACTOR’S EXPENSE.
9.ALL UTILITIES USED DURING CONSTRUCTION ARE THE
OWNER’S RESPONSIBILITY.
10.CONTRACTOR SHALL PROMPTLY REMOVE ALL
CONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE AT
CONCLUSION OF CONSTRUCTION.
11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATION
STATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN
“MATCH EXISTING AS CLOSELY AS POSSIBLE FROM
CURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.
12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESS
OTHERWISE SPECIFIED.
13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAIN
UNLESS OTHERWISE SPECIFIED.
14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER.
15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.
16.ROOM FINISHES PER FINISH SCHEDULE.
2'-1"1'-6 1/4"6'21'-3"3'-10 3/4"4'-6"7'-5"2'-6"3'-6"2'-6"3'2'-6"3/4"1'-6"9"9"1'-9 1/2"2'-10 1/2"1 3/4"3/4"2'-3"2'-6"2'-3"1'3"3'8'-6"3'-2 1/2"1'-9"1'-7 1/2"7'-9 7/8"7'-9 7/8"7'-2"3 3/4" UP
3" UP
EXISTING
SHELVES
TO REMAIN
SOFFIT TO
REMAIN
2x6
WALL
FRAME NEW FLOOR
SYSTEM HERE TO BE
FLUSH WITH EXISTING
BATH FLOOR RECESSEDMEDICINE CABINETDENNICHE WALL KEY
= NEW 2x4 INTERIOR WALL
= NEW 2x6 INTERIOR WALL
= NEW 2x4 HALF WALL
ROLL-IN
SHOWER
WALNUT COUNTERTOPON THESE BUILT-INS ONLYSpecifications
Divisions 2-4: Site Work, Concrete, Masonry
1.None
Division 5: Metals
1.Supply & install ducting to bath fan via shortest route to exterior wall
Division 6: Wood & Plastics
1.2x6 KD spruce interior wall studs @ 16" O.C. where existing wall is being infilled or continued
2.2x4 KD spruce interior wall studs @ 16" O.C. where wall is new
3.2x4 KD spruce interior half-wall studs @ 16" O.C., 36" half-wall height
4.Build soffits to hide duct using 2x material
5.Frame opening for new window; exterior wall is assumed to be 2x6 wall. No obstructions are assumed, and
if obstructions exist, cost will be extra to contract.
Bath Floor
1.Frame new bath floor system with 2x4 KD spruce floor joists cut down to approx. 3"
2.3/4" T&G Advantech subfloor; top of new subfloor to be flush with existing subfloor
3.Floor to be pitched at 1/4" in 12" at roll-in shower using mud pan
Division 7: Thermal & Moisture Protection
Exterior Trim and Siding
1.Supply & install rough sawn pine shiplap siding to match existing in new window location; new siding will
not be a perfect match to existing
2.Supply & install trim at new window to match existing trim as closely as possible
Insulation
1.Insulate gaps at window with spray foam
2.Existing insulation to remain; if additional insulation is needed, cost will be extra to contract
Division 8: Doors & Windows
1.Window and door headers per schedule
Doors
1.Supply & install (1) hinged interior door per plan and schedule
2.Supply & install (1) hinged exterior glass door per plan and schedule
3.Supply & install door hardware TBD by allowance
Windows
1.Supply & install (1) Marvin Elevate window per plan and schedule
Division 9: Finishes
Wall and Ceiling Finishes
1.Supply & install 1/2" standard drywall to all new wall framing in den and all new ceiling framing
2.Supply & install 1/2" MR drywall to bath walls only
3.Apply (3) coats of joint compound & sand to smooth finish
Flooring
1.Supply & install tile finish flooring in bath and roll-in shower per schedule
2.Supply & install 5" wide finish flooring in den to match existing as closely as possible; tooth in to existing
3.Finish new wood flooring only with (3) coats of satin oil-based floor finish; screened between coats
Tile
1.Supply & install tile shower walls, niche sides and top, and soffit in shower only per schedule
Interior Trim and Carpentry
1.Supply & install 1x6 primed pine baseboard in bath and on new den walls, patch around built-ins
2.Supply & install 1x4 primed pine door casing with corner rosettes to new doors
3.Existing shelves to remain
Painting
1.Fill nail heads
2.Apply (2) coats Benjamin Moore Aura latex paint to walls, ceilings, and trim
3.Contract limited to (5) paint colors; (1) wall color per room, (1) ceiling color, and (1) trim color
4.Painting is limited to bath and affected walls of den and sunroom
Division 10: Specialties
1.Supply & install shower glass TBD by allowance
2.Supply & install bath accessories and recessed medicine cabinet per schedule
Division 11: Equipment
1.None
Division 12: Furnishings
1.Supply & install vanity cabinet per plan
2.Supply & install vanity countertop and backsplash and shower half-wall cap per plan and schedule
3.Cabinet hardware will be supplied with cabinet
4.Cabinet interiors and underside of wall cabinets will not match the exterior finish of the cabinets unless
specifically noted otherwise.
5.Supply & install built-in bookshelves in den per plan
6.Supply & install walnut countertop on indicated built-ins
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Supply & install sink, faucet, toilet, toilet seat, shower head, shower valve trim, slide bar, shower arm, and
line drain per plan and schedule
2.Cap existing pipe in wall if possible
Heating
1.Supply & install Reggio cast iron register in existing location (existing register is 9" x 11 1/4"); new register
to match existing house registers as closely as possible
Division 16: Electrical
1.See electrical plan for specifications
1
A-4
1
A-4
2
A-4
2
A-4
3
A-4
3
A-4
PIPE TOREMAIN; CAPIN WALL IFPOSSIBLEBATH #1
SUNROOMNEW FLOOR
SLEEPERS RUN IN
THIS DIRECTION
NEW 5"
WIDE FINISH
FLOORING
BUILD SOFFIT TO
HIDE NEW DUCT
1
A-5
1
A-5
3
A-5
3
A-5
2
A-5
2
A-5
4
A-5
4
A-5
TOWEL
RING
TOWEL
BARS
TOILET
PAPER
HOLDER
PRIMED
THRESHOLD
SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS:
1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FOR
CONSTRUCTION, EXCEPT THAT OWNER SHALL BE
RESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLE
FEES, IF ANY.
2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OF
APPEALS, PLANNING BOARD AND/OR CONSERVATION
COMMISSION.
3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT.
4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLY
INCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED IN
THIS CONTRACT.
5.SITE SURVEY IS NOT INCLUDED
6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHER
HAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDE
ANY REMEDIATION OR ABATEMENT WORK.
7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BY
INTEGRITY OR INTEGRITY’S SUB-CONTRACTORS AND
SUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVE
DAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TO
THE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLE
FOR SUCH DELAYS.
8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITE
DUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BY
CONTRACTOR AT CONTRACTOR’S EXPENSE.
9.ALL UTILITIES USED DURING CONSTRUCTION ARE THE
OWNER’S RESPONSIBILITY.
10.CONTRACTOR SHALL PROMPTLY REMOVE ALL
CONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE AT
CONCLUSION OF CONSTRUCTION.
11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATION
STATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN
“MATCH EXISTING AS CLOSELY AS POSSIBLE FROM
CURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.
12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESS
OTHERWISE SPECIFIED.
13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAIN
UNLESS OTHERWISE SPECIFIED.
14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER.
15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.
16.ROOM FINISHES PER FINISH SCHEDULE.
3 3/4" UP
3" UP
EXISTING
SHELVES
TO REMAIN
SOFFIT TO
REMAIN
2x6
WALL
FRAME NEW FLOOR
SYSTEM HERE TO BE
FLUSH WITH EXISTING
BATH FLOORRECESSEDMEDICINE CABINETNICHEWALL KEY
= NEW 2x4 INTERIOR WALL
= NEW 2x6 INTERIOR WALL
= NEW 2x4 HALF WALL
ROLL-IN
SHOWER
WALNUT COUNTERTOPON THESE BUILT-INS ONLYSpecifications
Divisions 2-4: Site Work, Concrete, Masonry
1.None
Division 5: Metals
1.Supply & install ducting to bath fan via shortest route to exterior wall
Division 6: Wood & Plastics
1.2x6 KD spruce interior wall studs @ 16" O.C. where existing wall is being infilled or continued
2.2x4 KD spruce interior wall studs @ 16" O.C. where wall is new
3.2x4 KD spruce interior half-wall studs @ 16" O.C., 36" half-wall height
4.Build soffits to hide duct using 2x material
5.Frame opening for new window; exterior wall is assumed to be 2x6 wall. No obstructions are assumed, and
if obstructions exist, cost will be extra to contract.
Bath Floor
1.Frame new bath floor system with 2x4 KD spruce floor joists cut down to approx. 3"
2.3/4" T&G Advantech subfloor; top of new subfloor to be flush with existing subfloor
3.Floor to be pitched at 1/4" in 12" at roll-in shower using mud pan
Division 7: Thermal & Moisture Protection
Exterior Trim and Siding
1.Supply & install rough sawn pine shiplap siding to match existing in new window location; new siding will
not be a perfect match to existing
2.Supply & install trim at new window to match existing trim as closely as possible
Insulation
1.Insulate gaps at window with spray foam
2.Existing insulation to remain; if additional insulation is needed, cost will be extra to contract
Division 8: Doors & Windows
1.Window and door headers per schedule
Doors
1.Supply & install (1) hinged interior door per plan and schedule
2.Supply & install (1) hinged exterior glass door per plan and schedule
3.Supply & install door hardware TBD by allowance
Windows
1.Supply & install (1) Marvin Elevate window per plan and schedule
Division 9: Finishes
Wall and Ceiling Finishes
1.Supply & install 1/2" standard drywall to all new wall framing in den and all new ceiling framing
2.Supply & install 1/2" MR drywall to bath walls only
3.Apply (3) coats of joint compound & sand to smooth finish
Flooring
1.Supply & install tile finish flooring in bath and roll-in shower per schedule
2.Supply & install 5" wide finish flooring in den to match existing as closely as possible; tooth in to existing
3.Finish new wood flooring only with (3) coats of satin oil-based floor finish; screened between coats
Tile
1.Supply & install tile shower walls, niche sides and top, and soffit in shower only per schedule
Interior Trim and Carpentry
1.Supply & install 1x6 primed pine baseboard in bath and on new den walls, patch around built-ins
2.Supply & install 1x4 primed pine door casing with corner rosettes to new doors
3.Existing shelves to remain
Painting
1.Fill nail heads
2.Apply (2) coats Benjamin Moore Aura latex paint to walls, ceilings, and trim
3.Contract limited to (5) paint colors; (1) wall color per room, (1) ceiling color, and (1) trim color
4.Painting is limited to bath and affected walls of den and sunroom
Division 10: Specialties
1.Supply & install shower glass TBD by allowance
2.Supply & install bath accessories and recessed medicine cabinet per schedule
Division 11: Equipment
1.None
Division 12: Furnishings
1.Supply & install vanity cabinet per plan
2.Supply & install vanity countertop and backsplash and shower half-wall cap per plan and schedule
3.Cabinet hardware will be supplied with cabinet
4.Cabinet interiors and underside of wall cabinets will not match the exterior finish of the cabinets unless
specifically noted otherwise.
5.Supply & install built-in bookshelves in den per plan
6.Supply & install walnut countertop on indicated built-ins
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Supply & install sink, faucet, toilet, toilet seat, shower head, shower valve trim, slide bar, shower arm, and
line drain per plan and schedule
2.Cap existing pipe in wall if possible
Heating
1.Supply & install Reggio cast iron register in existing location (existing register is 9" x 11 1/4"); new register
to match existing house registers as closely as possible
Division 16: Electrical
1.See electrical plan for specificationsPIPE TOREMAIN; CAPIN WALL IFPOSSIBLENEW FLOOR
SLEEPERS RUN IN
THIS DIRECTION
NEW 5"
WIDE FINISH
FLOORING
BUILD SOFFIT TO
HIDE NEW DUCT
TOWEL
RING
TOWEL
BARS
TOILET
PAPER
HOLDER
PRIMED
THRESHOLD
SPECIFICATIONS DIVISION 1 – GENERAL REQUIREMENTS: 1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FORCONSTRUCTION, EXCEPT THAT OWNER SHALL BERESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLEFEES, IF ANY. 2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OFAPPEALS, PLANNING BOARD AND/OR CONSERVATIONCOMMISSION. 3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT. 4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLYINCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED INTHIS CONTRACT. 5.SITE SURVEY IS NOT INCLUDED6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHERHAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDEANY REMEDIATION OR ABATEMENT WORK. 7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BYINTEGRITY OR INTEGRITY’S SUB-CONTRACTORS ANDSUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVEDAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TOTHE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLEFOR SUCH DELAYS. 8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITEDUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BYCONTRACTOR AT CONTRACTOR’S EXPENSE. 9.ALL UTILITIES USED DURING CONSTRUCTION ARE THEOWNER’S RESPONSIBILITY. 10.CONTRACTOR SHALL PROMPTLY REMOVE ALLCONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE ATCONCLUSION OF CONSTRUCTION. 11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATIONSTATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN“MATCH EXISTING AS CLOSELY AS POSSIBLE FROMCURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESSOTHERWISE SPECIFIED. 13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAINUNLESS OTHERWISE SPECIFIED. 14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER. 15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.16.ROOM FINISHES PER FINISH SCHEDULE. 3 3/4" UP3" UPEXISTINGSHELVESTO REMAINSOFFIT TOREMAIN2x6WALLFRAME NEW FLOORSYSTEM HERE TO BEFLUSH WITH EXISTINGBATH FLOORRECESSEDMEDICINE CABINETNICHEWALL KEY= NEW 2x4 INTERIOR WALL= NEW 2x6 INTERIOR WALL= NEW 2x4 HALF WALLROLL-INSHOWERWALNUT COUNTERTOPON THESE BUILT-INS ONLYSpecifications
Divisions 2-4: Site Work, Concrete, Masonry
1.None
Division 5: Metals
1.Supply & install ducting to bath fan via shortest route to exterior wall
Division 6: Wood & Plastics
1.2x6 KD spruce interior wall studs @ 16" O.C. where existing wall is being infilled or continued
2.2x4 KD spruce interior wall studs @ 16" O.C. where wall is new
3.2x4 KD spruce interior half-wall studs @ 16" O.C., 36" half-wall height
4.Build soffits to hide duct using 2x material
5.Frame opening for new window; exterior wall is assumed to be 2x6 wall. No obstructions are assumed, and
if obstructions exist, cost will be extra to contract.
Bath Floor
1.Frame new bath floor system with 2x4 KD spruce floor joists cut down to approx. 3"
2.3/4" T&G Advantech subfloor; top of new subfloor to be flush with existing subfloor
3.Floor to be pitched at 1/4" in 12" at roll-in shower using mud pan
Division 7: Thermal & Moisture Protection
Exterior Trim and Siding
1.Supply & install rough sawn pine shiplap siding to match existing in new window location; new siding will
not be a perfect match to existing
2.Supply & install trim at new window to match existing trim as closely as possible
Insulation
1.Insulate gaps at window with spray foam
2.Existing insulation to remain; if additional insulation is needed, cost will be extra to contract
Division 8: Doors & Windows
1.Window and door headers per schedule
Doors
1.Supply & install (1) hinged interior door per plan and schedule
2.Supply & install (1) hinged exterior glass door per plan and schedule
3.Supply & install door hardware TBD by allowance
Windows
1.Supply & install (1) Marvin Elevate window per plan and schedule
Division 9: Finishes
Wall and Ceiling Finishes
1.Supply & install 1/2" standard drywall to all new wall framing in den and all new ceiling framing
2.Supply & install 1/2" MR drywall to bath walls only
3.Apply (3) coats of joint compound & sand to smooth finish
Flooring
1.Supply & install tile finish flooring in bath and roll-in shower per schedule
2.Supply & install 5" wide finish flooring in den to match existing as closely as possible; tooth in to existing
3.Finish new wood flooring only with (3) coats of satin oil-based floor finish; screened between coats
Tile
1.Supply & install tile shower walls, niche sides and top, and soffit in shower only per schedule
Interior Trim and Carpentry
1.Supply & install 1x6 primed pine baseboard in bath and on new den walls, patch around built-ins
2.Supply & install 1x4 primed pine door casing with corner rosettes to new doors
3.Existing shelves to remain
Painting
1.Fill nail heads
2.Apply (2) coats Benjamin Moore Aura latex paint to walls, ceilings, and trim
3.Contract limited to (5) paint colors; (1) wall color per room, (1) ceiling color, and (1) trim color
4.Painting is limited to bath and affected walls of den and sunroom
Division 10: Specialties
1.Supply & install shower glass TBD by allowance
2.Supply & install bath accessories and recessed medicine cabinet per schedule
Division 11: Equipment
1.None
Division 12: Furnishings
1.Supply & install vanity cabinet per plan
2.Supply & install vanity countertop and backsplash and shower half-wall cap per plan and schedule
3.Cabinet hardware will be supplied with cabinet
4.Cabinet interiors and underside of wall cabinets will not match the exterior finish of the cabinets unless
specifically noted otherwise.
5.Supply & install built-in bookshelves in den per plan
6.Supply & install walnut countertop on indicated built-ins
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Supply & install sink, faucet, toilet, toilet seat, shower head, shower valve trim, slide bar, shower arm, and
line drain per plan and schedule
2.Cap existing pipe in wall if possible
Heating
1.Supply & install Reggio cast iron register in existing location (existing register is 9" x 11 1/4"); new register
to match existing house registers as closely as possible
Division 16: Electrical
1.See electrical plan for specificationsPIPE TOREMAIN; CAPIN WALL IFPOSSIBLENEW FLOORSLEEPERS RUN INTHIS DIRECTIONNEW 5"WIDE FINISHFLOORINGBUILD SOFFIT TOHIDE NEW DUCTTOWELRINGTOWELBARSTOILETPAPERHOLDERPRIMEDTHRESHOLD
Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE3INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INS1
A-03
1
A-03
PROPOSED FIRST FLOOR PLAN
1/2" = 1'-0"
3'3"7'-4 7/16"2'-10 1/2"1 3/4"
1'-6"
3'3'-2"3'-6"6'-8"CABINET AND
COUNTERTOP
PER SCHEDULE
3" x 12"
BULLNOSE
EDGE TILE
GAZZINI12x12 TILEFIXTURES PERSCHEDULEMEDICINE
CABINET PER
SCHEDULE
REINSTALL
SAVED LIGHT
MIN. HEIGHT TO MEETIRC R305.1, EXCEPTION 2TILED
SOFFIT
3'4'-5 3/16"6 1/2"3"4'-5 1/2"
GAZZINI
12x12 TILE
SHELVES
TO REMAIN
MARMILINE
"SNOW" HALF-
WALL CAP
SHOWER GLASS
BY ALLOWANCE
3" x 12"
BULLNOSE TILE
TILED SOFFIT FOR DUCT
SOFFIT
FOR DUCT
FIXTURES PERSCHEDULESPECIFICATIONS DIVISION 1 – GENERAL REQUIREMENTS: 1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FORCONSTRUCTION, EXCEPT THAT OWNER SHALL BERESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLEFEES, IF ANY. 2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OFAPPEALS, PLANNING BOARD AND/OR CONSERVATIONCOMMISSION. 3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT. 4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLYINCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED INTHIS CONTRACT. 5.SITE SURVEY IS NOT INCLUDED
6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHER
HAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDE
ANY REMEDIATION OR ABATEMENT WORK.
7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BY
INTEGRITY OR INTEGRITY’S SUB-CONTRACTORS AND
SUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVE
DAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TO
THE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLE
FOR SUCH DELAYS.
8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITE
DUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BY
CONTRACTOR AT CONTRACTOR’S EXPENSE.
9.ALL UTILITIES USED DURING CONSTRUCTION ARE THE
OWNER’S RESPONSIBILITY.
10.CONTRACTOR SHALL PROMPTLY REMOVE ALL
CONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE AT
CONCLUSION OF CONSTRUCTION.
11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATION
STATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN
“MATCH EXISTING AS CLOSELY AS POSSIBLE FROM
CURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.
12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESS
OTHERWISE SPECIFIED.
13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAIN
UNLESS OTHERWISE SPECIFIED.
14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER.
15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.
16.ROOM FINISHES PER FINISH SCHEDULE.
FIXTURES
Location Fixture Supplied Manufac.Model Model #Size/Color/NOTES Qty.
By Name Spread Finish
FIRST-
FLOOR BATH VANITY INTEG ROOM & BOARD BERKELEY 34 1/2" x 21" x 33 1/4"WALNUT, BRUSHED
NICKEL HARDWARE FALSE DRAWER OVER DOUBLE DOOR VANITY ON LEGS 1
MEDICINE CABINET INTEG WEST ELM SEAMLESS MEDICINE CABINET 17" x 5" x 27"TBD RECESSED, WITH (3) GLASS SHELVES INSIDE 1
COUNTERTOP & BACKSPLASH INTEG ROOM & BOARD 4" BACK SPLASH ONLY, LEFT & RIGHT OVERHANGS, 3 FAUCET HOLES 8" APART 1
HALF-WALL CAP SUMMERLINS MARMILINE 1
SINK INTEG WHITE QUARTZ RECTANGULAR BOWL 1
FAUCET F. W. WEBB MOEN VOSS T6905BN 5 7/8" TALL BRUSHED NICKEL TWO-HANDLE LAVATORY FAUCET 1
FAUCET ROUGH-IN VALVE F. W. WEBB 9000 1
TOILET F. W. WEBB TOTO AQUIA MS446234CEMFG 15 1/2" x 28 1/4" x 29 13/16"COTTON DUAL FLUSH CLOSE COUPLED TOILET 1
TOILET SEAT F. W. WEBB AMERICAN STANDARD 505A.65PT WHITE ELONGATED TOILET SEAT WITH EVER-TITE BUMPERS 1
LINE DRAIN F. W. WEBB KERDI 48"PERFORATED DRAIN 1
SHOWER ARM F. W. WEBB DELTA U4993-SS 5 3/4" DEEP STAINLESS SHOWER ARM & FLANGE 1
SHOWER HEAD F. W. WEBB DELTA RP78575SS 5-SETTING RAINCAN SHOWER HEAD 1
SHOWER DIVERTER F. W. WEBB DELTA TRINSIC MONITOR 17 SERIES T27859-SS 6 5/8" DIAMETER STAINLESS TWO HANDLE VALVE TRIM WITH 3-SETTING INTEGRATED DIVERTER 1
SHOWER SLIDE BAR F. W. WEBB DELTA 51600-SS ADJUSTABLE SLIDE BAR / GRAB BAR ASSEMBLY WITH ELBOW 1
HAND SHOWER F. W. WEBB DELTA 59361-SS-PK 3 7/8" x 8 3/4"STAINLESS 1.75 GPM 4-SETTING 1
SHOWER ROUGH F. W. WEBB DELTA R22000 MULTICHOICE UNIVERSAL INTEGRATED SHOWER DIVERTER ROUGH 1
SHOWER GLASS TBD TBD BY ALLOWANCE 1
TOWEL RING F. W. WEBB DELTA COMPEL 77146-SS STAINLESS 1
TOWEL BAR F. W. WEBB DELTA TRINSIC 759240-SS 24" LONG STAINLESS 2
TOILET PAPER HOLDER F. W. WEBB DELTA TRINSIC 75950-SS 7" LONG BAR STAINLESS 1
ROBE HOOK F. W. WEBB DELTA TRINSIC 75935-SS 2 1/4" W x 3 1/8" H STAINLESS 1
FINISH SCHEDULE
Room Name Floor Material Floor Finish Base & Case Material Base & Case Finish Wall Material Wall Finish Ceiling Material Ceiling Finish Notes
Bath "Flecopio" 12" x 24" tile, running bond Grout TBD by allowance 1x6 primed pine baseboard and
1x4 primed pine door casing Paint, Color TBD 1/2" MR Drywall Smooth & Paint 1/2" Standard Drywall Smooth & Paint Tile floors to run under vanity; door
to have primed wood threshold
Shower "Flecopio" 12" x 24" tile, running bond Grout TBD by allowance N/A N/A Gazzini 12x12, "White Dolomite Natural"Grout TBD by allowance 1/2" Standard Drywall Smooth & Paint Marmiline half-wall cap
Den
In area where bricks were removed,
supply & install 5" wide finish flooring to
match existing as closely as possible
Finish new wood flooring with
(3) coats of satin oil-based
finish; screened between coats
1x6 primed pine baseboard on
new walls only and 1x4 primed
pine door casing at new door only
Paint, Color TBD 1/2" Standard Drywall Smooth & Paint 1/2" Standard Drywall Smooth & Paint
DOOR SCHEDULE
MANUFACTURER KEY LABEL FL.QTY.JAMB WIDTH HEIGHT R/O DESCRIPTION EXT. FINISH INT. FINISH SCREEN GRILL TEMP.HINGE
FINISH
HEADER &
JACK STUDS HANDLE LOCK BORE
D01 2668 1 1 6 9/16"2'-6"6'-8"2'-8 1/4" x
6'-10 1/2"LH 6-PANEL DOOR PAINT,
COLOR TBD
PAINT,
COLOR TBD N/A N/A N/A SATIN
NICKEL N/A TBD BY
ALLOWANCE PRIVACY SINGLE
THERMA-TRU D02 3066 1 1 6 9/16"3'-0"6'-6"3'-2 1/2" x
6'-8 1/2"
LH S-2000-LE SMOOTH
STAR FULL LITE
GLASS DOOR; LOW E
WITH ARGON GAS
PAINT,
COLOR TBD
PAINT,
COLOR TBD N N BRUSHED
NICKEL
USE
EXISTING
TBD BY
ALLOWANCE TBD SINGLE
TOTAL 2
3 3/4" UP3" UPEXISTINGSHELVESTO REMAINSOFFIT TOREMAIN2x6WALLFRAME NEW FLOORSYSTEM HERE TO BEFLUSH WITH EXISTINGBATH FLOORRECESSEDMEDICINE CABINETNICHEWALL KEY= NEW 2x4 INTERIOR WALL= NEW 2x6 INTERIOR WALL= NEW 2x4 HALF WALLROLL-INSHOWERWALNUT COUNTERTOPON THESE BUILT-INS ONLYSpecifications
Divisions 2-4: Site Work, Concrete, Masonry
1.None
Division 5: Metals
1.Supply & install ducting to bath fan via shortest route to exterior wall
Division 6: Wood & Plastics
1.2x6 KD spruce interior wall studs @ 16" O.C. where existing wall is being infilled or continued
2.2x4 KD spruce interior wall studs @ 16" O.C. where wall is new
3.2x4 KD spruce interior half-wall studs @ 16" O.C., 36" half-wall height
4.Build soffits to hide duct using 2x material
5.Frame opening for new window; exterior wall is assumed to be 2x6 wall. No obstructions are assumed, and
if obstructions exist, cost will be extra to contract.
Bath Floor
1.Frame new bath floor system with 2x4 KD spruce floor joists cut down to approx. 3"
2.3/4" T&G Advantech subfloor; top of new subfloor to be flush with existing subfloor
3.Floor to be pitched at 1/4" in 12" at roll-in shower using mud pan
Division 7: Thermal & Moisture Protection
Exterior Trim and Siding
1.Supply & install rough sawn pine shiplap siding to match existing in new window location; new siding will
not be a perfect match to existing
2.Supply & install trim at new window to match existing trim as closely as possible
Insulation
1.Insulate gaps at window with spray foam
2.Existing insulation to remain; if additional insulation is needed, cost will be extra to contract
Division 8: Doors & Windows
1.Window and door headers per schedule
Doors
1.Supply & install (1) hinged interior door per plan and schedule
2.Supply & install (1) hinged exterior glass door per plan and schedule
3.Supply & install door hardware TBD by allowance
Windows
1.Supply & install (1) Marvin Elevate window per plan and schedule
Division 9: Finishes
Wall and Ceiling Finishes
1.Supply & install 1/2" standard drywall to all new wall framing in den and all new ceiling framing
2.Supply & install 1/2" MR drywall to bath walls only
3.Apply (3) coats of joint compound & sand to smooth finish
Flooring
1.Supply & install tile finish flooring in bath and roll-in shower per schedule
2.Supply & install 5" wide finish flooring in den to match existing as closely as possible; tooth in to existing
3.Finish new wood flooring only with (3) coats of satin oil-based floor finish; screened between coats
Tile
1.Supply & install tile shower walls, niche sides and top, and soffit in shower only per schedule
Interior Trim and Carpentry
1.Supply & install 1x6 primed pine baseboard in bath and on new den walls, patch around built-ins
2.Supply & install 1x4 primed pine door casing with corner rosettes to new doors
3.Existing shelves to remain
Painting
1.Fill nail heads
2.Apply (2) coats Benjamin Moore Aura latex paint to walls, ceilings, and trim
3.Contract limited to (5) paint colors; (1) wall color per room, (1) ceiling color, and (1) trim color
4.Painting is limited to bath and affected walls of den and sunroom
Division 10: Specialties
1.Supply & install shower glass TBD by allowance
2.Supply & install bath accessories and recessed medicine cabinet per schedule
Division 11: Equipment
1.None
Division 12: Furnishings
1.Supply & install vanity cabinet per plan
2.Supply & install vanity countertop and backsplash and shower half-wall cap per plan and schedule
3.Cabinet hardware will be supplied with cabinet
4.Cabinet interiors and underside of wall cabinets will not match the exterior finish of the cabinets unless
specifically noted otherwise.
5.Supply & install built-in bookshelves in den per plan
6.Supply & install walnut countertop on indicated built-ins
Division 13: Special Construction
1.None
Division 14: Conveying Systems
1.None
Division 15: Mechanical
Plumbing
1.Supply & install sink, faucet, toilet, toilet seat, shower head, shower valve trim, slide bar, shower arm, and
line drain per plan and schedule
2.Cap existing pipe in wall if possible
Heating
1.Supply & install Reggio cast iron register in existing location (existing register is 9" x 11 1/4"); new register
to match existing house registers as closely as possible
Division 16: Electrical
1.See electrical plan for specificationsPIPE TOREMAIN; CAPIN WALL IFPOSSIBLENEW FLOORSLEEPERS RUN INTHIS DIRECTIONNEW 5"WIDE FINISHFLOORINGBUILD SOFFIT TOHIDE NEW DUCTTOWELRINGTOWELBARSTOILETPAPERHOLDER
WINDOW SCHEDULE
MANUFACTURER KEY LABEL FL.QTY.JAMB WIDTH HEIGHT R.O.DESCRIPTION EXT. FINISH INT. FINISH SCREEN GRILL TEMP.HARDWARE FINISH HEADER & JACK STUDS EGRESS
MARVIN INTEGRITY WOOD ULTREX W01 ITGL 4824 1 1 6 9/16"4'-0"2'-0 1/8"4'-0 3/4" x 2'-0 3/8"XO GLIDER; LOW E WITH ARGON GLASS;STONE WHITE PRE-FINISHED WHITE Y GBG N WHITE (2) 2x8 & 2 N
PRIMEDTHRESHOLD
3'4'-5 3/16"3"3'
11 1/4"1'1'-0 3/4"6'-8"1'1'SHOWER GLASS
BY ALLOWANCE
GAZZINI
12x12 TILE
MARMILINE
"SNOW" HALF-
WALL CAP
3" x 12"
BULLNOSE
TILE
3" x 12"
BULLNOSE TILE
MIN. HEIGHT TO MEETIRC R305.1, EXCEPTION 2TILED
SOFFIT
NICHE
Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE4INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INS1
A-04
1
A-04
PROPOSED ELEVATION
1/2" = 1'-0"
2
A-04
2
A-04
PROPOSED ELEVATION
1/2" = 1'-0"
3
A-04
3
A-04
PROPOSED ELEVATION
1/2" = 1'-0"
4
A-04
4
A-04
PROPOSED
SCHEDULES
TO REMAINTO REMAINTO REMAINTO REMAINTO REMAINTO REMAIN1 11/16"7'-6"3/4"2'-6"3'2'-6"
ALL DIMENSIONS ARE FINISH DIMENSIONS
FACE FRAME
WITH 1x2 MAPLE
3/4" PAINT GRADE PLYWOOD
DOORS WITH 1/2" MAPLE STILES
WIRE (1)
OUTLET
FLAT STOCK
ONLY, NO
CROWN
MOLDING
TO REMAINTO REMAINTO REMAINTO REMAINTO REMAINTO REMAIN
3/4"2'-3"2'-6"2'-3"1 11/16"4'-4 3/4"3'-1 1/4"ALL DIMENSIONS ARE FINISH DIMENSIONS
BUILD SOFFIT TO HIDE NEW
DUCT, EXACT SIZE TBD
FACE FRAME
WITH 1x2 MAPLE
WIRE (1) OUTLET ON
BACK OF BOOKCASE
FACE FRAME
WITH 1x2 MAPLE
WALNUT
COUNTERTOP
FLAT STOCK
ONLY, NO
CROWN
MOLDING
1'-6"1 11/16"7'-6"4'-6 1/4"2'-7 3/4"4"3"1'-3"1'-1"3/4"1'-0 7/8"3/4"1'-0 7/8"3/4"1'3/4"1'-2 3/4"3/4"1'-2"BUILD FRAME AND SHELVES OUT OF3/4" PAINT GRADE PLYWOOD; SHELVESON ADJUSTABLE STANDARDS3'-1 1/4"4'-4 3/4"1 11/16"1 1/2"2'-7 3/4"4"1'-0 1/2"3/4"1'-0 3/8"3/4"1'-0 3/8"3/4"1'1 1/2"1'-2"3/4"1'-2"BUILD FRAME AND SHELVES OUT OF3/4" PAINT GRADE PLYWOOD; SHELVESON ADJUSTABLE STANDARDSDevelopment & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE5INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INS3
A-05
3
A-05
PROPOSED BOOKCASE ELEVATION
1/2" = 1'-0"
1
A-05
1
A-05
PROPOSED BOOKCASE ELEVATION
1/2" = 1'-0"
2
A-05
2
A-05
PROPOSED BOOKCASE SECTION
1/2" = 1'-0"
4
A-05
4
A-05
PROPOSED BOOKCASE ELEVATION
1/2" = 1'-0"
REMOVE &
DISCARD TO REMAINREMOVE & DISCARDREMOVE & DISCARDTO REMAINTO REMAIN
Division 16: Electrical Demo.
1.All electrical to remain in existing locations unless otherwise specified
2.No work to existing house smoke/CO system included
3.Remove & discard switch and outlet in bathroom per plan
4.Remove & save vanity light
5.Relocate (1) outlet per plan
DEN
ETR ETR
ETR
ETR
ETR
REMOVE &
DISCARD
REMOVE & SAVE LIGHTREMOVE & DISCARDSWITCH AND OUTLETETR
BATH #1
SUNROOMRELOCATE
ELECTRICAL - DATA - AUDIO LEGEND
Division 16: Electrical Demo.
1.All electrical to remain in existing locations unless otherwise specified
2.No work to existing house smoke/CO system included
3.Remove & discard switch and outlet in bathroom per plan
4.Remove & save vanity light
5.Relocate (1) outlet per plan
ETR ETR
ETR
ETR
ETR
REMOVE &
DISCARD
REMOVE & SAVE LIGHTREMOVE & DISCARDSWITCH AND OUTLETETR
RELOCATE Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY
NWBALDI / YALEN RESIDENCE6INTEGRITYA-
SHEET:
DATE:
2/21/2020CONTRACT &BUILDING PERMIT SET136 CHESTNUT ST, FLORENCE, MA 01062BATH AND BUILT-INS1
E-01
1
E-01
EXISTING ELECTRICAL PLAN
1/2" = 1'-0"E-1
D01 - 2668 TO REMAIND02 - 3066ITGL 4824TO REMAINTO REMAIN
SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS:
1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FOR
CONSTRUCTION, EXCEPT THAT OWNER SHALL BE
RESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLE
FEES, IF ANY.
2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OF
APPEALS, PLANNING BOARD AND/OR CONSERVATION
COMMISSION.
3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT.
4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLY
INCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED IN
THIS CONTRACT.
5.SITE SURVEY IS NOT INCLUDED
6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHER
HAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDE
ANY REMEDIATION OR ABATEMENT WORK.
7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BY
INTEGRITY OR INTEGRITY’S SUB-CONTRACTORS AND
SUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVE
DAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TO
THE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLE
FOR SUCH DELAYS.
8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITE
DUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BY
CONTRACTOR AT CONTRACTOR’S EXPENSE.
9.ALL UTILITIES USED DURING CONSTRUCTION ARE THE
OWNER’S RESPONSIBILITY.
10.CONTRACTOR SHALL PROMPTLY REMOVE ALL
CONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE AT
CONCLUSION OF CONSTRUCTION.
11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATION
STATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN
“MATCH EXISTING AS CLOSELY AS POSSIBLE FROM
CURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.
12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESS
OTHERWISE SPECIFIED.
13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAIN
UNLESS OTHERWISE SPECIFIED.
14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER.
15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.
16.ROOM FINISHES PER FINISH SCHEDULE.
GFCI
Division 16: Electrical
1.All electrical to remain in existing locations unless otherwise
specified
2.All new electrical device locations to be confirmed w/ owner in field;
Cost of changes will be additional to contract
3.No work to existing house smoke/CO system included
4.All switches to be Decora style; Color white / ivory
5.All outlets to be duplex style; Color white/ivory
6.Wire (1) GFCI outlet per code
7.Wire (2) new wall outlets in den, (1) inside new built-in bookcase
8.Relocate (1) outlet to face of new built-ins
9.Install (1) saved wall sconce in new location on new single switch
10.Supply & install (1) Panasonic Whispergreen FV-05-11VKL1 fan /
light combo on separate switching
DEN
ETR ETR
ETR
ETR
ETR
ETR
REUSESAVEDNEWNEWNEWFAN
LIGHT
BATH #1
SUNROOMNEWNEW
RELOCATE OUTLET
HIGHER ON WALL AND
IN FRONT OF REAR
PANEL OF BUILT-IN
SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS:
1.CONTRACTOR WILL OBTAIN ALL NECESSARY PERMITS FOR
CONSTRUCTION, EXCEPT THAT OWNER SHALL BE
RESPONSIBLE FOR WATER, SEWER, ELECTRIC, AND CABLE
FEES, IF ANY.
2.CONTRACT EXCLUDES APPROVALS BY ZONING BOARD OF
APPEALS, PLANNING BOARD AND/OR CONSERVATION
COMMISSION.
3.CONTRACT EXCLUDES ARCHITECTURAL OVERSIGHT.
4.ANY OTHER REQUIREMENTS FROM TOWN NOT EXPLICITLY
INCLUDED IN THE PLANS OR SPECS ARE NOT INCLUDED IN
THIS CONTRACT.
5.SITE SURVEY IS NOT INCLUDED
6.CONTRACTOR HAS NOT TESTED FOR ASBESTOS AND OTHER
HAZARDOUS TESTING AND CONTRACT DOES NOT INCLUDE
ANY REMEDIATION OR ABATEMENT WORK.
7.ALL OWNER-SUPPLIED ITEMS ARE NOT UNDER WARRANTY BY
INTEGRITY OR INTEGRITY’S SUB-CONTRACTORS AND
SUPPLIERS. ANY OWNER-SUPPLIED ITEMS THAT ARRIVE
DAMAGED, LATE OR INCOMPLETE MAY CAUSE DELAYS TO
THE SCHEDULE AND INTEGRITY WILL NOT BE HELD LIABLE
FOR SUCH DELAYS.
8.ALL CONSTRUCTION DEBRIS WILL BE PLACED IN AN ONSITE
DUMPSTER PROVIDED BY CONTRACTOR AND REMOVED BY
CONTRACTOR AT CONTRACTOR’S EXPENSE.
9.ALL UTILITIES USED DURING CONSTRUCTION ARE THE
OWNER’S RESPONSIBILITY.
10.CONTRACTOR SHALL PROMPTLY REMOVE ALL
CONSTRUCTION EQUIPMENT AND MATERIALS FROM SITE AT
CONCLUSION OF CONSTRUCTION.
11.WHEREVER CONTRACTOR DRAWING OR SPECIFICATION
STATES, “MATCH EXISTING,” SUCH LANGUAGE SHALL MEAN
“MATCH EXISTING AS CLOSELY AS POSSIBLE FROM
CURRENTLY AVAILABLE STOCK ITEMS PURCHASED LOCALLY”.
12.ALL DIMENSIONS ARE FRAMING TO FRAMING UNLESS
OTHERWISE SPECIFIED.
13.ALL EXISTING STRUCTURAL COMPONENTS TO REMAIN
UNLESS OTHERWISE SPECIFIED.
14.ALL APPLIANCES, FURNITURE, ETC. SUPPLIED BY OWNER.
15.FRAME & FINISH NEW WALLS PER PLAN AND SPECIFICATIONS.
16.ROOM FINISHES PER FINISH SCHEDULE.
ELECTRICAL - DATA - AUDIO LEGEND
Division 16: Electrical
1.All electrical to remain in existing locations unless otherwise
specified
2.All new electrical device locations to be confirmed w/ owner in field;
Cost of changes will be additional to contract
3.No work to existing house smoke/CO system included
4.All switches to be Decora style; Color white / ivory
5.All outlets to be duplex style; Color white/ivory
6.Wire (1) GFCI outlet per code
7.Wire (2) new wall outlets in den, (1) inside new built-in bookcase
8.Relocate (1) outlet to face of new built-ins
9.Install (1) saved wall sconce in new location on new single switch
10.Supply & install (1) Panasonic Whispergreen FV-05-11VKL1 fan /
light combo on separate switching
ETR ETR
ETR
ETR
ETR
ETR
REUSESAVEDNEWNEWNEWFAN
LIGHT NEWNEW
RELOCATE OUTLET
HIGHER ON WALL AND
IN FRONT OF REAR
PANEL OF BUILT-IN Development & Construction, Inc.110 Pulpit Hill RoadAmherst, Ma 01002413-549-7919 FAX: 413-549-7918 EMAIL: INFO@INTEGBUILD.COMDESIGN BY