Massachusetts Electric Company&Nantucket Electric Company(d/b/a National Grid) M.D.P.U. 1248
Certificate of Completion for Simplified Process Interconnections
Installation Information: ❑ Check if owner-installed
Interconnecting Customer:Jo Lane Contact Person:
Mailing Address:6 Service Center Road
City: Northampton State: MA Zip Code:01060
Telephone(Daytime): 413-296-2702 (Evening):
Facsimile Number: E-Mail Address: to@jolanders.com
Address of Facility(if different from above):
Electrical Contractor's Name(if appropriate): Valley Solar
Mailing Address: PO BOX 60627
City: Florence State: MA Zip Code: 01062
Telephone(Daytime): 413-584-8844 (Evening):
Facsimile Number: E-Mail Address: Info@valleysolar.solar .3
erv,A.A .-4 /Zs1zoz2
License number:
Date of approval to install Facility granted by National Grid: 7/27/2021
Application ID number:00370816
Inspection:
The system has been installed and inspected in compliance with the local Building/Electrical Code of
(City/County):
Signed(Lo Electri Wiring Inspector, or attach signed electrical inspection):
Name(printed): 6ct rn� LU Date: / (fc• ak\
License#: 4/o (,(1,(
As a condition of interconnection you are required to send/e-mail a copy of this form along with a copy of the
signed electrical permit to National Grid:
National Grid
Attn: Distributed Generation
40 Sylvan Rd
Waltham,MA 02451
E-mail: distributed.generation@a,nationalgrid.com
Massachusetts:http://www.nationalgridus.co slectric/home/energyeff/distributed generation.asl