LWCF-quarterly-RockyHill-WF12-31-19PROGRESS REPORT: Land and Water Conservation Fund
Reporting period from: 9/1/2019 to: 12/31/2019
Project Name: Rocky Hill Greenway TrailProject Number: LWFC#25-00536Municipality: Northampton
Status of project and reason for delays, if any: Project complete, final billing once all checks clear
Acquisition Complete N/A
Design % Complete 100%
Construction % Complete 100%
Status of project costs and budget: Project completed, on-time and on-budget
Work completed this quarter: Construction completed
Work planned next quarter: Additional work funded by the City with funds beyond and above our LWCF match- additional drainage improvements to ensure maximum project longevity
Anticipated reimbursement schedule for construction projects:
1st & Final RequestDATE: 1/08/2020AMOUNT:$200,000% Complete: 100%
PROJECT SCHEDULE TO COMPLETION
Use These Symbols: Proposed Action ------Actually Completed xxxxx
Year/Quarter
Q3
FY19
Q4
FY19
Q1
FY20
Q2
FY20
Q3
FY20
DCS Accepted Appraisal
n/a
Municipal Appropriation
XXX
Deed Recorded
XXX
Design Contract
XXX
Survey (If Required)
n/a
Final Designs – DCS Approved
XXX
Bidding Period
XXX
Construction Contract Award
XXX
Construction Period
XXX
XXX
Final Inspection (DCS)
XXX
Submission of Final Reimbursement Request
XXX
Project Close-Out
XXX
Project Manager:Wayne Feiden Phone: (413) 587-1265