Loading...
4.12.17_ 100 Draft Northampton Pleasant St SpecsCITY OF NORTHAMPTON, MASSACHUSETTS CONTRACT AND SPECIFICATIONS FOR NORTHAMPTON DRAINAGE RELOCATION APRIL 2017 Draft Copy for City, MassDOT, and Pan Am Review Northampton Drainage Relocation TABLE OF CONTENTS 20164277.003A TOC - 1 TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS SECTION NO.SECTION TITLE 00020 Invitation to Bid 00100 Instructions to Bidders 00301 Bid Form 00430 Bid Bond (C-430-2002) 00500 Agreement 00510 Notice of Award (C-510-2002) 00550 Notice to Proceed (C-550-2002) 00610 Performance Bond (C-610-2002) 00615 Payment bond (C-615-2002) 00625 Certificate of Substantial Completion (C-625-2002) 00710 General Conditions (C-710-2002) 00800A Supplementary Conditions 00941 Change Order (C-941-2002) DIVISION 1 – GENERAL REQUIREMENTS SECTION NO.SECTION TITLE 01010 Summary of Work 01040 01050 01060 01069 Project Coordination Field Engineering Permits and Regulatory Requirements Massachusetts Laws 01110 Environmental Protection Procedures 01150 Measurement and Payment 01200 Project Meetings 01300 Submittal Procedures 01346 As-Built Drawings 01380 01390 Construction Photographs Preconstruction Survey 01400 Quality Assurance 01500 Temporary Facilities and Controls 01568 Erosion Control, Sedimentation and Containment of Construction Materials 01600 Control of Materials 01610 Delivery, Storage and Handling 01700 Contract Closeout 01740 Warranties and Bonds 01850 Traffic Management Northampton Drainage Relocation TABLE OF CONTENTS 20164277.003A TOC - 2 DIVISION 2 – SITE CONSTRUCTION SECTION NO.SECTION TITLE 02010 02015 Subsurface Investigation Geotechnical Instrumentation and Monitoring 02051 Demolition and Abatement 02100 Site Preparation 02140 Dewatering 02160 Temporary Excavation Support Systems 02210 Earth Excavation, Backfill, Fill and Grading 02273 Geotextile Fabric Water Mains (including disinfection) (To be Included in Bid Docs) Drainage Pipe (To be included in Bid Docs) 02431 Catch Basins 02444 Chain Link Fence and Gate 02498 Restoration of Disturbed Areas 02525 Paving, Sidewalks and Curbing 02604 Drain Manholes 02715 Precast Reinforced Concrete Box Culvert 02761 Stormwater Bypass Flow Handling DIVISION 3 – CONCRETE SECTION NO.SECTION TITLE 03346 Cast-In-Place Concrete DIVISION 7 – THERMAL AND MOISTURE PROTECTION SECTION NO.SECTION TITLE 07160 Bituminous Dampproofing APPENDIX A – Soil Borings APPENDIX B – Wage Rates APPENDIX C – USACE Permitting Documentation APPENDIX D – Notice of Intent and Order of Conditions Documentation END OF TABLE OF CONTENTS Northampton Drainage Relocation INVITATION TO BID 20164277.003A 00020 -1 SECTION 00020 INVITATION TO BID NORTHAMPTON DRAINAGE RELOCATION Sealed Bids for the Northampton Drainage Relocation will be received at the Northampton Department of Planning & Sustainability, 210 Main Street, Northampton, MA 01060, Attn.: Wayne Feiden, FAICP, Director Planning & Sustainability, until 2:00 PM of Monday, May 8, 2017 at which place and time said Bids will be publicly opened and read aloud. The work includes construction of approximately 330 linear feet of gravity box culvert storm drain and appurtenant work. Drawings and other Contract Documents may be examined at the Northampton Department of Public Works, Office of the City Engineer, 125 Locust Street, Northampton, MA 01060, Monday-Friday 9:00 AM to 4:00 PM. To obtain Contract Documents, a $50 non-refundable deposit is required. Cash will not be accepted. Drawings and other Contract Documents can be picked up at Kleinfelder (Cambridge Office), located at 215 First Street, Suite 320, Cambridge, MA 02142, Attn: Joseph Maliawco. Drawings and other Contract Documents will be mailed, if requested, upon receipt of a street address (not a P.O. Box) suitable for commercial carrier delivery, and an additional check in the amount of $25.00, payable to Kleinfelder Northeast as a non-refundable postage and handling fee. Do not combine amounts into one check. Requests for Drawings and other Contract Documents to be mailed should be sent to Kleinfelder Northeast, 215 First Street, Suite 320, Cambridge, MA 02142, Attn: Joseph Maliawco. Questions regarding the Bid shall be submitted in writing to Kleinfelder, Attn: Joseph Maliawco, 215 First Street, Suite 320, Cambridge, MA 02142, or jmaliawco@kleinfelder.com at least seven (7) days before the established date for receipt of Bids. Each general bid shall be accompanied by a bid security in the form of a certified, treasurer's or cashier's check, bid bond or cash in the amount of 5 percent of the value of the Bid. Every bid bond, every performance bond and every payment bond issued for any construction work in the Commonwealth shall be the bond of a surety company organized pursuant to Section 105 of Chapter 175 or of a surety company authorized to do business in Commonwealth under the provisions of Section 106 of said Chapter 175 and be approved by the U. S. Department of Treasury and acceptable as sureties and reinsurers on federal bonds under Title 31 of the United States Code, sections 9304 to 9308. All work must be completed within 158 calendar days, commencing ten (10) days following effective date of the Agreement. Successful General bidder must furnish six (6) copies of 100 percent Construction Performance Bond and 100 percent Construction Payment Bond. Northampton Drainage Relocation INVITATION TO BID 20164277.003A 00020 -2 The Owner reserves the right to waive any informalities or to reject any or all bids. Wage rates for this project are subject to the minimum wage rates per M.G.L., Chapter 149, Sections 26 to 27G, inclusive. No Bidder may withdraw his/her Bid for a period of sixty (60) business days, excluding Saturdays, Sundays, and legal holidays, after the actual date of the opening of the Bids. The bidding and award of the Contract shall be in full compliance with Sections 39M inclusive of Chapter 30 of the General Laws of the Commonwealth of Massachusetts as last revised. US Army Corps of Engineers permit NAE-2017-351 has been obtained through the City. The contractor is to follow all the conditions in this permit. A non-mandatory pre-bid conference will be held on Wednesday April 19, 2017 at 10:00 AM at the Northampton Department of Planning & Sustainability. City of Northampton, Massachusetts Wayne Feiden, FAICP, Director Department of Planning & Sustainability END OF SECTION 00020 Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -1 SECTION 00100 INSTRUCTIONS TO BIDDERS Article 1. Receipt and Opening of Bids Article 2. Deposit on Drawings and Documents Article 3. Ability and Experience of Bidder Article 4. Information not Guaranteed Article 5. Borings Article 6. Easements Article 7. (Not used) Article 8. Bidders to Investigate Article 9. Questions Regarding Drawings and Documents Article 10. Blank Form for Bid Article 11. (Not Used) Article 12. Bid Security Article 13. Withdrawal of Bids Article 14. Right to Reject Bids Article 15. Comparison of Bids Article 16. Reduction in Scope of Work Article 17. Contract Bonds Article 18. Execution of Agreement Article 19. Insurance Certificates Article 20. Massachusetts Sales and Use Tax Article 21. Massachusetts Wage Rates Article 22. Utility Underground Plant Damage Prevention System Article 23. Competitive Bidding Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -2 ARTICLE 1. RECEIPT AND OPENING OF BIDS 1.1 Sealed Bids for the work of this Contract will be received at the time and place indicated in the Invitation to Bid. Any bid received after the time and date specified shall not be considered. 1.2 OWNER may consider informal any Bid not prepared and submitted in accordance with the provisions hereof. 1.3 Bidders are cautioned that it is the responsibility of each individual bidder to assure that his or her bid is in the possession of the responsible official or designated alternate prior to the stated time and at the place of the Bid Opening. Owner is not responsible for bids delayed by mail and/or delivery services, of any nature. 1.4 Forthwith after the time limits for the filing of general bids and sub-bids, such bids shall be publicly opened and read aloud. 1.5 The bidding procedure shall be in accordance with the provisions of Chapter 30 of the General Laws of Massachusetts as amended to date. 1.6 If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope and labeled “General Bid, Northampton Drain Replacement” and addressed to Wayne Feiden, FAICP, Director Planning & Sustainability, Department of Planning & Sustainability, 210 Main Street, Northampton, MA 01060. ARTICLE 2. DEPOSIT ON DRAWINGS AND DOCUMENTS 2.1 Upon award of the Contract, the Contractor will be provided with two (2) copies of contract drawings and specifications. ARTICLE 3. ABILITY AND EXPERIENCE OF BIDDER 3.1 No award will be made to any bidder who cannot satisfy the Owner that he has sufficient ability and experience in this class of work and sufficient capital and plant to enable him to prosecute and complete the Work successfully within the time named. The Owner's decision or judgment on these matters shall be final, conclusive, and binding. 3.2 The Owner may make such investigations as it deems necessary, and the Bidder shall furnish to the Owner, under oath if so required, all such information and data for this purpose as the Owner may request. 3.3 All bidders shall submit with their bids, documentation to demonstrate experience and qualifications including but not limited to: Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -3 A. The bidder shall have been in the business of providing the product(s) and or service(s) for which it is submitting prices herein, for a period of no less than fifteen (15) consecutive years prior to the bid opening date. B. A resume and references of the bidder’s construction superintendent to be assigned to the work of this Contract demonstrating at least fifteen (15) years successful experience in this class of work. C. Project descriptions and references for at least five (5) successfully completed projects within the past five (5) years demonstrating experience in storm drain installation and decommisioning. D. For each of the five (5) projects listed in Item C, provide the bid amount and contract award amount. E. A list of all outstanding claims and disputes for projects for which the bidder has filed notice with the Owner. Bidders shall submit the above information with their bid package. Failure to submit the requested data or inability to show sufficient qualification as determined by the Owner shall be reason for disqualification of the Bidder. The Owner reserves the right to waive any or all qualification requirements if it feels it is in the best interest of the City of Northampton. The City reserves the right to reject any or all Bids, if it is in the public interest to do so. The City reserves the right to reject any or all Bids, if it determines that the Bidder does not possess the qualifications to perform the Work specified in the Bidding Documents. The City reserves the right to reject the Bid of any Bidder who the City has determined has not completed a prior project, whether with the City or elsewhere, because of the fault of the Bidder, its Subcontractors or employees; has been declared in default on a prior contract whether with the City or elsewhere; has failed to complete a prior project in a timely fashion whether with the City or elsewhere; based on its work record, is not capable of performing the work within Contract whether due to lack of sufficient prior experience, as determined by the City, or any other reason; has a work record of its Subcontractors demanding direct payment from the City; has a work record of its Subcontractors, employees or material suppliers complaining to the City or other awarding authority regarding the Bidder’s failure to pay them; has a record of complaints made to the City or other awarding authority by persons offended by the behavior of the Bidder, its Subcontractors or employees; or has a record of its failure to comply with the Commonwealth and/or City laws or requirements. "Work record" or "record" constitutes a minimum of one event in the work history of the Bidder. Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -4 ARTICLE 4. INFORMATION NOT GUARANTEED 4.1 All information given on the Drawings or in the other Contract Documents relating to subsurface and other conditions, natural phenomena, existing pipes, and other structures is from the best sources at present available to the Owner. All such information is furnished only for the information and convenience of bidders and is not guaranteed. 4.2 It is agreed and understood that the Owner does not warrant or guarantee that the subsurface or other conditions, natural phenomena, existing pipes or other structures encountered during construction will be the same as those indicated on the Drawings or in the other Contract Documents. 4.3 It is agreed further and understood that no bidder or Contractor shall use or be entitled to use any of the information made available to him or obtained in any examination made by him in any manner as a basis of or ground for any claim or demand against the Owner or the Engineer, arising from or by reason of any variance which may exist between the information made available and the actual subsurface or other conditions, natural phenomena, existing pipes or other structures actually encountered during the construction work, except as may otherwise be expressly provided for in the Contract Documents. ARTICLE 5. SUBSURFACE INVESTIGATION 5.1 Subsurface investigations have been made in the approximate locations indicated on the drawings. Investigation logs are bound at the back of the documents in Appendix A. 5.2 Subsurface information has been obtained for the purpose of design of the project, and such data indicated on the drawings may be limited and subject to error or misunderstandings. 5.3 Groundwater levels shown on the boring logs were reported at the time subsurface investigations were made and do not necessarily represent permanent groundwater levels. 5.4 The conditions affecting the cost or quantity of the work to be done may differ from the conditions which may be indicated by the data obtained from the subsurface investigations. The bidder shall make for his/her own information all additional borings and tests necessary to enable him to fairly and accurately estimate the figures which he/she records in the schedule of prices. ARTICLE 6. EASEMENTS 6.1 As indicated on the drawings, a portion of the work will be located in easements through private property obtained or which will be obtained by the Owner. Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -5 6.2 On all other lands, the Contractor has no rights unless he obtains them from the proper parties. 6.3 The Contractor shall not work on property requiring obtaining of an easement until the Owner has obtained the necessary easement. 6.4 The Contractor shall have no claim for additional compensation or damage on account of any delay in obtaining the necessary easements. 6.5 All areas impacted by construction shall be restored in accordance with the plans, unless otherwise approved by the Owner, or as indicated on the drawings. 6.6 The Owner shall have no responsibility for agreements made between the Contractor and private parties. ARTICLE 7. OTHER CONTRACTS - (Not Used) ARTICLE 8. BIDDERS TO INVESTIGATE 8.1 Bidders must satisfy themselves by personal examination of the site of the Work and by such other means as they may wish, as to the actual conditions there existing, the character and requirements of the Work, the difficulties attendant upon its execution, and the accuracy of all estimated quantities stated in the Bid. ARTICLE 9. QUESTIONS REGARDING DRAWINGS AND DOCUMENTS 9.1 In general, no answer will be given to prospective bidders in reply to an oral question if the question involves an interpretation of the intent or meaning of the Drawings or other Contract Documents, or the equality or use of products or methods other than those designated or described on the Drawings or in the Specifications. Any information given to bidders other than by means of the Drawings and other Contract Documents, including Addenda, as described below, is given informally, for information and the convenience of the bidder only and is not guaranteed. The bidder agrees that such information shall not be used as the basis of nor shall the giving of any such information entitle the bidder to assert any claim or demand against the Owner or the Engineer on account thereof. 9.2 To receive consideration, such questions shall be submitted in writing to the Engineer (Kleinfelder, 215 First Street, Suite 320, Cambridge, MA 02142, Attention: Joseph Maliawco, or jmaliawco@kleinfelder.com) at least seven days before the established date for receipt of Bids. The Engineer will neither approve nor disapprove particular products prior to the opening of Bids; such products will be considered when offered by the Contractor for incorporation into the Work, in accordance with the requirements of Section 01300 - SUBMITTAL PROCEDURES. 9.3 The Engineer will set forth as Addenda, which shall become a part of the Contract Documents, such questions received as above provided as in his sole judgment are Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -6 appropriate or necessary and his decision regarding each. At least five days prior to the receipt of Bids, he will send a copy of these Addenda to those prospective bidders and parties known to have taken out sets of the Drawings and Contract Documents. 9.4 The Contractor agrees to use and base his/her bid on the products and methods designated or described in the Specifications as amended by the Addenda. ARTICLE 10. BLANK FORM FOR BID 10.1 All bids must be upon the blank form for Bid annexed hereto, state the proposed price of each item of the Work, both in words and in figures, and be signed by the bidder with his business address and place of residence. ARTICLE 11. SUBCONTRACTS - (Not Used) ARTICLE 12. BID SECURITY 12.1 Each bid must be accompanied by a bid deposit in the form of cash or a certified check on, or a treasurer's or cashier's check issued by, a responsible bank or trust company and payable to the order of the City of Northampton or by a bid bond prepared on the form of BID BOND (see Section 00430) attached hereto duly executed and acknowledged by the bidder, as Principal, and by a surety company qualified to do business in the Commonwealth of Massachusetts and satisfactory to the Owner, as Surety. 12.2 Every bid bond, every performance bond and every payment bond issued for any construction work in the Commonwealth shall be the bond of a surety company organized pursuant to Section 105 of Chapter 175 or of a surety company authorized to do business in Commonwealth under the provisions of Section 106 of said Chapter 175 and be approved by the U. S. Department of Treasury and acceptable as sureties and reinsurers on federal bonds under Title 31 of the United States Code, sections 9304 to 9308. 12.3 The cash, check or bid bond shall be in the sum of 5 percent of the value of the Bid or Sub-Bid, as applicable, and shall be enclosed in a sealed envelope with the Bid or Sub-Bid. 12.4 Each such check, bid bond, or cash amount may be held by the Owner as security for the fulfillment of the bidder's agreements as hereinabove set forth and as set forth in the BID. Should the bidder fail to fulfill such agreements his cash or bid check shall become the property of the Owner or if a bid bond was furnished the bid bond shall become payable to the Owner, as liquidated damages; otherwise, the cash or bid check shall be returned to the bidder as hereinafter provided, or if the security is a bid bond, the bid bond shall become null and void. 12.5 Bid securities will be returned to all except the three lowest bidders within five days, Sundays and legal holidays excluded, after the opening of Bids, and to the three Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -7 lowest bidders within five days, Sundays and legal holidays excluded, after the Owner and the accepted bidder have executed the AGREEMENT. In the event that the AGREEMENT has not been executed by both the accepted bidder and the Owner within sixty consecutive days after the opening of Bids, the bid security will be returned promptly to any bidder who has not been notified of the acceptance of his Bid. 12.6 Bid checks or cash accompanying Bids which are rejected will be returned within five days, Sundays and legal holidays excluded, after rejection. 12.7 None of the three lowest Bids shall be deemed rejected, notwithstanding acceptance of any BID, until the AGREEMENT has been executed by both the Owner and the accepted bidder. ARTICLE 13. WITHDRAWAL OF BIDS 13.1 Except as hereinafter in this subsection otherwise expressly provided, once his Bid is submitted and received by the Owner for consideration and comparison with other bids similarly submitted, the bidder agrees that he may not and will not withdraw it within sixty days excluding Saturdays, Sundays and legal holidays after the actual date of the opening of Bids. 13.2 Upon proper written request and identification, Bids may be withdrawn only as follows: 1. At any time prior to the designated time for the opening of Bids. 2. Provided the Bid has not theretofore been accepted by the Owner, at any time subsequent to the expiration of the period during which the bidder has agreed not to withdraw his Bid. 13.3 Unless a Bid is withdrawn as provided above, the bidder agrees that it shall be deemed open for acceptance until the AGREEMENT has been executed by both parties thereto or until the Owner notifies a bidder in writing that his Bid is rejected or that the Owner does not intend to accept it, or returns his Bid deposit. Notice of acceptance of a Bid shall not constitute rejection of any other Bid. ARTICLE 14. RIGHT TO REJECT BIDS 14.1 The Owner reserves the right to reject any or all Bids, should the Owner deem it to be in the public interest to do so. 14.2 The Owner may reject Bids which in its sole judgment are either incomplete, conditional, obscure or not responsive or which contain additions not called for, erasures not properly initialed, alterations, or similar irregularities, or the Owner may waive such omissions, conditions or irregularities. Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -8 ARTICLE 15. COMPARISON OF BIDS 15.1 Bids will be compared on the basis of the quantities and unit and lump sum prices stated in the BID. 15.2 In the event that there is a discrepancy in the Bid between the lump sum or unit prices written in words and figures, the prices written in words shall govern. 15.3 The Owner agrees to examine and consider each Bid submitted in consideration of the Bidder's agreements, as hereinabove set forth and as set forth in the BID. ARTICLE 16. REDUCTION IN SCOPE OF WORK 16.1 The Owner reserves the right to decrease the scope of the work to be done under this Contract and to omit any work in order to bring the cost within available funds. To this end, the Owner reserves the right to reduce the quantity of any items or omit all of any items as set forth in the BID, either prior to executing the Contract or at any time during the progress of the work. The Owner further reserves the right, at any time during the progress of the work, to restore all or part of any items previously omitted or reduced. Exercise by the Owner of the above rights shall not constitute any ground or basis of claim for damages or for anticipated profits on the work omitted. ARTICLE 17. CONTRACT BONDS 17.1 The Bidder whose Bid is accepted agrees to furnish the Contract Bonds in the forms which follow in Section No. 00610 Performance Bond and Section 00615 Payment Bond, each in the sum of the full amount of the Contract and duly executed by the said bidder as Principal and by a surety company qualified to do business under the laws of the Commonwealth of Massachusetts and satisfactory to the Owner, as Surety, for the faithful performance of the Contract and payment for labor and materials. The premiums for such Bonds shall be paid by the Contractor. 17.2 Every bid bond, every performance bond and every payment bond issued for any construction work in the Commonwealth shall be the bond of a surety company organized pursuant to Section 105 of Chapter 175 or of a surety company authorized to do business in Commonwealth under the provisions of Section 106 of said Chapter 175 and be approved by the U. S. Department of Treasury and acceptable as sureties and reinsurers on federal bonds under Title 31 of the United States Code, sections 9304 to 9308. ARTICLE 18. EXECUTION OF AGREEMENT 18.1 The Bidder whose Bid is accepted will be required and agrees to duly execute the AGREEMENT and furnish the required CONTRACT BONDS within the time limit stated in the BID after notification that the AGREEMENT is ready for signature. Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -9 18.2 The Bidder to whom the Contract is awarded shall comply with the provisions of Chapter 30, Section 39R of the General Laws of Massachusetts as amended to date; and as provided therein shall, prior to execution of the contract, file a statement of management on internal accounting controls and an audited financial statement for the most recent completed fiscal year. ARTICLE 19. INSURANCE CERTIFICATES 19.1 The Contractor will not be permitted to start any construction work until he has submitted certificates covering all insurances called for under Supplementary Condition 2.01B of Section 00800. ARTICLE 20. MASSACHUSETTS SALES AND USE TAX 20.1 Materials and equipment purchased for permanent installation in this project will be exempt from the Massachusetts Sales and Use Tax. The exemption certificate number will be furnished to the Contractor. Each bidder shall take this exemption into account in calculating his bid for the work. ARTICLE 21. MASSACHUSETTS WAGE RATES 21.1 Massachusetts Wage Rates as established pursuant to the provisions of M.G.L. Chapter 149 Section 26-27G apply to this project. The Massachusetts Wage Determination is attached to these specifications in Appendix B. It is the responsibility of the Contractor, before bid opening, to request, if necessary, any additional information on Massachusetts Wage Rates for those tradespeople who are not covered by the applicable Massachusetts Wage Decision, but who may be employed for the proposed work under this contract. ARTICLE 22. UTILITY UNDERGROUND PLANT DAMAGE PREVENTION SYSTEM 22.1 All excavations within public or private ways are subject to the requirements of Massachusetts General Law, Chapter 82, Section 40 included in Part II of the Supplementary Conditions. ARTICLE 23. COMPETITIVE BIDDING 23.1 The bidding and award of the Contract shall be in full compliance with Section 39 M inclusive of Chapter 30 of the General Laws of the Commonwealth of Massachusetts as last revised. 23.2 If at the time this contract is to be awarded, the lowest bid submitted by a responsible eligible bidder does not exceed the amount of funds then estimated by the Owner as available to finance the contract, the contract will be awarded on the basis of such bid. If such bid exceeds such amount, the Owner may reject all bids or take other action deemed to be in the best interest of the City of Northampton. END OF SECTION 00100 Northampton Drainage Relocation INSTRUCTIONS TO BIDDERS 20164277.003A 00100 -10 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation BID FORM 20164277.003A 00301 -1 SECTION 00301 BID FORM To the City of Northampton, herein called the Owner, acting by and through its Department of Planning & Sustainability: The Undersigned, as bidder, herein referred to as singular and masculine, declares as follows: (1) The only parties interested in this BID as Principals are named herein; (2) this BID is made without collusion with any other person, firm, or corporation; (3) no officer, agent, or employee of the Owner is directly or indirectly interested in this BID; (4) he has carefully examined the site of the proposed Work and fully informed and satisfied himself as to the conditions there existing, the character and requirements of the proposed Work, the difficulties attendant upon its execution and the accuracy of all estimated quantities stated in this BID, and he has carefully read and examined the Drawings, the annexed proposed AGREEMENT and the Specifications and other Contract Documents therein referred to and knows and understands the terms and provisions thereof; (5) he understands that information relative to subsurface and other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) has been furnished only for his information and convenience without any warranty or guarantee, expressed or implied, that the subsurface and/or other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) actually encountered will be the same as those shown on the Drawings or in any of the other Contract Documents and he agrees that he shall not use or be entitled to use any such information made available to him through the Contract Documents or otherwise or obtained by him in his own examination of the site, as a basis of or ground for any claim against the Owner or the Engineer arising from or by reason of any variance which may exist between the aforesaid information made available to or acquired by him and the subsurface and/or other conditions, Northampton Drainage Relocation BID FORM 20164277.003A 00301 -2 natural phenomena, existing pipes and other structures (surface and/or subsurface) actually encountered during the construction work, and he has made due allowance therefor in this BID; (6) and he understands that the quantities of work tabulated in this BID or indicated on the Drawings or in the Specifications or other Contract Documents are only approximate and are subject to increase or decrease as deemed necessary by the Engineer; and he agrees that, if this BID is accepted he will contract with the Owner, as provided in the copy of the Contract Documents deposited in the office of the Engineer, this BID form being part of said Contract Documents, and that he will perform all the work and furnish all the materials and equipment, and provide all labor, services, plant, machinery, apparatus, appliances, tools, supplies and all other things required by the Contract Documents in the manner and within the time therein prescribed and according to the requirements of the Engineer as therein set forth, and that he will take in full payment therefor the lump sum or unit price applicable to each item of the Work as stated in the schedule below. (Note: Bidders must bid on each item. All entries in the entire BID must be made clearly and in ink. In case of discrepancy between prices in writing and in figures; the writing shall govern. In case of discrepancy between the product obtained by multiplying the estimated quantity by the unit price, and the extended amount, the product obtained shall govern. In case of discrepancy between total of extended amounts and total amount of bid stated, total of items shall govern. Use the pages in this document when submitting proposal and submit contract documents intact). Refer to Section 01150 - Measurement and Payment for Item Descriptions. Item No. Description Units Total Estimated Quantity Total Dollars ($) 1 Mobilization/Demobilization ______________________________ Dollars ($ ) (Not to exceed 5% of total remaining Bid Items) lump sum 1 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -3 Item No. Description Units Total Estimated Quantity Total Dollars ($) 2 Erosion and Sedimentation Control ______________________________ Dollars ($ ) lump sum 1 3 Exploratory Excavation ______________________________ Dollars ($ ) cubic yard 150 4 Site Preparation ______________________________ Dollars ($ ) lump sum 1 5 Utility & Railroad Coordination ______________________________ Dollars ($ ) Lump sum 1 6 Geotechnical Instrumentation & Monitoring ______________________________ Dollars ($ ) lump sum 1 7 Stormwater Bypass Pumping ______________________________ Dollars ($ ) lump sum 1 8 Groundwater Control ______________________________ Dollars ($ ) lump sum 1 9 6-ft x 6-ft Reinforced Box Culvert ______________________________ Dollars ($ ) Linear foot 338 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -4 Item No. Description Units Total Estimated Quantity Total Dollars ($) 10A 12-inch (Class IV) Reinforced Concrete Pipe ______________________________ Dollars ($ ) linear foot 128 10B 15-inch (Class IV) Reinforced Concrete Pipe ______________________________ Dollars ($ ) linear foot 24 10C 24-inch (Class IV) Reinforced Concrete Pipe ______________________________ Dollars ($ ) linear foot 48 11 12-inch (Class 53) Ductile Iron Pipe ______________________________ Dollars ($ ) linear foot 40 12 10-inch PVC Pipe ______________________________ Dollars ($ ) linear foot 120 13 Catch Basin ______________________________ Dollars ($ ) vertical foot 10 14A 4-ft Drain Manhole ______________________________ Dollars ($ ) Vertical foot 32 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -5 Item No. Description Units Total Estimated Quantity Total Dollars ($) 14B 4-ft Drop Manhole ______________________________ Dollars ($ ) vertical foot 12 14C 5-ft Drain Drop Manhole ______________________________ Dollars ($ ) Vertical foot 14 15 Demolition & Removal Drainage Pipe, Manhole, Catch Basin or Other Structure ______________________________ Dollars ($ ) Lump sum 1 16 Abandonment Existing Brick Arch Culvert with Flowable Fill ______________________________ Dollars ($ ) linear foot 310 17 Excavation of Unsuitable Material Below Grade ______________________________ Dollars ($ ) cubic yard 75 18 Rock Excavation ______________________________ Dollars ($ ) cubic yard 50 19 Dense Graded Crushed Stone ______________________________ Dollars ($ ) square yard 400 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -6 Item No. Description Units Total Estimated Quantity Total Dollars ($) 20A Bituminous Concrete Pavement – Top Course ______________________________ Dollars ($ ) Tons 10 20B Bituminous Concrete Pavement – Binder Course ______________________________ Dollars ($ ) Tons 60 20C Bituminous Concrete Pavement – Base Course ______________________________ Dollars ($ ) Tons 55 21 Protection & Maintenance of Traffic ______________________________ Dollars ($ ) lump sum 1 22 Uniformed Police for Traffic Control ______________________________ Dollars ($ ) Hours 900 23 Chain Link Fence and Gate ______________________________ Dollars ($ ) LF 100 24 Remaining Miscellaneous Work ______________________________ Dollars ($ ) lump sum 1 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -7 Item No. Description Units Total Estimated Quantity Total Dollars ($) 25A Price Adjustment for Fuel, Diesel for Excavation/Borrow Work _________TBD_________________ Dollars ($ TBD ) cubic yard 1,000 $0.00 25B Price Adjustment for Fuel, Diesel for Surfacing Work _________TBD_________________ Dollars ($ TBD ) ton 100 $0.00 26 Price Adjustment for Liquid Asphalt _________TBD_________________ Dollars ($ TBD ) ton 100 $0.00 27 Price Adjustment for Portland Cement _________TBD_________________ Dollars ($ TBD ) ton 100 $0.00 *The lump sum price for Mobilization / Demobilization shall not exceed 5% of the total of all items, excluding this item. Total Amount of Bid (Basis of Award) (Items 1 through 27) inclusive: $ (Amount in figures) (Amount in words) Northampton Drainage Relocation BID FORM 20164277.003A 00301 -8 The undersigned agrees that for extra work, if any, will be performed in accordance with Article 10 of the General Conditions of the Contract and will be paid for in accordance with Article 11 of the General Conditions of the Contract. The bid security accompanying this BID shall be in the amount of 5 percent of the BID. The undersigned must furnish 100 percent Construction Performance Bond and 100 percent Construction Payment Bond with a surety company acceptable to the Owner. The bidding and award of the contract will be in full compliance with Section 39M inclusive of Chapter 30 of the General Laws of the Commonwealth of Massachusetts as last revised. If this BID is accepted by the Owner, the undersigned agrees to complete the entire work provided to be done under the Contract within 158 calendar days as stipulated in the AGREEMENT. Liquidated damages for each calendar day of delay shall be $1000.00 per day as stipulated in the AGREEMENT. As provided in the INSTRUCTIONS TO BIDDERS, the bidder hereby agrees that he will not withdraw this BID within sixty consecutive calendar days after the actual date of the opening of Bids and that, if the Owner shall accept this BID, the bidder will duly execute and acknowledge the AGREEMENT and furnish, duly executed and acknowledged, the required CONTRACT BONDS within ten (10) days after notification that the AGREEMENT and other Contract Documents are ready for signature. Should the bidder fail to fulfill any of his agreements as hereinabove set forth, the Owner shall have the right to retain as liquidated damages the amount of the bid check or cash which shall become the Owner's property. If a bid bond was given, it is agreed that the amount thereof shall be paid as liquidated damages to the Owner by the Surety. This BID includes Addenda number ______________________ (To be filled in by Bidder if Addenda are issued.) The bidder, by submittal of this BID, agrees with the Owner that the amount of the bid security deposited with this BID fairly and reasonably represents the amount of damages the Owner will suffer due to the failure of the bidder to fulfill his agreements as above provided. Northampton Drainage Relocation BID FORM 20164277.003A 00301 -9 The undersigned certifies under penalties of perjury that this bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this paragraph the word "person" shall mean any natural person, joint venture, partnership, corporation or other business or legal entity. The attached CERTIFICATE OF NON-COLLUSION must be signed and submitted as part of the Bid Proposal. Bidder certifies, that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed in the work certifies that all employees to be employed at the worksite will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and shall furnish documentation of successful completion of said course with the first certified payroll report for each employee. (SEAL)__________________L.S. By ______________________________ (Name of Bidder) (Signature and title of authorized representative) _____________________________ _________________________________ (Telephone) (Business address) ______________________________ _________________________________ (Fax Number) (City and State) Date __________________________ Northampton Drainage Relocation BID FORM 20164277.003A 00301 -10 The bidder is a corporation incorporated in the State (or Commonwealth) of ____________ - a partnership - an individual. (Bidder must add and delete as necessary to make this sentence read correctly.) (Note: If the bidder is a corporation, affix corporate seal and give below the names of its president, treasurer, and general manager if any; if a partnership, give full names and residential addresses of all partners; and if an individual, give residential address if different from business address.) The required names and addresses of all persons interested in the foregoing Bid, as Principals, are as follows: Northampton Drainage Relocation BID FORM 20164277.003A 00301 -11 The bidder is requested to state below what work of a similar character to that included in the proposed Contract he has done and to give references that will enable the Owner to judge his experience, skill, and business standing. Project Name Contact Name Title Telephone No. Add supplementary page if necessary. Northampton Drainage Relocation BID FORM 20164277.003A 00301 -12 CERTIFICATE OF NON-COLLUSION The undersigned certifies under penalties of perjury that this bid or proposal has been made and submitted in good faith and without collusion or fraud with any other person. As used in this certification, the work "person" shall mean any natural person, business, partnership, corporation, union, committee, club, or other organization, entity, or group of individuals. _______________________________________ (Name of person signing bid or proposal _______________________________________ (Name of business) Northampton Drainage Relocation BID FORM 20164277.003A 00301 -13 CERTIFICATE AS TO PAYMENT OF STATE TAXES Pursuant to M.G.L. Ch. 62C Sec. 49A, I certify under the penalties of perjury that I have, to my best knowledge and belief, complied with the law of the commonwealth relating to taxes, reporting of employees and contractors, and withholding and remitting child support. Contractor to provide W-9 form (Payment of State Taxes) with this certificate. ________________________________ ________________________________ Social Security Number of Federal Signature of Individual or Corporate Name Identification Number ________________________________ Corporate Officer (if applicable) Northampton Drainage Relocation BID FORM 20164277.003A 00301 -14 CERTIFICATE AS TO CORPORATE BIDDER I, ________________________________, certify that I am the __________________________ of the Corporation named as bidder in the attached Bid Form; that ________________________, who signed said Bid Form on behalf of the bidder was then _________________________ of said Corporation; that I know his/her signature hereto is genuine and that said Bid Form was duly signed, sealed and executed for and in behalf of said Corporation by authority of its governing body. (Corporate Seal) By: _____________________________________ Name – Type or Print ________________________________ Signature This Certificate must be completed where Bidder is a Corporation and should be so completed by its Clerk. In the event that the Clerk is the person signing the Proposal on behalf of the Corporation, this certificate must be completed by another Officer of the Corporation. Northampton Drainage Relocation BID FORM 20164277.003A 00301 -15 FOREIGN CORPORATION CERTIFICATION AFFIDAVIT OF COMPLIANCE Form AF-4A 1/78 EXECUTIVE OFFICE FOR ADMINISTRATION AND FINANCE The Commonwealth of Massachusetts _____ MASSACHUSETTS BUSINESS CORPORATION _____ NON-PROFIT CORPORATION _____ FOREIGN (non-Massachusetts) Corporation I ____________________________________________________, President Clerk of ___________________________________________________________________________ (Name of Corporation) whose principal office is located_____________________________________________________________________ do hereby certify that the above named Corporation has filed with the State Secretary all certificates and annual reports required by Chapter 156B, Section 109 (Business Corporation), by Chapter 181, Section 4 (Foreign Corporation), or by Chapter 180, Section 26A (non-profit Corporation) of the Massachusetts General Laws. SIGNED UNDER THE PENALTIES OF PERJURY THIS ____ day of _______________, 20____. Signature of responsible Corporate Officer END OF SECTION 00301 Northampton Drainage Relocation BID FORM 20164277.003A 00301 -16 THIS PAGE INTENTIONALLY LEFT BLANK PENAL SUM FORM SECTION 00430 BID BOND Northampton Drainage Relocation BID BOND 20164277.003A 00431 -1 BIDDER (Name and Address): SURETY (Name and Address of Principal Place of Business): OWNER (Name and Address): BID Bid Due Date: __________________________________________________ Project (Brief Description Including Location): BOND Bond Number: __________________________________________________ Date (Not later than Bid due date): __________________________________ Penal sum (Words) (Figures) Surety and Bidder, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this Bid Bond to be duly executed on its behalf by its authorized officer, agent, or representative. BIDDER SURETY (Seal ) (Seal) Bidder's Name and Corporate Seal Surety’s Name and Corporate Seal By: By: Signature and Title Signature and Title (Attach Power of Attorney) Attest: Attest: Signature and Title Signature and Title Note: 1. Above addresses are to be used for giving required notice. 2. Any singular reference to Bidder, Surety, Owner, or other party shall be considered plural where applicable. PENAL SUM FORM SECTION 00430 BID BOND Northampton Drainage Relocation BID BOND 20164277.003A 00431 -2 1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Surety’s liability. 2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents. 3. This obligation shall be null and void if: 3.1. Owner accepts Bidder's Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or 3.2. All Bids are rejected by Owner, or 3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof). 4. Payment under this Bond will be due and payable upon default by Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due. 5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from Bid due date without Surety's written consent. 6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after Bid due date. 7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located. 8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned. 9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby. 10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect. 11. The term "Bid" as used herein includes a Bid, offer, or proposal as applicable. Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -1 AGREEMENT SECTION 00500 CITY OF NORTHAMPTON, MASSACHUSETTS DRAINAGE RELOCATION INDEX ARTICLE 1 WORK ARTICLE 2 ENGINEER ARTICLE 3 CONTRACT TIMES ARTICLE 4 CONTRACT PRICE ARTICLE 5 PAYMENT PROCEDURES ARTICLE 6 CONTRACTOR'S REPRESENTATIONS ARTICLE 7 CONTRACT DOCUMENTS ARTICLE 8 MISCELLANEOUS Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -2 THIS AGREEMENT is dated as of the __________ day of ________________ in the year 2017 by and between the City of Northampton, Massachusetts, acting by and through its Director of Planning & Sustainability, duly authorized therefor, who acts herein solely for said City and without personal liability to itself, (hereinafter called OWNER) and _____________________________________ (hereinafter called CONTRACTOR). OWNER AND CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is as described in SECTION 01010, SUMMARY OF WORK. ARTICLE 2. ENGINEER The Project has been designed by Kleinfelder Northeast, Inc. of Cambridge, MA, who is hereinafter called ENGINEER and who is to act as OWNER'S representative, and have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 3. CONTRACT TIMES 3.1 Substantial completion must be achieved by the Contractor in or within One Hundred and Fifty-eight (158) consecutive calendar days following the date of commencement of the work as specified in the Notice to Proceed. Full and final completion of all contract work must be achieved by the Contractor in or within One Hundred and Fifty-eight (158) consecutive calendar days following the date of commencement of the work as specified in the Notice to Proceed. 3.2 Substantial Completion Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense, and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER One Thousand Dollars ($1,000.00) for each day that expires after the time specified in paragraph 3.1 for Substantial Completion until the Work is substantially complete. After Substantial Completion, if CONTRACTOR shall neglect, refuse, or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper extension thereof granted by OWNER. CONTRACTOR shall pay OWNER One Thousand Dollars ($1,000.00) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment. Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -3 ARTICLE 4. CONTRACT PRICE OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the prices stipulated in the CONTRACTOR'S BID attached to this Agreement. ARTICLE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1 Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as recommended by ENGINEER, and in accordance with the applicable Massachusetts General Law during construction as provided in paragraphs 5.1.1 and 5.2 below. All such payments will be measured by the schedule of values established in paragraph 2.07 of the General Conditions or, in the event there is no schedule of values, as provided in the General Requirements. 5.2 Progress payments will be made in an amount equal to 95 percent of Work completed (with the balance being retainage) but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.02.B.5 of the General Conditions. 5.3 Final Payment. Upon final completion and acceptance of the Work in accordance with paragraph 14.07 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.07. ARTICLE 6. CONTRACTOR'S REPRESENTATIONS In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 6.1 CONTRACTOR has examined and carefully studied the Contract Documents (including the Addenda listed in paragraph 8) and the other related data identified in the Bidding Documents including "technical data." 6.2 CONTRACTOR has visited the site and become familiar with and is satisfied as to the general, local, and site conditions that may affect cost, progress, performance, or furnishing of the Work. Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -4 6.3 CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, performance, and furnishing of the Work. 6.4 CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the site that relates to the Work as indicated in the Contract Documents. 6.4 CONTRACTOR has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in paragraph 4.02.A.1 of the General conditions. CONTRACTOR accepts the determination set forth in paragraph SC- 4.02 of the Supplementary Conditions of the extent of the "technical data" contained in such reports and drawings upon which CONTRACTOR is entitled to rely as provided in paragraph 4.02 of the General Conditions. CONTRACTOR acknowledges that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the site. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance, or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies, or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents. CONTRACTOR has correlated the information known to CONTRACTOR, information and observations obtained from visits to the site, reports, and drawings identified in the Contract Documents with the Contract Documents. 6.6 CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that CONTRACTOR has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. ARTICLE 7. CONTRACT DOCUMENTS The Contract Documents which comprise the entire agreement between OWNER and CONTRACTOR concerning the Work consist of the following: Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -5 7.1 Invitation to Bid. 7.2 Instructions to Bidders. 7.3 CONTRACTOR'S Bid. 7.4 This Agreement. 7.5 Performance, Payment, and other Bonds. 7.6 General Conditions EJCDC Document C-710, 2002 edition. 7.7 Supplementary Conditions. 7.8 Specifications as listed in table of contents thereof. 7.9 Drawings named “Drain Relocation”, dated March 2017. 7.10 Addenda numbers _______ to _______, inclusive. 7.11 The following which may be delivered or issued after the Effective Date of the Agreement and are not attached hereto: All Written Amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraph 3.04 of the General Conditions. ARTICLE 8. MISCELLANEOUS 8.1 Terms used in this Agreement which are defined in Article 1 of the General Conditions will have the meanings indicated in the General Conditions. 8.2 No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically, but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment with release or discharge the assignor from any duty or responsibility under the Contract Documents. 8.3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents. 8.4 Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon OWNER and CONTRACTOR, who Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -6 agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. IN WITNESS WHEREOF, OWNER AND CONTRACTOR have signed this Agreement in six original copies each. Three counterpart has been delivered to the OWNER, and one counterpart each has been delivered to the CONTRACTOR and ENGINEER. All portions of the Contract Documents have been signed, initialed or identified by OWNER and CONTRACTOR or identified by ENGINEER on their behalf. This Agreement will be effective on ____________________, 20__ (which is the Effective Date of the Agreement). OWNER: MAYOR OF THE CITY OF NORTHAMPTON, MASSACHUSETTS __________________________________ David Narkewicz DIRECTOR OF PLANNING & SUSTAINABILITY NORTHAMPTON, MASSACHUSETTS __________________________________ Wayne Feiden, FAICP Approved as to the Availability of Appropriation: __________________________________ __________________________________ City Auditor Date Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -7 Approved as to Form: __________________________________ __________________________________ City Solicitor Date CONTRACTOR ______________________________________ CORPORATE SEAL Company Name By:___________________________________ Signature Name:_________________________________ Type or Print ______________________________________ ATTEST Title Address:_______________________________ By:___________________________________ Signature ______________________________________ Name:________________________________ Type or Print Phone:________________________________ Note: If the CONTRACTOR to whom this Contract is awarded is a corporation, an affidavit giving the principal the right to sign the contract must accompany the executed Contract. END OF SECTION 00500 Northampton Drainage Relocation AGREEMENT 20164277.003A 00500 -8 THIS PAGE INTENTIONALLY LEFT BLANK EJCDC No. C-510 (2002 Edition) Page 1 of 1 Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00510-1 Notice of Award Dated Project: Owner: Owner's Contract No.: Contract: Engineer's Project No.: Bidder: Bidder's Address: (send Certified Mail, Return Receipt Requested) You are notified that your Bid dated for the above Contract has been considered. You are the Successful Bidder and are awarded a Contract for (Indicate total Work, alternates or sections or Work awarded.) The Contract Price of your Contract is Dollars ($ ). (Insert appropriate data if Unit Prices are used. Change language for Cost-Plus contracts.) copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award. sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within [15] days of the date you receive this Notice of Award. 1. Deliver to the Owner [ ] fully executed counterparts of the Contract Documents. 2. Deliver with the executed Contract Documents the Contract security [Bonds] as specified in the Instructions to Bidders (Article 20), [and] General Conditions (Paragraph 5.01) [and Supplementary Conditions (Paragraph SC-5.01).] 3. Other conditions precedent: Failure to comply with these conditions within the time specified will entitle Owner to consider you in default, annul this Notice of Award and declare your Bid security forfeited. Within ten days after you comply with the above conditions, Owner will return to you one fully executed counterpart of the Contract Documents. Owner By: Authorized Signature Title Copy to Engineer EJCDC No. C-510 (2002 Edition) Page 1 of 1 Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00510-2 THIS PAGE INTENTIONALLY LEFT BLANK EJCDC No. C-550 (2002 Edition) Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00550-1 Notice to Proceed Date: _______________ Owner's Contract No.: Engineer's Project No.: Contractor: Contractor's Address: [send Certified Mail, Return Receipt Requested] You are notified that the Contract Times under the above contract will commence to run on . On or before that date, you are to start performing your obligations under the Contract Documents. In accordance with Article 4 of the Agreement, the date of Substantial Completion is , and the date of readiness for final payment is . Before you may start any Work at the Site, Paragraph 2.01.B of the General Conditions provides that you and Owner must each deliver to the other (with copies to Engineer and other identified additional insureds) certificates of insurance which each is required to purchase and maintain in accordance with the Contract Documents. Also, before you may start any Work at the Site, you must [add other requirements]: Owner Given by: Authorized Signature Title Date Copy to Engineer EJCDC No. C-550 (2002 Edition) Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00550-1 THIS PAGE INTENTIONALLY LEFT BLANK 00610-1 PERFORMANCE BOND Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable. CONTRACTOR (Name and Address): SURETY (Name and Address of Principal Place of Business): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ OWNER (Name and Address): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ CONTRACT Date:________________________________________________ Amount: _____________________________________________ Description (Name and Location): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ BOND Bond Number: ________________________________________ Date (Not earlier than Contract Date): ______________________ Amount: _____________________________________________ Modifications to this Bond Form:_________________________________________________________________________ Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this Performance Bond to be duly executed on its behalf by its authorized officer, agent, or representative. CONTRACTOR AS PRINCIPAL SURETY Company: Signature: (Seal) (Seal) Name and Title: Surety’s Name and Corporate Seal By: Signature and Title (Attach Power of Attorney) (Space is provided below for signatures of additional parties, if required.) Attest: Signature and Title CONTRACTOR AS PRINCIPAL SURETY Company: Signature: (Seal) (Seal) Name and Title: Surety’s Name and Corporate Seal By: Signature and Title (Attach Power of Attorney) Attest: Signature and Title: EJCDC No. C-610 (2002 Edition) Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General Contractors of America, and the American Institute of Architects. 00610-2 1. Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to Owner for the performance of the Contract, which is incorporated herein by reference. 2. If Contractor performs the Contract, Surety and Contractor have no obligation under this Bond, except to participate in conferences as provided in Paragraph 3.1. 3. If there is no Owner Default, Surety's obligation under this Bond shall arise after: 3.1. Owner has notified Contractor and Surety, at the addresses described in Paragraph 10 below, that Owner is considering declaring a Contractor Default and has requested and attempted to arrange a conference with Contractor and Surety to be held not later than 15 days after receipt of such notice to discuss methods of performing the Contract. If Owner, Contractor and Surety agree, Contractor shall be allowed a reasonable time to perform the Contract, but such an agreement shall not waive Owner's right, if any, subsequently to declare a Contractor Default; and 3.2. Owner has declared a Contractor Default and formally terminated Contractor's right to complete the Contract. Such Contractor Default shall not be declared earlier than 20 days after Contractor and Surety have received notice as provided in Paragraph 3.1; and 3.3. Owner has agreed to pay the Balance of the Contract Price to: 1. Surety in accordance with the terms of the Contract; 2. Another contractor selected pursuant to Paragraph 4.3 to perform the Contract. 4. When Owner has satisfied the conditions of Paragraph 3, Surety shall promptly and at Surety's expense take one of the following actions: 4.1. Arrange for Contractor, with consent of Owner, to perform and complete the Contract; or 4.2. Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or 4.3. Obtain bids or negotiated proposals from qualified contractors acceptable to Owner for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by Owner and Contractor selected with Owner's concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Contract, and pay to Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by Owner resulting from Contractor Default; or 4.4. Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances: 1. After investigation, determine the amount for which it may be liable to Owner and, as soon as practicable after the amount is determined, tender payment therefor to Owner; or 2. Deny liability in whole or in part and notify Owner citing reasons therefor. 5. If Surety does not proceed as provided in Paragraph 4 with reasonable promptness, Surety shall be deemed to be in default on this Bond 15 days after receipt of an additional written notice from Owner to Surety demanding that Surety perform its obligations under this Bond, and Owner shall be entitled to enforce any remedy available to Owner. If Surety proceeds as provided in Paragraph 4.4, and Owner refuses the payment tendered or Surety has denied liability, in whole or in part, without further notice Owner shall be entitled to enforce any remedy available to Owner. 6. After Owner has terminated Contractor's right to complete the Contract, and if Surety elects to act under Paragraph 4.1, 4.2, or 4.3 above, then the responsibilities of Surety to Owner shall not be greater than those of Contractor under the Contract, and the responsibilities of Owner to Surety shall not be greater than those of Owner under the Contract. To a limit of the amount of this Bond, but subject to commitment by Owner of the Balance of the Contract Price to mitigation of costs and damages on the Contract, Surety is obligated without duplication for: 6.1. The responsibilities of Contractor for correction of defective Work and completion of the Contract; 6.2. Additional legal, design professional, and delay costs resulting from Contractor's Default, and resulting from the actions or failure to act of Surety under Paragraph 4; and 6.3. Liquidated damages, or if no liquidated damages are specified in the Contract, actual damages caused by delayed performance or non- performance of Contractor. 7. Surety shall not be liable to Owner or others for obligations of Contractor that are unrelated to the Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than Owner or its heirs, executors, administrators, or successors. 8. Surety hereby waives notice of any change, including changes of time, to Contract or to related subcontracts, purchase orders, and other obligations. 9. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the Work or part of the Work is located and shall be instituted within two years after Contractor Default or within two years after Contractor ceased working or within two years after Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. 10. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the address shown on the signature page. 11. When this Bond has been furnished to comply with a statutory requirement in the location where the Contract was to be performed, any provision in this Bond conflicting with said statutory requirement shall be deemed deleted herefrom and provisions conforming to such statutory requirement shall be deemed incorporated herein. The intent is that this Bond shall be construed as a statutory bond and not as a common law bond. 12. Definitions. 12.1 Balance of the Contract Price: The total amount payable by Owner to Contractor under the Contract after all proper adjustments have been made, including allowance to Contractor of any amounts received or to be received by Owner in settlement of insurance or other Claims for damages to which Contractor is entitled, reduced by all valid and proper payments made to or on behalf of Contractor under the Contract. 12.2. Contract: The agreement between Owner and Contractor identified on the signature page, including all Contract Documents and changes thereto. 12.3. Contractor Default: Failure of Contractor, which has neither been remedied nor waived, to perform or otherwise to comply with the terms of the Contract. 12.4. Owner Default: Failure of Owner, which has neither been remedied nor waived, to pay Contractor as required by the Contract or to perform and complete or comply with the other terms thereof. FOR INFORMATION ONLY – Name, Address and Telephone Surety Agency or Broker Owner’s Respresentative (engineer or other party) 00615-1 PAYMENT BOND Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable. CONTRACTOR (Name and Address): SURETY (Name and Address of Principal Place of Business): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ OWNER (Name and Address): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ CONTRACT Date: _________________________________________________ Amount: ______________________________________________ Description (Name and Location): _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ BOND Bond Number: _________________________________________ Date (Not earlier than Contract Date): _______________________ Amount: ______________________________________________ Modifications to this Bond Form: _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this Payment Bond to be duly executed on its behalf by its authorized officer, agent, or representative. CONTRACTOR AS PRINCIPAL SURETY Company: Signature: (Seal) (Seal) Name and Title: Surety’s Name and Corporate Seal By: Signature and Title (Attach Power of Attorney) (Space is provided below for signatures of additional parties, if required.) Attest: Signature and Title CONTRACTOR AS PRINCIPAL SURETY Company: Signature: (Seal) (Seal) Name and Title: Surety’s Name and Corporate Seal By: Signature and Title (Attach Power of Attorney) Attest: Signature and Title: EJCDC No. C-615 (2002 Edition) Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General Contractors of America, the American Institute of Architects, the American Subcontractors Association, and the Associated Specialty Contractors. 00615-2 1. Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to Owner to pay for labor, materials, and equipment furnished by Claimants for use in the performance of the Contract, which is incorporated herein by reference. 2. With respect to Owner, this obligation shall be null and void if Contractor: 2.1. Promptly makes payment, directly or indirectly, for all sums due Claimants, and 2.2. Defends, indemnifies, and holds harmless Owner from all claims, demands, liens, or suits alleging non-payment by Contractor by any person or entity who furnished labor, materials, or equipment for use in the performance of the Contract, provided Owner has promptly notified Contractor and Surety (at the addresses described in Paragraph 12) of any claims, demands, liens, or suits and tendered defense of such claims, demands, liens, or suits to Contractor and Surety, and provided there is no Owner Default. 3. With respect to Claimants, this obligation shall be null and void if Contractor promptly makes payment, directly or indirectly, for all sums due. 4. Surety shall have no obligation to Claimants under this Bond until: 4.1. Claimants who are employed by or have a direct contract with Contractor have given notice to Surety (at the addresses described in Paragraph 12) and sent a copy, or notice thereof, to Owner, stating that a claim is being made under this Bond and, with substantial accuracy, the amount of the claim. 4.2. Claimants who do not have a direct contract with Contractor: 1. Have furnished written notice to Contractor and sent a copy, or notice thereof, to Owner, within 90 days after having last performed labor or last furnished materials or equipment included in the claim stating, with substantial accuracy, the amount of the claim and the name of the party to whom the materials or equipment were furnished or supplied, or for whom the labor was done or performed; and 2. Have either received a rejection in whole or in part from Contractor, or not received within 30 days of furnishing the above notice any communication from Contractor by which Contractor had indicated the claim will be paid directly or indirectly; and 3. Not having been paid within the above 30 days, have sent a written notice to Surety and sent a copy, or notice thereof, to Owner, stating that a claim is being made under this Bond and enclosing a copy of the previous written notice furnished to Contractor. 5. If a notice by a Claimant required by Paragraph 4 is provided by Owner to Contractor or to Surety, that is sufficient compliance. 6. When a Claimant has satisfied the conditions of Paragraph 4, the Surety shall promptly and at Surety's expense take the following actions: 6.1. Send an answer to that Claimant, with a copy to Owner, within 45 days after receipt of the claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed. 6.2. Pay or arrange for payment of any undisputed amounts. 7. Surety's total obligation shall not exceed the amount of this Bond, and the amount of this Bond shall be credited for any payments made in good faith by Surety. 8. Amounts owed by Owner to Contractor under the Contract shall be used for the performance of the Contract and to satisfy claims, if any, under any performance bond. By Contractor furnishing and Owner accepting this Bond, they agree that all funds earned by Contractor in the performance of the Contract are dedicated to satisfy obligations of Contractor and Surety under this Bond, subject to Owner's priority to use the funds for the completion of the Work. 9. Surety shall not be liable to Owner, Claimants, or others for obligations of Contractor that are unrelated to the Contract. Owner shall not be liable for payment of any costs or expenses of any Claimant under this Bond, and shall have under this Bond no obligations to make payments to, give notices on behalf of, or otherwise have obligations to Claimants under this Bond. 10. Surety hereby waives notice of any change, including changes of time, to the Contract or to related Subcontracts, purchase orders and other obligations. 11. No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the location in which the Work or part of the Work is located or after the expiration of one year from the date (1) on which the Claimant gave the notice required by Paragraph 4.1 or Paragraph 4.2.3, or (2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract, whichever of (1) or (2) first occurs. If the provisions of this paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. 12. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the addresses shown on the signature page. Actual receipt of notice by Surety, Owner, or Contractor, however accomplished, shall be sufficient compliance as of the date received at the address shown on the signature page. 13. When this Bond has been furnished to comply with a statutory requirement in the location where the Contract was to be performed, any provision in this Bond conflicting with said statutory requirement shall be deemed deleted herefrom and provisions conforming to such statutory requirement shall be deemed incorporated herein. The intent is that this Bond shall be construed as a statutory Bond and not as a common law bond. 14. Upon request of any person or entity appearing to be a potential beneficiary of this Bond, Contractor shall promptly furnish a copy of this Bond or shall permit a copy to be made. 15. DEFINITIONS 15.1. Claimant: An individual or entity having a direct contract with Contractor, or with a first-tier subcontractor of Contractor, to furnish labor, materials, or equipment for use in the performance of the Contract. The intent of this Bond shall be to include without limitation in the terms "labor, materials or equipment" that part of water, gas, power, light, heat, oil, gasoline, telephone service, or rental equipment used in the Contract, architectural and engineering services required for performance of the Work of Contractor and Contractor's Subcontractors, and all other items for which a mechanic's lien may be asserted in the jurisdiction where the labor, materials, or equipment were furnished. 15.2. Contract: The agreement between Owner and Contractor identified on the signature page, including all Contract Documents and changes thereto. 15.3. Owner Default: Failure of Owner, which has neither been remedied nor waived, to pay Contractor as required by the Contract or to perform and complete or comply with the other terms thereof. FOR INFORMATION ONLY – Name, Address and Telephone Surety Agency or Broker: Owner’s Representative (engineer or other party): EJCDC No. C-625 (2002 Edition) Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00625-1 Certificate of Substantial Completion Project: Owner: Owner's Contract No.: Contract: Date of Contract: Contractor: Engineer's Project No.: This [tentative] [definitive] Certificate of Substantial Completion applies to: All Work under the Contract Documents: The following specified portions: Date of Substantial Completion The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor and Engineer, and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby declared and is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below. A [tentative] [revised tentative] [definitive] list of items to be completed or corrected, is attached hereto. This list may not be all- inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat, utilities, insurance and warranties shall be as provided in the Contract Documents except as amended as follows: Amended Responsibilities Not Amended Owner's Amended Responsibilities: Contractor's Amended Responsibilities: The following documents are attached to and made part of this Certificate: This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract Documents. Executed by Engineer Date Accepted by Contractor Date Accepted by Owner Date EJCDC No. C-625 (2002 Edition) Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. 00625-1 THIS PAGE INTENTIONALLY LEFT BLANK EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 1 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT FUNDING AGENCY EDITION Prepared by ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE and Issued and Published Jointly By PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE a practice division of the NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS ___________________ AMERICAN COUNCIL OF ENGINEERING COMPANIES ___________________ AMERICAN SOCIETY OF CIVIL ENGINEERS ___________________ This document has been approved and endorsed by The Associated General Contractors of America and the Construction Specification Institute These General Conditions have been prepared for use with the Suggested Forms of Agreement Between Owner and Contractor Funding Agency Edition No. C-521 (2002 Edition). Their provisions are interrelated and a change in one may necessitate a change in the other. Comments concerning their usage are contained in the EJCDC Construction Documents, General and Instructions (No. C-001, 2002 Edition). For guidance in the preparation of Supplementary Conditions, see Guide to the Preparation of Supplementary Conditions (No. C-800, 2002 Edition). EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 2 Copyright © 2002 National Society of Professional Engineers 1420 King Street, Alexandria, VA 22314-2794 (703) 684-2882 American Council of Engineering Companies 1015 15th Street N.W., Washington, DC 20005 (202) 347-7474 American Society of Civil Engineers 1801 Alexander Bell Drive, Reston, VA 20191-4400 (800) 548-2723 EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 3 TABLE OF CONTENTS Page Article 1 – Definitions and Terminology ............................................................................................................................................ 6 1.01 Defined Terms ............................................................................................................................................................ 6 1.02 Terminology ............................................................................................................................................................... 9 Article 2 – Preliminary Matters ........................................................................................................................................................ 10 2.01 Delivery of Bonds and Evidence of Insurance ........................................................................................................ 10 2.02 Copies of Documents ............................................................................................................................................... 10 2.03 Commencement of Contract Times; Notice to Proceed .......................................................................................... 10 2.04 Starting the Work ..................................................................................................................................................... 11 2.05 Before Starting Construction ................................................................................................................................... 11 2.06 Preconstruction Conference ..................................................................................................................................... 11 2.07 Initial Acceptance of Schedules ............................................................................................................................... 11 Article 3 – Contract Documents: Intent, Amending, Reuse ............................................................................................................ 11 3.01 Intent ......................................................................................................................................................................... 11 3.02 Reference Standards ................................................................................................................................................. 12 3.03 Reporting and Resolving Discrepancies .................................................................................................................. 12 3.04 Amending and Supplementing Contract Documents ............................................................................................... 13 3.05 Reuse of Documents ................................................................................................................................................ 13 3.06 Electronic Data ......................................................................................................................................................... 13 Article 4 – Availability of Lands; Subsurface and Physical Conditions; Hazardous Environmental Conditions; Reference Points13 4.01 Availability of Lands ................................................................................................................................................ 13 4.02 Subsurface and Physical Conditions ........................................................................................................................ 14 4.03 Differing Subsurface or Physical Conditions........................................................................................................... 14 4.04 Underground Facilities ............................................................................................................................................. 15 4.05 Reference Points ....................................................................................................................................................... 16 4.06 Hazardous Environmental Condition at Site ........................................................................................................... 16 Article 5 – Bonds and Insurance ....................................................................................................................................................... 18 5.01 Performance, Payment, and Other Bonds ................................................................................................................ 18 5.02 Licensed Sureties and Insurers ................................................................................................................................. 18 5.03 Certificates of Insurance........................................................................................................................................... 18 5.04 Contractor’s Liability Insurance .............................................................................................................................. 18 5.05 Owner’s Liability Insurance ..................................................................................................................................... 19 5.06 Property Insurance ................................................................................................................................................... 20 5.07 Waiver of Rights ...................................................................................................................................................... 21 5.08 Receipt and Application of Insurance Proceeds ...................................................................................................... 21 5.09 Acceptance of Bonds and Insurance; Option to Replace ........................................................................................ 21 5.10 Partial Utilization, Acknowledgment of Property Insurer ....................................................................................... 22 Article 6 – Contractor’s Responsibilities .......................................................................................................................................... 22 6.01 Supervision and Superintendence ............................................................................................................................ 22 6.02 Labor; Working Hours ............................................................................................................................................. 22 6.03 Services, Materials, and Equipment ......................................................................................................................... 22 6.04 Progress Schedule .................................................................................................................................................... 23 6.05 Substitutes and “Or-Equals” .................................................................................................................................... 23 6.06 Concerning Subcontractors, Suppliers, and Others ................................................................................................. 25 6.07 Patent Fees and Royalties......................................................................................................................................... 26 6.08 Permits ...................................................................................................................................................................... 26 6.09 Laws and Regulations .............................................................................................................................................. 26 6.10 Taxes ........................................................................................................................................................................ 27 EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 4 6.11 Use of Site and Other Areas ..................................................................................................................................... 27 6.12 Record Documents ................................................................................................................................................... 27 6.13 Safety and Protection ............................................................................................................................................... 28 6.14 Safety Representative ............................................................................................................................................... 28 6.15 Hazard Communication Programs ........................................................................................................................... 28 6.16 Emergencies ............................................................................................................................................................. 28 6.17 Shop Drawings and Samples .................................................................................................................................... 29 6.18 Continuing the Work ................................................................................................................................................ 30 6.19 Contractor’s General Warranty and Guarantee ....................................................................................................... 30 6.20 Indemnification ........................................................................................................................................................ 31 6.21 Delegation of Professional Design Services ............................................................................................................ 31 Article 7 – Other Work at the Site .................................................................................................................................................... 32 7.01 Related Work at Site ................................................................................................................................................ 32 7.02 Coordination ............................................................................................................................................................. 32 7.03 Legal Relationships .................................................................................................................................................. 33 Article 8 – Owner’s Responsibilities ................................................................................................................................................ 33 8.01 Communications to Contractor ................................................................................................................................ 33 8.02 Replacement of Engineer ......................................................................................................................................... 33 8.03 Furnish Data ............................................................................................................................................................. 33 8.04 Pay When Due.......................................................................................................................................................... 33 8.05 Lands and Easements; Reports and Tests ................................................................................................................ 33 8.06 Insurance .................................................................................................................................................................. 33 8.07 Change Orders .......................................................................................................................................................... 33 8.08 Inspections, Tests, and Approvals ........................................................................................................................... 33 8.09 Limitations on Owner’s Responsibilities ................................................................................................................. 34 8.10 Undisclosed Hazardous Environmental Condition .................................................................................................. 34 8.11 Evidence of Financial Arrangements ....................................................................................................................... 34 Article 9 – Engineer’s Status During Construction .......................................................................................................................... 34 9.01 Owner’s Representative ........................................................................................................................................... 34 9.02 Visits to Site ............................................................................................................................................................. 34 9.03 Project Representative.............................................................................................................................................. 34 9.04 Authorized Variations in Work ................................................................................................................................ 35 9.05 Rejecting Defective Work ........................................................................................................................................ 35 9.06 Shop Drawings, Change Orders and Payments ....................................................................................................... 35 9.07 Determinations for Unit Price Work ........................................................................................................................ 35 9.08 Decisions on Requirements of Contract Documents and Acceptability of Work ................................................... 35 9.09 Limitations on Engineer’s Authority and Responsibilities ...................................................................................... 36 Article 10 – Changes in the Work; Claims ....................................................................................................................................... 36 10.01 Authorized Changes in the Work ............................................................................................................................. 36 10.02 Unauthorized Changes in the Work ......................................................................................................................... 36 10.03 Execution of Change Orders .................................................................................................................................... 37 10.04 Notification to Surety ............................................................................................................................................... 37 10.05 Claims ....................................................................................................................................................................... 37 Article 11 – Cost of the Work; Allowances; Unit Price Work ......................................................................................................... 38 11.01 Cost of the Work ...................................................................................................................................................... 38 11.02 Allowances ............................................................................................................................................................... 40 11.03 Unit Price Work ....................................................................................................................................................... 40 Article 12 – Change of Contract Price; Change of Contract Times ................................................................................................. 41 12.01 Change of Contract Price ......................................................................................................................................... 41 12.02 Change of Contract Times ....................................................................................................................................... 42 EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 5 12.03 Delays ....................................................................................................................................................................... 42 Article 13 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ........................................................ 43 13.01 Notice of Defects ...................................................................................................................................................... 43 13.02 Access to Work ........................................................................................................................................................ 43 13.03 Tests and Inspections ............................................................................................................................................... 43 13.04 Uncovering Work ..................................................................................................................................................... 43 13.05 Owner May Stop the Work ...................................................................................................................................... 44 13.06 Correction or Removal of Defective Work ............................................................................................................. 44 13.07 Correction Period ..................................................................................................................................................... 44 13.08 Acceptance of Defective Work ................................................................................................................................ 45 13.09 Owner May Correct Defective Work ....................................................................................................................... 45 Article 14 – Payments to Contractor and Completion ...................................................................................................................... 46 14.01 Schedule of Values ................................................................................................................................................... 46 14.02 Progress Payments ................................................................................................................................................... 46 14.03 Contractor’s Warranty of Title ................................................................................................................................. 48 14.04 Substantial Completion ............................................................................................................................................ 48 14.05 Partial Utilization ..................................................................................................................................................... 49 14.06 Final Inspection ........................................................................................................................................................ 49 14.07 Final Payment ........................................................................................................................................................... 49 14.08 Final Completion Delayed ....................................................................................................................................... 50 14.09 Waiver of Claims ..................................................................................................................................................... 51 Article 15 – Suspension of Work and Termination .......................................................................................................................... 51 15.01 Owner May Suspend Work ...................................................................................................................................... 51 15.02 Owner May Terminate for Cause............................................................................................................................. 51 15.03 Owner May Terminate For Convenience ................................................................................................................ 52 15.04 Contractor May Stop Work or Terminate ................................................................................................................ 52 Article 16 – Dispute Resolution ........................................................................................................................................................ 53 16.01 Methods and Procedures .......................................................................................................................................... 53 Article 17 – Miscellaneous ............................................................................................................................................................... 53 17.01 Giving Notice ........................................................................................................................................................... 53 17.02 Computation of Times.............................................................................................................................................. 53 17.03 Cumulative Remedies .............................................................................................................................................. 53 17.04 Survival of Obligations ............................................................................................................................................ 54 17.05 Controlling Law ....................................................................................................................................................... 54 17.06 Headings ................................................................................................................................................................... 54 Article 18 – Federal Requirements ................................................................................................................................................... 54 18.01 Agency Not a Party .................................................................................................................................................. 54 18.02 Contract Approval .................................................................................................................................................... 54 18.03 Conflict of Interest ................................................................................................................................................... 54 18.04 Gratuities .................................................................................................................................................................. 54 18.05 Audit and Access to Records ................................................................................................................................... 55 18.06 Small, Minority and Women’s Businesses .............................................................................................................. 55 18.07 Anti-Kickback .......................................................................................................................................................... 55 18.08 Clean Air and Pollution Control Acts ...................................................................................................................... 55 18.09 State Energy Policy .................................................................................................................................................. 55 18.10 Equal Opportunity Requirements............................................................................................................................. 55 18.11 Restrictions on Lobbying ......................................................................................................................................... 56 18.12 Environmental Requirements ................................................................................................................................... 56 EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 6 GENERAL CONDITIONS ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Addenda – Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents. 2. Agency – The Federal or state agency named as such in the Agreement. 3. Agreement – The written instrument which is evidence of the agreement between Owner and Contractor covering the Work. 4. Application for Payment – The form acceptable to Engineer which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents. 5. Asbestos – Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 6. Bid – The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. 7. Bidder – The individual or entity who submits a Bid directly to Owner. 8. Bidding Documents – The Bidding Requirements and the proposed Contract Documents (including all Addenda). 9. Bidding Requirements – The Advertisement or Invitation to Bid, Instructions to Bidders, bid security of acceptable form, if any, and the Bid Form with any supplements. 10. Change Order – A document recommended by Engineer which is signed by Contractor and Owner and Agency and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement. 11. Claim – A demand or assertion by Owner or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim. 12. Contract – The entire and integrated written agreement between the Owner and Contractor concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 13. Contract Documents – Those items so designated in the Agreement. Only printed or hard copies of the items listed in the Agreement are Contract Documents. Approved Shop Drawings, other Contractor’s submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 7 14. Contract Price – The moneys payable by Owner to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work). 15. Contract Times – The number of days or the dates stated in the Agreement to: (i) achieve Milestones, if any, (ii) achieve Substantial Completion; and (iii) complete the Work so that it is ready for final payment as evidenced by Engineer’s written recommendation of final payment. 16. Contractor – The individual or entity with whom Owner has entered into the Agreement. 17. Cost of the Work – See Paragraph 11.01.A for definition. 18. Drawings – That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined. 19. Effective Date of the Agreement – The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. 20. Engineer – The individual or entity named as such in the Agreement. 21. Field Order – A written order issued by Engineer which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times. 22. General Requirements – Sections of Division 1 of the Specifications. The General Requirements pertain to all sections of the Specifications. 23. Hazardous Environmental Condition – The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto in connection with the Work. 24. Hazardous Waste – The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time. 25. Laws and Regulations; Laws or Regulations – Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 26. Liens – Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 27. Milestone – A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work. 28. Notice of Award – The written notice by Owner to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, Owner will sign and deliver the Agreement. 29. Notice to Proceed – A written notice given by Owner to Contractor fixing the date on which the Contract Times will commence to run and on which Contractor shall start to perform the Work under the Contract Documents. 30. Owner – The individual or entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed. 31. PCBs – Polychlorinated biphenyls. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 8 32. Petroleum – Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils. 33. Progress Schedule – A schedule, prepared and maintained by Contractor, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Times. 34. Project – The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part. 35. Project Manual – The bound documentary information prepared for bidding and constructing the Work. A listing of the contents of the Project Manual, which may be bound in one or more volumes, is contained in the table(s) of contents. 36. Radioactive Material – Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time. 37. Related Entity – An officer, director, partner, employee, agent, consultant, or subcontractor. 38. Resident Project Representative – The authorized representative of Engineer who may be assigned to the Site or any part thereof. 39. Samples – Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 40. Schedule of Submittals – A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 41. Schedule of Values – A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor’s Applications for Payment. 42. Shop Drawings – All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 43. Site – Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by Owner which are designated for the use of Contractor. 44. Specifications – That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. 45. Subcontractor – An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 46. Substantial Completion – The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended. The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof. 47. Successful Bidder – The Bidder submitting a responsive Bid to whom Owner makes an award. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 9 48. Supplementary Conditions – That part of the Contract Documents which amends or supplements these General Conditions. 49. Supplier – A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or any Subcontractor. 50. Underground Facilities – All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 51. Unit Price Work – Work to be paid for on the basis of unit prices. 52. Work – The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 53. Work Change Directive – A written statement to Contractor issued on or after the Effective Date of the Agreement and signed by Owner and Agency upon recommendation of the Engineer ordering an addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed or to emergencies. A Work Change Directive will not change the Contract Price or the Contract Times but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times. 1.02 Terminology A. The following words or terms are not defined but, when used in the Bidding Requirements or Contract Documents, have the following meaning. B. Intent of Certain Terms or Adjectives 1. The Contract Documents include the terms “as allowed,” “as approved,” “as ordered”, “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Work. It is intended that such exercise of professional judgment, action or determination will be solely to evaluate, in general, the Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective is not intended to and shall not be effective to assign to Engineer any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of Paragraph 9.09 or any other provision of the Contract Documents. C. Day 1. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 10 D. Defective 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents, or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents, or c. has been damaged prior to Engineer’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial Completion in accordance with Paragraph 14.04 or 14.05). E. Furnish, Install, Perform, Provide 1. The word “furnish,” when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition. 2. The word “install,” when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use. 3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use. 4. When “furnish,” “install,” “perform,” or “provide” is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of Contractor, “provide” is implied. F. Unless stated otherwise in the Contract Documents, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. ARTICLE 2 – PRELIMINARY MATTERS 2.01 Delivery of Bonds and Evidence of Insurance A. When Contractor delivers the executed counterparts of the Agreement to Owner, Contractor shall also deliver to Owner such bonds as Contractor may be required to furnish. B. Evidence of Insurance: Before any Work at the Site is started, Contractor and Owner shall each deliver to the other, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance which either of them or any additional insured may reasonably request) which Contractor and Owner respectively are required to purchase and maintain in accordance with Article 5. 2.02 Copies of Documents A. Owner shall furnish to Contractor up to ten printed or hard copies of the Drawings and Project Manual. Additional copies will be furnished upon request at the cost of reproduction. 2.03 Commencement of Contract Times; Notice to Proceed A. The Contract Times will commence to run on the thirtieth day after the Effective Date of the Agreement or, if a Notice to Proceed is given, on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 30 days after the Effective Date of the Agreement. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 11 2.04 Starting the Work A. Contractor shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run. 2.05 Before Starting Construction A. Preliminary Schedules: Within 10 days after the Effective Date of the Agreement (unless otherwise specified in the General Requirements), Contractor shall submit to Engineer for timely review: 1. a preliminary Progress Schedule; 2. a preliminary Schedule of Submittals; and 3. a preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. 2.06 Preconstruction Conference A. Before any Work at the Site is started, a conference attended by Owner, Contractor, Engineer, Agency, and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in Paragraph 2.05.A, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records. 2.07 Initial Acceptance of Schedules A. At least 10 days before submission of the first Application for Payment a conference attended by Contractor, Engineer, and others as appropriate will be held to review for acceptability to Engineer as provided below the schedules submitted in accordance with Paragraph 2.05.A. Contractor shall have an additional 10 days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to Contractor until acceptable schedules are submitted to Engineer. 1. The Progress Schedule will be acceptable to Engineer if it provides an orderly progression of the Work to completion within the Contract Times. Such acceptance will not impose on Engineer responsibility for the Progress Schedule, for sequencing, scheduling, or progress of the Work nor interfere with or relieve Contractor from Contractor’s full responsibility therefor. 2. Contractor’s Schedule of Submittals will be acceptable to Engineer if it provides a workable arrangement for reviewing and processing the required submittals. 3. Contractor’s Schedule of Values will be acceptable to Engineer as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work. ARTICLE 3 – CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE 3.01 Intent A. The Contract Documents are complementary; what is required by one is as binding as if required by all. B. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 12 as being required to produce the intended result will be provided whether or not specifically called for at no additional cost to Owner. C. Clarifications and interpretations of the Contract Documents shall be issued by Engineer as provided in Article 9. 3.02 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision of any such standard, specification, manual or code, or any instruction of a Supplier shall be effective to change the duties or responsibilities of Owner, Contractor, or Engineer, or any of their subcontractors, consultants, agents, or employees from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to Owner, or Engineer, or any of their Related Entities, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.03 Reporting and Resolving Discrepancies A. Reporting Discrepancies 1. Contractor’s Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein and all applicable field measurements. Contractor shall promptly report in writing to Engineer any conflict, error, ambiguity, or discrepancy which Contractor may discover and shall obtain a written interpretation or clarification from Engineer before proceeding with any Work affected thereby. 2. Contractor’s Review of Contract Documents During Performance of Work: If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents or between the Contract Documents and any provision of any Law or Regulation applicable to the performance of the Work or of any standard, specification, manual or code, or of any instruction of any Supplier, Contractor shall promptly report it to Engineer in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph 6.16.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04. 3. Contractor shall not be liable to Owner or Engineer for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor knew or reasonably should have known thereof. B. Resolving Discrepancies 1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and: a. the provisions of any standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Contract Documents); or b. the provisions of any Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation). EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 13 3.04 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by either a Change Order or a Work Change Directive. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by one or more of the following ways: 1. A Field Order; 2. Engineer’s approval of a Shop Drawing or Sample; (Subject to the provisions of Paragraph 6.17.D.3) or 3. Engineer’s written interpretation or clarification. 3.05 Reuse of Documents A. Contractor and any Subcontractor or Supplier shall not: 1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or Engineer’s consultants, including electronic media editions; or 2. reuse any of such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of Owner and Engineer and specific written verification or adaption by Engineer. B. The prohibition of this Paragraph 3.05 will survive final payment, or termination of the Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes. 3.06 Electronic Data A. Copies of data furnished by Owner or Engineer to Contractor or Contractor to Owner or Engineer that may be relied upon are limited to the printed copies (also known as hard copies). Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user’s sole risk. If there is a discrepancy between the electronic files and the hard copies, the hard copies govern. B. Because data stored in electronic media format can deteriorate or be modified inadvertently or otherwise without authorization of the data’s creator, the party receiving electronic files agrees that it will perform acceptance tests or procedures within 60 days, after which the receiving party shall be deemed to have accepted the data thus transferred. Any errors detected within the 60-day acceptance period will be corrected by the transferring party. C. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data’s creator. ARTICLE 4 – AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS 4.01 Availability of Lands A. Owner shall furnish the Site. Owner shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. Owner will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. If Contractor and Owner are unable to agree on entitlement to or on the amount or extent, if any, EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 14 of any adjustment in the Contract Price or Contract Times, or both, as a result of any delay in Owner’s furnishing the Site or a part thereof, Contractor may make a Claim therefor as provided in Paragraph 10.05. B. Upon reasonable written request, Owner shall furnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed and Owner’s interest therein as necessary for giving notice of or filing a mechanic’s or construction lien against such lands in accordance with applicable Laws and Regulations. C. Contractor shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment. 4.02 Subsurface and Physical Conditions A. Reports and Drawings: The Supplementary Conditions identify: 1. those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Contract Documents; and 2. those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Contract Documents. B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the general accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such “technical data,” Contractor may not rely upon or make any claim against Owner or Engineer, or any of their Related Entities with respect to: 1. the completeness of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or 3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information. 4.03 Differing Subsurface or Physical Conditions A. Notice: If Contractor believes that any subsurface or physical condition at or contiguous to the Site that is uncovered or revealed either: 1. is of such a nature as to establish that any “technical data” on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate; or 2. is of such a nature as to require a change in the Contract Documents; or 3. differs materially from that shown or indicated in the Contract Documents; or 4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.16.A), notify Owner and Engineer in writing about such condition. Contractor shall not further disturb EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 15 such condition or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so. B. Engineer’s Review: After receipt of written notice as required by Paragraph 4.03.A, Engineer will promptly review the pertinent condition, determine the necessity of Owner’s obtaining additional exploration or tests with respect thereto, and advise Owner in writing (with a copy to Contractor) of Engineer’s findings and conclusions. C. Possible Price and Times Adjustments 1. The Contract Price or the Contract Times, or both, will be equitably adjusted to the extent that the existence of such differing subsurface or physical condition causes an increase or decrease in Contractor’s cost of, or time required for, performance of the Work; subject, however, to the following: a. such condition must meet any one or more of the categories described in Paragraph 4.03.A; and b. with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of Paragraphs 9.07 and 11.03. 2. Contractor shall not be entitled to any adjustment in the Contract Price or Contract Times if: a. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to Owner with respect to Contract Price and Contract Times by the submission of a Bid or becoming bound under a negotiated contract; or b. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test, or study of the Site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for Contractor prior to Contractor’s making such final commitment; or c. Contractor failed to give the written notice as required by Paragraph 4.03.A. 3. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times, or both, a Claim may be made therefor as provided in Paragraph 10.05. However, Owner and Engineer, and any of their Related Entities shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. 4.04 Underground Facilities A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to Owner or Engineer by the owners of such Underground Facilities, including Owner, or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: 1. Owner and Engineer shall not be responsible for the accuracy or completeness of any such information or data; and 2. the cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for: a. reviewing and checking all such information and data, b. locating all Underground Facilities shown or indicated in the Contract Documents, EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 16 c. coordination of the Work with the owners of such Underground Facilities, including Owner, during construction, and d. the safety and protection of all such Underground Facilities and repairing any damage thereto resulting from the Work. B. Not Shown or Indicated 1. If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.16.A), identify the owner of such Underground Facility and give written notice to that owner and to Owner and Engineer. Engineer will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility. 2. If Engineer concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in Contract Price or Contract Times, Owner or Contractor may make a Claim therefor as provided in Paragraph 10.05. 4.05 Reference Points A. Owner shall provide engineering surveys to establish reference points for construction which in Engineer’s judgment are necessary to enable Contractor to proceed with the Work. Contractor shall be responsible for laying out the Work, shall protect and preserve the established reference points and property monuments, and shall make no changes or relocations without the prior written approval of Owner. Contractor shall report to Engineer whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points or property monuments by professionally qualified personnel. 4.06 Hazardous Environmental Condition at Site A. Reports and Drawings: Reference is made to the Supplementary Conditions for the identification of those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that have been utilized by the Engineer in the preparation of the Contract Documents. B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the general accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such “technical data,” Contractor may not rely upon or make any claim against Owner or Engineer, or any of their Related Entities with respect to: 1. the completeness of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by Contractor and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings; or EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 17 3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions or information. C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom Contractor is responsible. D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 6.16.A); and (iii) notify Owner and Engineer (and promptly thereafter confirm such notice in writing). Owner shall promptly consult with Engineer concerning the necessity for Owner to retain a qualified expert to evaluate such condition or take corrective action, if any. E. Contractor shall not be required to resume Work in connection with such condition or in any affected area until after Owner has obtained any required permits related thereto and delivered to Contractor written notice: (i) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work; or (ii) specifying any special conditions under which such Work may be resumed safely. If Owner and Contractor cannot agree as to entitlement to or on the amount or extent, if any, of any adjustment in Contract Price or Contract Times, or both, as a result of such Work stoppage or such special conditions under which Work is agreed to be resumed by Contractor, either party may make a Claim therefor as provided in Paragraph 10.05. F. If after receipt of such written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then Owner may order the portion of the Work that is in the area affected by such condition to be deleted from the Work. If Owner and Contractor cannot agree as to entitlement to or on the amount or extent, if any, of an adjustment in Contract Price or Contract Times as a result of deleting such portion of the Work, then either party may make a Claim therefor as provided in Paragraph 10.05. Owner may have such deleted portion of the Work performed by Owner’s own forces or others in accordance with Article 7. G. To the fullest extent permitted by Laws and Regulations, Owner shall indemnify and hold harmless Contractor, Subcontractors, and Engineer, and the officers, directors, partners, employees, agents, consultants, and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition, provided that such Hazardous Environmental Condition: (i) was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be included within the scope of the Work, and (ii) was not created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06.G shall obligate Owner to indemnify any individual or entity from and against the consequences of that individual’s or entity’s own negligence. H. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants, and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06. H shall obligate Contractor to indemnify any individual or entity from and against the consequences of that individual’s or entity’s own negligence. I. The provisions of Paragraphs 4.02, 4.03, and 4.04 do not apply to a Hazardous Environmental Condition uncovered or revealed at the Site. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 18 ARTICLE 5 – BONDS AND INSURANCE 5.01 Performance, Payment, and Other Bonds A. Contractor shall furnish performance and payment bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. These bonds shall remain in effect until one year after the date when final payment becomes due or until completion of the correction period specified in Paragraph 13.07, whichever is later, except as provided otherwise by Laws or Regulations or by the Contract Documents. Contractor shall also furnish such other bonds as are required by the Contract Documents. B. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the current list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent must be accompanied by a certified copy of the agent’s authority to act. C. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located or it ceases to meet the requirements of Paragraph 5.01.B, Contractor shall promptly notify Owner and Engineer and shall, within 20 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 5.01.B and 5.02. 5.02 Licensed Sureties and Insurers A. All bonds and insurance required by the Contract Documents to be purchased and maintained by Owner or Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5.03 Certificates of Insurance A. Contractor shall deliver to Owner, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by Owner or any other additional insured) which Contractor is required to purchase and maintain. B. Owner shall deliver to Contractor, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by Contractor or any other additional insured) which Owner is required to purchase and maintain. 5.04 Contractor’s Liability Insurance A. Contractor shall purchase and maintain such liability and other insurance as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees; EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 19 3. claims for damages because of bodily injury, sickness or disease, or death of any person other than Contractor’s employees; 4. claims for damages insured by reasonably available personal injury liability coverage which are sustained: a. by any person as a result of an offense directly or indirectly related to the employment of such person by Contractor, or b. by any other person for any other reason; 5. claims for damages, other than to the Work itself, because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; and 6. claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle. B. The policies of insurance required by this Paragraph 5.04 shall: 1. with respect to insurance required by Paragraphs 5.04.A.3 through 5.04.A.6 inclusive, include as additional insureds (subject to any customary exclusion regarding professional liability) Owner and Engineer, and any other individuals or entities identified in the Supplementary Conditions, all of whom shall be listed as additional insureds, and include coverage for the respective officers, directors, partners, employees, agents, consultants and subcontractors of each and any of all such additional insureds, and the insurance afforded to these additional insureds shall provide primary coverage for all claims covered thereby; 2. include at least the specific coverages and be written for not less than the limits of liability provided in the Supplementary Conditions or required by Laws or Regulations, whichever is greater; 3. include completed operations insurance; 4. include contractual liability insurance covering Contractor’s indemnity obligations under Paragraphs 6.11 and 6.20; 5. contain a provision or endorsement that the coverage afforded will not be canceled, materially changed or renewal refused until at least 30 days prior written notice has been given to Owner and Contractor and to each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued (and the certificates of insurance furnished by the Contractor pursuant to Paragraph 5.03 will so provide); 6. remain in effect at least until final payment and at all times thereafter when Contractor may be correcting, removing, or replacing defective Work in accordance with Paragraph 13.07; and 7. with respect to completed operations insurance, and any insurance coverage written on a claims-made basis, remain in effect for at least two years after final payment. a. Contractor shall furnish Owner and each other additional insured identified in the Supplementary Conditions, to whom a certificate of insurance has been issued, evidence satisfactory to Owner and any such additional insured of continuation of such insurance at final payment and one year thereafter. 5.05 Owner’s Liability Insurance A. In addition to the insurance required to be provided by Contractor under Paragraph 5.04, Owner, at Owner’s option, may purchase and maintain at Owner’s expense Owner’s own liability insurance as will protect Owner against claims which may arise from operations under the Contract Documents. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 20 5.06 Property Insurance A. Unless otherwise provided in the Supplementary Conditions, Contractor shall purchase and maintain property insurance upon the Work at the Site in the amount of the full replacement cost thereof (Contractor shall be responsible for any deductible or self-insured retention.). This insurance shall: 1. include the interests of Owner, Contractor, Subcontractors, and Engineer, and any other individuals or entities identified in the Supplementary Conditions, and the officers, directors, partners, employees, agents, consultants and subcontractors of any of them, each of whom is deemed to have an insurable interest and shall be listed as an insured or additional insured; 2. be written on a Builder’s Risk “all-risk” or open peril or special causes of loss policy form that shall at least include insurance for physical loss or damage to the Work, temporary buildings, falsework, and materials and equipment in transit, and shall insure against at least the following perils or causes of loss: fire, lightning, extended coverage, theft, vandalism and malicious mischief, earthquake, collapse, debris removal, demolition occasioned by enforcement of Laws and Regulations, water damage (other than caused by flood), and such other perils or causes of loss as may be specifically required by the Supplementary Conditions; 3. include expenses incurred in the repair or replacement of any insured property (including but not limited to fees and charges of engineers and architects); 4. cover materials and equipment stored at the Site or at another location that was agreed to in writing by Owner prior to being incorporated in the Work, provided that such materials and equipment have been included in an Application for Payment recommended by Engineer; 5. allow for partial utilization of the Work by Owner; 6. include testing and startup; and 7. be maintained in effect until final payment is made unless otherwise agreed to in writing by Owner, Contractor, and Engineer with 30 days written notice to each other additional insured to whom a certificate of insurance has been issued. B. Contractor shall purchase and maintain such boiler and machinery insurance or additional property insurance as may be required by the Supplementary Conditions or Laws and Regulations which will include the interests of Owner, Contractor, Subcontractors, and Engineer, and any other individuals or entities identified in the Supplementary Conditions, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them, each of whom is deemed to have an insurable interest and shall be listed as an insured or additional insured. C. All the policies of insurance (and the certificates or other evidence thereof) required to be purchased and maintained in accordance with Paragraph 5.06 will contain a provision or endorsement that the coverage afforded will not be canceled or materially changed or renewal refused until at least 30 days prior written notice has been given to Owner and Contractor and to each other additional insured to whom a certificate of insurance has been issued and will contain waiver provisions in accordance with Paragraph 5.07. D. Owner shall not be responsible for purchasing and maintaining any property insurance specified in this Paragraph 5.06 to protect the interests of Contractor, Subcontractors, or others in the Work to the extent of any deductible amounts that are identified in the Supplementary Conditions. The risk of loss within such identified deductible amount will be borne by Contractor, Subcontractors, or others suffering any such loss, and if any of them wishes property insurance coverage within the limits of such amounts, each may purchase and maintain it at the purchaser’s own expense. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 21 5.07 Waiver of Rights A. Owner and Contractor intend that all policies purchased in accordance with Paragraph 5.06 will protect Owner, Contractor, Subcontractors, and Engineer, and all other individuals or entities identified in the Supplementary Conditions to be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) in such policies and will provide primary coverage for all losses and damages caused by the perils or causes of loss covered thereby. All such policies shall contain provisions to the effect that in the event of payment of any loss or damage the insurers will have no rights of recovery against any of the insureds or additional insureds thereunder. Owner and Contractor waive all rights against each other and their respective officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them for all losses and damages caused by, arising out of or resulting from any of the perils or causes of loss covered by such policies and any other property insurance applicable to the Work; and, in addition, waive all such rights against Subcontractors, and Engineer, and all other individuals or entities identified in the Supplementary Conditions to be listed as insured or additional insured (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) under such policies for losses and damages so caused. None of the above waivers shall extend to the rights that any party making such waiver may have to the proceeds of insurance held by Contractor as trustee or otherwise payable under any policy so issued. B. Owner waives all rights against Contractor, Subcontractors, and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them for: 1. loss due to business interruption, loss of use, or other consequential loss extending beyond direct physical loss or damage to Owner’s property or the Work caused by, arising out of, or resulting from fire or other perils whether or not insured by Owner; and 2. loss or damage to the completed Project or part thereof caused by, arising out of, or resulting from fire or other insured peril or cause of loss covered by any property insurance maintained on the completed Project or part thereof by Owner during partial utilization pursuant to Paragraph 14.05, after Substantial Completion pursuant to Paragraph 14.04, or after final payment pursuant to Paragraph 14.07. C. Any insurance policy maintained by Owner covering any loss, damage or consequential loss referred to in Paragraph 5.07.B shall contain provisions to the effect that in the event of payment of any such loss, damage, or consequential loss, the insurers will have no rights of recovery against Contractor, Subcontractors, or Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them. 5.08 Receipt and Application of Insurance Proceeds A. Any insured loss under the policies of insurance required by Paragraph 5.06 will be adjusted with Contractor and made payable to Contractor as fiduciary for the insureds, as their interests may appear, subject to the requirements of any applicable mortgage clause and of Paragraph 5.08.B. Contractor shall deposit in a separate account any money so received and shall distribute it in accordance with such agreement as the parties in interest may reach. If no other special agreement is reached, the damaged Work shall be repaired or replaced, the moneys so received applied on account thereof. B. Contractor as fiduciary shall have power to adjust and settle any loss with the insurers unless one of the parties in interest shall object in writing within 15 days after the occurrence of loss to Contractor’s exercise of this power. If such objection be made, Contractor as fiduciary shall make settlement with the insurers in accordance with such agreement as the parties in interest may reach. If no such agreement among the parties in interest is reached, Contractor as fiduciary shall adjust and settle the loss with the insurers and, if required in writing by any party in interest, Contractor as fiduciary shall give bond for the proper performance of such duties. 5.09 Acceptance of Bonds and Insurance; Option to Replace A. If either Owner or Contractor has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the other party in accordance with Article 5 on the basis of EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 22 non-conformance with the Contract Documents, the objecting party shall so notify the other party in writing within 10 days after receipt of the certificates (or other evidence requested) required by Paragraph 2.01.B. Owner and Contractor shall each provide to the other such additional information in respect of insurance provided as the other may reasonably request. If either party does not purchase or maintain all of the bonds and insurance required of such party by the Contract Documents, such party shall notify the other party in writing of such failure to purchase prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. Without prejudice to any other right or remedy, the other party may elect to obtain equivalent bonds or insurance to protect such other party’s interests at the expense of the party who was required to provide such coverage, and a Change Order shall be issued to adjust the Contract Price accordingly. 5.10 Partial Utilization, Acknowledgment of Property Insurer A. If Owner finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion of all the Work as provided in Paragraph 14.05, no such use or occupancy shall commence before the insurers providing the property insurance pursuant to Paragraph 5.06 have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be canceled or permitted to lapse on account of any such partial use or occupancy. ARTICLE 6 – CONTRACTOR’S RESPONSIBILITIES 6.01 Supervision and Superintendence A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. Contractor shall not be responsible for the negligence of Owner or Engineer in the design or specification of a specific means, method, technique, sequence, or procedure of construction which is shown or indicated in and expressly required by the Contract Documents. B. At all times during the progress of the Work, Contractor shall assign a competent resident superintendent who shall not be replaced without written notice to Owner and Engineer except under extraordinary circumstances. The superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communications given to or received from the superintendent shall be binding on Contractor. 6.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to survey and lay out the Work and perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours. Contractor will not permit the performance of Work on a Saturday, Sunday, or any legal holiday without Owner’s written consent (which will not be unreasonably withheld) given after prior written notice to Engineer. 6.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, testing, start-up, and completion of the Work. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 23 B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of Owner. If required by Engineer, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. C. All materials and equipment shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 6.04 Progress Schedule A. Contractor shall adhere to the Progress Schedule established in accordance with Paragraph 2.07 as it may be adjusted from time to time as provided below. 1. Contractor shall submit to Engineer for acceptance (to the extent indicated in Paragraph 2.07) proposed adjustments in the Progress Schedule that will not result in changing the Contract Times. Such adjustments will comply with any provisions of the General Requirements applicable thereto. 2. Proposed adjustments in the Progress Schedule that will change the Contract Times shall be submitted in accordance with the requirements of Article 12. Adjustments in Contract Times may only be made by a Change Order. 6.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment or material or equipment of other Suppliers may be submitted to Engineer for review under the circumstances described below. 1. “Or-Equal” Items: If in Engineer’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by Engineer as an “or-equal” item, in which case review and approval of the proposed item may, in Engineer’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. in the exercise of reasonable judgment Engineer determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the Owner or increase in Contract Times, and 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 24 2. Substitute Items a. If in Engineer’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 6.05.A.1, it will be considered a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow Engineer to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by Engineer from anyone other than Contractor. c. The procedure requirements for review by Engineer will be as set forth in Paragraph 6.05.A.2.d, as supplemented in the General Requirements and as Engineer may decide is appropriate under the circumstances. d. Contractor shall make written application to Engineer for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application: 1) shall certify that the proposed substitute item will: a) will perform adequately the functions and achieve the results called for by the general design, b) be similar in substance to that specified, and c) be suited to the same use as that specified; 2) will state: a) the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of Substantial Completion on time; b) whether or not use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with Owner for other work on the Project) to adapt the design to the proposed substitute item; and c) whether or not incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; 3) will identify: a) all variations of the proposed substitute item from that specified , and b) available engineering, sales, maintenance, repair, and replacement services; 4) and shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by Engineer. Contractor shall submit sufficient information to allow Engineer, in Engineer’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. The requirements for review by Engineer will be similar to those provided in Paragraph 6.05.A.2. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 25 C. Engineer’s Evaluation: Engineer will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. Engineer may require Contractor to furnish additional data about the proposed substitute item. Engineer will be the sole judge of acceptability. No “or equal” or substitute will be ordered, installed or utilized until Engineer’s review is complete, which will be evidenced by either a Change Order for a substitute or an approved Shop Drawing for an “or equal.” Engineer will advise Contractor in writing of any negative determination. D. Special Guarantee: Owner may require Contractor to furnish at Contractor’s expense a special performance guarantee or other surety with respect to any substitute. E. Engineer’s Cost Reimbursement: Engineer will record Engineer’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.B. Whether or not Engineer approves a substitute item so proposed or submitted by Contractor, Contractor shall reimburse Owner for the charges of Engineer for evaluating each such proposed substitute. Contractor shall also reimburse Owner for the charges of Engineer for making changes in the Contract Documents (or in the provisions of any other direct contract with Owner) resulting from the acceptance of each proposed substitute. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. 6.06 Concerning Subcontractors, Suppliers, and Others A. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity (including those acceptable to Owner as indicated in Paragraph 6.06.B), whether initially or as a replacement, against whom Owner may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection. B. If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, or other individuals or entities to be submitted to Owner in advance for acceptance by Owner by a specified date prior to the Effective Date of the Agreement, and if Contractor has submitted a list thereof in accordance with the Supplementary Conditions, Owner’s acceptance (either in writing or by failing to make written objection thereto by the date indicated for acceptance or objection in the Bidding Documents or the Contract Documents) of any such Subcontractor, Supplier, or other individual or entity so identified may be revoked on the basis of reasonable objection after due investigation. Contractor shall submit an acceptable replacement for the rejected Subcontractor, Supplier, or other individual or entity, and the Contract Price will be adjusted by the difference in the cost occasioned by such replacement, and an appropriate Change Order will be issued. No acceptance by Owner of any such Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, shall constitute a waiver of any right of Owner or Engineer to reject defective Work. C. Contractor shall be fully responsible to Owner and Engineer for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between Owner or Engineer and any such Subcontractor, Supplier or other individual or entity, nor 2. shall anything in the Contract Documents create any obligation on the part of Owner or Engineer to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. D. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 26 E. Contractor shall require all Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work to communicate with Engineer through Contractor. F. The divisions and sections of the Specifications and the identifications of any Drawings shall not control Contractor in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade. G. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of Owner and Engineer. Whenever any such agreement is with a Subcontractor or Supplier who is listed as an additional insured on the property insurance provided in Paragraph 5.06, the agreement between the Contractor and the Subcontractor or Supplier will contain provisions whereby the Subcontractor or Supplier waives all rights against Owner, Contractor, and Engineer, and all other individuals or entities identified in the Supplementary Conditions to be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them) for all losses and damages caused by, arising out of, relating to, or resulting from any of the perils or causes of loss covered by such policies and any other property insurance applicable to the Work. If the insurers on any such policies require separate waiver forms to be signed by any Subcontractor or Supplier, Contractor will obtain the same. 6.07 Patent Fees and Royalties A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if to the actual knowledge of Owner or Engineer its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by Owner in the Contract Documents. B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 6.08 Permits A. Unless otherwise provided in the Supplementary Conditions, Contractor shall obtain and pay for all construction permits and licenses. Owner shall assist Contractor, when necessary, in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement. Owner shall pay all charges of utility owners for connections for providing permanent service to the Work. 6.09 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither Owner nor Engineer shall be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s primary responsibility to make certain EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 27 that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.03. C. Changes in Laws or Regulations not known at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids) having an effect on the cost or time of performance of the Work shall be the subject of an adjustment in Contract Price or Contract Times. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Paragraph 10.05. 6.10 Taxes A. Contractor shall pay all sales, consumer, use, and other similar taxes required to be paid by Contractor in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance of the Work. 6.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. Should any claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly settle with such other party by negotiation or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law. 3. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against Owner, Engineer, or any other party indemnified hereunder to the extent caused by or based upon Contractor’s performance of the Work. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Cleaning: Prior to Substantial Completion of the Work, Contractor shall clean the Site and the Work and make it ready for utilization by Owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition all property not designated for alteration by the Contract Documents. D. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 6.12 Record Documents A. Contractor shall maintain in a safe place at the Site one record copy of all Drawings, Specifications, Addenda, Change Orders, Work Change Directives, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 28 Samples and a counterpart of all approved Shop Drawings will be available to Engineer for reference. Upon completion of the Work, these record documents, Samples, and Shop Drawings will be delivered to Engineer for Owner. 6.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. All damage, injury, or loss to any property referred to in Paragraph 6.13.A.2 or 6.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor (except damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions of Owner or Engineer or , or anyone employed by any of them, or anyone for whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of Contractor or any Subcontractor, Supplier, or other individual or entity directly or indirectly employed by any of them). D. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and Engineer has issued a notice to Owner and Contractor in accordance with Paragraph 14.07.B that the Work is acceptable (except as otherwise expressly provided in connection with Substantial Completion). 6.14 Safety Representative A. Contractor shall designate a qualified and experienced safety representative at the Site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs. 6.15 Hazard Communication Programs A. Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the Site in accordance with Laws or Regulations. 6.16 Emergencies A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give Engineer prompt written notice if Contractor believes that any significant changes in the Work or variations from the Contract EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 29 Documents have been caused thereby or are required as a result thereof. If Engineer determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Work Change Directive or Change Order will be issued. 6.17 Shop Drawings and Samples A. Contractor shall submit Shop Drawings and Samples to Engineer for review and approval in accordance with the acceptable Schedule of Submittals (as required by Paragraph 2.07). Each submittal will be identified as Engineer may require. 1. Shop Drawings a. Submit number of copies specified in the General Requirements. b. Data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show Engineer the services, materials, and equipment Contractor proposes to provide and to enable Engineer to review the information for the limited purposes required by Paragraph 6.17.D. 2. Samples a. Submit number of Samples specified in the Specifications. b. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as Engineer may require to enable Engineer to review the submittal for the limited purposes required by Paragraph 6.17.D. B. Where a Shop Drawing or Sample is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to Engineer’s review and approval of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. Submittal Procedures 1. Before submitting each Shop Drawing or Sample, Contractor shall have determined and verified: a. all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto; b. the suitability of all materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work; c. all information relative to Contractor’s responsibilities for means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto; and d. shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents. 2. Each submittal shall bear a stamp or specific written certification that Contractor has satisfied Contractor’s obligations under the Contract Documents with respect to Contractor’s review and approval of that submittal. 3. With each submittal, Contractor shall give Engineer specific written notice of any variations, that the Shop Drawing or Sample may have from the requirements of the Contract Documents. This notice shall be both a written communication separate from the Shop Drawings or Sample submittal; and, in addition, by a specific notation made on each Shop Drawing or Sample submitted to Engineer for review and approval of each such variation. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 30 D. Engineer’s Review 1. Engineer will provide timely review of Shop Drawings and Samples in accordance with the Schedule of Submittals acceptable to Engineer. Engineer’s review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 2. Engineer’s review and approval will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. 3. Engineer’s review and approval shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Paragraph 6.17.C.3 and Engineer has given written approval of each such variation by specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample. Engineer’s review and approval shall not relieve Contractor from responsibility for complying with the requirements of Paragraph 6.17.C.1. E. Resubmittal Procedures 1. Contractor shall make corrections required by Engineer and shall return the required number of corrected copies of Shop Drawings and submit, as required, new Samples for review and approval. Contractor shall direct specific attention in writing to revisions other than the corrections called for by Engineer on previous submittals. 6.18 Continuing the Work A. Contractor shall carry on the Work and adhere to the Progress Schedule during all disputes or disagreements with Owner. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by Paragraph 15.04 or as Owner and Contractor may otherwise agree in writing. 6.19 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to Owner that all Work will be in accordance with the Contract Documents and will not be defective. Engineer and its Related Entities shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by Engineer; 2. recommendation by Engineer or payment by Owner of any progress or final payment; EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 31 3. the issuance of a certificate of Substantial Completion by Engineer or any payment related thereto by Owner; 4. use or occupancy of the Work or any part thereof by Owner; 5. any review and approval of a Shop Drawing or Sample submittal or the issuance of a notice of acceptability by Engineer; 6. any inspection, test, or approval by others; or 7. any correction of defective Work by Owner. 6.20 Indemnification A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless Owner and Engineer, and the officers, directors, partners, employees, agents, consultants and subcontractors of each and any of them from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to the performance of the Work, provided that any such claim, cost, loss, or damage is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom but only to the extent caused by any negligent act or omission of Contractor, any Subcontractor, any Supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work or anyone for whose acts any of them may be liable. B. In any and all claims against Owner or Engineer or any of their respective consultants, agents, officers, directors, partners, or employees by any employee (or the survivor or personal representative of such employee) of Contractor, any Subcontractor, any Supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, the indemnification obligation under Paragraph 6.20.A shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for Contractor or any such Subcontractor, Supplier, or other individual or entity under workers’ compensation acts, disability benefit acts, or other employee benefit acts. C. The indemnification obligations of Contractor under Paragraph 6.20.A shall not extend to the liability of Engineer and Engineer’s officers, directors, partners, employees, agents, consultants and subcontractors arising out of: 1. the preparation or approval of, or the failure to prepare or approve, maps, Drawings, opinions, reports, surveys, Change Orders, designs, or Specifications; or 2. giving directions or instructions, or failing to give them, if that is the primary cause of the injury or damage. 6.21 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. Contractor shall not be required to provide professional services in violation of applicable law. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, Owner and Engineer will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings and other submittals prepared by such professional. Shop Drawings and other submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to Engineer. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 32 C. Owner and Engineer shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided Owner and Engineer have specified to Contractor all performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 6.21, Engineer’s review and approval of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. Engineer’s review and approval of Shop Drawings and other submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 6.17.D.1. E. Contractor shall not be responsible for the adequacy of the performance or design criteria required by the Contract Documents. ARTICLE 7 – OTHER WORK AT THE SITE 7.01 Related Work at Site A. Owner may perform other work related to the Project at the Site with Owner’s employees, or via other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then: 1. written notice thereof will be given to Contractor prior to starting any such other work; and 2. if Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times that should be allowed as a result of such other work, a Claim may be made therefor as provided in Paragraph 10.05. B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner and Owner, if Owner is performing other work with Owner’s employees, proper and safe access to the Site, a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and shall properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written consent of Engineer and the others whose work will be affected. The duties and responsibilities of Contractor under this Paragraph are for the benefit of such utility owners and other contractors to the extent that there are comparable provisions for the benefit of Contractor in said direct contracts between Owner and such utility owners and other contractors. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to Engineer in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects and deficiencies in such other work. 7.02 Coordination A. If Owner intends to contract with others for the performance of other work on the Project at the Site, the following will be set forth in Supplementary Conditions: 1. the individual or entity who will have authority and responsibility for coordination of the activities among the various contractors will be identified; 2. the specific matters to be covered by such authority and responsibility will be itemized; and 3. the extent of such authority and responsibilities will be provided. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 33 B. Unless otherwise provided in the Supplementary Conditions, Owner shall have sole authority and responsibility for such coordination. 7.03 Legal Relationships A. Paragraphs 7.01.A and 7.02 are not applicable for utilities not under the control of Owner. B. Each other direct contract of Owner under Paragraph 7.01.A shall provide that the other contractor is liable to Owner and Contractor for the reasonable direct delay and disruption costs incurred by Contractor as a result of the other contractor’s actions or inactions. C. Contractor shall be liable to Owner and any other contractor for the reasonable direct delay and disruption costs incurred by such other contractor as a result of Contractor’s action or inactions. ARTICLE 8 – OWNER’S RESPONSIBILITIES 8.01 Communications to Contractor A. Except as otherwise provided in these General Conditions, Owner shall issue all communications to Contractor through Engineer. 8.02 Replacement of Engineer A. In case of termination of the employment of Engineer, Owner shall appoint an engineer to whom Contractor makes no reasonable objection, whose status under the Contract Documents shall be that of the former Engineer. 8.03 Furnish Data A. Owner shall promptly furnish the data required of Owner under the Contract Documents. 8.04 Pay When Due A. Owner shall make payments to Contractor when they are due as provided in Paragraphs 14.02.C and 14.07.C. 8.05 Lands and Easements; Reports and Tests A. Owner’s duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to Owner’s identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions and drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by Engineer in preparing the Contract Documents. 8.06 Insurance A. Owner’s responsibilities, if any, in respect to purchasing and maintaining liability and property insurance are set forth in Article 5. 8.07 Change Orders A. Owner is obligated to execute Change Orders as indicated in Paragraph 10.03. 8.08 Inspections, Tests, and Approvals A. Owner’s responsibility in respect to certain inspections, tests, and approvals is set forth in Paragraph 13.03.B. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 34 8.09 Limitations on Owner’s Responsibilities A. The Owner shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. Owner will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. 8.10 Undisclosed Hazardous Environmental Condition A. Owner’s responsibility in respect to an undisclosed Hazardous Environmental Condition is set forth in Paragraph 4.06. 8.11 Evidence of Financial Arrangements A. If and to the extent Owner has agreed to furnish Contractor reasonable evidence that financial arrangements have been made to satisfy Owner’s obligations under the Contract Documents, Owner’s responsibility in respect thereof will be as set forth in the Supplementary Conditions. ARTICLE 9 – ENGINEER’S STATUS DURING CONSTRUCTION 9.01 Owner’s Representative A. Engineer will be Owner’s representative during the construction period. The duties and responsibilities and the limitations of authority of Engineer as Owner’s representative during construction are set forth in the Contract Documents and will not be changed without written consent of Owner and Engineer. 9.02 Visits to Site A. Engineer will make visits to the Site at intervals appropriate to the various stages of construction as Engineer deems necessary in order to observe as an experienced and qualified design professional the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, Engineer, for the benefit of Owner, will determine, in general, if the Work is proceeding in accordance with the Contract Documents. Engineer will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. Engineer’s efforts will be directed toward providing for Owner a greater degree of confidence that the completed Work will conform generally to the Contract Documents. On the basis of such visits and observations, Engineer will keep Owner informed of the progress of the Work and will endeavor to guard Owner against defective Work. B. Engineer’s visits and observations are subject to all the limitations on Engineer’s authority and responsibility set forth in Paragraph 9.09. Particularly, but without limitation, during or as a result of Engineer’s visits or observations of Contractor’s Work Engineer will not supervise, direct, control, or have authority over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. 9.03 Project Representative A. If Owner and Engineer agree, Engineer will furnish a Resident Project Representative to assist Engineer in providing more extensive observation of the Work. The authority and responsibilities of any such Resident Project Representative and assistants will be as provided in the Supplementary Conditions, and limitations on the responsibilities thereof will be as provided in Paragraph 9.09. If Owner designates another representative or agent to represent Owner at the Site who is not Engineer’s consultant, agent or employee, the responsibilities and authority and limitations thereon of such other individual or entity will be as provided in the Supplementary Conditions. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 35 9.04 Authorized Variations in Work A. Engineer may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Times and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on Owner and also on Contractor, who shall perform the Work involved promptly. If Owner or Contractor believes that a Field Order justifies an adjustment in the Contract Price or Contract Times, or both, and the parties are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Paragraph 10.05. 9.05 Rejecting Defective Work A. Engineer will have authority to reject Work which Engineer believes to be defective, or that Engineer believes will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Engineer will also have authority to require special inspection or testing of the Work as provided in Paragraph 13.04, whether or not the Work is fabricated, installed, or completed. 9.06 Shop Drawings, Change Orders and Payments A. In connection with Engineer’s authority, and limitations thereof, as to Shop Drawings and Samples, see Paragraph 6.17. B. In connection with Engineer’s authority, and limitations thereof, as to design calculations and design drawings submitted in response to a delegation of professional design services, if any, see Paragraph 6.21. C. In connection with Engineer’s authority as to Change Orders, see Articles 10, 11, and 12. D. In connection with Engineer’s authority as to Applications for Payment, see Article 14. 9.07 Determinations for Unit Price Work A. Engineer will determine the actual quantities and classifications of Unit Price Work performed by Contractor. Engineer will review with Contractor the Engineer’s preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application for Payment or otherwise). Engineer’s written decision thereon will be final and binding (except as modified by Engineer to reflect changed factual conditions or more accurate data) upon Owner and Contractor, subject to the provisions of Paragraph 10.05. 9.08 Decisions on Requirements of Contract Documents and Acceptability of Work A. Engineer will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. All matters in question and other matters between Owner and Contractor arising prior to the date final payment is due relating to the acceptability of the Work, and the interpretation of the requirements of the Contract Documents pertaining to the performance of the Work, will be referred initially to Engineer in writing within 30 days of the event giving rise to the question. B. Engineer will, with reasonable promptness, render a written decision on the issue referred. If Owner or Contractor believe that any such decision entitles them to an adjustment in the Contract Price or Contract Times or both, a Claim may be made under Paragraph 10.05. The date of Engineer’s decision shall be the date of the event giving rise to the issues referenced for the purposes of Paragraph 10.05.B. C. Engineer’s written decision on the issue referred will be final and binding on Owner and Contractor, subject to the provisions of Paragraph 10.05. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 36 D. When functioning as interpreter and judge under this Paragraph 9.08, Engineer will not show partiality to Owner or Contractor and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity. 9.09 Limitations on Engineer’s Authority and Responsibilities A. Neither Engineer’s authority or responsibility under this Article 9 or under any other provision of the Contract Documents nor any decision made by Engineer in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility by Engineer shall create, impose, or give rise to any duty in contract, tort, or otherwise owed by Engineer to Contractor, any Subcontractor, any Supplier, any other individual or entity, or to any surety for or employee or agent of any of them. B. Engineer will not supervise, direct, control, or have authority over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. Engineer will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. C. Engineer will not be responsible for the acts or omissions of Contractor or of any Subcontractor, any Supplier, or of any other individual or entity performing any of the Work. D. Engineer’s review of the final Application for Payment and accompanying documentation and all maintenance and operating instructions, schedules, guarantees, bonds, certificates of inspection, tests and approvals, and other documentation required to be delivered by Paragraph 14.07.A will only be to determine generally that their content complies with the requirements of, and in the case of certificates of inspections, tests, and approvals that the results certified indicate compliance with the Contract Documents. E. The limitations upon authority and responsibility set forth in this Paragraph 9.09 shall also apply to the Resident Project Representative, if any, and assistants, if any. ARTICLE 10 – CHANGES IN THE WORK; CLAIMS 10.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, Owner may, subject to written approval by Agency at any time or from time to time, order additions, deletions, or revisions in the Work by a Change Order, or a Work Change Directive. Upon receipt of any such document, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). B. If Owner and Contractor are unable to agree on entitlement to, or on the amount or extent, if any, of an adjustment in the Contract Price or Contract Times, or both, that should be allowed as a result of a Work Change Directive, a Claim may be made therefor as provided in Paragraph 10.05. 10.02 Unauthorized Changes in the Work A. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an emergency as provided in Paragraph 6.16 or in the case of uncovering Work as provided in Paragraph 13.04.B. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 37 10.03 Execution of Change Orders A. Owner and Contractor shall execute appropriate Change Orders recommended by Engineer covering: 1. changes in the Work which are: (i) ordered by Owner pursuant to Paragraph 10.01.A, (ii) required because of acceptance of defective Work under Paragraph 13.08.A or Owner’s correction of defective Work under Paragraph 13.09, or (iii) agreed to by the parties; 2. changes in the Contract Price or Contract Times which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed in accordance with a Work Change Directive; and 3. changes in the Contract Price or Contract Times which embody the substance of any written decision rendered by Engineer pursuant to Paragraph 10.05; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents and applicable Laws and Regulations, but during any such appeal, Contractor shall carry on the Work and adhere to the Progress Schedule as provided in Paragraph 6.18.A. 10.04 Notification to Surety A. If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Times) is required by the provisions of any bond to be given to a surety, the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted to reflect the effect of any such change. 10.05 Claims A. Engineer’s Decision Required: All Claims, except those waived pursuant to Paragraph 14.09, shall be referred to the Engineer for decision. A decision by Engineer shall be required as a condition precedent to any exercise by Owner or Contractor of any rights or remedies either may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Claims. B. Notice: Written notice stating the general nature of each Claim shall be delivered by the claimant to Engineer and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. The responsibility to substantiate a Claim shall rest with the party making the Claim. Notice of the amount or extent of the Claim, with supporting data shall be delivered to the Engineer and the other party to the Contract within 60 days after the start of such event (unless Engineer allows additional time for claimant to submit additional or more accurate data in support of such Claim). A Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 12.01.B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 12.02.B. Each Claim shall be accompanied by claimant’s written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event. The opposing party shall submit any response to Engineer and the claimant within 30 days after receipt of the claimant’s last submittal (unless Engineer allows additional time). C. Engineer’s Action: Engineer will review each Claim and, within 30 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any, take one of the following actions in writing: 1. deny the Claim in whole or in part, 2. approve the Claim, or 3. notify the parties that the Engineer is unable to resolve the Claim if, in the Engineer’s sole discretion, it would be inappropriate for the Engineer to do so. For purposes of further resolution of the Claim, such notice shall be deemed a denial. D. In the event that Engineer does not take action on a Claim within said 30 days, the Claim shall be deemed denied. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 38 E. Engineer’s written action under Paragraph 10.05.C or denial pursuant to Paragraphs 10.05.C.3 or 10.05.D will be final and binding upon Owner and Contractor, unless Owner or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial. F. No Claim for an adjustment in Contract Price or Contract Times will be valid if not submitted in accordance with this Paragraph 10.05. ARTICLE 11 – COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK 11.01 Cost of the Work A. Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in Paragraph 11.01.B, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work covered by a Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of the Work, the costs to be reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work or because of the event giving rise to the Claim. Except as otherwise may be agreed to in writing by Owner, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items, and shall not include any of the costs itemized in Paragraph 11.01.B. 1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by Owner and Contractor. Such employees shall include, without limitation, superintendents, foremen, and other personnel employed full time at the Site. Payroll costs for employees not employed full time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall include, but not be limited to, salaries and wages plus the cost of fringe benefits, which shall include social security contributions, unemployment, excise, and payroll taxes, workers’ compensation, health and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto. The expenses of performing Work outside of regular working hours, on Saturday, Sunday, or legal holidays, shall be included in the above to the extent authorized by Owner. 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers’ field services required in connection therewith. All cash discounts shall accrue to Contractor unless Owner deposits funds with Contractor with which to make payments, in which case the cash discounts shall accrue to Owner. All trade discounts, rebates and refunds and returns from sale of surplus materials and equipment shall accrue to Owner, and Contractor shall make provisions so that they may be obtained. 3. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by Owner, Contractor shall obtain competitive bids from subcontractors acceptable to Owner and Contractor and shall deliver such bids to Owner, who will then determine, with the advice of Engineer, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor’s Cost of the Work and fee shall be determined in the same manner as Contractor’s Cost of the Work and fee as provided in this Paragraph 11.01. 4. Costs of special consultants (including but not limited to Engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work. 5. Supplemental costs including the following: a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor’s employees incurred in discharge of duties connected with the Work. b. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 39 consumed in the performance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor. c. Rentals of all construction equipment and machinery, and the parts thereof whether rented from Contractor or others in accordance with rental agreements approved by Owner with the advice of Engineer, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. d. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable, imposed by Laws and Regulations. e. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses. f. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work (except losses and damages within the deductible amounts of property insurance established in accordance with Paragraph 5.06.D), provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of Owner. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor’s fee. g. The cost of utilities, fuel, and sanitary facilities at the Site. h. Minor expenses such as telegrams, long distance telephone calls, telephone service at the Site, expressages, and similar petty cash items in connection with the Work. i. The costs of premiums for all bonds and insurance Contractor is required by the Contract Documents to purchase and maintain. B. Costs Excluded: The term Cost of the Work shall not include any of the following items: 1. Payroll costs and other compensation of Contractor’s officers, executives, principals (of partnerships and sole proprietorships), general managers, safety managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor’s principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 11.01.A.1 or specifically covered by Paragraph 11.01.A.4, all of which are to be considered administrative costs covered by the Contractor’s fee. 2. Expenses of Contractor’s principal and branch offices other than Contractor’s office at the Site. 3. Any part of Contractor’s capital expenses, including interest on Contractor’s capital employed for the Work and charges against Contractor for delinquent payments. 4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property. 5. Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in Paragraphs 11.01.A and 11.01.B. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 40 C. Contractor’s Fee: When all the Work is performed on the basis of cost-plus, Contractor’s fee shall be determined as set forth in the Agreement. When the value of any Work covered by a Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor’s fee shall be determined as set forth in Paragraph 12.01.C. D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to Paragraphs 11.01.A and 11.01.B, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in a form acceptable to Engineer an itemized cost breakdown together with supporting data. 11.02 Allowances A. It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to Owner and Engineer. B. Cash Allowances 1. Contractor agrees that: a. the cash allowances include the cost to Contractor (less any applicable trade discounts) of materials and equipment required by the allowances to be delivered at the Site, and all applicable taxes; and b. Contractor’s costs for unloading and handling on the Site, labor, installation, overhead, profit, and other expenses contemplated for the cash allowances have been included in the Contract Price and not in the allowances, and no demand for additional payment on account of any of the foregoing will be valid. C. Contingency Allowance 1. Contractor agrees that a contingency allowance, if any, is for the sole use of Owner to cover unanticipated costs. D. Prior to final payment, an appropriate Change Order will be issued as recommended by Engineer to reflect actual amounts due Contractor on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.03 Unit Price Work A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by Engineer subject to the provisions of Paragraph 9.07. C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover Contractor’s overhead and profit for each separately identified item. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 41 D. Owner or Contractor may make a Claim for an adjustment in the Contract Price in accordance with Paragraph 10.05 if: 1. the Bid price of a particular item of Unit Price Work amounts to more than 5 percent of the Contract Price and the variation in the quantity of that particular item of Unit Price Work performed by Contractor differs by more than 25 percent from the estimated quantity of such item indicated in the Agreement; and 2. there is no corresponding adjustment with respect to any other item of Work; and 3. Contractor believes that Contractor is entitled to an increase in Contract Price as a result of having incurred additional expense or Owner believes that Owner is entitled to a decrease in Contract Price and the parties are unable to agree as to the amount of any such increase or decrease. ARTICLE 12 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES 12.01 Change of Contract Price A. The Contract Price may only be changed by a Change Order. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the Engineer and the other party to the Contract in accordance with the provisions of Paragraph 10.05. B. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows: 1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 11.03); or 2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 12.01.C.2); or 3. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached under Paragraph 12.01.B.2, on the basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor’s fee for overhead and profit (determined as provided in Paragraph 12.01.C). C. Contractor’s Fee: The Contractor’s fee for overhead and profit shall be determined as follows: 1. a mutually acceptable fixed fee; or 2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost of the Work: a. for costs incurred under Paragraphs 11.01.A.1 and 11.01.A.2, the Contractor’s fee shall be 15 percent; b. for costs incurred under Paragraph 11.01.A.3, the Contractor’s fee shall be five percent; c. where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraph 12.01.C.2.a is that the Subcontractor who actually performs the Work, at whatever tier, will be paid a fee of 15 percent of the costs incurred by such Subcontractor under Paragraphs 11.01.A.1 and 11.01.A.2 and that any higher tier Subcontractor and Contractor will each be paid a fee of five percent of the amount paid to the next lower tier Subcontractor; d. no fee shall be payable on the basis of costs itemized under Paragraphs 11.01.A.4, 11.01.A.5, and 11.01.B; EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 42 e. the amount of credit to be allowed by Contractor to Owner for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor’s fee by an amount equal to five percent of such net decrease; and f. when both additions and credits are involved in any one change, the adjustment in Contractor’s fee shall be computed on the basis of the net change in accordance with Paragraphs 12.01.C.2.a through 12.01.C.2.e, inclusive. 12.02 Change of Contract Times A. The Contract Times may only be changed by a Change Order. Any Claim for an adjustment in the Contract Times shall be based on written notice submitted by the party making the Claim to the Engineer and the other party to the Contract in accordance with the provisions of Paragraph 10.05. B. Any adjustment of the Contract Times covered by a Change Order or any Claim for an adjustment in the Contract Times will be determined in accordance with the provisions of this Article 12. 12.03 Delays A. Where Contractor is prevented from completing any part of the Work within the Contract Times due to delay beyond the control of Contractor, the Contract Times will be extended in an amount equal to the time lost due to such delay if a Claim is made therefor as provided in Paragraph 12.02.A. Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by Owner, acts or neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God. B. If Owner, Engineer, or other contractors or utility owners performing other work for Owner as contemplated by Article 7, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitable adjustment in the Contract Price or the Contract Times, or both. Contractor’s entitlement to an adjustment of the Contract Times is conditioned on such adjustment being essential to Contractor’s ability to complete the Work within the Contract Times. C. If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions, acts of God, acts or failures to act of utility owners not under the control of Owner, or other causes not the fault of and beyond control of Owner and Contractor, then Contractor shall be entitled to an equitable adjustment in Contract Times, if such adjustment is essential to Contractor’s ability to complete the Work within the Contract Times. Such an adjustment shall be Contractor’s sole and exclusive remedy for the delays described in this Paragraph 12.03.B. 1. delays caused by or within the control of Contractor; or D. Owner, Engineer and the Related Entities of each of them shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of Engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. E. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 43 ARTICLE 13 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 13.01 Notice of Defects A. Prompt notice of all defective Work of which Owner or Engineer has actual knowledge will be given to Contractor. All defective Work may be rejected, corrected, or accepted as provided in this Article 13. 13.02 Access to Work A. Owner, Engineer, their consultants and other representatives and personnel of Owner, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspecting, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s Site safety procedures and programs so that they may comply therewith as applicable. 13.03 Tests and Inspections A. Contractor shall give Engineer timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. Owner shall employ and pay for the services of an independent testing laboratory to perform all inspections, tests, or approvals required by the Contract Documents except: 1. for inspections, tests, or approvals covered by Paragraphs 13.03.C and 13.03.D below; 2. that costs incurred in connection with tests or inspections conducted pursuant to Paragraph 13.04.B shall be paid as provided in said Paragraph 13.04.C; and 3. as otherwise specifically provided in the Contract Documents. C. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested, or approved by an employee or other representative of such public body, Contractor shall assume full responsibility for arranging and obtaining such inspections, tests, or approvals, pay all costs in connection therewith, and furnish Engineer the required certificates of inspection or approval. D. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, or approvals required for Owner’s and Engineer’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, or approvals shall be performed by organizations acceptable to Owner and Engineer. E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of Engineer, it must, if requested by Engineer, be uncovered for observation. F. Uncovering Work as provided in Paragraph 13.03.E shall be at Contractor’s expense unless Contractor has given Engineer timely notice of Contractor’s intention to cover the same and Engineer has not acted with reasonable promptness in response to such notice. 13.04 Uncovering Work A. If any Work is covered contrary to the written request of Engineer, it must, if requested by Engineer, be uncovered for Engineer’s observation and replaced at Contractor’s expense. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 44 B. If Engineer considers it necessary or advisable that covered Work be observed by Engineer or inspected or tested by others, Contractor, at Engineer’s request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as Engineer may require, that portion of the Work in question, furnishing all necessary labor, material, and equipment. C. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others); and Owner shall be entitled to an appropriate decrease in the Contract Price. If the parties are unable to agree as to the amount thereof, Owner may make a Claim therefor as provided in Paragraph 10.05. D. If, the uncovered Work is not found to be defective, Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Times, or both, directly attributable to such uncovering, exposure, observation, inspection, testing, replacement, and reconstruction. If the parties are unable to agree as to the amount or extent thereof, Contractor may make a Claim therefor as provided in Paragraph 10.05. 13.05 Owner May Stop the Work A. If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, Owner may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of Owner to stop the Work shall not give rise to any duty on the part of Owner to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 13.06 Correction or Removal of Defective Work A. Promptly after receipt of notice, Contractor shall correct all defective Work, whether or not fabricated, installed, or completed, or, if the Work has been rejected by Engineer, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, Contractor shall take no action that would void or otherwise impair Owner’s special warranty and guarantee, if any, on said Work. 13.07 Correction Period A. If within one year after the date of Substantial Completion (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents) or by any specific provision of the Contract Documents, any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by Owner or permitted by Laws and Regulations as contemplated in Paragraph 6.11.A is found to be defective, Contractor shall promptly, without cost to Owner and in accordance with Owner’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by Owner, remove it from the Project and replace it with Work that is not defective, and EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 45 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of Owner’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, Owner may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications. D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work will be extended for an additional period of one year after such correction or removal and replacement has been satisfactorily completed. E. Contractor’s obligations under this Paragraph 13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitation or repose. 13.08 Acceptance of Defective Work A. If, instead of requiring correction or removal and replacement of defective Work, Owner (and, prior to Engineer’s recommendation of final payment, Engineer) prefers to accept it, Owner may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to Owner’s evaluation of and determination to accept such defective Work (such costs to be approved by Engineer as to reasonableness) and the diminished value of the Work to the extent not otherwise paid by Contractor pursuant to this sentence. If any such acceptance occurs prior to Engineer’s recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and Owner shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work so accepted. If the parties are unable to agree as to the amount thereof, Owner may make a Claim therefor as provided in Paragraph 10.05. If the acceptance occurs after such recommendation, an appropriate amount will be paid by Contractor to Owner. 13.09 Owner May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from Engineer to correct defective Work or to remove and replace rejected Work as required by Engineer in accordance with Paragraph 13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, Owner may, after seven days written notice to Contractor, correct or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 13.09, Owner shall proceed expeditiously. In connection with such corrective or remedial action, Owner may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, take possession of Contractor’s tools, appliances, construction equipment and machinery at the Site, and incorporate in the Work all materials and equipment stored at the Site or for which Owner has paid Contractor but which are stored elsewhere. Contractor shall allow Owner, Owner’s representatives, agents and employees, Owner’s other contractors, and Engineer and Engineer’s consultants access to the Site to enable Owner to exercise the rights and remedies under this Paragraph. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 46 C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by Owner in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and Owner shall be entitled to an appropriate decrease in the Contract Price. If the parties are unable to agree as to the amount of the adjustment, Owner may make a Claim therefor as provided in Paragraph 10.05. Such claims, costs, losses and damages will include but not be limited to all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Contractor’s defective Work. D. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performance of the Work attributable to the exercise by Owner of Owner’s rights and remedies under this Paragraph 13.09. ARTICLE 14 – PAYMENTS TO CONTRACTOR AND COMPLETION 14.01 Schedule of Values A. The Schedule of Values established as provided in Paragraph 2.07.A will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to Engineer. Progress payments on account of Unit Price Work will be based on the number of units completed. 14.02 Progress Payments A. Applications for Payments 1. At least 20 days before the date established in the Agreement for each progress payment (but not more often than once a month), Contractor shall submit to Engineer for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that Owner has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect Owner’s interest therein, all of which must be satisfactory to Owner. 2. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that all previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior Applications for Payment. 3. The amount of retainage with respect to progress payments will be as stipulated in the Agreement. B. Review of Applications 1. Engineer will, within 10 days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to Owner or return the Application to Contractor indicating in writing Engineer’s reasons for refusing to recommend payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. Engineer’s recommendation of any payment requested in an Application for Payment will constitute a representation by Engineer to Owner, based on Engineer’s observations on the Site of the executed Work as an experienced and qualified design professional and on Engineer’s review of the Application for Payment and the accompanying data and schedules, that to the best of Engineer’s knowledge, information and belief: a. the Work has progressed to the point indicated; EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 47 b. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under Paragraph 9.07, and to any other qualifications stated in the recommendation); and c. the conditions precedent to Contractor’s being entitled to such payment appear to have been fulfilled in so far as it is Engineer’s responsibility to observe the Work. 3. By recommending any such payment Engineer will not thereby be deemed to have represented that: a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to Engineer in the Contract Documents; or b. that there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by Owner or entitle Owner to withhold payment to Contractor. 4. Neither Engineer’s review of Contractor’s Work for the purposes of recommending payments nor Engineer’s recommendation of any payment, including final payment, will impose responsibility on Engineer: a. to supervise, direct, or control the Work, or b. for the means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or c. for Contractor’s failure to comply with Laws and Regulations applicable to Contractor’s performance of the Work, or d. to make any examination to ascertain how or for what purposes Contractor has used the moneys paid on account of the Contract Price, or e. to determine that title to any of the Work, materials, or equipment has passed to Owner free and clear of any Liens. 5. Engineer may refuse to recommend the whole or any part of any payment if, in Engineer’s opinion, it would be incorrect to make the representations to Owner stated in Paragraph 14.02.B.2. Engineer may also refuse to recommend any such payment or, because of subsequently discovered evidence or the results of subsequent inspections or tests, revise or revoke any such payment recommendation previously made, to such extent as may be necessary in Engineer’s opinion to protect Owner from loss because: a. the Work is defective, or completed Work has been damaged, requiring correction or replacement; b. the Contract Price has been reduced by Change Orders; c. Owner has been required to correct defective Work or complete Work in accordance with Paragraph 13.09; or d. Engineer has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02.A. C. Payment Becomes Due 1. Ten days after presentation of the Application for Payment to Owner with Engineer’s recommendation, the amount recommended will (subject to the provisions of Paragraph 14.02.D) become due, and when due will be paid by Owner to Contractor. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 48 D. Reduction in Payment 1. Owner may refuse to make payment of the full amount recommended by Engineer because: a. claims have been made against Owner on account of Contractor’s performance or furnishing of the Work; b. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to Owner to secure the satisfaction and discharge of such Liens; c. the Contractor's performance or furnishing of the Work is inconsistent with funding Agency requirements; d. there are other items entitling Owner to a set-off against the amount recommended; or e. Owner has actual knowledge of the occurrence of any of the events enumerated in Paragraphs 14.02.B.5.a through 14.02.B.5.c or Paragraph 15.02.A. 2. If Owner refuses to make payment of the full amount recommended by Engineer, Owner will give Contractor immediate written notice (with a copy to Engineer) stating the reasons for such action and promptly pay Contractor any amount remaining after deduction of the amount so withheld. Owner shall promptly pay Contractor the amount so withheld, or any adjustment thereto agreed to by Owner and Contractor, when Contractor corrects to Owner’s satisfaction the reasons for such action. 3. If it is subsequently determined that Owner’s refusal of payment was not justified, the amount wrongfully withheld shall be treated as an amount due as determined by Paragraph 14.02.C.1. 14.03 Contractor’s Warranty of Title A. Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. 14.04 Substantial Completion A. When Contractor considers the entire Work ready for its intended use Contractor shall notify Owner and Engineer in writing that the entire Work is substantially complete (except for items specifically listed by Contractor as incomplete) and request that Engineer issue a certificate of Substantial Completion. B. Promptly after Contractor’s notification, Owner, Agency, Contractor, and Engineer shall make a prefinal inspection of the Work to determine the status of completion. If Engineer does not consider the Work substantially complete, Engineer will notify Contractor in writing giving the reasons therefor. C. If Engineer considers the Work substantially complete, Engineer will deliver to Owner a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment. Owner shall have seven days after receipt of the tentative certificate during which to make written objection to Engineer as to any provisions of the certificate or attached list. If, after considering such objections, Engineer concludes that the Work is not substantially complete, Engineer will within 14 days after submission of the tentative certificate to Owner notify Contractor in writing, stating the reasons therefor. If, after consideration of Owner’s objections, Engineer considers the Work substantially complete, Engineer will within said 14 days execute and deliver to Owner and Contractor a definitive certificate of Substantial Completion (with a revised tentative list of items to be completed or corrected) reflecting such changes from the tentative certificate as Engineer believes justified after consideration of any objections from Owner. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 49 D. At the time of delivery of the tentative certificate of Substantial Completion, Engineer will deliver to Owner and Contractor a written recommendation as to division of responsibilities pending final payment between Owner and Contractor with respect to security, operation, safety, and protection of the Work, maintenance, heat, utilities, insurance, and warranties and guarantees. Unless Owner and Contractor agree otherwise in writing and so inform Engineer in writing prior to Engineer’s issuing the definitive certificate of Substantial Completion, Engineer’s aforesaid recommendation will be binding on Owner and Contractor until final payment. E. Owner shall have the right to exclude Contractor from the Site after the date of Substantial Completion subject to allowing Contractor reasonable access to complete or correct items on the tentative list. 14.05 Partial Utilization A. Prior to Substantial Completion of all the Work, Owner may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which Owner, Engineer, and Contractor agree constitutes a separately functioning and usable part of the Work that can be used by Owner for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work, subject to the following conditions. 1. Owner at any time may request Contractor in writing to permit Owner to use or occupy any such part of the Work which Owner believes to be ready for its intended use and substantially complete. If and when Contractor agrees that such part of the Work is substantially complete, Contractor will certify to Owner and Engineer that such part of the Work is substantially complete and request Engineer to issue a certificate of Substantial Completion for that part of the Work. 2. Contractor at any time may notify Owner and Engineer in writing that Contractor considers any such part of the Work ready for its intended use and substantially complete and request Engineer to issue a certificate of Substantial Completion for that part of the Work. 3. Within a reasonable time after either such request, Owner, Contractor, and Engineer shall make an inspection of that part of the Work to determine its status of completion. If Engineer does not consider that part of the Work to be substantially complete, Engineer will notify Owner and Contractor in writing giving the reasons therefor. If Engineer considers that part of the Work to be substantially complete, the provisions of Paragraph 14.04 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto. 4. No use or occupancy or separate operation of part of the Work may occur prior to compliance with the requirements of Paragraph 5.10 regarding property insurance. 14.06 Final Inspection A. Upon written notice from Contractor that the entire Work or an agreed portion thereof is complete, Engineer will promptly make a final inspection with Owner, Agency, and Contractor and will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 14.07 Final Payment A. Application for Payment 1. After Contractor has, in the opinion of Engineer, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Contract Documents, all maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurance certificates of inspection, marked-up record documents (as provided in Paragraph 6.12), and other documents, Contractor may make application for final payment following the procedure for progress payments. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 50 2. The final Application for Payment shall be accompanied (except as previously delivered) by: a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.04.B.7; b. consent of the surety, if any, to final payment; c. a list of all Claims against Owner that Contractor believes are unsettled; and d. complete and legally effective releases or waivers (satisfactory to Owner) of all Lien rights arising out of or Liens filed in connection with the Work. 3. In lieu of the releases or waivers of Liens specified in Paragraph 14.07.A.2 and as approved by Owner, Contractor may furnish receipts or releases in full and an affidavit of Contractor that: (i) the releases and receipts include all labor, services, material, and equipment for which a Lien could be filed; and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which Owner or Owner’s property might in any way be responsible have been paid or otherwise satisfied. If any Subcontractor or Supplier fails to furnish such a release or receipt in full, Contractor may furnish a bond or other collateral satisfactory to Owner to indemnify Owner against any Lien. B. Engineer’s Review of Application and Acceptance 1. If, on the basis of Engineer’s observation of the Work during construction and final inspection, and Engineer’s review of the final Application for Payment and accompanying documentation as required by the Contract Documents, Engineer is satisfied that the Work has been completed and Contractor’s other obligations under the Contract Documents have been fulfilled, Engineer will, within ten days after receipt of the final Application for Payment, indicate in writing Engineer’s recommendation of payment and present the Application for Payment to Owner for payment. At the same time Engineer will also give written notice to Owner and Contractor that the Work is acceptable subject to the provisions of Paragraph 14.09. Otherwise, Engineer will return the Application for Payment to Contractor, indicating in writing the reasons for refusing to recommend final payment, in which case Contractor shall make the necessary corrections and resubmit the Application for Payment. C. Payment Becomes Due 1. Thirty days after the presentation to Owner of the Application for Payment and accompanying documentation, the amount recommended by Engineer, less any sum Owner is entitled to set off against Engineer’s recommendation, including but not limited to liquidated damages, will become due and will be paid by Owner to Contractor. 14.08 Final Completion Delayed A. If, through no fault of Contractor, final completion of the Work is significantly delayed, and if Engineer so confirms, Owner shall, upon receipt of Contractor’s final Application for Payment (for Work fully completed and accepted) and recommendation of Engineer, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by Owner for Work not fully completed or corrected is less than the retainage stipulated in the Agreement, and if bonds have been furnished as required in Paragraph 5.01, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by Contractor to Engineer with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of Claims. The remaining balance of any sum included in the final Application for Payment but held by OWNER for Work not fully completed and accepted will become due when the Work is fully completed and accepted. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 51 14.09 Waiver of Claims A. The making and acceptance of final payment will constitute: 1. a waiver of all Claims by Owner against Contractor, except Claims arising from unsettled Liens, from defective Work appearing after final inspection pursuant to Paragraph 14.06, from failure to comply with the Contract Documents or the terms of any special guarantees specified therein, or from Contractor’s continuing obligations under the Contract Documents; and 2. a waiver of all Claims by Contractor against Owner other than those previously made in accordance with the requirements herein and expressly acknowledged by Owner in writing as still unsettled. ARTICLE 15 – SUSPENSION OF WORK AND TERMINATION 15.01 Owner May Suspend Work A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 90 consecutive days by notice in writing to Contractor and Engineer which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be granted an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in Paragraph 10.05. 15.02 Owner May Terminate for Cause A. The occurrence of any one or more of the following events will justify termination for cause: 1. Contractor’s persistent failure to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the Progress Schedule established under Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04); 2. Contractor’s disregard of Laws or Regulations of any public body having jurisdiction; 3. Contractor’s disregard of the authority of Engineer; or 4. Contractor’s violation in any substantial way of any provisions of the Contract Documents. B. If one or more of the events identified in Paragraph 15.02.A occur, Owner may, after giving Contractor (and surety) seven days written notice of its intent to terminate the services of Contractor: 1. exclude Contractor from the Site, and take possession of the Work and of all Contractor’s tools, appliances, construction equipment, and machinery at the Site, and use the same to the full extent they could be used by Contractor (without liability to Contractor for trespass or conversion), 2. incorporate in the Work all materials and equipment stored at the Site or for which Owner has paid Contractor but which are stored elsewhere, and 3. complete the Work as Owner may deem expedient. C. If Owner proceeds as provided in Paragraph 15.02.B, Contractor shall not be entitled to receive any further payment until the Work is completed. If the unpaid balance of the Contract Price exceeds all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Owner arising out of or relating to completing the Work, such excess will be paid to Contractor. If such claims, costs, losses, and damages exceed such unpaid balance, Contractor shall pay the difference to Owner. Such claims, costs, losses, and damages incurred by EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 52 Owner will be reviewed by Engineer as to their reasonableness and, when so approved by Engineer, incorporated in a Change Order. When exercising any rights or remedies under this Paragraph Owner shall not be required to obtain the lowest price for the Work performed. D. Notwithstanding Paragraphs 15.02.B and 15.02.C, Contractor’s services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice. E. Where Contractor’s services have been so terminated by Owner, the termination will not affect any rights or remedies of Owner against Contractor then existing or which may thereafter accrue. Any retention or payment of moneys due Contractor by Owner will not release Contractor from liability. F. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 5.01.A, the termination procedures of that bond shall supersede the provisions of Paragraphs 15.02.B, and 15.02.C. 15.03 Owner May Terminate For Convenience A. Upon seven days written notice to Contractor and Engineer, Owner may, without cause and without prejudice to any other right or remedy of Owner, terminate the Contract. In such case, Contractor shall be paid for (without duplication of any items): 1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 2. expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses; 3. all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred in settlement of terminated contracts with Subcontractors, Suppliers, and others; and 4. reasonable expenses directly attributable to termination. B. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination. 15.04 Contractor May Stop Work or Terminate A. If, through no act or fault of Contractor, (i) the Work is suspended for more than 90 consecutive days by Owner or under an order of court or other public authority, or (ii) Engineer fails to act on any Application for Payment within 30 days after it is submitted, or (iii) Owner fails for 30 days to pay Contractor any sum finally determined to be due, then Contractor may, upon seven days written notice to Owner and Engineer, and provided Owner or Engineer do not remedy such suspension or failure within that time, terminate the Contract and recover from Owner payment on the same terms as provided in Paragraph 15.03. B. In lieu of terminating the Contract and without prejudice to any other right or remedy, if Engineer has failed to act on an Application for Payment within 30 days after it is submitted, or Owner has failed for 30 days to pay Contractor any sum finally determined to be due, Contractor may, seven days after written notice to Owner and Engineer, stop the Work until payment is made of all such amounts due Contractor, including interest thereon. The provisions of this Paragraph 15.04 are not intended to preclude Contractor from making a Claim under Paragraph 10.05 for an adjustment in Contract Price or Contract Times or otherwise for expenses or damage directly attributable to Contractor’s stopping the Work as permitted by this Paragraph. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 53 ARTICLE 16 – DISPUTE RESOLUTION 16.01 Methods and Procedures A. Owner and Contractor may mutually request mediation of any Claim submitted to Engineer for a decision under Paragraph 10.05 before such decision becomes final and binding. The mediation will be governed by the Construction Industry Mediation Rules of the American Arbitration Association in effect as of the Effective Date of the Agreement. The request for mediation shall be submitted in writing to the American Arbitration Association. Timely submission of the request shall stay the effect of Paragraph 10.05.E. B. Owner and Contractor shall participate in the mediation process in good faith. The process hall be concluded within 60 days of filing of the request. The date of termination of the mediation shall be determined by application of the mediation rules referenced above. C. If the claim is not resolved by mediation, Engineer’s action under Paragraph 10.05.C or a denial pursuant to Paragraphs 10.05.C.3 or 10.05.D shall become final and binding 30 days after termination of the mediation unless, within that time period, Owner or Contractor: 1. elects in writing to invoke any dispute resolution process provided for in the Supplementary Conditions, or 2. agrees with the other party to submit the Claim to another dispute resolution process, or 3. gives written notice to the other party of their intent to submit the Claim to a court of competent jurisdiction. ARTICLE 17 – MISCELLANEOUS 17.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. 17.02 Computation of Times A. When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation. 17.03 Cumulative Remedies A. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 54 17.04 Survival of Obligations A. All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 17.05 Controlling Law A. This Contract is to be governed by the law of the state in which the Project is located. 17.06 Headings A. Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. ARTICLE 18 – FEDERAL REQUIREMENTS 18.01 Agency Not a Party A. This Contract is expected to be funded in part with funds provided by Agency. Neither Agency, nor any of its departments, entities, or employees is a party to this Contract. 18.02 Contract Approval A. Owner and Contractor will furnish Owner’s attorney such evidence as required so that Owner’s attorney can complete and execute the following “Certificate of Owner’s Attorney” (Exhibit GC-A) before Owner submits the executed Contract Documents to Agency for approval. B. Concurrence by Agency in the award of the Contract is required before the Contract is effective. 18.03 Conflict of Interest A. Contractor may not knowingly contract with a supplier or manufacturer if the individual or entity who prepared the plans and specifications has a corporate or financial affiliation with the supplier or manufacturer. B. Owner’s officers, employees, or agents shall not engage in the award or administration of this Contract if a conflict of interest, real or apparent, would be involved. Such a conflict would arise when: (i) the employee, officer or agent; (ii) any member of their immediate family; (iii) their partner or (iv) an organization that employs, or is about to employ, any of the above, has a financial interest in Contractor. Owner’s officers, employees, or agents shall neither solicit nor accept gratuities, favors or anything of monetary value from Contractor or subcontractors. 18.04 Gratuities A. If Owner finds after a notice and hearing that Contractor, or any of Contractor’s agents or representatives, offered or gave gratuities (in the form of entertainment, gifts, or otherwise) to any official, employee, or agent of Owner or Agency in an attempt to secure this Contract or favorable treatment in awarding, amending, or making any determinations related to the performance of this Contract, Owner may, by written notice to Contractor, terminate this Contract. Owner may also pursue other rights and remedies that the law or this Contract provides. However, the existence of the facts on which Owner bases such findings shall be an issue and may be reviewed in proceedings under the dispute resolution provisions of this Contract. B. In the event this Contract is terminated as provided in paragraph 18.04.A, Owner may pursue the same remedies against Contractor as it could pursue in the event of a breach of this Contract by Contractor. As a penalty, in addition to any other damages to which it may be entitled by law, Owner may pursue exemplary damages in an EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 55 amount (as determined by Owner) which shall not be less than three nor more than ten times the costs Contractor incurs in providing any such gratuities to any such officer or employee. 18.05 Audit and Access to Records A. For all negotiated contracts and negotiated modifications (except those of $10,000 or less), Owner, Agency, the Comptroller General, or any of their duly authorized representatives, shall have access to any books, documents, papers, and records of the Contractor, which are pertinent to the Contract, for the purpose of making audits, examinations, excerpts and transcriptions. Contractor shall maintain all required records for three years after final payment is made and all other pending matters are closed. 18.06 Small, Minority and Women’s Businesses A. If Contractor intends to let any subcontracts for a portion of the work, Contractor shall take affirmative steps to assure that small, minority and women’s businesses are used when possible as sources of supplies, equipment, construction, and services. Affirmative steps shall consist of: (1) including qualified small, minority and women’s businesses on solicitation lists; (2) assuring that small, minority and women’s businesses are solicited whenever they are potential sources; (3) dividing total requirements when economically feasible, into small tasks or quantities to permit maximum participation of small, minority, and women’s businesses; (4) establishing delivery schedules, where the requirements of the work permit, which will encourage participation by small, minority and women’s businesses; (5) using the services and assistance of the Small Business Administration and the Minority Business Development Agency of the U.S. Department of Commerce; (6) requiring each party to a subcontract to take the affirmative steps of this section; and (7) Contractor is encouraged to procure goods and services from labor surplus area firms. 18.07 Anti-Kickback A. Contractor shall comply with the Copeland Anti-Kickback Act (18 USC 874 and 40 USC 276c) as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Buildings or Public Works Financed in Whole or in Part by Loans or Grants of the United States”). The Act provides that Contractor or subcontractor shall be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public facilities, to give up any part of the compensation to which they are otherwise entitled. Owner shall report all suspected or reported violations to Agency. 18.08 Clean Air and Pollution Control Acts A. If this Contract exceeds $100,000, Contractor shall comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 USC 7401 et seq.) and the Federal Water Pollution Control Act as amended (33 USC 1251 et seq.). Contractor will report violations to the Agency and the Regional Office of the EPA. 18.09 State Energy Policy A. Contractor shall comply with the Energy Policy and Conservation Act (P.L. 94-163). Mandatory standards and policies relating to energy efficiency, contained in any applicable State Energy Conservation Plan, shall be utilized. 18.10 Equal Opportunity Requirements A. If this Contract exceeds $10,000, Contractor shall comply with Executive Order 11246, “Equal Employment Opportunity,” as amended by Executive Order 11375, “Amending Executive Order 11246 Relating to Equal Employment Opportunity,” and as supplemented by regulations at 41 CFR part 60, “Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor.” B. Contractor’s compliance with Executive Order 11246 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative active obligations required by the Standard Federal Equal Employment EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 56 Opportunity Construction Contract Specifications, as set forth in 41 CFR Part 60-4 and its efforts to meet the goals established for the geographical area where the Contract is to be performed. The hours of minority and female employment and training must be substantially uniform throughout the length of the Contract, and in each trade, and Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting Contractor’s goals shall be a violation of the Contract, the Executive Order, and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed. C. Contractor shall provide written notification to the Director of the Office of Federal Contract Compliance Programs within 10 working days of award of any construction subcontract in excess of $10,000 at any tier for construction work under the Contract resulting from this solicitation. The notification shall list the name, address, and telephone number of the subcontractor; employer identification number; estimated dollar amount of subcontract; estimated starting and completion dates of the subcontract; and the geographical area in which the Contract is to be performed. 18.11 Restrictions on Lobbying A. Contractor and each subcontractor shall comply with Restrictions on Lobbying (Public Law 101-121, Section 319) as supplemented by applicable Agency regulations. This Law applies to the recipients of contracts and subcontracts that exceed $100,000 at any tier under a Federal loan that exceeds $150,000 or a Federal grant that exceeds $100,000. If applicable, Contractor must complete a certification form on lobbying activities related to a specific Federal loan or grant that is a funding source for this Contract. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant, or any other award covered by 31 USC 1352. Each tier shall disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Certifications and disclosures are forwarded from tier to tier up to the Owner. Necessary certification and disclosure forms shall be provided by Owner. 18.12 Environmental Requirements A. When constructing a project involving trenching and/or other related earth excavations, Contractor shall comply with the following environmental constraints: 1. Wetlands – When disposing of excess, spoil, or other construction materials on public or private property, Contractor shall not fill in or otherwise convert wetlands. 2. Floodplains – When disposing of excess, spoil, or other construction materials on public or private property, Contractor shall not fill in or otherwise convert 100 year floodplain areas delineated on the latest Federal Emergency Management Agency Floodplain Maps, or other appropriate maps, i.e., alluvial soils on NRCS Soil Survey Maps. 3. Historic Preservation – Any excavation by Contractor that uncovers an historical or archaeological artifact shall be immediately reported to Owner and a representative of Agency. Construction shall be temporarily halted pending the notification process and further directions issued by Agency after consultation with the State Historic Preservation Officer (SHPO). 4. Endangered Species – Contractor shall comply with the Endangered Species Act, which provides for the protection of endangered and/or threatened species and critical habitat. Should any evidence of the presence of endangered and/or threatened species or their critical habitat be brought to the attention of Contractor, Contractor will immediately report this evidence to Owner and a representative of Agency. Construction shall be temporarily halted pending the notification process and further directions issued by Agency after consultation with the U.S. Fish and Wildlife Service. EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 57 EXHIBIT GC-A Certificate of Owner’s Attorney I, the undersigned, ___________________________________, the duly authorized and acting legal representative of ___________________________________________________________, do hereby certify as follows: I have examined the attached Contract(s) and performance and payment bond(s) and the manner of execution thereof, and I am of the opinion that each of the aforesaid agreements is adequate and has been duly executed by the proper parties thereto acting through their duly authorized representatives; that said representatives have full power and authority to execute said agreements on behalf of the respective parties named thereon; and that the foregoing agreements constitute valid and legally binding obligations upon the parties executing the same in accordance with the terms, conditions, and provisions thereof. __________________________________________________ Date: ____________________________ EJCDC C-710 Standard General Conditions of the Construction Contract, Funding Agency Edition Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved. 00710 - 58 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -1 SECTION 00800A SUPPLEMENTARY CONDITIONS These Supplementary Conditions amend or supplement the Standard General Conditions of the Construction Contract (EJCDC No. C-710, 2002 Edition) and other provisions of the Contract Documents as indicated below. All provisions which are not specifically amended or supplemented hereby remain in full force and effect. ARTICLE 1. DEFINITIONS SC-1.01. A.13 Add the following language at the beginning of the definition entitled "Contract Documents" in the General Conditions: The Invitation to Bid, Instructions to Bidders SC-1.01.A.30 Add the following language to the definition entitled “Owner” in the General Conditions: The term “Owner” shall mean the City of Northampton, Massachusetts acting through its Department of Planning & Sustainability. SC-1.01.A.46 Delete the definition of Substantial Completion in the General Conditions in its entirety and add the following in its place: The Work required by the Contract has been completed except for work having a Contract Price of less than one percent of the then adjusted total contract price, or substantially all of the Work has been completed and opened to Owner's use except for minor incomplete or unsatisfactory work items that do not materially impair the usefulness of the Work required by the Contract. SC-1.01.A.54 Add the following definition to the General Conditions: State – The entity that shall mean the Commonwealth of Massachusetts. Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -2 ARTICLE 2. PRELIMINARY MATTERS SC-2.01 Delete paragraph 2.01.B of the General Conditions in its entirety and insert the following in its place: 2.01.B Before any work at the site is started, CONTRACTOR shall deliver to OWNER, with a copy to ENGINEER, certificates of insurance (and other evidence of insurance requested by OWNER) which CONTRACTOR is required to purchase and maintain in accordance with the requirements of Article 5. Add the following new paragraphs immediately after paragraph 2.01.B of the General Conditions which is to read as follows: 2.01.B.1 Contractor shall include and identify on the certificate of insurance, indemnification as required by Article 6.20 of the General Conditions (Section 00710). SC-2.03 Delete paragraph 2.03 of the General Conditions in its entirety and insert the following in its place: 2.03.A The Contract Time will commence to run on the tenth day following the effective date of the Agreement. ARTICLE 3. CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE SC-3.01 Add the following new paragraphs immediately after paragraph 3.01.A of the General Conditions which is to read as follows: 3.01.A.1 Each and every provision of law and clause required by law to be inserted in the Contract shall be deemed to be inserted herein, and the Contract shall be read and enforced as though they were included herein. If through mistake or otherwise any such provision is not inserted, or is not correctly inserted, then upon the application of either party, the Contract shall forthwith be physically amended to make such insertion. 3.01.A.2 Sections of Division 1 - General Requirements govern the execution of the work of all sections of the specifications. ARTICLE 4. AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -3 SC-4.01 Add the following new paragraph immediately after paragraph 4.01.A of the General Conditions which is to read as follows: 4.01.A.1 If all lands and rights-of-way are not obtained as herein contemplated before construction begins, CONTRACTOR shall begin the Work upon such land and rights-of-way as OWNER has previously acquired and no claim for damages whatsoever will be allowed by reason of the delay in obtaining the remaining lands and rights-of-way. Should OWNER be prevented or enjoined from proceeding with the Work, or from authorizing its prosecution, either before or after the commencement, by reason of any litigation, or by reason of its inability to procure any lands or rights-of-way for the Work, CONTRACTOR shall not be entitled to make or assert claim for damage by reason of said delay, or to withdraw from the Agreement except by consent of OWNER. Time for completion of the Work will be extended as provided in Article 12, to such time as OWNER determines will compensate for the time lost by such delay. SC-4.02 Delete paragraphs 4.02.A.1 and 4.02.A.2 in its entirety and insert the following in its place: 4.02.A.1 ENGINEER has relied upon data obtained from subsurface investigations made at the site in the form of test borings and/or rock probes. Such data is in the form of boring logs and/or probe logs which are included in Appendix A to the bound Specifications. The locations of the test borings and probes are indicated on the Drawings. SC-4.03.D Add the following new paragraph immediately after paragraph 4.03.C of the General Conditions which is to read as follows: 4.03.D Adjustments resulting from actual subsurface or latent physical conditions from those indicated will be in accordance with Massachusetts General Law, Chapter 30, Section 39N and the applicable provisions of the Contract Documents. SC-4.05.B Add the following new paragraph at the end of paragraph 4.05.A of the General Conditions which is to read as follows: 4.05.B ENGINEER may check the lines, elevations, reference marks, batter boards, etc., set by CONTRACTOR, and CONTRACTOR shall correct any errors disclosed by such check. Such a check shall not be considered as approval of CONTRACTOR's work and shall not relieve CONTRACTOR of the responsibility for accurate and satisfactory construction and completion of the entire Work. CONTRACTOR shall furnish personnel to assist ENGINEER in checking lines and grades. Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -4 ARTICLE 5. BONDS AND INSURANCE SC-5.01 Amend General Conditions Paragraph 5.01B by adding the following language: 5.01B Every bid bond, every performance bond and every payment bond issued for any construction work in the commonwealth shall be the bond of a surety company organized pursuant to Section 105 of Chapter 175 or of a surety company authorized to do business in Commonwealth under the provisions of Section 106 of said Chapter 175 and be approved by the U. S. Department of Treasury and acceptable as sureties and reinsurers on federal bonds under Title 31 of the United States Code, sections 9304 to 9308. SC-5.04 The limits of liability for the insurance required by paragraph 5.04 of the General Conditions shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations: 5.04.A.1 and 5.04.A.2 Worker's Compensation, etc. under paragraphs 5.04.A.1 and 5.04.A.2 of the General Conditions: (1) Worker's Compensation As required by the laws of the Commonwealth of Massachusetts (2) Employer's Liability $1,000,000 5.04.A.3, 5.04.A.4, and 5.04.A.5 Contractor's Liability Insurance under paragraphs 5.04.A.3 through 5.04.A.5 of the General Conditions which shall also include completed operations and product liability coverages and eliminate the exclusion with respect to property under the care, custody, and control of Contractor: (1) General Aggregate (Except Products--Completed Operations) $1,000,000 (2) Products--Completed Operations Aggregate $1,000,000 (3) Personal and Advertising Injury (Per Person/ Organization) $1,000,000 (4) Each Occurrence (Bodily Injury and Property Damage) $1,000,000 Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -5 (5) Property Damage liability insurance including Collapse, and Underground coverages. If blasting is to be used, also include explosion coverage. $1,000,000 5.04.A.6 Automobile Liability: (1) Bodily Injury: Each Person $1,000,000 Each Accident $1,000,000 Property Damage: Each Accident $1,000,000 or (2) Combined Single Limit (Bodily Injury and Property Damage): Each Accident $2,000,000 SC-5.04.B.4 The Contractual Liability coverage required by paragraph 5.04.B.4 in the General Conditions shall provide coverage for not less than the following amounts: (1) General Aggregate $2,000,000 (2) Each Occurrence (Bodily Injury and Property Damage) $1,000,000 SC-5.05 Delete paragraph 5.05 of the General Conditions in its entirety and insert the following in its place: 5.05.A CONTRACTOR shall purchase and maintain a separate Owner's Protective Liability policy, issued to OWNER at the expense of CONTRACTOR, including OWNER and ENGINEER as named insured. This insurance shall provide coverage for not less than the following amounts: 5.05.A.1 Bodily Injury: Each Occurrence $1,000,000 5.05.A.2 Property Damage: Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -6 Each Occurrence $1,000,000 Annual Aggregate $1,000,000 SC-5.06 Delete paragraphs 5.06A.1 through 5.06.A.7 of the General Conditions in their entirety and insert the following in its place: 5.06.A CONTRACTOR shall purchase and maintain Equipment Installation Insurance in the amount of the total insurable value of all equipment to be installed, this insurance shall: 5.06.A.1 Include the interests of OWNER, CONTRACTOR, Subcontractors, ENGINEER, and ENGINEER'S Consultants, each of whom is deemed to have an insurable interest and shall be listed as an insured or additional insured; 5.06.A.2 Be written as Equipment Installation Insurance with an "All Risk" Installation Floater that shall at least include coverage for physical loss and damage to the equipment; 5.06.A.3 Include expenses incurred in the repair or replacement of any insured equipment (including but not limited to fees and charges of engineers and architects); 5.06.A.4 Cover materials and equipment in transit for incorporation in the Work or stored at the site or at another location that was agreed to in writing by OWNER prior to being incorporated in the Work, provided that such materials and equipment have been included in an Application for Payment recommended by ENGINEER; and 5.06.A.5 Be maintained in effect until final payment is made unless otherwise agreed to in writing by OWNER, CONTRACTOR, and ENGINEER with thirty days written notice to each other additional insured to whom a certificate of insurance has been issued. The policies of insurance required to be purchased and maintained by CONTRACTOR in accordance with this paragraph 5.06 shall comply with requirements of GC-5.06.C. SC-5.07 Delete paragraph 5.07A of the General Conditions in its entirety. Delete paragraph 5.07B of the General Conditions in its entirety. Delete paragraph 5.07C of the General Conditions in its entirety. ARTICLE 6. CONTRACTOR'S RESPONSIBILITIES SC-6.06.D Add the following new subparagraph as follows: Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -7 6.06.D.1 OWNER or ENGINEER may furnish to any such Subcontractor, Supplier, or other person or organization, to the extent practicable, information about amounts paid to CONTRACTOR in accordance with CONTRACTOR's Applications for Payment on account of the particular Subcontractor's, Suppliers, other person's, or other organization's Work. SC-6.06.F Add the following language at the beginning of Paragraph 6.06F of the General Conditions: 6.06.F Except as otherwise required by Massachusetts General Law, Chapter 149, Section 44F, SC-6.10 Add the following language at the end of paragraph 6.10.A of the General Conditions: 6.10.A.1 The materials and supplies to be used in the Work under this Contract are exempt from the Sales and Use Tax of the Commonwealth of Massachusetts. Contractor shall obtain the proper certificates, maintain the necessary records, and otherwise comply with all applicable requirements governing the exemption from sales tax. SC-6.17 Add the following new paragraph immediately after paragraph 6.17.E of the General Conditions, which is to read as follows: 6.17.F The accuracy of all such information submitted by the Contractor is the responsibility of the Contractor. In reviewing Shop Drawings, Samples and similar submittals, the Engineer shall be entitled to rely upon the Contractor’s representation that such information is correct and accurate. ARTICLE 9. ENGINEER'S STATUS DURING CONSTRUCTION SC-9.04 Add the following new paragraph immediately after paragraph 9.04.A of the General Conditions which is to read as follows: 9.04.A.1 ENGINEER'S interpretations will be made in accordance with Massachusetts General Law, Chapter 30, Section 39P. ARTICLE 10. CHANGES IN THE WORK; CLAIMS SC-10.01.A Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -8 Add the following new paragraph immediately after paragraph 10.01A of the General Conditions, which is to read as follows: 10.01.A.1 Upon request of the Owner or the Engineer, the Contractor shall without cost to the Owner submit to the Engineer, in such form as the Engineer may require, an accurate written estimate of the cost of any such proposed extra Work or change. The estimate shall indicate the quantity and unit cost of each item of materials, and the number of hours of work and hourly rate for each class of labor, as well as the description and amounts of all other costs chargeable under the terms of this Article. Unit labor costs for the installation of each item of materials shall be shown if required by the Engineer. The contractor shall promptly revise and resubmit such estimate if the Engineer determines that it is not in compliance with the requirements of this Article, or that it contains errors of fact or mathematical errors. If required by the Engineer, in order to establish the exact cost of new Work added or previously required Work omitted, the Contractor shall obtain and furnish to the Engineer bona fide proposals from recognized suppliers for furnishing any material included in such Work. Such estimates shall be furnished promptly so as to occasion no delay in the Work, and shall be furnished at the Contractor’s expense. The Contractor shall state in the estimate any extension of time required for the competition of the Work if the change or extra work is ordered. SC-10.01.C Add the following new paragraph immediately after paragraph 10.01B of the General Conditions, which is to read as follows: 10.01.C All Change Orders shall be executed utilizing the form in the Bidding Documents. Refer to Section 00941. No other forms will be allowed unless otherwise required by Owner. ARTICLE 11. CHANGE OF CONTRACT PRICE SC-11.01 In the second sentence of paragraph 11.01.A.1 delete the word "superintendents". SC-11.02 Delete paragraph 11.02 of the General Conditions in its entirety. ARTICLE 14. PAYMENTS TO CONTRACTOR AND COMPLETION SC-14.02 Add the following new paragraphs immediately after paragraph 14.02.A.1 of the General Conditions to read as follows: 14.02.A.1.a No payment will be made for material stored on site. Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -9 SC-14.02 Delete paragraph 14.02.C.1 of the General Conditions in its entirety and insert the following in its place: 14.02.C.1 Thirty days after presentation of the Application for Payment to Owner with Engineer’s recommendation, the amount recommended will (subject to the provisions of Paragraph 14.02.D) become due, and when due will be paid by Owner to Contractor. ARTICLE 16. DISPUTE RESOLUTION SC-16 Add the following new paragraph immediately after paragraph 16.01.A of the General Conditions to read as follows: 16.01.A.1 CONTRACTOR shall carry on the Work and maintain the progress schedule during the dispute resolution proceedings unless otherwise agreed in writing by OWNER and CONTRACTOR. ARTICLE 17. MISCELLANEOUS SC-17.06 Delete 17.06 of the General Conditions in its entirety and insert the following in its place: 17.06 Legal Address of Contractor 17.06.A CONTRACTOR'S business address and his office at or near the site of the Work are both hereby designated as places to which communications shall be delivered. The depositing of any letter, notice, or other communication in a postpaid wrapper directed to the CONTRACTOR'S business address in a post office box regularly maintained by the Post Office Department or the delivery at either designated address of any letter, notice, or other communication by mail or otherwise shall be deemed sufficient service thereof upon CONTRACTOR, and the date of such service shall be the date of receipt. The first-named address may be changed at any time by an instrument in writing, executed and acknowledged by CONTRACTOR and delivered to ENGINEER. Service of any notice, letter, or other communication upon the CONTRACTOR personally shall likewise be deemed sufficient service. SC-17.07 Add the following new paragraphs immediately after paragraph 17.06 of the General Conditions as follows: 17.07 Headings: Northampton Drainage Relocation SUPPLEMENTARY CONDITIONS 20164277.003A 00800A -10 17.07.A The headings or titles of any article, paragraph, subparagraph, section, subsection, or part of the Contract Documents shall not be deemed to limit or restrict the article, paragraph, section, or part. ARTICLE 18. FEDERAL REQUIREMENTS Delete Article 18 of the General Conditions in its entirety. Delete the Exhibit GC-A of the General Conditions in its entirety. PART II - COMMONWEALTH OF MASSACHUSETTS PROVISIONS State Government Provisions included herein, have been selected from those to which specific references have been made elsewhere in the Contract Documents. Each and every other provision of law or clause required by law to be inserted in this Contract shall be deemed to be also inserted herein in accordance with paragraph SC-3.01.A.1 of the Supplementary Conditions. 1.0. COMMONWEALTH OF MASSACHUSETTS PROVISIONS 1.1. The OWNER and CONTRACTOR agree that the following Commonwealth of Massachusetts Provisions apply to work to be performed under this Contract and that these provisions supersede any conflicting provisions of this Contract. 1.2. Applicable provisions of Massachusetts General Laws and Regulations and/or the United States Code and Code of Federal Regulations govern this Contract and any provision violation of the foregoing shall be deemed null, void and of no effect. 1.3. Additional relevant excerpts from the Massachusetts General Laws and Regulations are included in Specification Section 01069 – Massachusetts General Laws. 2.0. MASSACHUSETTS WAGE RATES 2.1. Minimum Wage Rates as determined by the Commissioner of Department of Labor and Industries under the provision of the Massachusetts General Laws, Chapter 149, Section 26 to 27D, as amended, apply to this project. It is the responsibility of the CONTRACTOR, before the bid opening, to request if necessary, any additional information on Minimum Wage Rates for those tradespeople who may be employed for the proposed work under this Contract. 2.2. The schedule of Minimum Wage Rates is included as an appendix to the Specifications. END OF SECTION 00800A EJCDC No. C-941 (2002 Edition) Page 1 of 2 Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. Change Order No. ___________ Date of Issuance: Effective Date: Project: Owner: Owner's Contract No.: Contract: Date of Contract: Contractor: Engineer's Project No.: The Contract Documents are modified as follows upon execution of this Change Order: Description: Attachments: (List documents supporting change): CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: Original Contract Times: Working days Calendar days Substantial completion (days or date): $ Ready for final payment (days or date): [Increase] [Decrease] from previously approved Change Orders No.____________ to No.____________: [Increase] [Decrease] from previously approved Change Orders No.____________ to No.____________: Substantial completion (days): $ Ready for final payment (days): Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial completion (days or date): $ Ready for final payment (days or date): [Increase] [Decrease] of this Change Order: [Increase] [Decrease] of this Change Order: Substantial completion (days or date): $ Ready for final payment (days or date): Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial completion (days or date): $ Ready for final payment (days or date): RECOMMENDED: ACCEPTED: ACCEPTED: By: By: By: Engineer (Authorized Signature) Owner (Authorized Signature) Contractor (Authorized Signature) Date: Date: Date: Approved by Funding Agency (if applicable): Date: EJCDC No. C-941 (2002 Edition) Page 2 of 2 Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. Change Order Instructions A. GENERAL INFORMATION This document was developed to provide a uniform format for handling contract changes that affect Contract Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent Change Order if they affect Price or Times. Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes. If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed. For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a Field Order should be used. B. COMPLETING THE CHANGE ORDER FORM Engineer normally initiates the form, including a description of the changes involved and attachments based upon documents and proposals submitted by Contractor, or requests from Owner, or both. Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval, depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated agreement for a previously performed change. After approval by one contracting party, all copies should be sent to the other party for approval. Engineer should make distribution of executed copies after approval by both parties. If a change only applies to price or to times, cross out the part of the tabulation that does not apply. Northampton Drainage Relocation SUMMARY OF WORK 20164277.003A 01010 - 1 SECTION 01010 SUMMARY OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A.Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 LOCATION OF WORK A.The work of this Contract runs through 256 Pleasant Street (former Northampton Lumberyard) and across Holyoke Street in the City of Northampton, Massachusetts. B.The work area is generally located to the west of the existing railroad right of way owned by MassDOT. The MassDOT railroad right of way is adjacent to the site and the right of way property line is a shared property line with the project site. 1.3 SUMMARY A.Furnish all labor, materials, equipment and incidentals for installation of the stormwater box culvert and associated work complete and fully functional as indicated on the Drawings and specified herein, including: 1.Stormwater precast reinforced concrete box culvert installation. 2.Drainage modifications. 3.Utility relocation. 4.Road, sidewalk, and driveway reconstruction and paving. B.The Work includes, but is not necessarily limited to, the following items: 1.Maintenance and protection of traffic and pedestrians. 2.Erosion and sedimentation controls installation, maintenance and removal. 3.Site preparation. Northampton Drainage Relocation SUMMARY OF WORK 20164277.003A 01010 - 2 4.Temporary bypassing of existing stormwater flows. 5.Dewatering. 6.Replace and restore disturbed landscaping, roadways, sidewalk, utilities and other amenities disturbed by proposed work. 7.Coordination of the work with the Owner and/or their representative. 8.Coordination with utility owners and railroad for utility relocation and monitoring of infrastructure. 9.Compliance with all applicable permits, including local, state, and federal laws and regulations. C.The work shall also conform to such additional Drawings and addenda to these Specifications and Drawings as may be published or exhibited prior to the opening of bid proposals and to such drawings in explanation of details, or as may be furnished by the Engineer from time to time during the construction. D.US Army Corps of Engineers permit NAE-2017-351 has been obtained through the City. The contractor is to follow all the conditions in this permit. Refer to Appendix C herein. E. Notice of Intent Permit No. (xxx-xxx) has been obtained through the City. The contractor is to comply with the Order of Conditions No. (xxx-xx) Refer to Appendix D herein. F.Work and materials which are necessary in the construction but which are not specifically referred to in the Specification, or shown on the Drawings, but implied by the Contract shall be furnished by the Contractor at his own cost and expense and shall be such as will correspond with the general character of the work as may be determined by the Engineer, whose decisions as to the necessity for and character of such work and materials shall be final and conclusive. It is the intent of these Specifications to produce a complete, operational and finished project whether shown in every detail or not. 1.4 WORK BY OTHERS A.Refer to Article 7 of the General Conditions for requirements. 1.5 WORK SEQUENCE: A.A suggested sequence of construction is presented below. The Contractor may use the suggested sequence or develop a different plan; however, Contractor will be responsible for the continuous operation of the storm drain system and all connections and utilities throughout the project. The proposed sequence shall be in accordance with the approved schedule submitted by the Contractor. Northampton Drainage Relocation SUMMARY OF WORK 20164277.003A 01010 - 3 The suggested sequence does not relieve the Contractor from its responsibility to sequence and carry out the work so as not to cause harm to the existing systems, environment, or community. This paragraph is not intended to list administrative sequencing (e.g. submittal and approval of schedules and shop drawings) that are required prior to construction. 1.Pre-construction Survey; 2.Establish baseline Sedimentation and Erosion Control; 3.Coordination with required permitting agency to establish permit conditions, if needed (e.g. NPDES permit); 4.Coordinate with railroad owner to establish construction schedule, and monitoring requirements prior to construction. 5.Coordinate with the railroad owner and operator for railroad insurance requirements including railroad protective insurance. 6.Coordinate with the railroad owner and operator for railroad training, inspections, and flaggers. 7.Establish baseline Geotechnical Instrumentation and Monitoring; 8.Layout of site work and survey control; 9.Mobilization; 10.Perform Test Pits: All Test Pits identified on the Contract Drawings as well as those identified by the Owner and Engineer shall be performed and completed prior to any other work commencing on the site; 11.Establish the construction dewatering treatment system; 12.Prior to installation of the Work, the Contractor shall verify the relocation of any existing utilities that are scheduled for relocation, coordinate with the responsible utility, and relocate those utilities which are the Contractor’s responsibility as per these Contract Documents; 13.Establish traffic management control; 14.Relocation of conflicting utilities; 15.Install project proposed infrastructure and improvement; Northampton Drainage Relocation SUMMARY OF WORK 20164277.003A 01010 - 4 16.Abandon, demolish and remove existing drainage structures and conveyance piping as indicated on the plans. 17.Surface and utility restoration including but not limited to completion of sidewalk and curb work; paving; fence; striping of roadway; permanent water main and utilities. 1.6 CONTRACTOR'S USE OF PREMISES: A.Contractor shall limit the use of the premises for the performance of the Work and storage of materials and equipment to allow for the Owner's use in operating and maintaining roadway access. B.Contractor shall coordinate with Owner, access for normal maintenance requirements. C.Contractor shall assume full responsibility for security of all his and his subcontractors’ materials and equipment stored on the site. D.If directed by the Owner, Contractor shall move stored items which interfere with operations of Owner. E.Obtain and pay for use of additional storage or work areas if needed to perform the Work. 1.7 UNDERGROUND UTILITIES A.The underground utilities indicated on the drawings have been located primarily from information furnished by others and are considered approximate both as to size and location. There are additional utilities to be encountered that are not shown on the drawings, and it shall be the Contractor's responsibility to locate all existing utilities and to protect same from damage or harm. All utilities interfered with or damaged shall be properly restored, at the expense of the Contractor, to the satisfaction of its Owner. 1.8 PROJECT CONDITIONS A. The Contractor shall conduct the Work at all times in such a manner and in such sequence as will assure the least interference with vehicular and pedestrian traffic, operations of the railroad and consumer entrances to and exits from adjacent buildings and properties. The Contractor shall pay close attention to the location of detours and to the provisions for handling pedestrian traffic. B.The Contractor shall conduct his work in such a manner and at such times and with such precautions and safeguards, including but not limited to, debris shields or other protective screens, as the owner or operator of the railroad may Northampton Drainage Relocation SUMMARY OF WORK 20164277.003A 01010 - 5 require for the purpose of preventing fouling of the track right-of-way and avoiding interference with the safe and continuous operation of railroad services. C. All workers employed by the Contractor or subcontractors who work adjacent to the track right-of-way, shall be required to attend a safety awareness course conducted by the railroad or its operator. The location and time of such training sessions will be at the sole discretion of the railroad or its operator. The cost of attending training sessions shall be borne by the Contractor and will not be reimbursed. D. The Contractor is specifically prohibited from conducting any operations next to or over the tracks that have a potential to adversely impact the operation of the railroad including: a.When an object or operation is or can be brought nearer than the foul zone of an operating track or has the potential to get within the foul zone. b.When cranes, trucks, power shovels or any other equipment items are working in such a position that failure with or without load could occur. It shall be the responsibility of the Contractor to inform the owner of the railroad and its operators in writing thirty (30) working days prior to all times when they intend to perform hazardous work as described above. Submittal must include a site plan, each individual location where work of a different nature is to be performed, the nature of such work, and the number of days, including time schedule, the Contractor intends to remain on the property at each location. Failure of the Contractor to provide the specified advance notice of hazardous work could result in the stoppage of work by the railroad or its operators. 1.9 RAILROAD INSURANCE REQUIREMENTS A. Prior to performing work on this project, the Contractor and its subcontractors shall obtain and provide, to the City or the City’s Engineer, a copy of any certificate or certificates of insurance required by the railroad owner or operator to work within the railroad ROW. During the term hereof, if the contractor is required to renew and replace any expired certificate, the contractor shall provide a copy of the renewed certificate to the City or the City’s Engineer. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01010 Northampton Drainage Relocation PROJECT COORDINATION 20164277.003A 01040 - 1 SECTION 01040 PROJECT COORDINATION PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section specifies administrative and supervisory requirements necessary for Project scheduling and construction including, but not necessarily limited to: 1. Coordination 2. Administrative and supervisory personnel 3. General installation provisions 4. Cleaning and protection B. Requirements for the Contractor's field engineering are included in Section 01050 – “Field Engineering”. C. Progress meetings and preconstruction conferences are included in Section 01200 – "Project Meetings". D. Requirements for the Contractor's Construction Schedule are included in Section 01300 – “Submittal Procedures”. PART 2 – PRODUCTS (NOT USED) PART 3 – EXECUTION 3.1 GENERAL INSTALLATION PROVISIONS A. Inspection of Conditions: Inspect the conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner, and at no additional cost to the Owner. Northampton Drainage Relocation PROJECT COORDINATION 20164277.003A 01040 - 2 B. Manufacturer’s Written Instructions: Comply with manufacturer's written installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in the Contract Documents. C. Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items at no additional cost to the Owner. D. Provide attachment and connection devices and methods for securing work. Secure work true to line and level. Allow for expansion and utility movement. E. Recheck measurements and dimensions before starting installation or erection. F. Install each component during weather conditions and Project status and sequencing that will ensure the best possible results. Isolate each part of the completed construction from incompatible material to prevent deterioration. G. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose. 3.2 CLEANING AND PROTECTION A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Install protective covering to ensure protection from damage or deterioration. B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where applicable, such exposures include, but are not limited to, the following: 1. Excessive static or dynamic loading 2. Excessive internal or external pressures 3. Excessively high or low temperatures 4. Air contamination or pollution 5. Water or ice 6. Solvents 7. Chemicals 8. Heavy traffic 9. Misalignment 10. Unprotected storage 11. Improper shipping or handling Northampton Drainage Relocation PROJECT COORDINATION 20164277.003A 01040 - 3 12. Theft 13. Vandalism 3.3 HOURS OF CONSTRUCTION A. The Contractor shall perform work between the hours of 7:00 AM to 3:30 PM, Monday through Friday, legal holidays excluded. 3.4 SEQUENCE OF WORK A. It is imperative that all existing storm drain conveyance remain operational throughout construction. The Contractor shall prepare a program acceptable to the Engineer and Owner to ensure that stormwater management is adequately manage during construction. B. Construction sequence shall be planned and coordinated to complete construction as expeditiously as possible without interrupting existing storm drain service. Construction sequence shall limit the duration of by-pass pumping operation to the shortest possible time frame. C. Contractor shall ultimately be responsible for the schedule of work that will minimize interruptions to the existing sewer system. END OF SECTION 01040 Northampton Drainage Relocation PROJECT COORDINATION 20164277.003A 01040 - 4 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 1 SECTION 01050 FIELD ENGINEERING PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Examination of site and conditions of construction. 2. Establishment of lines, grades, and easements. 3. Connections to existing facilities. 4. Restoration and protection of public and private property. B. Related section includes the following: 1. Section 02100 – Site Preparation 2. Section 02525 – Paving, Sidewalks and Curbing 3. Section 02715 – Reinforced Concrete Box Culvert 1.3 SUBMITTALS A. Submit the following in accordance with Section 01300 – Submittal Procedures: 1. As-Built Drawings: The Contractor shall be responsible for maintaining one set of redline “as-built locations and dimensions of work.” The As-Built Drawings shall be submitted to the Owner at substantial completion of the project. 2. The Contractor shall submit copies of field records and “in-progress” As-Built Drawings each month with project invoices. Field data shall be updated each month as applicable. Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 2 3. The maintenance of these As-Built Drawings and field records does not in any way relieve the Contractor of his responsibility to notify and make available for review to the Engineer, all elements of the work in progress and work completed, to determine compliance with the Contract Documents. Any portion of the work backfilled or otherwise made inaccessible, prior to its review by the Engineer, shall be unexcavated and exposed for review at no additional cost to the Owner. 1.4 PROJECT/SITE CONDITIONS: A. Environmental Requirements: 1. Unfavorable Construction Conditions: a. During unfavorable weather, wet ground, or other unsuitable construction conditions, confine operations to work which will not be affected adversely by such conditions. b. No portion of Work shall be constructed under conditions which adversely affect quality or efficiency thereof, unless special means or precautions are taken to perform Work in manner acceptable to the Engineer. B. Field Measurements: 1. Lines and Grades: a. All Work shall be done to lines, grades, and elevations indicated on drawings or specified herein. b. Basic vertical control points have been established or designated by the Engineer. Contractor shall be responsible for maintaining or subsequently replacing these controls to the satisfaction of the Engineer if these controls are disturbed. The Contractor shall be responsible for verifying all vertical control information that is used. (1) Vertical control points shall be used as datum for work. (2) Contractor shall be responsible for transferring all lines and grades from basic survey control points. Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 3 c. Contractor to perform all additional survey, layout, and measurement work. (1) The Contractor shall provide survey work by a firm having successfully completed at least two projects of similar size and complexity within the last five years, and who shall employ experienced personnel, subject to the satisfaction and approval of the Engineer. (2) Surveyor shall be a registered land surveyor in the location of the project. d. Keep the Engineer informed, in writing, two weeks in advance, of times and places at which work is to be performed, so that horizontal and vertical control points may be established and any checking deemed necessary by the Engineer may be performed. e. Remove and reconstruct Work which is improperly located as determined by the Engineer and at no additional cost to the Owner. 2. Easements and Rights-of-Way: a. Easements and rights-of-way for utilities, if required, will be provided by the Owner. b. Confine construction operations within limits indicated on drawings and/or within limits of easements or public ways. c. Place construction tools, equipment, excavated materials, and pipeline materials and supplies, so as to cause least possible damage to property and interference with traffic. PART 2 – PRODUCTS 2.1 MATERIALS A. Use new materials in restoration of existing facilities except where soil materials and plants may be reused, as appropriate. Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 4 PART 3 – EXECUTION 3.1 EXAMINATION A. Examination of Site and Verification of Conditions: 1. Before starting operations, examine site to become acquainted with conditions to be encountered. 2. Verify exact locations of sewers, water mains, gas mains, above or below ground electrical wires, storm drain, other utilities, conduits and structures which may interfere with work. 3. Contractor shall perform test pit excavations where he feels information is required to perform the work, as shown on the plans or as directed by the Engineer. 3.2 APPLICATION A. Connections to Existing Facilities: 1. Make connections to existing facilities as indicated on drawings or as specified. 2. Obtain permission from specific utility owners in writing prior to undertaking connections. a. Protect facilities against deleterious substances and damage. 3. Plan in advance all connections to existing facilities which are in service. a. All equipment, materials, and labor shall be on hand at time of undertaking connections to existing facilities in service. b. Work shall proceed continuously if necessary to complete connections within the time designated by the Engineer. 4. Operation of valves or other appurtenances on existing utilities, when required, shall be performed by respective utility personnel. a. City water distribution system valves shall be operated by the City’s Water Department personnel only. The Contractor shall give the City three (3) working days advance notice prior to performing any work requiring the operation of City water distribution system valves. (1) A tight shutdown of existing City valves is not Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 5 guaranteed; Contractor shall control leakage past valves to satisfaction of the Owner and Engineer and at no additional cost to the Owner. B. Restoration and Protection of Public and Private Property: 1. Protect, shore, brace, support, and maintain all underground pipes, conduits, drains, and other underground construction uncovered or otherwise affected by construction operations. 2. Restore all public and private property including pavement, surfacing, curbs, walks, utility poles, guy wires, fences, and other surface structures affected by construction operations, together with all sod and landscaping to their original condition or better, whether within or outside easements. END OF SECTION 01050 Northampton Drainage Relocation FIELD ENGINEERING 20164277.003A 01050 - 6 THIS PAGE INTENTIONALLY LEFT BLANK PERMITS AND REGULATORY Northampton Drainage Relocation REQUIREMENTS 20164277.003A 01060-1 SECTION 01060 PERMITS AND REGULATORY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A.Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 REGULATORY AGENCIES A.Contractor shall comply with all laws, rules, regulations, and ordinances promulgated by any authority having jurisdiction over the Work. B.The Contractor shall be fully responsible for obtaining and paying for at no additional cost to the Owner, the required permit(s) not already obtained. Additionally, the contractor shall ensure that all other necessary permits from regulatory agencies and/or inspectional authorities having jurisdiction including but not limited to electrical, plumbing, road opening, buildings, pressure vessels etc. are obtained and paid for by the Contractor or its subcontractor(s) as appropriate and or required by the State Building code at no additional cost to the Owner. If the Work or portions of the Work is not covered by the State Building Code, Contractor shall obtain a written determination from the Division of Inspection that no permit is required. Within five days of receipt of the permit or the determination that no permit is required, Contractor shall provide a copy of said permit or determination to the Engineer. 1.4 PERMITS OBTAINED BY THE CONTRACTOR A.The Contractor or its subcontractor shall be responsible for obtaining and paying for at no additional cost to the Owner, all permits, licenses, certifications or approvals required for the work of this contract, with the exception of those permits already obtained by the City. Contractor shall be responsible for compliance, at no additional cost to the Owner, with the requirements of all such permits. The Contractor's responsibility includes but is not limited to building, electrical and other permits required for his equipment, work force, and of particular operations (such as transportation and storage of explosives, fuel, chemical or material storage and air emission) and the like in the performance of the work or facility construction (such as cross- connection/backflow preventers, above or below ground tanks and piping installation and/or removal and chemical handling). Proper equipment shall be installed, tested and maintained in accordance with local, state and federal requirements. PERMITS AND REGULATORY Northampton Drainage Relocation REQUIREMENTS 20164277.003A 01060-2 B.The permits that the Contractor shall be responsible for obtaining, complying with, paying for, at no additional cost to the Owner, include but are not limited to the following (as necessary): 1.City of Northampton Excavation/Trench Permit C.The Contractor shall also be responsible for scheduling and coordinating inspections and receipt of local or state permits/approvals/certifications for any tanks, piping and associated appurtenances which are constructed, installed, tested or removed as part of this Contract. Receipt of approvals for storage and use of test chemicals/gasses will be the responsibility of the Contractor. D.National Pollutant Discharge Elimination System (NPDES) General Permits For Dewatering Activity Discharges (BRP WM10). 1.5 PERMITS OBTAINED BY THE OWNER A.U.S. Army Corps (USACE) Programmatic General Permit (Appendix C). B.Massachusetts Department of Environmental Protection (MADEP) - Notice of Intent and Order of Conditions (Appendix D). PART 2- PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01060 MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 1 SECTION 01069 MASSACHUSETTS GENERAL LAWS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 EXCERPTS FROM MASSACHUSETTS STATUTES A. In addition to the requirements as set forth under “Compliance with Laws” in the AGREEMENT, particular attention is directed to certain stipulations of Chapter 30 of the General Laws of Massachusetts, as amended to date as follows: Section 39F. “(1) Every contract awarded shall contain the following subparagraphs and in each case those subparagraphs shall be binding between the general contractor and each subcontractor. “(a) Forthwith after the general contractor receives payment on account of a periodic estimate, the general contractor shall pay to each subcontractor the amount paid for the labor performed and the materials furnished by that subcontractor, less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the subcontractor by the general contractor. “(b) Not later than the sixty-fifth day after each subcontractor substantially completes his work in accordance with the plans and specifications, the entire balance due under the subcontract less amounts retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, shall be due the subcontractor; and the awarding authority shall pay that amount to the general contractor. The general contractor shall forthwith pay to the subcontractor the full amount received from the awarding authority less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the subcontractor by the general contractor. “(c) Each payment made by the awarding authority to the general contractor pursuant to subparagraphs (a) and (b) of this paragraph for the labor performed and the materials furnished by a MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 2 subcontractor shall be made to the general contractor for the account of that subcontractor; and the awarding authority shall take reasonable steps to compel the general contractor to make each such payment to each such subcontractor. If the awarding authority has received a demand for direct payment from a subcontractor for any amount which has already been included in a payment to the general contractor or which is to be included in the payment to the general contractor for payment to the subcontractor as provided in sub-paragraphs (a) and (b), the awarding authority shall act upon the demand as provided in this section. “(d) If, within seventy days after the subcontractor has substantially completed the subcontract work, the subcontractor has not received from the general contractor the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, the subcontractor may demand direct payment of that balance from the awarding authority. The demand shall be by a sworn statement delivered to or sent by certified mail to the awarding authority, and a copy shall be delivered to or sent by certified mail to the general contractor at the same time. The demand shall contain a detailed breakdown of the balance due under the subcontract and also a statement of the status of completion of the subcontract work. Any demand made after substantial completion of the subcontract work shall be valid even if delivered or mailed prior to the seventieth day after the subcontract work. Within ten days after the subcontractor has delivered or so mailed the demand to the awarding authority and delivered or so mailed a copy to the general contractor, the general contractor may reply to the demand. The reply shall be by a sworn statement delivered to or sent by certified mail to the awarding authority and a copy shall be delivered to or sent by certified mail to the subcontractor at the same time. The reply shall contain a detailed breakdown of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor and of amount due for each claim made by the general contractor against the subcontractor. “(e) Within fifteen days after receipt of the demand by the awarding authority, but in no event prior to the seventieth day after substantial completion of the subcontract work, the awarding authority shall make direct payment to the subcontractor of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount (i) retained by the awarding authority as the estimated MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 3 cost of completing the incomplete or unsatisfactory items of work, (ii) specified in any court proceedings barring such payment, or (iii) disputed by the general contractor in the sworn reply; provided, that the awarding authority shall not deduct from any direct payment any amount as provided in part (iii) if the reply is not sworn to, or for which the sworn reply does not contain the detailed breakdown required by subparagraph (d). The awarding authority shall make further direct payments to the subcontractor forthwith after the removal of the basis for deductions from direct payments made as provided in parts (i) and (ii) of this subparagraph. “(f) The awarding authority shall forthwith deposit the amount deducted from a direct payment as provided in part (iii) of subparagraph (e) in the interest-bearing joint account in the names of the general contractor and the subcontractor in a bank in Massachusetts selected by the awarding authority or agreed upon by the general contractor and the subcontractor and shall notify the general contractor and the subcontractor of the date of the deposit and the bank receiving the deposit. The bank shall pay the amount in the account, including accrued interest, as provided in an agreement between the general contractor and the subcontractor or as determined by decree of court of competent jurisdiction. “(g) All direct payments and all deductions from demands for direct payments deposited in an interest-bearing account or accounts in a bank pursuant to paragraph (f) shall be made out of amounts payable to the general contractor at the time of receipt of a demand for direct payment for a subcontractor and out of amounts which later become payable to the general contractor and in order of receipt of such demands from subcontractors. All direct payments shall discharge the obligation of the awarding authority to the general contractor to the extent of such payment. “(h) The awarding authority shall deduct from payments to a general contractor amounts which, together with the deposits in interest- bearing accounts pursuant to subparagraph (f), are sufficient to satisfy all unpaid balances of demands for direct payment received from subcontractors. All such amounts shall be earmarked for such direct payments, and the subcontractors shall have a right in such deductions prior to any claims against such amounts by creditors of the general contractor. “(i) If the subcontractor does not receive payment as provided in subparagraph (a) or if the general contractor does not submit a periodic estimate for the value of the labor or materials performed or furnished by the subcontractor and the subcontractor does not MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 4 receive payment for same when due less the deductions provided for in subparagraph (a), the subcontractor may demand direct payment by following the procedure in subparagraph (d) and the general contractor may file a sworn reply as provided in that same subparagraph. A demand made for the first day of the month following that for which the subcontractor performed or furnished the labor and materials for which the subcontractor seeks payment shall be valid even if delivered or mailed prior to the time payment was due on a periodic estimate from the general contractor. Thereafter the awarding authority shall proceed as provided in subparagraph (e), (f), (g), and (h).” Section 39K. “Every contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building by the commonwealth, or by any county, city, town, district, board, commission or other pubic body, when the amount is more than five thousand dollars in the case of the commonwealth and more than two thousand dollars in the case of any county, city, town, district, board, commission or other public body, shall contain the following paragraph: Within fifteen days (twenty-four days in the case of the commonwealth) after receipt from the contractor, at the place designated by the awarding authority if such a place is so designated, of a periodic estimate requesting payment of the amount due for the preceding month, the awarding authority will make a period payment to the contractor for the work performed during the preceding month and for the materials not incorporated in the work but delivered and suitably stored at the site (or at some location agreed upon in writing) to which the Contractor has title or to which the subcontractor has title or to which a subcontractor has title and has authorized the contractor to transfer title to the awarding authority, less (1) a retention based on its estimate of the fair value of its claims against the contractor and less (2) a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, and less (3) a retention not exceeding five percent of the approved amount of the periodic payment. After the receipt of a periodic estimate requesting final payment and within sixty-five days after (a) the contractor fully completes the work or substantially completes the work so that the value of the work remaining to be done is, in the estimate of the awarding authority, less than one percent of the original contract price, or (b) the contractor substantially completes the work and the awarding authority takes possession for occupancy, whichever occurs first, the awarding authority shall pay the contractor the entire balance due on the contract less (1) a retention based on its estimate of the fair value of its claims against the contractor and the cost of completing the incomplete and unsatisfactory items of work and less (2) a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, or based on the record of payments by the contractor to the subcontractors under this contract if such record of payment indicates that the contractor has not paid subcontractors as provided in section thirty- MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 5 nine F. If the awarding authority fails to make payment as herein provided, there shall be added to each such payment daily interest at the rate of three percentage points above the rediscount rate then charged by the Federal Reserve Bank of Boston commencing on the first day after said payment is due and continuing until the payment is delivered or mailed to the contractor; provided, that no interest shall be due in any event, on the amount due on a periodic estimate for final payment within fifteen days (twenty-four days in the case of the commonwealth) after receipt of such periodic estimate from the contractor, at the place designated by the awarding authority if such a place is so designated. The contractor agrees to pay each subcontractor a portion of any such interest paid in accordance with the amount due each subcontractor. “The awarding authority may make changes in any periodic estimate submitted by the contractor and the payment due on such periodic estimate shall be computed in accordance with the changes so made, but such changes or any requirement for corrected periodic estimate shall not affect the due date for the periodic payment or the date for the commencement of interest charges on the amount of the periodic payment computed in accordance with the changes made, as provided herein; provided, that the awarding authority may, within seven days after receipt, return to the contractor for correction, any periodic estimate which is not in the required form or which contains computations not arithmetically correct and, in that event, the date of receipt of such periodic estimate shall be the date of receipt of the corrected period estimate in proper form and with arithmetically correct computations. The date of receipt of a periodic estimate received on Saturday shall be the first working day thereafter. The provisions of section thirty-nine G shall not apply to any contractor for the construction, reconstruction, alteration, remodeling, repair or demolition for any public building to which this section applies. “All periodic estimates shall be submitted to the awarding authority, or to its designee as set forth in writing to the contractor, and the date of receipt by the awarding authority or its designee shall be marked on the estimate. All periodic estimates shall contain a separate item for each filed subtrade and a column listing the amount paid to each filed subcontractor as of the date the periodic estimate is filed. The person making payment for the awarding authority shall add the daily interest provided for herein to each payment for each day beyond the due date based on the date of receipt marked on the estimate.” Section 39N. “Every contract subject to section forty-four A of chapter one hundred and forty-nine or subject to section thirty-nine M of chapter thirty shall contain the following paragraph in its entirety and an awarding authority may adopt reasonable rules or regulations in conformity with that paragraph concerning the filing, investigation and settlement of such claims: “If, during the progress of the work, the contractor or the awarding authority MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 6 discovers that the actual subsurface or latent physical conditions encountered at the site differ substantially or materially from those shown on the plans or indicated in the contract documents either the contractor or the contracting authority may request an equitable adjustment in the contract price of the contract applying to work affected by the differing site conditions. A request for such an adjustment shall be in writing and shall be delivered by the party making such claim to the other party as soon as possible after such conditions are discovered. Upon receipt of such a claim from a contractor, or upon its own initiative, the contracting authority shall make an investigation of such physical conditions, and if they differ substantially or materially from those shown on the plans or as indicated in the contract documents or from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the plans and contract documents and are of such a nature to cause an increase or decrease in the cost of performance of the work or a change in the construction methods required for the performance of the work which results in an increase or decrease in the cost of the work, the contracting authority shall make an equitable adjustment in the contract price and the contract shall be modified in writing accordingly.” Section 39O. “Every contract subject to the provisions of section thirty-nine M of this chapter or subject to section forty-four A of chapter one hundred forty-nine shall contain the following provisions (a) and (b) in their entirety: “(a) The awarding authority may order the general contract in writing to suspend, delay, or interrupt all or any part of the work for such period of time as it may determine to be appropriate for the convenience of the awarding authority; provided however, that if there is a suspension, delay or interruption for fifteen days or more or due to a failure of the awarding authority to act within the time specified in this contract, the awarding authority shall make an adjustment in the contract price for any increase in the cost of performance of this contract but shall not include any profit to the general contractor on such increase; and provided further, that the awarding authority shall not make any adjustment in the contact price under this provision for any suspension, delay, interruption or failure to act to the extent that such is due to any cause for which this contract provides for an equitable adjustment of the contract price under any other contract provisions. “(b) The general contractor must submit the amount of a claim under provision (a) to the awarding authority in writing as soon as practicable after the end of the suspension, delay, interruption or failure to act and, in any event, not later than the date of final payment under this contract and, except for costs due to a suspension order, the awarding authority shall not approve any costs in the claim incurred more than twenty days before the MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 7 general contractor notified the awarding authority in writing of the act or failure to act involved in the claim. Section 39P. “Every contract subject to section thirty-nine M of this chapter or section forty-four A of chapter one hundred forty-nine which requires the awarding authority, any official, its architect or engineer to make a decision on interpretation of the specifications, approval of equipment, material or any other approval, or progress of the work, shall require that the decision made promptly and, in any event, no later than thirty days after the written submission for decision; but if such decision requires extended investigation and study, the awarding authority, the official, architect or engineer shall, within thirty days after the receipt of the submission, give the party making the submission written notice of the reasons why the decision cannot be made within the thirty-day period and the date by which the decision will be made.” Section 39Q. “Every contract awarded by any state agency as defined by section thirty-nine A of chapter seven for the construction, reconstruction, alteration, remodeling, repair or demolition of any capital facility as defined by the aforesaid section thirty-nine A shall contain the following subparagraphs (a) through (d) in their entirety: “(a) Disputes regarding changes in and interpretations of the terms or scope of the contract and denials of or failures to act upon claims for payment for extra work or materials shall be resolved according to the following procedures, which shall constitute the exclusive method for resolving such disputes. Written notice of the matter in dispute shall be submitted promptly by the claimant to the chief executive official of the state agency which awarded the contract or his designee. No person or business entity having a contract with a state agency shall delay, suspend, or curtail performance under that contract as a result of any dispute subject to this section. Any disputed order, decision or action by the agency or its authorized representative shall be fully performed or complied with pending resolution of the dispute. “(b) Within thirty days of submission of the dispute to the chief executive official of the state agency or his designee, he shall issue a written decision stating the reasons therefor, and shall notify the parties of their right of appeal under this section. If the official or his designee is unable to issue a decision within thirty days, he shall notify the parties to the dispute in writing of the reasons why a decision cannot be issued within thirty days and of the date by which the decision shall issue. Failure to issue a decision within the thirty-day period or within the additional time period specified in such written notice shall be deemed to constitute a denial of the MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 8 claim and shall authorize resort to the appeal procedure described below. The decision of the chief executive official or his designee shall be final and conclusive unless an appeal is taken as provided below. “(c) Within twenty-one calendar days of the receipt of a written decision or of the failure to issue a decision as stated in the preceding subparagraph, any aggrieved party may file a notice of claim for an adjudicatory hearing with the division of hearing officers or the aggrieved party may file an action directly in a court of competent jurisdiction and shall serve copies thereof upon all other parties in the form and manner prescribed by the rules governing the conduct of adjudicatory proceedings of the division of hearing officers. In the event an aggrieved party exercises his option to file an action directly in court as provided in the previous sentence, the twenty- one day period shall not apply to such filing and the period of filing such action shall be the same period otherwise applicable for filing a civil action in superior court. The appeal shall be referred to a hearing officer experienced in construction law and shall be prosecuted in accordance with the formal rules of procedure for the conduct of adjudicatory hearings of the division of hearing officers, except as provided below. The hearing officer shall issue a final decision as expeditiously as possible, but in no event more than one hundred and twenty calendar days after conclusion of the adjudicatory hearing, unless the decision is delayed by a request for extension of time for filing post-hearing briefs or other submissions assented to by all parties. Whenever, because an extension of time has been granted, the hearing officer is unable to issue a decision within one hundred and twenty days, he shall notify all parties of the reasons for the delay and the date when the decision will issue. Failure to issue a decision within the one hundred and twenty-day period or within the additional period specified in such written notice shall give the petitioner the right to pursue any legal remedies available to him without further delay. “(d) When the amount in dispute is less than ten thousand dollars, a contractor who is party to the dispute may elect to submit the appeal to a hearing officer experienced in construction law for expedited hearing in accordance with the informal rules of practice and procedure of the division of hearing officers. An expedited hearing under this subparagraph shall be available at the sole option of the contractor. The hearing officer shall issue a decision no later than sixty days following the conclusion of any hearing conducted pursuant to this subparagraph. The hearing officer’s decision shall be final and conclusive, and shall not be set aside except in cases of fraud.” MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 9 Section 39R. ‘(a) The words herein shall have the meaning stated below whenever they appear in this section: “(1) “Contractor” means any person, corporation, partnership, joint venture, sole proprietorship, or other entity awarded a contract pursuant to section thirty-nine M of chapter thirty, sections forty-four A through H, inclusive, of chapter one hundred and forty-nine and sections thirty B through thirty P, inclusive, of chapter seven. “(2) “Contract” means any contract awarded or executed pursuant to sections thirty B through thirty P, inclusive, of chapter seven and any contract awarded or executed pursuant to section thirty-nine M of chapter thirty, or sections forty-four A through H, inclusive, of chapter one hundred and forty- nine, which is for an amount or estimated amount greater than one hundred thousand dollars. “(3) “Records” means books of original entry, accounts, checks, bank statements and all other banking documents, correspondence, memoranda, invoices, compute printouts, tapes, discs, papers and other documents or transcribed information of any type, whether expressed in ordinary or machine language. “(4) “Independent Certified Public Accountant” means a person duly registered in good standing and entitled to practice as a certified public accountant under the laws of the place of his/her residence or principal office and who is in fact independent. In determining whether an accountant is independent with respect to a particular person, appropriate consideration should be given to all relationships between the accountant and that person or any affiliate thereof. Determination of an accountant’s independence shall not be confined to the relationships existing in connection with the filing of reports with the awarding authority. “(5) “Audit”, when used in regard to financial statements, means an examination of records by an independent certified public accountant in accordance with generally accepted accounting principals and auditing standards for the purpose of expressing a certified opinion thereon, or, in the alternative, a qualified opinion or a declination to express an opinion for stated reasons. MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 10 “(6) “Accountant’s Report”, when used in regard to financial statements, means a document in which an independent certified public accountant indicates the scope of the audit which he/she has made and sets forth his/her opinion regarding the financial statements taken as a whole with a listing of noted exceptions and qualifications, or an assertion to the effect that an overall opinion cannot be expressed. When an overall opinion cannot be expressed the reason therefore shall be stated. An accountant’s report shall include as part thereof a signed statement by the responsible corporate officer attesting that management has fully disclosed all material facts to the independent certified public accountant, and that the audited financial statement is a true and complete statement of the financial condition of the contractor. “(7) “Management”, when used herein, means the chief executive officers, partners, principals or other person or persons primarily responsible for the financial and operational policies and practices of the contractor. “(8) Accounting terms, unless otherwise defined herein, shall have a meaning in accordance with generally accepted accounting principals and auditing standards. “(b) Subsection (a)(2) hereof notwithstanding, every agreement of contract awarded or executed pursuant to sections thirty B through thirty P, inclusive, of chapter seven, and pursuant to section thirty- nine M of chapter thirty or to section forty-four A through H, inclusive, of chapter one hundred and forty-nine, shall provide that: “(1) The contractor shall make, and keep for at least six years after final payment, books, records, and accounts which in reasonable detail accurately and fairly reflect the transactions and dispositions of the contractor, and “(2) until the expiration of six years after final payment, the officer of inspector general, and the deputy commissioner of capital planning and operations shall have the right to examine any books, documents, papers or records of the contractor or his/her subcontractors that directly pertain to, and involve transactions relating to, the contractor or his/her subcontractors, and “(3) if the agreement is a contract as defined herein, the contractor shall describe any change in the method of maintaining records or recording transactions which materially affect any MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 11 statements filed with the awarding authority, including in his/her description with a letter from the contractor’s independent certified public accountant approving or otherwise commenting on the changes, and “(4) if the agreement is a contract as defined herein, the contractor has filed a statement of management on internal accounting controls as set forth in paragraph (c) below prior to the execution of the contract, and “(5) if the agreement is a contract as defined herein, the contractor has filed prior to the execution of the contracts and will continue to file annually, an audited financial statement for the most recent completed fiscal year as set forth in paragraph (d) below. “(c) Every Contractor awarded a contract shall file with the awarding authority a statement of management as to whether the system of internal accounting controls of the contractor and its subsidiaries reasonably assures that: “(1) transactions are executed in accordance with management’s general and specific authorization; “(2) transactions are recorded as necessary i. to permit preparation of financial statements in conformity with generally accepted accounting principles, and ii. to maintain accountability for assets; “(3) access to assets is permitted only in accordance with management’s general or specific authorization; and “(4) the recorded accountability for assets is compared with the existing assets at reasonable intervals and appropriate action was taken with respect to any difference. “Every contractor awarded a contract shall also file in the awarding authority a statement prepared and signed by an independent certified public accountant, stating that he/she has examined the statement of management on internal accounting controls, and expressing an opinion as to “(1) whether the representations of management in response to this paragraph and paragraph (b) above are consistent with the result of management’s evaluation of the system of internal accounting controls; and MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 12 “(2) whether such representations of management are, in addition, reasonable with respect to transactions and assets in amounts which would be material when measured in relation to the applicant’s financial statements. “(d) Every contractor awarded a contract by the commonwealth or by any political subdivision thereof shall annually file with the deputy commissioner of capital planning and operations during the term of the contract a financial statement prepared by an independent certified public accountant on the basis of an audit by such accountant. The financial statement filed shall include the date of final payment. All statements shall be accompanied by an accountant’s report. Such statements shall be made available to the awarding authority upon request. “(e) The office of inspector general, the deputy commissioner for capital planning and operations and any other awarding authority shall enforce the provisions of this section. The deputy commissioner of capital planning and operations may after providing an opportunity for the inspector general and other interested parties to comment, promulgate pursuant to the provisions of chapter thirty A such rules, regulations and guidelines as are necessary to effectuate the purposes of this section. Such rules, regulations and guidelines may be applicable to all awarding authorities. A contractor’s failure to satisfy any of the requirements of this section may be grounds for debarment pursuant to section forty-four C of chapter one hundred and forty-nine. “(f) Records and statements required to be made, kept or filed under provisions of this section shall not be public records as defined in section seven of chapter four and shall not be open to public inspection; provided, however, that such records and statements shall be made available pursuant to the provisions of clause (2) of paragraph (b). 1.3 SAFETY AND HEALTH A. This project is subject to the Safety and Health regulation of the U.S. Department of Labor set forth in 29 CFR Part 1926, and to the Massachusetts Department of Labor and Industries, Division of Industrial Safety “Rules and Regulations for the Prevention of Accidents in Construction Operations (Industrial Bulletin No. 12)”. Contractors shall be familiar with the requirements of these regulations. B. Chapter 306 of the Acts of 2004, An Act Relative to the Health and Safety on Public Construction Projects, amends Section 39M of Chapter 30 of the Massachusetts General Laws. In summary fashion, the Act states that the lowest responsible and MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 13 eligible bidder (who is awarded the c.30 or c.149 contract) shall certify that all employees to be employed at the worksite will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and shall furnish documentation of successful completion of said course with the first certified payroll report for each employee. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01069 MASSACHUSETTS Northampton Drainage Relocation GENERAL LAWS 20164277.003A 01069 - 14 THIS PAGE INTENTIONALLY LEFT BLANK ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 1 SECTION 01110 ENVIRONMENTAL PROTECTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SCOPE OF WORK: A. The work covered by this section consists of furnishing all labor materials and equipment and performing all work required for the prevention of environmental pollution in conformance with applicable laws and regulations, during and as the result of construction operations under this Contract. For the purpose of this Specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to man; or degrade the utility of the environmental for aesthetic and/or recreational purposes. B. The control of environmental pollution requires consideration of air, water, and land, and involves management of noise and solid waste, as well as other pollutants. C. Schedule and conduct all work in a manner that will minimize the erosion of soils in the area of the work. Provide erosion control measures such as diversion channels, sedimentation or filtration systems, berms, staked hay bales, seeding, mulching, or other special surface treatments as are required to prevent silting and muddying of streams, rivers, impoundments, lakes, etc. All erosion control measures shall be in place in an area prior to any construction activity in that area. Specific requirements for erosion and sedimentation controls are specified in Section 01568. D. These Specifications are intended to ensure that construction is achieved with a minimum of disturbance to the existing ecological balance between a water resource and its surroundings. These are general guidelines. It is the Contractor's responsibility to determine the specific construction techniques to meet these guidelines. E. Schedule and conduct all work in a manner that will minimize the level of noise escaping the site. ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 2 1.3 APPLICABLE REGULATIONS: A. Comply with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement. 1.4 NOTIFICATIONS: A. The Engineer will notify the Contractor in writing of any non-compliance with the foregoing provisions or of any environmentally objectionable acts and corrective action to be taken. State or local agencies responsible for verification of certain aspects of the environmental protection requirements shall notify the Contractor in writing, through the Engineer, of any non-compliance with State or local requirements. The Contractor shall, after receipt of such notice from the Engineer or from the regulatory agency through the Engineer, immediately take corrective action. Such notice, when delivered to the Contractor or his authorized representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Owner may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor unless it is later determined that the Contractor was in compliance. 1.5 IMPLEMENTATION: A. Prior to commencement of the work, meet with the Engineer to develop mutual understandings relative to compliance with this provision and administration of the environmental pollution control program. B. Remove temporary environmental control features, when approved by the Engineer, and incorporate permanent control features into the project at the earliest practicable time. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION 3.1 EROSION CONTROL: A. Provide positive means of erosion control such as shallow ditches around construction to carry off surface water. Erosion control measures such as siltation basins, hay check dams, mulching, jute netting, and other equivalent techniques shall be used as appropriate. Where possible, offsite surface water shall be diverted around the site. Flow of surface water into excavated areas shall be prevented. At the completion of the work, ditches shall be backfilled and the ground surface restored to original condition. ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 3 3.2 PROTECTION OF STREAMS WETLANDS, AND SURFACE WATER: A. Care shall be taken to prevent any damage to any stream, drainage ditch, storm drain of sewer from pollution by debris, sediment, or other material, or from the manipulation of equipment and/or materials in or near such streams. Water that has been used for washing or processing, or that contains oils or sediments that will reduce the quality of the water in the stream, shall not be directly returned to the stream. Such water will be diverted through a settling basin or filter for treatment before being directed into the streams. B. The Contractor shall not discharge water from dewatering operations directly into any live or intermittent stream, channel, wetlands, surface water, or any storm sewer. Water from dewatering operations shall be treated by filtration, settling basins, or other approved method to reduce the amount of sediment contained in the water to allowable levels. C. All preventative measures shall be taken to avoid spillage of petroleum products and other pollutants. In the event of any spillage, prompt remedial action shall be taken in accordance with a contingency action drawing or plan prepared by the contractor and approved by the Department of Environmental Protection. Contractor shall submit two copies of approved contingency drawings or plans to the Engineer. 3.3 PROTECTION OF LAND RESOURCES: A. Land resources within the project boundaries and outside the limits of permanent work shall be restored to a condition, after completion of construction, that will appear to be natural and not detract from the appearance of the project. Confine all construction activities to areas shown on the Drawings. B. Outside of areas requiring earthwork for the construction of the new facilities, the Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them without prior approval. No ropes, cables, or guys shall be fastened to or attached to any existing nearby trees for anchorage unless specifically authorized by the Engineer. Where such special emergency use is permitted, first wrap the trunk with a sufficient thickness of burlap or rags over which softwood cleats shall be tied before any rope, cable, or wire is placed. The Contractor shall in any event be responsible for any damage resulting from such use. C. Where trees may possibly be defaced, bruised, injured, or otherwise damaged by the Contractor's equipment, dumping or other operations, protect such trees by placing boards, planks, or poles around them. Monuments and markers shall be protected similarly before beginning operations near them. D. Any trees or other landscape feature scarred or damaged by the Contractor's equipment or operations shall be restored as nearly as possible to its original condition. The Engineer will decide what method of restoration shall be used and whether damaged trees shall be treated and healed or removed and disposed of. ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 4 All scars made on trees by equipment, construction operations, or by the removal of limbs larger than 1-in. in diameter shall be coated as soon as possible with an approved tree wound dressing. All trimming or pruning shall be performed in an approved manner by experienced workmen with saws or pruning shears. Tree trimming with axes will not be permitted. Trees that are to remain, either within or outside established clearing limits, that are subsequently damaged by the Contractor and are beyond saving in the opinion of the Engineer, shall be immediately removed and replaced. E. Remove all signs of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess of waste materials, or any other vestiges of construction as directed by the Engineer. It is anticipated that excavation, filling, and plowing of roadways will be required to restore the area to near natural conditions which will permit the growth of vegetation thereon. The disturbed areas shall be prepared and seeded as described in Section 01568, or as approved by the Engineer. F. All debris and excess material will be disposed of outside wetland or floodplain areas in an environmentally sound manner. 3.4 PROTECTION OF AIR QUALITY: A. Burning. The use of burning at the project site for the disposal of refuse and debris will not be permitted. B. Dust Control. The Contractor will be required to maintain all excavations, embankments, stockpiles, access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which could cause the standards for air pollution to be exceeded, and which would cause a hazard or nuisance to others. C. An approved method of stabilization consisting of sprinkling or other similar methods will be permitted to control dust. The use of chlorides may be permitted with approval from the Engineer. If the Engineer decides that it is necessary to use calcium chloride, and it is allowed by local authorities, for more effective dust control, the Contractor shall furnish and apply the material as directed. D. Calcium chloride shall be commercial grade, furnished in 100 lb., 5-ply bags, stored under weatherproof cover and stacked alternately for ventilation. Application for dust control shall be at the rate of about ½ pound per square yard, unless otherwise directed by the Engineer. E. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor must have sufficient competent equipment on the job to accomplish this if sprinkling is used. Dust control ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 5 shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs, as determined by the Engineer. 3.5 MAINTENANCE OF POLLUTION CONTROL FACILITIES DURING CONSTRUCTION: A. During the life of this Contract, maintain all facilities constructed for pollution control as long as the operations creating the particular pollutant are being carried out or until the material concerned has become stabilized to the extent that pollution is no longer being created. 3.6 NOISE CONTROL: A. The Contractor shall make every effort to minimize noises caused by construction operations. Equipment shall be equipped with silencers or mufflers designed to operate with the least possible noise in compliance with State and Federal (OSHA) regulations. END OF SECTION 01110 ENVIRONMENTAL PROTECTION Northampton Drainage Relocation PROCEDURES 20164277.003A 01110 - 6 THIS PAGE INTENTIONALLY LEFT BLANK MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 1 SECTION 01150 MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.1 SUMMARY A. Under the price specified to be paid for each item, the Contractor shall furnish all materials and equipment, furnish all labor and plant, and perform all operations to complete all work as indicated and specified. Provide all supervision, overhead items, protection and precautions, and all other costs, incidental to the construction work, complete, and as specified, are also included. B. A complete, finished, working job, as intended by the general nature of these Specifications, shall be produced whether or not any particular wording or direction is omitted or inadvertently not clearly stated. C. Measurement for payment shall be by the Engineer, except where noted elsewhere in this specification. Measurement for payment for lump sum items shall be on the basis of percentage of work complete. D. Each unit or lump sum price stated in the Bid shall constitute full compensation as herein specified for each item of work completed in accordance with the Drawings and Specifications. E. The prices for those items that involve excavation shall include compensation for clearing and grubbing, excavation, backfill, compaction, testing, dust control, excavation support systems, dewatering, stockpiling, removal of excess material, and restoration of disturbed areas. F. The prices for all pipe items shall constitute full compensation for saw cutting temporary pavement, pipe, stone or sand bedding, laying, jointing, and testing of pipe, trench excavation, providing supplemental gravel, backfilling using flowable fill or approved excavated material as directed and specified, compaction, providing impervious membranes to protect trench and stockpiles, and clean up. G. In all items involving excavation, the price shall be based on doing the entire excavation in earth. Where rock is excavated, the price thereof shall be in addition to the cost of excavating earth, and no deduction will be made in the amount for earth excavation. H. Clearing and grubbing shall not be measured separately for payment, but shall be included in the general cost of the contract and the various items of work. J. Unit prices submitted for various items of work will be utilized for determining prices of MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 2 any additional work necessary during construction. 1.2 ITEM DESCRIPTIONS Item 1, Mobilization/Demobilization: 1. Under the lump sum price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to move his equipment to the site and prepare to begin construction. It shall also include payment for removal of same equipment at the completion of the project. Mobilization costs are the costs of initiating the Contract, exclusive of the cost of materials. 2. Payment for mobilization will be at the lump sum price bid for this item and will be limited to 75 percent of the lump sum amount of this item until the work is complete and the contractor has completely demobilized. The initial payment of 75 percent mobilization costs shall be payable when the Contractor is operational on site. Operational shall mean the substantial commencement of work on site, not prior to commencement. The lump sum price bid for mobilization shall not exceed 5 percent of the total of all items excluding this item. Item 2, Erosion and Sedimentation Control: 1. Under the lump sum price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to control soil erosion and sedimentation as specified. The lump sum price shall include, but not be limited to full compensation for all labor, equipment and services involved in furnishing, maintaining and removing all systems as shown on the plans or as directed by the Engineer. 2. Measurement for payment shall be on the basis of percentage of work completed as measured by the Engineer. Item 3, Exploratory Excavation 1. Under the unit price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to excavate and backfill as shown and as directed to locate pipe, utilities, and possible obstructions. The complete construction also includes saw-cutting pavement, clearing and grubbing, excavation, backfill using excavated materials and gravel as indicated, compaction, dewatering, temporary excavation MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 3 support systems, coordination with utility companies, protection of utilities, temporary pavement repairs, removing unsuitable and excess material from the job, restoration of disturbed areas, clean up and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be based on the actual cubic yards of material excavated, as approved by the Engineer prior to the work. Item 4, Site Preparation: 1. Under the lump sum price bid for this Item, the Contractor shall provide general construction services necessary to prepare the site for proposed improvements. This shall include the following: a. Remove and stockpile existing fencing and gates as identified on the Drawings, which may interfere with the proposed construction activities, as well as all incidental. b. The existing chain link fence and gates along Holyoke Street shall be demolished and disposed of in an appropriate manner. c. Demolishing the existing cantilevered canopy structure and slab located adjacent to the upstream tie-in location and disposing of the material off site. Contractor to remove sufficient footprint of the existing concrete slab to be allow for the construction of support of excavation and the installation of the proposed box culvert. d. As part of the site preparation work the Contractor shall perform a survey of the existing culvert alignment (inside the existing culvert) at the designated upstream and downstream culvert tie-in locations. Contractor shall collect survey data and prepare a Culvert Tie-in Plan for review by the Engineer prior to submitting proposed box culvert submittals. The Culvert Tie-in Survey Plan shall include the following information: i. Contractor to survey the existing culvert alignment for a distance of 60-lf at both tie-in locations. The Contractor shall determine the proposed tie-in location inside the existing culvert and collect the required survey information at a distance 30-ft upgradient and 30-ft downgradient of the designated tie-in location. ii. Contractor collect culvert survey data at a minimum of every 10-ft within the required survey Culvert Tie-in limit. Contractor shall collect invert elevation and MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 4 crown elevation along the centerline alignment, in addition to the width of culvert. iii. Contractor shall coordinate testing pitting activity with the collection of this survey work. Contractor will be required to include test pit information collected at the upgradient test pit. From the proposed Test Pit Location #1, (test pit to be paid for under Item 3 Exploratory Excavation), the Contractor shall survey top (exterior face) of existing brick culvert and present this information on the Culvert Tie-in Survey Plan. iv. Contractor shall superimpose the proposed box culvert alignment to complete the Culvert Tie-in Survey Plan. e. Contractor shall remove, relocate and stockpile approximately 50-lf of jersey barriers located along the northeast perimeter of the site and widen a level area (to the limit of work) for the purpose of allowing construction access along the northern perimeter of the proposed culvert excavation. Contractor shall also include the cost for restoration and re-installation of the jersey barriers at the completion of the project. f. All other incidental site preparation work, including any clearing and grubbing and related activities as outlined in Specification Section 02100, which must be performed to fulfill the obligations of the Contract. 2. Payment for this lump sum Item shall be made on the percentage of work completed as determined by the Engineer. Item 5, Utility & Railroad Coordination: 1. Payment for Utility and Railroad Coordination shall be based on the lump sum price bid for this item. Under the lump sum price for this item, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals required to coordinate with those Utility Companies and the Railroad for completion of all construction within their easement, right-of-ways, properties and zones of influence. The work includes, but is not limited to; coordinating and attending meetings; scheduling flagmen; providing construction support for the railroad; obtaining insurance as required by the Railroad; coordination of ground monitoring; utility monitoring; establishment of staging areas adjacent to MassDOT property and all incidental work. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 5 2. Measurement for payment for Utility and Railroad Coordination will be based on a percentage of the lump sum value bid completed based on the Contractor’s Schedule of Values as approved by the Engineer. Item 6, Geotechnical Instrumentation & Monitoring: 1. Under the Lump Sum Price for Geotechnical Instrumentation and Monitoring, the Contractor shall furnish all labor, materials, instrumentation, tools, equipment, and incidentals required to perform all geotechnical monitoring as specified in the Contract Specifications and also as directed by the Engineer. Payment under this Item includes, but is not limited to; furnishing, installation and maintenance of earth support settlement and deformation monitoring points; monitoring earth support settlement and deformation monitoring points and submission of all data to the Engineer; furnishing, installation and maintenance of ground surface and structure deformation monitoring points; monitoring ground surface and structure deformation monitoring points and submission of all data to the Engineer; furnishing, installation and maintenance of railroad track deformation monitoring points; monitoring railroad track deformation monitoring points and submission of all data to the Engineer; furnishing, installation and maintenance of utility monitoring points along existing utilities as shown on the Contract Drawings, including but not limited to the gas mains varying in size from 4 to 8 inches, the 12-inch water main, and telecom duct banks; monitoring utility monitoring points and submission of all data to the Engineer; furnishing, installation, and maintenance of crack monitoring gauges; monitoring crack monitoring gauges and submission of all data to the Engineer; furnishing, installation and maintenance of seismographs; monitoring seismograph data and submission of all data to the Engineer; submission of shop drawings and submittals as required. 2. Measurement for payment for Geotechnical Instrumentation and Monitoring shall be based on percent completed for the duration defined in the specification related to earthwork activities, and as determined in the field by the Engineer. Payment will not be made until all required submittals have been approved by the Engineer. Further, payment will be contingent upon the Contractor meeting the requirements in the specifications for monitoring, maintenance, and submission of reports. Payment may be withheld, at the Engineer’s discretion, for late submission of reporting requirements. Costs for additional monitoring done for the Contractor’s convenience shall not be compensated for. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 6 Item 7, Stormwater Bypass Pumping: 1. Payment for Stormwater Bypass Pumping shall be based on the Lump Sum price bid for this item. Under the Lump Sum for this item, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals required to establish, maintain, and remove a bypass pumping system complete as required to handle existing stormwater flows while completing the required various elements of the Work at the site. The work includes, but is not limited to, furnishing, installing, and performing the following: design of the bypass pumping system; pumps; suction hoses; discharge pipes or hoses; pump controls; freeze protection if anticipating cold weather; generators, or electrical supply; fuel; temporary plug(s) and restraint/anchoring, fittings, couplings, temporary bulkheads, and appurtenances; redundant/backup equipment; pavement saw-cutting, excavation of bituminous concrete; excavation for temporary burial of bypass pipes, and hoses, or discharge location manhole access; protecting existing structures to remain; transporting material to/from soil staging area; temporary excavation support; removal of concrete top of proposed discharge manhole; selective demolition of proposed suction manhole; preparation of subgrade; assembling bypass pumping system; backfill around buried pipes or hoses; temporary ramps over bypass piping/hose; testing of pumping system prior to bypassing operations; weather monitoring; periodic bypass suspension; emergency service during non-work hours; manning pumps or other bypasses as may be required; protection of discharge locations; temporary plating of suction and discharge manholes when pumping operation is suspended; protection of bypass measures; removal of all bypass pumping system equipment at the end of the pumping operation; recasting top to access manhole; re-exposing buried pipes or hoses for removal, resetting concrete top of discharge manhole; backfill around discharge manhole and empty bypassing pipe trench; compaction; subbase including grading and compaction; site restoration after pumping system is removed; and all appurtenances and incidental work not specifically included for payment elsewhere. 2. Measurement for payment for this item shall be based on a percent of the Lump Sum bid based on the Schedule of Values for the stormwater bypassing flow needed to complete the work as approved by the Owner or Engineer. Item 8, Groundwater Control: 1. Payment for construction dewatering will be based on the lump sum price bid for this item. Under the lump sum price for this item, the MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 7 Contractor shall furnish all labor, materials, tools, equipment, and incidentals required for treatment and control of construction dewatering complete, as required and as directed by the Engineer. The work includes but is not limited to mobilization and demobilization of the complete system(s); design of the system(s); furnishing and installing treatment system(s); maintenance of the treatment system(s); “breakdown”, transportation and set-up of the treatment system(s) between on-site areas requiring treatment; sampling; reporting; maintenance of all logs and other documentation required; laboratory testing; coordination with permitting agencies and the Owner and Engineer; compliance with all permit requirements; removal, transportation, stockpiling, testing and disposal of all collected sediment; Dewatering Professional services; Dewatering Specialist services and all incidental work not included for payment elsewhere. 2. Measurement for payment for construction dewatering will be on a percent complete basis for treatment and control of dewatering activities, as determined by the Engineer. The Contractor shall be paid once the dewatering system(s) is onsite and operational, as required by the applicable dewatering permits, and as directed by the Owner or Engineer. A dewatering treatment system shall include a settling tank, hose connections, hoses and other treatment apparatus. Item 9, 6-ft x 6-ft Reinforced Concrete Box Culvert: 1. Under the unit price, the Contractor shall furnish and install Reinforced Concrete Box Culvert as shown on the plans. The unit price will constitute full compensation for furnishing and installing reinforced precast concrete culvert of size indicated on the plans complete, including furnishing and installing culvert and fittings, angled (sweep) culvert, making connections to structures, removal and disposal of existing pipes and fittings, damp-proofing, and providing a certificate of design. The complete construction also includes, saw-cutting pavement, excavation, backfill using excavated materials and gravel as indicated, crushed stone bedding, geotextile filter fabric, compaction, compaction testing, dewatering, temporary excavation support furnished and installed complete, left in place, and cut off below grade as required or where directed, protection of utilities, repair and/or relocation of any utility lines broken and/or conflicting with construction, temporary pavement repairs, restoration of disturbed areas, clean up and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 8 2. Measurement for payment for box culvert items will be based on the actual linear feet of pipe installed, and accepted, complete as shown on the Contract Drawings or as directed by the Engineer and as measured by the Engineer along the centerline of the pipe from the inside face of the upstream tie-in collar to inside face of the downstream tie-in collar. Item 10A, Pipe RCP 12-inch Pipe: Item 10B, Pipe RCP 15-inch Pipe: Item 10C, Pipe RCP 24-inch Pipe: 1. Payment for Reinforced Concrete Pipe Items shall be based on the unit price bid for this item. Under the unit price for each pipe item, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals required to install Reinforced Concrete (Class IV) Pipe complete as shown on the Contract Drawings or at the direction of the Engineer. The work includes, but is not limited to; saw cutting; excavation; furnishing and placing backfill per one of the approved methods; preparation of subgrade; furnish, install and compact gravel road sub-base; furnish and install filter fabric as required; compaction; temporary excavation support furnished and installed complete, left in place, and cut off below grade as required or where directed; furnishing, installing and compacting bedding; furnishing and installing reinforced concrete pipe, fittings, couplings and appurtenances; connections to existing and proposed pipes and structures; construction dewatering; and all incidental work not specifically included for payment elsewhere. The complete construction also includes saw cutting the roadway for trenches, excavation, backfill, bedding, rigid insulation, compaction, dewatering, temporary excavation support systems, protection of utilities, repair and/or relocation of any utility lines broken and/or conflicting with construction, removing excess material from the job, clean up and all other appurtenant materials, and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment for Reinforced Concrete Pipe Items will be based on the actual linear feet of pipe installed, of all classes and at all depths, and accepted, complete as shown on the Contract Drawings or as directed by the Engineer and as measured by the Engineer along the centerline of the pipe from the inside face of structures to inside face of structures or to the points of connection with existing pipes. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 9 Item11, Pipe DI 12-inch Diameter: 1. Under the unit price bid, the Contractor shall furnish and install permanent 12-inch ductile iron water main as shown on the plans and as indicated in the specifications, including fittings of the same size and pressure rating, and material grade. The unit price bid will constitute full compensation for constructing the water main complete, including furnishing and installing all fittings and couplings; connections to existing mains where required, pressure testing, including taps with corporations or bleeder valves on plugs for testing of water mains; providing water for pressure and leakage tests; disinfection; sampling; and laboratory analyses; and removal and disposal of existing pipe and fittings within and outside of trench limits and as indicated. The complete construction also includes saw cutting the roadway for trenches, excavation, backfill, bedding, rigid insulation, compaction, dewatering, temporary excavation support systems, protection of utilities, repair and/or relocation of any utility lines broken and/or conflicting with construction, removing excess material from the job, clean up and all other appurtenant materials, and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be by the linear foot of water main installed, complete and accepted in place. Measurement will be along the water main centerline without deduction for valves and fittings. . Temporary relocation of water main shall included as part of the proposed box culvert bid item. Item 12, Pipe PVC 10-inch Diameter: 1. Under the unit price bid, the Contractor shall furnish and install Polyvinyl Chloride (PVC) SDR 35 pipe including fittings of the same size and rating, and material grade as shown on the plans. The unit price will constitute full compensation for constructing the pipe complete; including furnishing and installing pipe and fittings, making connections to existing catch basin structure to the proposed drainage structures, including coring existing catch basin structure and bypassing and maintaining existing flows. The complete construction also includes, saw cutting pavement, excavation, backfill using flowable fill or approved material, furnish and install pipe bedding material, geotextile filter fabric, compaction, dewatering, temporary excavation support systems, protection of utilities, repair and/or relocation of any utility lines broken and/or MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 10 conflicting with construction, removing excess material from the job, restoration of disturbed areas, clean up and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be by the linear foot of pipe installed as measured by the Engineer along the horizontal projection of the centerline of the completed pipe from the mainline to the coupling. Item 13, Catch Basin: 1. Under the unit price bid, the Contractor shall furnish and install drainage structures as shown on the plans. The unit price bid will constitute full compensation for furnishing and installing reinforced precast concrete base, riser sections, cones or top slabs, catch basin frames, grates, and covers, buoyancy collars, and brick and mortar under frames, steps, damp-proofing, hooded outlet device, and adjusting frames to grade. The complete construction also includes, saw-cutting pavement, excavation, backfill using excavated materials or approved backfill, stone bedding, geotextile filter fabric, compaction, dewatering, temporary excavation support systems, protection of utilities, repair and/or relocation of any utility lines broken and/or conflicting with construction, removing excess material from the job, restoration of disturbed areas, clean up and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be by the vertical foot completed as measured by the Engineer from the top of frame elevation to the outlet pipe invert within the catch basin. Item 14A, Manhole – Precast 4-ft Diameter: Item 14B, Drop Manhole – Precast 4-ft Diameter: Item 14C, Drop Manhole – Precast 5-ft Diameter: 1. Under the unit price bid, the Contractor shall furnish and install drainage manhole structures as shown on the plans. The unit price bid will constitute full compensation for furnishing and installing reinforced precast or cast-in place concrete base, precast concrete riser sections, cones or top slabs, landing platforms, standard frames and covers, buoyancy collars, and brick and mortar risers under frames, steps, damp-proofing, specialty pipe fittings and drop piping, constructing brick inverts, removal, disposal and/or abandonment of existing structures, testing for leakage, bypassing and maintaining MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 11 existing flows, and adjusting frames to grade. The complete construction also includes, saw cutting pavement, excavation, backfill using excavated materials and gravel as indicated, stone bedding, compaction, dewatering, temporary excavation support systems, protection of utilities, repair and/or relocation of any utility lines broken and/or conflicting with construction, removing excess material from the job site, restoration of disturbed areas, clean up and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be by the vertical foot completed as measured by the Engineer from the top of frame elevation to the lowest pipe invert within the manhole. Item 15, Demolish and Remove Drainage Pipe, Manholes, Catch Basins and Other Structures: 1. Under the lump sum price bid, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals required to demolish and remove pipes and/or structures, and to cut and cap pipe to be abandoned inplace, as specified. The work includes, but is not limited to; saw cutting; excavation; support of excavation, backfill, furnish and placing approved backfill material; and removal of existing pipes and/or structures as specified or directed by the Engineer; capping of abandoned pipe end (which are to remain in place) with masonry plugs or bulkheads; construction dewatering; disconnecting existing pipe, and other connections; for removal of covers/grates/castings (to be provide to Owner), demolition verify function of all existing connections including those that are abandoned or those to be transferred to an active and functioning pipe; demolition and removal of the specified pipe or structure; and disposal of removed material. 2. Measurement for payment shall be on a lump sum basis for the abandonment, demolition and removal of pipe and structures identified on the plans. Item 16, Abandon Existing Brick Arched Culvert with Flowable Fill 1. Under unit price bid, the Contractor shall abandon the existing arched brick culvert in-place with flowable fill, as indicated. The unit price bid will constitute full compensation for furnishing and installing control density fill (MassDOT M4.08.0, Type 2E), providing a temporary vent for air release when the control density fill is installed, constructing bulkhead and/or masonry plugs at ends of each pipe and any excavation, backfill, dewatering required. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 12 2. Measurement for payment will be on the basis of linear feet of pipe abandoned in place as measured by the Engineer. Item 17, Excavate Unsuitable Material Below Grade: 1. Under the unit price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to remove peat or other unsuitable material below the pipe or manhole bedding as approved by the Engineer. The unit price bid will constitute full compensation for performing all required excavations, including load, transport, and disposal of such material away from the job; furnishing and placing crushed stone and filter fabric in the place of material removed, and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Measurement for payment will be on the basis of cubic yards of unsuitable material excavated. The depth of unsuitable material in pipe trenches will be measured from the bottom of normal bedding to the depth of replacement. The maximum allowable depth of replacement shall be 12 inches. The allowable width of unsuitable material shall be limited to the trench width limits as shown on the plans. Item 18, Rock Excavation: 1. Under the unit price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to excavate, remove, and dispose of rock from trenches and excavated areas as required and approved by the Engineer. Blasting of rock will not be permitted. The unit price bid will constitute full compensation for performing all required excavations, including related costs such as drilling, splitting, hammering, and replacement with suitable gravel material, and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 3. Measurement for payment will be on the basis of cubic yards of rock excavated. Depth of rock in pipe trenches will be measured from the rock surface to 6-inches below the invert of the pipe and the maximum trench width shall be as shown on the typical trench details as shown on the Drawings. Any rock excavated to a depth or width greater than the above shall be backfilled with gravel at the Contractor's expense. The pay limit for rock removal outside manholes and structures will be one foot outside the widest dimension of the structure or shall be the maximum trench width, whichever is greater. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 13 Item19, Dense Graded Crushed Stone: 1. Under the unit price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to place dense graded crushed stone to construct the 12-inch thick roadway subbase course, 12-inch thick sidewalk subbase course, or for final trench (12-inch thick) surface restoration to the limits as shown on the plans. The unit price bid will constitute full compensation for placing the dense graded crushed stone, compaction, compaction testing, dust control, and preparation, grading, and compaction of existing subbase. 2. Measurement for payment will be on the basis of square yards of dense graded crushed stone completed and accepted in place as measured by the Engineer. Dense graded crushed stone used in other items of work not referenced above will not be measured for payment under this item, but shall be included in the unit prices for the other items of work. Item 20A, Bituminous Concrete Pavement – Top Course: Item 20B, Bituminous Concrete Pavement – Binder Course: Item 20C, Bituminous Concrete Pavement – Base Course: 1. Under this unit price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to place a bituminous concrete pavement in paved sections of roadway, sidewalks or driveways as shown on the plans and as directed. The unit price bid will constitute full compensation for saw-cutting or trimming of pavement, preparation of the subgrade, compaction of subgrade, dust control, resetting utility castings, placing pavements, including placing tack coat, compaction, compaction testing, and replacement of disturbed pavement markings and all other appurtenant materials and work incidental thereto and not specifically included for payment under other items. 2. Payment for Bituminous Concrete Pavement Course (Top, Binder, & Base Course) shall be based on the unit price bid for the specific course in the proposal. Under the unit price for these items, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals required to install Bituminous Concrete Pavement Course to depth and width indicated within the payment limits, complete, as shown in the Contract Documents or at the direction of the Engineer. The work includes, but is not limited to the following; raising and resetting existing structures, castings and boxes; installation and compaction of bituminous concrete pavement course to the depth and width and in the area specified; compaction testing; power sweeping; MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 14 keyways and other jointing between new and existing asphalt; furnish and place tack coat; and all incidental work not included for payment elsewhere. Payment for bituminous concrete roadways, sidewalks, driveways and parking areas shall all be included herein. Any pavements that during the course of construction are damaged by negligent operations of the Contractor shall not be measured for payment, but repaired by the Contractor at his expense as directed by the Engineer. “Temporary” pavement repairs placed as indicated on the plans and as directed will not be measured for payment under this item, but shall be included under the general cost of the contract and in the unit prices for the other items of work. Item 21, Protection and Maintenance of Traffic: 1. Under the lump sum price bid, the Contractor shall furnish all plant, labor, equipment, appurtenances and materials to control traffic as specified. The lump sum price shall include, but not be limited to full compensation for all labor, equipment and services involved in erection, maintenance, moving, adjusting, cleaning, relocating, and storing of steel plates, signs, barricades, drums, traffic cones and delineators furnished by the Contractor as well as all costs of labor and equipment involved in the maintenance of traffic lanes and detours maintenance of traffic as directed and approved by the City. The lump sum price shall also include the cost of furnishing the aforementioned steel plates, signs, barricades, warning lights, drums, traffic cones and delineators. The Contractor shall coordinate traffic control requirements with the City on a daily basis throughout the course of the work. The lump sum price includes the cost for coordinating traffic control requirements and scheduling of uniformed police for traffic control. 2. Measurement for payment shall be on the basis of percentage of work completed, inspected and accepted by the Engineer. The Contractor shall maintain and protect the traffic throughout the entire duration of the Contract. No claim for additional payment due to unusual construction conditions encountered or delay caused by the Contractor or other outside agencies shall be considered. MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 15 Item 22, Uniformed Police for Traffic Control: 1. Payment for uniformed police shall be made for expenses billed to the Contractor by the Police Department in the normal course of providing supervision for traffic control during construction operations. 2. Uniformed police and police car fees, when required by the Police Department, shall be paid under the allowance stated in the Bid. The allowance stated in the Bid is approximate, and the actual amount to be paid may be more or less, but shall match the actual amount paid to the Police Department as authorized by the Engineer. 3. The Contractor shall record the actual amount paid for uniformed police and, at the end of each month, Contractor shall submit the total amount paid during the month, in four copies, to the Engineer, who will review such amounts, when verified, in monthly payment requests from the Contractor to the Owner. 4. If the uniformed police expenses are greater than the stated allowance, the Contractor shall be reimbursed the difference in the actual costs as billed. Any unexpended amount shall remain with the Owner as a credit on the total base bid. 5. No mark-up for uniformed police shall be allowed. Only documented police invoice amounts shall be reimbursed to the Contractor. 6. No payment will be allowed for police details ordered but not utilized due to the Contractor’s cancellation of work activities without appropriate advance notification to the Police Department in accordance with the requirements of the Police Department. 7. No payment will be allowed for uniformed police required due to the Contractor’s failure to furnish and maintain traffic control measures including but not limited to project signage, barriers, and warning devices in accordance with the Specifications and the Contractor’s Traffic Control Plan, as approved by the Engineer. 8. The Contractor shall coordinate with the City’s Department of Public Works, Police Department and the Engineer to determine daily uniformed police detail requirements. No payment will be allowed for uniformed police details ordered without such coordination. Item 23, Chain Link Fence and Gate: 1. Under the unit price bid for this Item, the Contractor shall perform all work necessary to furnish and install 6-foot-high chain link fence and MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 16 20-ft wide double swing gate in the location shown and detailed on the Drawings and specified in the Specifications Section 02830. Payment for this Item shall include excavation of post holes; installation of the line and end posts in concrete, top and middle rails, tension wire (where required), braces, post caps, fabric, and all miscellaneous parts to install the fence and gate; restoration of surface; clean up; and all else incidental thereto, for which separate payment is not provided under other Pay Items. Payment for this Item shall also include furnishing and installing galvanized fence fabric with galvanized posts and appurtenances. 2. Payment for this Item shall be on a lump sum basis for the 6-foot-high fence and gate installed in accordance with the Contract Documents and as approved by the Engineer. Item 24, Remain Miscellaneous Work: 1. Under the lump sum price for this Item, the Contractor shall furnish and install all work required to complete the project which is not specifically addressed under the other Pay Items specified herein. These remaining lump sum items shall include, but are not limited to, the following. a. Attending the pre-construction conference and all required project progress meetings, and coordination of all construction activities with the appropriate local authorities and utilities. b. Submission of all schedules, lists, laboratory test results, materials and sources, survey documentation, environmental monitoring documentation, and shop drawings, as required, in a timely manner to the Engineer for review and approval. c. Providing the engineer field office (construction trailer), including all specified furnishings and temporary utilities. d. Providing all field engineering surveying activities not expressly identified under other Pay Items, and all related surveying activities necessary to maintain construction control at the site. e. Preparing construction sequencing plan(s) as required to execute the work in a manner that allows existing site operations to continue uninterrupted, as specified in Specification Section 01300 – SUBMITTALS. f. Preparing a pre-construction survey for those properties near the site and identified in Specification Section 01390 – PROJECT MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 17 PRE-CONSTRUCTION SURVEYS. g. Providing construction photographs. h. Protection of existing monitoring wells and repair of any wells damaged during construction. In addition, the Contractor shall also include the installation of proposed gas monitoring wells, protective casings and lockable cover and lock as shown on the Drawings. i. Coordination of all construction activities with Town personnel. 2. Payment for this Item shall be based upon the percentage of work completed, as determined by the Engineer. The Contractor shall provide the Engineer with a cost breakdown for each of the lump sum items included in the Bid Proposal (Section 00301 - BID FORMS of these Specifications). The Engineer reserves the right to adjust any unbalanced lump sum items. Item 25A, Price Adjustment for Fuel, Diesel for Excavation Work: Item 25B, Price Adjustment for Fuel, Diesel for Surface Work: 1. A base price for the material shall be set by the City at the time of advertisement. The diesel base price is $2.091/gallon, as indicated by actual prices paid by MassDOT – Highway Division. 2. Price adjustments shall provide for additional compensation to the Contractor or repayment to the City, depending on whether the variance from the base price is an increase or decrease. 3. Payment for the price adjustment for diesel fuel shall be made on a monthly basis for Excavation and Borrow Work at a fuel factor of 0.29 Gal/CY, and for Surfacing Work at a fuel factor of 2.90 Gal/Ton; when the variance from the base price is 5% or more for a monthly period. 4. The Contractor shall submit for payment under these items upon completion of the work, using the difference between the base price and the monthly period price for the month during which the work was performed. 5. The Contractor shall document and submit proof of quantities of materials, in the appropriate units for each item, per each month for review and approval by the Engineer. 6. The fuel factors will be multiplied by the approved quantities of work done during each monthly period and further multiplied by the variance in price from the base price to the period price, as shown in the MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 18 following equations. a. Excavation/Borrow Work: (0.29 gal/CY)*(CY)*[period price-$2.333/gal] b. Surfacing Work: (2.90 gal/ton)*(tons)*[period price-$2.333/gal] 7. No price adjustments shall be allowed beyond the completion date of the Contract. Item 26, Price Adjustment for Liquid Asphalt: 1. A base price for the material shall be set by the City at the time of advertisement. The base price is $377.50/ton, as indicated by actual prices paid by MassDOT – Highway Division. 2. Price adjustments shall provide for additional compensation to the Contractor or repayment to the City, depending on whether the variance from the base price is an increase or decrease. 3. Payment for the price adjustment for liquid asphalt shall be made on a monthly basis for quantities greater than 100 tons of hot mix asphalt mixtures containing liquid asphalt cement, when the variance from the base price is 5% or more for a monthly period. The price adjustment shall not include transportation or other charges. 4. The Contractor shall submit for payment under these items upon completion of the work, using the difference between the base price and the monthly period price for the month during which the work was performed. 5. The Contractor shall document and submit proof of quantities of materials, in the appropriate units for each item, per each month for review and approval by the Engineer. 6. The approved number of tons of hot mix asphalt mixtures placed during each monthly period will be multiplied by the liquid asphalt content percentage, and further multiplied by the variance in price between the base price and the period price, as shown in the following equation. (tons placed)*(content percentage)*[period price-$505.00/ton] 7. No price adjustments shall be allowed beyond the completion date of MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 19 the Contract. Item 27, Price Adjustment for Portland Cement: 1. A base price for each material shall be set by the City at the time of advertisement. The base price is $121.80/ton, as indicated by actual prices paid by MassDOT – Highway Division. 2. Price adjustments shall provide for additional compensation to the Contractor or repayment to the City, depending on whether the variance from the base price is an increase or decrease. 3. Payment for the price adjustment for Portland cement concrete containing Portland cement shall be made on a monthly basis for quantities greater than 100 cubic yards, when the variance from the base price is 5% or more for a monthly period. The price adjustment shall not include transportation or other charges. 4. The Contractor shall submit for payment under these items upon completion of the work, using the difference between the base price and the monthly period price for the month during which the work was performed. 5. The Contractor shall document and submit proof of quantities of materials, in the appropriate units for each item, per each month for review and approval by the Engineer. 6. The approved number of cubic yards of Portland cement concrete placed during each monthly period will be multiplied by the Portland cement content percentage, and further multiplied by the variance in price between the base price and the period price, as shown in the following equation. (tons placed)*(content percentage)*[period price - $123.78/ton] 7. No price adjustments shall be allowed beyond the completion date of the Contract. END OF SECTION 01150 MEASUREMENT Northampton Drainage Relocation AND PAYMENT 20164277.003A 01150 - 20 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation PROJECT MEETINGS 20164277.003A 01200 - 1 SECTION 01200 PROJECT MEETINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 PRE-BID CONFERENCE A. Prior to the opening of the bids, a site conference may be held with prospective bidders. All Contractors are urged to attend. Approximately two (2) weeks before the bid opening, all Contractors who have requested bid documents shall be furnished with the date, time and place of the meeting. 1.3 PRE-CONSTRUCTION CONFERENCE A. A preconstruction conference will be held between the Contractor, the Engineer, the Owner, and applicable agency representatives to review the Contractor's proposed methods of complying with the requirements of the Contract Documents. B. Contractor will be notified of the time, date and place where the preconstruction conference will be held. 1.4 PROGRESS MEETINGS WITH ENGINEER A. In addition to other regular project meetings for other purposes (as indicated elsewhere in the Contract Documents), hold general progress meetings twice each month with times coordinated with preparation of payment requests. Meeting dates shall be established by the Engineer. Require every entity then involved in the planning, coordination or performance of work to be properly represented at each meeting. Include (when applicable) consultants, separate contractors (if any), principal subcontractors, suppliers/ manufacturers/fabricators, governing authorities, insurers, special supervisory personnel and others with an interest or expertise in the progress of the work. Review each entity's present and future needs including interface requirements, time, sequence, deliveries, access, site utilization, temporary facilities and services, hours of work, hazards and risks, housekeeping, submittals, change orders, and documentation of information for payment requests. Discuss whether each element of current work is ahead of schedule. Northampton Drainage Relocation PROJECT MEETINGS 20164277.003A 01200 - 2 Determine how behind-time work will be expedited, and secure commitments from the entities involved in doing so. Discuss whether schedule revisions are required to ensure that current work and subsequent work will be completed within the Contract Time. Review everything of significance which could affect the progress of the work. B. Within seven days after each progress meeting date, the Engineer will forward copies of the minutes-of-the-meeting, to the Contractor. C. Immediately following each progress meeting where revisions to the Progress Schedule/Critical Path Schedule have been made or recognized (regardless of whether agreed to by each entity represented), revise the Schedule. Reissue revised Schedule within 10 days after meeting. At intervals matching the preparation of payment requests, revise and reissue the Schedule to show actual progress of the work in relation to the latest revision of the Schedule. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01200 Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 1 SECTION 01300 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section specifies the general methods and requirements of submissions applicable to the following work-related submittals. 1. Shop Drawings. 2. Product Data. 3. Certificates of Design. 4. Samples. 5. Construction Photographs. 6. Construction or Submittal Schedules. 7. Or equal submittals. B. Additional general submission requirements are contained in Paragraph 6.17 of the General Conditions. C. Detailed submittal requirements will be specified in the technical specifications section. 1.3 SHOP DRAWINGS, PRODUCT DATA, SAMPLES A. Shop Drawings: 1. Shop drawings, as defined in the General Conditions, and as specified in individual work sections include, but are not necessarily limited to: custom-prepared data Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 2 such as fabrication and erection/installation (working) drawings of concrete reinforcement, structural details and piping layout, schedule information, setting diagrams, actual shopwork manufacturing instructions, custom templates, special wiring diagrams, coordination drawings, individual system or equipment inspection and test reports including performance curves and certifications as applicable to the work. 2. All shop and working drawings shall be prepared on standard size, 24-in. by 36-in. sheets, except those which are made by changing existing standard shop or working drawings. 3. All shop drawings shall be submitted using a transmittal form approved by the Engineer. Submittal form shall include identification of transmittal number and specification section number. 4. All shop drawings submitted by subcontractors for review shall be sent directly to the Contractor for approval. The Contractor shall be responsible for their submission at the proper time so as to prevent delays in delivery of materials. 5. The Contractor shall check all subcontractor's shop drawings regarding measurements, size of members, materials, and details to satisfy himself that they conform to the intent of the Drawings and Specifications. Shop drawings found to be inaccurate or otherwise in error shall be returned to the subcontractors for correction before submission thereof. 6. All details on shop drawings submitted for approval shall show clearly the relation of the various parts of the main members and lines of the structure, and where correct fabrication of the work depends upon field measurements, such measurements shall be made and noted on the drawings before being submitted for approval. B. Product Data: 1. Product data as specified in individual sections, include, but are not necessarily limited to, standard prepared data for manufactured products (sometimes referred to as catalog data), such as the manufacturer's product specification and printed installation instructions, availability of colors and patterns, manufacturer's printed statements of compliances including certificates of compliance and applicability, roughing-in diagrams and templates, catalog cuts, product photographs, standard wiring diagrams, printed performance curves and operational-range diagrams, production or quality control inspection and test reports and certifications and Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 3 recommended spare-parts listing, and printed product warranties, as applicable to the Work. C. Samples: 1. Samples specified in individual sections, include, but are not necessarily limited to, physical examples of the work such as sections of manufactured or fabricated work, small cuts or containers of materials, complete units of repetitively-used products, color/texture/pattern swatches and range sets, specimens for coordination of visual effect, graphic symbols, and units of work to be used by the Engineer or Owner for independent inspection and testing, as applicable to the Work. The Contractor shall furnish such samples of material as may be required for examination and test. All samples of materials for tests hall be taken according to ASTM Specifications or as provided in the Contract Documents. All samples shall be submitted by the Contractor with a covering letter indicating that such samples are recommended by the Contractor for the service intended and that the Contractor’s Guarantee will fully apply. 2. All materials, equipment and workmanship shall be in accordance with samples guaranteed by the Contractor and reviewed by the Engineer. 1.4 CONTRACTOR'S RESPONSIBILITIES A. The Contractor shall review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: 1. Field measurements 2. Field construction criteria 3. Catalog numbers and similar data 4. Conformance with the Specifications B. Each shop drawing, sample, and product data submitted by the Contractor shall have affixed to it the following Certification Statement including the Contractor's Company name and signed by the Contractor: "Certification Statement: by this submittal, I hereby represent that I have determined and verified all field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data, and I have checked and coordinated each item with other applicable approved shop drawings and all Contract requirements." Shop drawings and product data sheets 11-in. X 17-in. and smaller shall be bound together in an orderly fashion and bear the above Certification Statement on the Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 4 cover sheet. The cover sheet shall fully describe the packaged data and include a listing of all items within the package. Provide to the Engineer a copy of each submittal transmittal form for shop drawings, product data and samples at the time of submittal of said drawings, product data and samples to the Engineer. 1. Submittals received “WITHOUT” Certification Statement shall not be reviewed. C. If a shop drawing shows any deviation from the requirements of the Contract Documents, the Contractor shall make specific mention of the deviations in the Transmittal Form furnished by the Engineer and provide a description of the deviations in a letter attached to the submittal. D. The review and approval of shop drawings, samples or product data by the Engineer shall not relieve the Contractor from his responsibility with regard to the fulfillment of the terms of the Contract. All risks of error and omission are assumed by the Contractor and the Engineer will not have responsibility therefor. E. No portion of the work requiring a shop drawing, sample, or product data shall be started nor shall any materials be fabricated or installed prior to the approval or qualified approval of such item. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data shall be at the Contractor's risk. The Owner will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. F. Project work, materials, fabrication, and installation shall conform with approved shop drawings, applicable samples, and product data. 1. Manufacturer’s printed installation instructions, a part of product data submitted to the Engineer will not be reviewed and are for informational purposes only. 1.5 “OR EQUAL” A. Should the Contractor seek approval of a product other than the brand or brands named in these specifications, it shall furnish written evidence that such product conforms in all respects to the specified requirements, and that it has been used successfully elsewhere under similar conditions. Where the specified requirements involve conformance to recognized codes or standards the Contractor shall furnish evidence of such conformance in the form of test or inspection reports, prepared by a recognized agency, and baring an authorized signature. B. Manufacturers’ standard data and catalog cut sheets will not be considered sufficient in themselves, and the Engineer will not be responsible for seeking further data from the Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 5 manufacturer, or for otherwise researching the product. Failure to provide complete data will be cause for rejection of the product. C. The Contractor shall be responsible for all additional costs including license fees, foundation, piping and electrical work necessary to accommodate the proposed “or equal” equipment. Items which result in a cost reduction shall be presented and a change order will be prepared and the contract price modified. 1.6 SUBMISSION REQUIREMENTS A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. All complete submittals shall be submitted sufficiently in advance of construction requirements to provide no less than fifteen (15) days, excluding Saturdays, Sundays and legal holidays for review from the time received at the Engineer’s reviewing office. For submittals of major equipment, that require more than fifteen (15) days to review, due to its sheer complexity and amount of detail and also requiring review by more than one engineering discipline, a letter will be sent by the Project Manager or his/her designee to the Contractor informing him/her of the circumstances and the date it is expected the submittal will be returned to the Contractor. C. Number of submittals required: 1. Shop Drawings: Unless otherwise stated in the respective Specifications Sections, submit six (6) copies. 2. Product Data: Unless otherwise stated in the respective Specifications submit six (6) copies. 3. Samples: Submit the number stated in the respective Specification Sections. D. Submittals shall contain: 1. The date of submission and the dates of any previous submissions. 2. The Project title and number. 3. Contractor identification. 4. The names of: Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 6 a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the specification section number, page and paragraph(s). 6. Field dimensions, clearly identified as such. 7. Relation to adjacent or critical features of the Work or materials. 8. Applicable standards, such as ASTM or Federal Specification numbers. 9. Identification of deviations from Contract Documents. 10. Identification of revisions on resubmittals. 11. An 8-in. X 3-in. blank space for Contractor and Engineer stamps. E. Each shipment of drawings shall be accompanied by a transmittal form furnished by the Engineer giving a list of the drawing numbers and the names mentioned above. 1.7 REVIEW OF SHOP DRAWINGS, PRODUCT DATA, WORKING DRAWINGS AND SAMPLES A. The Engineer's review is for general conformance with the design concept and contract drawings. Markings or comments shall not be construed as relieving the Contractor from compliance with the contract plans and specifications or from departures therefrom. The Contractor remains responsible for details and accuracy, for coordinating the work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly, and for performing work in a safe manner. B. The review of shop drawings, data, and samples will be general. They shall not be construed: 1. as permitting any departure from the Contract requirements; 2. as relieving the Contractor of responsibility for any errors, including details, dimensions, and materials; 3. as approving departures from details furnished by the Engineer, except as otherwise provided herein. Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 7 C. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which the Engineer finds to be in the interest of the Owner and to be so minor as not to involve a change in Contract Price or time for performance, the Engineer may return the reviewed drawings without noting an exception. D. Two (maximum) copies of shop drawings or product data will be returned to the Contractor. Samples will not be returned. E. Submittals will be returned to the Contractor under one of the action codes indicated and defined on the transmittal form furnished by the Engineer. F. Resubmittals will be handled in the same manner as first submittals. On resubmittals the Contractor shall direct specific attention, in writing, on the letter of transmittal and on resubmitted shop drawings by use of revision triangles or other similar methods, to revisions other than the corrections requested by the Engineer, on previous submissions. Any such revisions which are not clearly identified shall be made at the risk of the Contractor. The Contractor shall make corrections to any work done because of this type revision that is not in accordance to the Contract Documents as may be required by the Engineer. G. Partial submittals may not be reviewed. The Engineer will be the only judge as to the completeness of a submittal. Submittals not complete will be returned to the Contractor, and will be considered "Rejected" until resubmitted. The Engineer may at his option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. H. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, the Contractor shall give written notice thereof to the Engineer at least seven working days prior to release for manufacture. I. When the shop drawings have been completed to the satisfaction of the Engineer, the Contractor shall carry out the construction in accordance therewith and shall make no further changes therein except upon written instructions from the Engineer. 1.8 GENERAL PROCEDURES FOR SUBMITTALS A. Coordination of Submittal Times: Prepare and transmit each submittal sufficiently in advance of performing the related work or other applicable activities, or within the time specified in the individual work sections, of the Specifications, so that the installation will not be delayed by processing times including disapproval resubmittal (if required), coordination with other submittals, inspection, testing (off-site and on-site), purchasing, fabrication, delivery and similar sequenced activities. No extension of time will be Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 8 authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. 1.9 CERTIFICATION FORMS A. If specifically specified in other sections of these Specifications, the Contractor shall submit the applicable certification form for each item required, and in the form attached to this section, completely filled in and stamped. 1.10 CERTIFICATES OF COMPLIANCE A. Certificates of Compliance specified in the specifications shall include and mean certificates, manufacturer’s certificates, certifications, certified copies, letters of certification and certificate of materials. B. The Contractor shall be responsible for providing Certificates of Compliance requested and specified in the technical specifications. Certificates are required for demonstrating proof that the Contractor has reviewed, checked and approved the shop drawings, so that they are in harmony with specification requirements, and that he/she has verified all field measurements and construction criteria, materials, catalog numbers and similar data. Certificates shall be executed in 6 copies unless otherwise specified. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Supplier, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Supplier from furnishing satisfactory material, if after tests are performed on selected samples, the material is found not to meet the specific requirements. The Contractor shall also certify that the work represented by the shop drawings is recommended by the Contractor and the Contractor’s Guarantee will fully apply. 1.11 CONSTRUCTION SEQUENCING PLAN A. Within 15 calendar days of Owner’s issuance of the Notice to Proceed, the Contractor shall submit his proposed Construction Sequencing Plan for the project. The Sequencing Plan will describe in detail the Contractor’s proposed approach for completing all required construction activities in a manner that allows existing drainage and utility at the site to continue uninterrupted. The Sequencing Plan shall identify in numerical order the task hierarchy (first, second, third, etc. priority of work items required to accomplish the sequencing objectives) of each work activity to be performed and include a detailed narrative of that activity and how it relates to each successive sequential work item. Each proposed sequencing work activity Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 9 (task) shall identify the proposed calendar time line for performing the work and shall tie to the Contractor’s overall master construction schedule prepared for the project. The Construction Sequencing Plan shall also include an annotated site plan graphically depicting each sequencing task (bounding the area of work that will be completed under the specific sequencing activity) with its respective task number indicating the order in which it will be completed relative to the other sequencing tasks. 1.12 CONTRACTOR'S COST BREAKDOWN (SCHEDULE OF VALUES) A. Within ten (10) days of contract award, the Contractor shall provide the Engineer with a complete breakdown of the cost of the lump sum items in the Bid Proposal in such a manner that the breakdown may be used as a basis for estimating the value of work completed to the end of any month. The extent and basis of the breakdown shall meet the Engineer's approval. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01300 Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 10 CERTIFICATE OF DESIGN The undersigned hereby certifies that he/she is a Professional Engineer registered in the state of Massachusetts and that he/she has been employed by (Name of Contractor) ________________________ to design _____________________________ in accordance with Specifications Section _____ for the Drain Relocation project. The undersigned further certifies that he/she has performed similar designs previously and has personally performed or directly supervised the design of the __________________________; that said design is in conformance with all applicable local, state, and federal codes, rules, and regulations and professional practice standards; that his/her signature and Professional Engineer (P.E.) Stamp have been affixed to all calculations and drawings used in, and resulting from, the design; and that the use of that stamp signifies the full responsibility of the undersigned for that design. The undersigned hereby certifies that he/she has Professional Liability Insurance or will be covered by an Employer Policy with limits of $1,000,000.00 and a Certificate of Insurance is attached. The undersigned hereby agrees to make all original design drawings and calculations available to the City of Northampton or Owner’s representative within seven (7) days following written request therefore by the Owner. __________________________ ____________________________ P.E. Name Contractor’s Name __________________________ ____________________________ Signature Signature __________________________ ____________________________ Title Title __________________________ ____________________________ Address Address Northampton Drainage Relocation SUBMITTAL PROCEDURES 20164277.003A 01300 - 11 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation AS-BUILT DRAWINGS 20164277.003A 01346 - 1 SECTION 01346 AS-BUILT DRAWINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. As-Built Drawings: a. The Contractor shall maintain and keep a record copy of as- built drawings. The drawings shall show all materials as installed. For utility projects, a minimum of two (2) swingties to permanent structures shall be shown for all fittings, valves, corporation stops, sewer services and any other item which will be backfilled upon completion of the work. As-built drawings shall be kept current and will be reviewed monthly. Failure to maintain current as-built drawings will be cause to delay progress payments. As-built drawings shall be available to the Engineer at all times during the life of the Contract. Upon request, the Owner will provide one set of reproducibles of the original Contract Drawings and a sample record drawing showing required style and quality, for this purpose. General Contractor shall be responsible for coordinating, collecting and updating as-built drawings from subcontractors. 1) All drawings shall be made a part of the record drawings and shall include the following: a) Contract Drawings: Annotate or redraft, as required, to show all revisions, substitutions, variations, omissions and discrepancies made or discovered during construction concerning location and depth of utilities, piping, ductbanks, conduits, manholes, pumps, Northampton Drainage Relocation AS-BUILT DRAWINGS 20164277.003A 01346 - 2 valves, vaults and other equipment. Revisions shall be made and shown on all drawing views with actual dimensions established to permanent points. b) Working Drawings: Same as a) above, when working drawings are required. Include, for example, actual layouts of conduit runs between various items or electrical equipment for power, control and instrumentation; wire sizes, numbers and functions; configuration of conduits; piping layouts; and duct layouts. Sections and details shall be added as required, for clarity. Drawings and switchgear, motors, control centers and other equipment shall be revised to show actual installations. 2) Prior to preliminary inspection, furnish a reproducible of the record drawings. At the completion of the Contract and before final payment is made, furnish the Engineer one set of reproducibles of the finally approved record drawings reflecting all revisions herein described. PART 2 - PRODUCTS (NOT USED) PART 3 – EXECUTION (NOT USED) END OF SECTION 01346 Northampton Drainage Relocation CONSTRUCTION PHOTOGRAPHS 20164277.003A 01380 - 1 SECTION 01380 CONSTRUCTION PHOTOGRAPHS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. Provide pre-construction photographic survey to document existing conditions structure surfaces, equipment, and adjacent improvements that might be misconstrued as damage related to construction operations. 1.3 SUBMITTALS A. Pre-construction photographic survey to be filed with Owner's Representative prior to start of all work. 1.4 QUALITY ASSURANCE: A. Contractor / Photographer to make and retain detailed records of all photographs under this Contract: 1. The records to be in sufficient detail to support any attestation that may be required. Contractor to retain such records for a period not less than two years from the final acceptance of entire work under this Contract. PART 2 - PRODUCTS 2.1 PRE-CONSTRUCTION PHOTOGRAPHIC SURVEY A. Provide pre-construction photographic survey to document existing conditions structure surfaces, equipment, and adjacent improvements that might be misconstrued as damage related to removal operations. B. Pre-construction survey consisting of digital photographs taken with a camera with a minimum of 6.0 mega pixels, or a 30 minute video of existing conditions. Photographs to be submitted electronically. Northampton Drainage Relocation CONSTRUCTION PHOTOGRAPHS 20164277.003A 01380 - 2 2.2 ELECTRONIC IMAGES A. Submit electronic images consisting of digital photographs taken with a camera with a minimum of 6.0 mega pixels. B. Photograph file names should include descriptive identifier and date. PART 3 - EXECUTION 3.1 GENERAL REQUIREMENTS A. All views to contain a reference point that is identifiable at the location. Reference points could include items such as buildings, trees, signs, etc. END OF SECTION 01380 PRE-CONSTRUCTION Northampton Drainage Relocation CONDITION SURVEY 20164277.003A 01390-1 SECTION 01390 PRE-CONSTRUCTION CONDITION SURVEY PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. B. Examine all Drawings and all other Sections of the Specifications for requirements therein affecting the work of this Section. 1.2 SUMMARY A. The work under this item shall consist of the furnishing all necessary labor, equipment, professional services, and materials required to perform pre- construction condition surveys to document the condition of the interior and exterior of the existing above and below grade structures and surfaces to be conducted by an independent Consultant employed by the Contractor. Exterior portions of the pre-construction surveys shall be completed from street and walkway level. B. Pre-construction condition surveys shall be performed no earlier than four (4) weeks before construction begins in the area. Pre-construction conditions surveys shall be conducted on the following structures: 1. Building located at 19 Holyoke Street (Harold’s garage), 2. Building located at 300 Pleasant Street, and 3. Any additional Structure requested by the City. 1.3 SUBMITTALS A. Reports: Submit separate reports for each structure in accordance with Section 01300 – SUBMITTALS. Each report shall include the following, as a minimum: 1. Location and description of property and improvements; 2. Results of visual inspection including sketches, and photographs and DVD video showing deterioration, deficiencies, or lack of deficiencies; and PRE-CONSTRUCTION Northampton Drainage Relocation CONDITION SURVEY 20164277.003A 01390-2 3. Information provided by the property owners. 1.4 QUALITY ASSURANCE A. The contractor shall retain the services of a Massachusetts Registered Professional Civil/Structural Engineer to perform pre-construction condition surveys on the structures described above. The Registered Professional Engineer shall have at least five (5) years experience and three (3) projects in performing pre-construction surveys of heavy civil construction projects similar to this project, including work in urban areas, and a record of performance in completing condition surveys of similar types of structures and buildings. The Contractor shall submit such qualifications for review and acceptance prior to beginning work. B. The Contractor shall provide sufficient notice to the Engineer to allow the Engineer to be present to observe the Work. Cooperate with the Engineer in all respects to facilitate any testing or observations. C. The presence of the Engineer (including observations and review of the data) shall not relieve the Contractor of its sole responsibility to perform the work in accordance with the Contract Documents, nor shall they be construed to relieve the Contractor from full responsibility for the means and methods of construction and for safety on the construction site. PART 2 – PRODUCTS NOT USED PART 3 – EXECUTION 3.1 SURVEY A. The survey shall include detailed examination of the structure exterior and interior including documentation of exterior visual survey of the property, on- site improvements and plantings; detailed video inspection of the exterior of building and interior areas; digitized color photographs of the interior/exterior showing visually evident structural faults, and including but not limited to: 1. Exterior façade and interior of buildings as described herein. 2. Location and size of cracks in interior and exterior walls, especially instances of cracked or missing plaster or bricks within the defined survey areas; 3. Damaged masonry or roofing within the defined survey areas; 4. Damaged windows or doorways within the defined survey areas; 5. Walls which are not vertical within the defined survey areas; PRE-CONSTRUCTION Northampton Drainage Relocation CONDITION SURVEY 20164277.003A 01390-3 6. Damage to foundations, including interior/exterior; and tightness of fit of doors and windows in their respective jambs. 7. Sidewalks, planters, paved areas, utility poles, stairways, patios, fencing and landscaped areas including condition of trees to be measured. B. The design professional conducting the survey shall interview the property owners regarding existing conditions and structural faults, and determine dates and extent of recent repairs. This information shall be documented in the reports. 3.2 REPORTS A. Separate reports shall be prepared for each structure. Each report shall include the following, as a minimum: 1. Location and description of property and improvements; 2. Results of visual inspection including sketches, and photographs and DVD video showing deterioration, deficiencies, or lack of deficiencies; and 3. Information provided by the property owners. END OF SECTION 01390 PRE-CONSTRUCTION Northampton Drainage Relocation CONDITION SURVEY 20164277.003A 01390-4 [THIS PAGE INTENTIONALLY LEFT BLANK] Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 1 SECTION 01400 QUALITY ASSURANCE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section covers Quality Assurance requirements for this contract. B. The Contractor is responsible for controlling the quality of work, including work of its subcontractors and suppliers and for assuring the quality specified in the Technical Specifications is achieved. 1.3 TESTING LABORATORY SERVICES A. All tests which require the services of a laboratory to determine compliance with the Contract Documents, shall be performed by an independent commercial testing laboratory engaged by the Contractor and acceptable to the Engineer. The laboratory shall be staffed with experienced technicians, properly equipped, and fully qualified to perform the tests in accordance with the specified standards. B. Preliminary Testing Services: Unless otherwise specified, the Contractor shall be responsible for all testing laboratory services in connection with concrete materials and mix designs, the design of asphalt mixtures, gradation tests for structural and embankment fills, backfill materials, and all other tests and engineering data required for the Engineer's review of materials and equipment proposed to be used in the Work. The Contractor shall obtain the Engineer's acceptance of the testing laboratory before having services performed, and shall pay all costs for services. C. Quality Control Testing Services: Perform all quality control tests in the field or in the laboratory on concrete, asphalt mixtures, moisture-density (Proctor) and gradation tests on structural and embankment fills, and backfill materials, in-place field density tests on structural and embankment fills, and other materials and equipment, during and after their incorporation in the Work. Field sampling and testing shall be performed in the general manner indicated in the specifications, with minimum interference with construction Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 2 operations. The Engineer shall determine the exact time and location of field sampling and testing, and may require such additional sampling and testing as necessary to determine that materials and equipment conform with data previously furnished by Contractor and with the Contract Documents. D. Arrangements for delivery of samples and test specimens to the testing laboratory will be made by the Contractor. The laboratory tests shall be performed within a reasonable time consistent with the specified standards. Furnish a written report of each test to the Engineer. E. Contractor shall furnish all sample materials and cooperate in the sampling and field testing activities, interrupting the Work when necessary. When sampling or testing activities are performed in the field, the Contractor shall furnish personnel and facilities to assist in the activities. F. The Contractor shall not retain any testing laboratory against which the Owner or the Engineer have reasonable objection, and if at any time during the construction process the services become unacceptable to the Owner, or the Engineer, either the Owner or the Engineer may direct in writing that such services be terminated. The request must be supported with evidence of improper testing or unreasonable delay. If the Engineer determines that sufficient cause exists, the Contractor shall terminate the services and engage a different testing laboratory. G. Transmittal of Test Reports: Written reports of testing and engineering data furnished by the Contractor for the Engineer's review of materials and equipment proposed to be used in the Work shall be submitted as specified for Shop Drawings. H. The testing laboratory shall furnish four copies of a written report of each test performed by laboratory personnel in the field or laboratory to the Contractor. Distribution shall be two copies of each test report to the Engineer's Representative, one copy to the Owner, and one copy for the Contractor within three days after each test is completed. 1.4 QUALITY ASSURANCE A. Codes and Standards: Refer to Article 3 - Contract Documents, Intent, Amending, Reuse, paragraph 3.02 of the General Conditions. B. Copies of applicable referenced standards are not included in the Contract Documents. Where copies of standards are needed by the Contractor for superintendence and quality control of the work, the Contractor shall obtain a copy or copies directly from the publication source and maintain at the jobsite, available to the Contractor's personnel, subcontractors, and Engineer. Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 3 C. Quality of Materials: Unless otherwise specified, all materials and equipment furnished for permanent installation in the Work shall conform to applicable standards and specifications and shall be new, unused, and free from defects and imperfections, when installed or otherwise incorporated in the Work. Material and equipment shall not be used by the Contractor for any purpose other than that intended or specified unless such use is authorized by the Engineer. D. Where so specified, products or workmanship shall also conform to the additional performance requirements included within the Contract Documents to establish a higher or more stringent standard or quality than that required by the referenced standard. 1.5 OFFSITE INSPECTION A. When the specifications require inspection of materials or equipment during the production, manufacturing, or fabricating process, or before shipment, such services shall be performed by an independent testing laboratory, or inspection organization acceptable to Engineer in conjunction with or by the Engineer. B. The Contractor shall give appropriate written notice to the Engineer not less than 30 days before offsite inspection services are required, and shall provide for the producer, manufacturer, or fabricator to furnish safe access and proper facilities and to cooperate with inspecting personnel in the performance of their duties. C. The inspection organization shall submit a written report to the Contractor who shall provide copies to the Engineer. 1.6 MATERIALS AND EQUIPMENT A. The Contractor shall maintain control over procurement sources to ensure that materials and equipment conform to specified requirements in the Contract Documents. B. The Contractor shall comply with manufacturer’s printed instructions regarding all facets of materials and/or equipment movement, storage, installation, testing, startup, and operation. Should circumstances occur where the contract documents are more stringent than the manufacturer’s printed instructions, the Contractor shall comply with the specifications. In cases where the manufacturer’s printed instructions are more stringent than the contract documents, the Contractor shall advise the Engineer of the disparity and conform to the manufacturer’s printed instructions. In either case, the Contractor is to apply the more stringent specification or recommendation, unless approved otherwise by the Engineer. Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 4 1.7 SHOP AND FIELD TESTING A. The Contractor is also responsible for providing the shop and field testing specified in the technical specification sections. B. The Contractor and its Subcontractor shall perform inspections, tests, and other services as required by the Contract Documents. C. Contractor shall provide twenty one days notice to the Engineer so that the Engineer may witness Contractor and/or Subcontractors off site and on site tests. The Engineer’s witnessing of tests does not relieve the Contractor and/or Subcontractors of their obligation to comply with the requirements of the Contract Documents. 1.8 MANUFACTURER'S FIELD SERVICES A. When specified in the technical specifications sections, the Contractor shall arrange for and provide technical representation from manufacturer’s of respective equipment, items or components. The manufacturer's representative shall be a factory trained service engineer/technician with the type and length of experience specified in the technical specifications. B. Services Furnished Under This Contract: An experienced, competent, and authorized factory trained service engineer/technician representative of the manufacturer of each item of equipment for which field services are indicated in the specifications shall visit the site of the Work and inspect, operate, test, check, adjust if necessary, and approve the equipment installation. In each case, the manufacturer's service representative shall be present when the equipment is placed in operation. The manufacturer's service representative shall revisit the jobsite as often as necessary until all problems are corrected and the equipment installation and operation are satisfactory to the Engineer. 1.9 CERTIFICATION FORMS AND CERTIFICATES A. The Contractor shall be responsible for submitting the certification forms and certificates in conformance with the requirements specified in Section 01300 - Submittals. PART 2 - PRODUCTS (NOT USED) Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 5 PART 3 – EXECUTION 3.1 QUALITY CONTROL A. Quality control is the responsibility of the Contractor, and the Contractor shall maintain control over construction and installation processes to assure compliance with specified requirements. B. Certifications for personnel, procedures, and equipment associated with special processes shall be maintained in the Contractor’s field office, available for inspection by the Engineer. Copies will be made available to the Engineer upon request. C. Means and methods of construction and installation processes are the responsibility of the Contractor, and at no time is it the intent of the Engineer or Owner to supersede or void that responsibility. END OF SECTION 01400 Northampton Drainage Relocation QUALITY ASSURANCE 20164277.003A 01400 - 6 THIS PAGE INTENTIONALLY LEFT BLANK TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 1 SECTION 01500 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 PLANT AND HOURS OF CONSTRUCTION A. Furnish plant and equipment which will be efficient, appropriate, and large enough to secure a satisfactory quality of work and a rate of progress which will insure the completion of the work within the Contract Time. If at any time such plant appears to the Engineer to be inefficient, inappropriate, or insufficient for securing the quality of work required or for producing the rate of progress aforesaid, he may order the Contractor to increase the efficiency, change the character, or increase the plant equipment, and the Contractor shall conform to such order. Failure of the Engineer to give such order shall in no way relieve the Contractor of his obligations to secure the quality of the work and rate of progress required. B. Normal construction activity shall take place only between the hours of 7:00 a.m. to 5:00 p.m., excluding Saturdays, Sundays, and legal holidays. Work outside the above time periods will be permitted only on an emergency basis and only with the approval of the Owner. C. No work shall take place on holidays without prior permission of the Owner and the Engineer. Work shall not occur after noon on the Friday preceding a 3-day holiday weekend, or after noon on days before legal holidays. 1.3 OCCUPYING PRIVATE LAND A. The Contractor shall not (except after written consent from the proper parties) enter or occupy with men, tools, materials, or equipment any land outside the rights of way or property of the Owner. A copy of the written consent shall be given to the Engineer, prior to entering or occupying private property. TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 2 1.4 PIPE LOCATIONS A. Exterior pipelines will be located substantially as indicated on the Drawings, but the right is reserved to the Owner, acting through the Engineer, to make such modifications in location as may be found desirable to avoid interference with existing structures or for other reasons. Where fittings, etc., are noted on the Drawings, such notation is for the Contractor's convenience and does not relieve him from laying and jointing different or additional items where required. 1.5 DIMENSION OF EXISTING STRUCTURES A. Where the dimensions and locations of existing structures are of importance in the installation or connection of any part of the Work, the Contractor shall verify such dimensions and locations in the field before the fabrication of any material or equipment which is dependent on the correctness of such information. 1.6 OPEN EXCAVATIONS A. All open excavations shall be adequately safeguarded by providing temporary barricades, fencing, caution signs, lights, and other means to prevent accidents to persons and damage to property. The Contractor shall, at his own expense, provide suitable and safe bridges and other crossings for accommodating travel by pedestrians and workmen. Bridges provided for access during construction shall be removed when no longer required. The length or size of excavation will be controlled by the particular surrounding conditions, but shall always be confined to the limits prescribed by the Engineer. If the excavation becomes a hazard, or if it excessively restricts traffic at any point, the Engineer may require special construction procedures such as limiting the length of the open trench, prohibiting stacking excavated material in the street, and requiring that the trench shall not remain open overnight. No excavations will be allowed to remain opened during non- work hours, including but not limited to weekends and legal holidays. B. The Contractor shall take precautions to prevent injury to the public due to open trenches. All trenches, excavated material, equipment, or other obstacles which could be dangerous to the public shall be well lighted at night. C. Costs incurred for public safety personnel to address unsafe conditions shall be the responsibility of the Contractor. TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 3 1.7 TEST PITS A. Test pits for the purpose of locating underground pipeline or structures in advance of the construction shall be excavated and backfilled by the Contractor at locations shown on the drawings or in areas where the Contractor deems it necessary to obtain subsurface information. Additional test pits which are deemed necessary by the contractor shall be approved by the engineer. Test pits shall be backfilled immediately after their purpose has been satisfied and the surface restored and maintained in a manner satisfactory to the Engineer. B. Test pits shall be excavated by means of mechanical excavators or vacuum excavators. 1.8 INTERFERENCE WITH AND PROTECTION OF STREETS A. Contractor shall not close or obstruct any portion of a street, road, or private way without prior notification and obtaining permits therefor from the proper authorities. If any street, road or private way shall be rendered unsafe by the Contractor's operations, he shall make such repairs or provide such temporary ways or guards as shall be acceptable to the proper authorities. B. Streets, roads, private ways, and walks not closed shall be maintained passable and safe by the Contractor, who shall assume and have full responsibility for the adequacy and safety of provisions made therefore C. The Contractor shall, at least 48 hours in advance, notify the Police, Fire and School Departments in writing, with a copy to the Engineer and Owner. He shall cooperate with the Police Department in the establishment of alternate routes and shall provide adequate detour signs, plainly marked and well lighted, in order to minimize confusion. 1.9 CARE AND PROTECTION OF PROPERTY A. The Contractor shall be responsible for the preservation of all public and private property, and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be restored by the Contractor, at his expense, to a condition similar or equal to that existing before the damage was done, or he shall make good the damage in other manner acceptable to the Engineer. B. Along the location of this work, all fences, walks, bushes, trees, shrubbery, and other physical features shall be protected and restored in a thoroughly workmanlike manner. Fences and other features removed by the Contractor TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 4 shall be replaced in their original location or as indicated on the Drawings as soon as conditions permit. All grass areas beyond the limits of construction which have been damaged by the Contractor shall be graded and seeded. C. Trees close to the work shall be boxed or otherwise protected against injury. The Contractor shall trim all branches that are liable to damage because of his operations, but in no case shall any trees be cut or removed without prior notification of the Town’s Tree Warden or other person in charge. All injuries to bark, trunk, limbs, and roots of trees shall be repaired by dressing, cutting, and painting according to approved methods using only approved tools and materials. D. The protection, removal, and replacement of existing physical features along the line of work shall be a part of the work under the Contract, and all costs in connection therewith shall be included in the Bid Proposal. 1.10 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND UTILITIES A. The Contractor shall assume full responsibility for the protection of all buildings, structures, and utilities, public or private, including poles, signs, services to buildings, utilities in the street, gas pipes, water pipes, hydrants, sewers, drains, and electric and telephone cables, whether or not they are shown on the Drawings. The Contractor shall carefully support and protect all such structures and utilities from injury of any kind. Any damage resulting from the Contractor's operations shall be repaired by him at his expense. B. Assistance will be given the Contractor in determining the location of existing services. The Contractor, however, shall bear full responsibility for obtaining all locations of underground structures and utilities (including existing water services, drain lines, gas, and sewers). Services to buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by the Contractor. C. Protection of existing utilities and structures as described in this section shall be a part of the work under the Contract and all costs in connection therewith shall be included in the Total Price Bid in the Bid Form. D. If, in the opinion of the Engineer, permanent relocation of a utility owned by the City is required, he may direct the Contractor, in writing, to perform the work. Work so ordered will be paid at the Contract unit prices, if applicable, or as extra work under Article 10 of the General Conditions. If relocation of a privately owned utility is required, the Contractor will notify the Utility to coordinate the work as expeditiously as possible. The Contractor shall fully cooperate with the City of Northampton, MA and Utility Company, and shall TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 5 have no claim for delay due to such relocation. Utility Company backcharges related to utility relocations will be paid under the applicable bid item, or as extra work under Article 10 of the General Conditions, if no bid item exists. E. The Contractor shall notify all utility companies at least 72 hours (excluding Saturdays, Sundays, and Legal holidays) before excavating in any public way. Contractor shall also notify Dig Safe (1-888-DIGSAFE) at least 72 hours prior to start of work. F. The Contractor shall coordinate the removal and replacement of traffic loops and signals, if required for the performance of the work, at no additional cost to the Owner. 1.11 INSPECTION OF WORK AWAY FROM THE SITE A. If work to be done away from the construction site is to be inspected on behalf of the Owner during its fabrication, manufacture, or testing, or before shipment, the Contractor shall give notice to the Engineer of the place and time where such fabrication, manufacture, testing, or shipping is to be done. Such notice shall be in writing and delivered to the Engineer in ample time so that the necessary arrangements for the inspection can be made. 1.12 COOPERATION WITHIN THIS CONTRACT A. All firms or persons authorized to perform any work under this Contract shall cooperate with General Contractor and his Subcontractors or trades, and shall assist in incorporating the work of other trades where necessary or required. B. Cutting and patching, drilling and fitting shall be carried out where required by the trade or subcontractor having jurisdiction, unless otherwise indicated herein or directed by the Engineer. 1.13 CLEANUP AND DISPOSAL OF EXCESS MATERIAL A. During the course of the work, the Contractor shall keep the site of his operations in as clean and as neat a condition as is possible. He shall dispose of all residue resulting from the construction work and, at the conclusion of the work, he shall remove and haul away any surplus excavation, broken pavement, lumber, equipment, temporary structures, and any other refuse remaining from the construction operations, and shall leave the entire site of the work in a neat and orderly condition. B. In order to prevent environmental pollution arising from the construction activities related to the performance of this Contract, the Contractor and his subcontractors shall comply with all applicable Federal, State, and local laws, TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 6 and regulations concerning waste material disposal, as well as the specific requirements stated in this section and elsewhere in the Specifications. C. The Contractor is advised that the disposal of excess excavated material in wetlands, stream corridors, and plains is strictly prohibited even if the permission of the property owner is obtained. Any violation of this restriction by the Contractor or any person employed by him, will be brought to the immediate attention of the responsible regulatory agencies, with a request that appropriate action be taken against the offending parties. Therefore, the Contractor will be required to remove the fill at his own expense and restore the area impacted. 1.14 PROTECTION OF CONSTRUCTION AND EQUIPMENT A. All newly constructed work shall be carefully protected from injury in any way. No wheeling or walking or placing of heavy loads on it shall be allowed and all portions injured shall be reconstructed by the Contractor at its own expense. B. If, in the final inspection of the work, any defects, faults or omissions are found, the Contractor shall cause the same to be repaired or removed and replaced by proper materials and workmanship without extra compensation for the materials and labor required. Further, the Contractor shall be fully responsible for the satisfactory maintenance and repair of the construction and other work undertaken herein for at least the guarantee period described in the Contract Documents. C. The Contractor shall take all necessary precautions to prevent damage to any structure due to water pressure during and after construction and until such structure is accepted and taken over by the Owner. 1.15 TEMPORARY UTILITIES A. Temporary Light and Power: The Contractor shall at his own expense, provide his own temporary light and power as required for the prosecution and completion of work. B. Temporary Heat: The Contractor shall, at his own expense, provide sufficient temporary heat to maintain a minimum temperature of 50 degrees F at all times in all areas designated elsewhere in these documents. C. Temporary Telephone: The Contractor shall have installed at his own expense a job telephone for his use. The Contractor shall pay all phone charges. D. Temporary Water: Water for drinking purposes and other usage will be provided by the Contractor at his own expense. TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 7 E. Sanitary Provisions: The Contractor shall provide and maintain sanitary accommodations for the use of his employees and the Engineer, as may be necessary to comply with the requirements and regulations of the local and state departments of health. 1.16 WATER SUPPLY A. The Contractor shall make arrangements and pay for all water necessary for completion of construction operations under this contract. 1.17 ACCESS TO THE WORK A. The Contractor shall provide sufficient and proper facilities at all times for inspection of all work under this project in preparation or in progress, by the Owner, the agents and employees of the Owner, by authorized representatives of the State of Massachusetts and the Federal Government and by the Engineers. B. The Contractor shall furnish the Engineer or his authorized representative and other personnel mentioned above with such facilities and assistance as are necessary to ascertain performance of the work in accordance with the plans and specifications. 1.18 DUST CONTROL A. During the progress of the work, the Contractor shall conduct his operations and maintain the area of his activities, including sweeping and sprinkling of water as necessary, so as to minimize the creation and dispersion of dust. If the Engineer decides that it is necessary to use calcium chloride, and it is allowed by local authorities, for more effective dust control, the Contractor shall furnish and apply the material as directed. B. Calcium chloride shall be commercial grade, furnished in 100 lb, 5-ply bags, stored under weatherproof cover and stacked alternately for ventilation. Application for dust control shall be at the rate of about 1/2 pound per square yard, unless otherwise directed by the Engineer. 1.19 POLLUTION CONTROL A. The Contractor shall conduct clean-up and disposal operations, as necessary, to comply with state and local ordinances and anti-pollution laws. B. Outdoor burning of rubbish and waste material on the site will not be permitted. C. Disposal of volatile fluid wastes (such as mineral spirits, oil, gasoline, or paint thinner) in storm or sanitary sewer systems or into streams or waterways is not TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 8 permitted. 1.20 PRECAUTIONS DURING ADVERSE WEATHER A. During adverse weather and against the possibility thereof, the Contractor shall take all necessary precautions to protect the work. 1.21 ENGINEER’S FIELD OFFICE A. The Contractor shall provide and maintain, at an approved location at the site, for the duration of the project, a construction trailer for use as a field office by the Contractor and Engineer (shared trailer). The office shall be equipped with electric lights, heating facilities, air conditioners, telephone services (two telephone, two fax), water and sanitary conveniences. B. The office trailer shall be a new nominal size 10 foot by 50 foot trailer with two separate offices (one for the Engineer; one for the Contractor) with privacy doors and meeting/conference room between, tile floors, base board heating, venetian blinds and security grates on windows, security bars on all access doors, metal stairway units with handrails to each access door, and shall contain the following new equipment: 2- Flat top desks with drawers 2- Free standing book shelves with 4 or 5 shelves 3- Air conditioners 3- Metal, 4 drawer file cabinets with locks and hanging folder racks 1- Wardrobe closet 1- Plan rack w/ holders for 6 plans minimum 3- Swivel chairs w/arms 8- Folding chairs 2- Drafting tables, 3 foot by 6 foot metal 2- Drafting stools 2- Telephones 2- Telephone answering machines with time and date stamp 1- Electric water cooler w/hot water, refrigerator, and bottled water as required 1- Microwave oven, 1.5 cu. ft. 1- Four (4)-cubic foot refrigerator 1- Two-light fluorescent drafting desk lamp 2- 10 pound ABC fire extinguishers 1- First aid kit, large metal cabinet type 2- Full function desk top electric calculators 1- Metal table 72” x 30” with folding legs 1- Photocopy machine w/networking, reduce and enlarge, scan, 11” x 17” capacity, mounting cabinet with storage, and including all TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 9 supplies and a service contract for the life of the project 1- HP Officejet Pro X576dw color printer with toner for duration of the project 1- Wireless access point, Verizon or AT&T with data plan sufficient to the needs of the Engineer’s site representative 1- Scandisk Extreme 32GB USB 3.0 thumb drive 1- Samsung 840 EVO MZ-7TE500BW 2.5” SATA III internal SSD 50- Blank DVD-RW disks 50- DVD cases 1- 100 foot fiberglass measuring tape 1- 300 foot fiberglass measuring tape 12- K&E field books 200- 1/3 cut manila file folders 100- Reinforced hanging file folders 2- Boot scraper/brush, 1 installed on each access stair as directed 3- 10 gallon wastepaper baskets C. The plans and construction of the office shall be approved by the Engineer. The Contractor shall submit catalogs and vendor data for the trailer and equipment and shall confirm any substitutions with the Engineer prior to delivery. D. Furnish all cleaning equipment such as broom, mop, pail, dustpan, vacuum cleaner and related products and supplies. E. Furnish and construct an insulated skirt around the base of the trailer of 5/8 plywood with 2 x 4 framing. F. The Contractor shall maintain the office during construction and remove it upon completion of the work. The cost for operation of the Engineer’s field office, including paying all permits, fees and expenses, shall be the responsibility of the Contractor and included in his Bid price. Operation and maintenance shall include: supplying toilet paper, paper towels, liquid hand soap, paper, bottled water, monthly utility costs, heating, cooling costs, restocking the first aid kit, cleaning of the copier on a monthly basis, and cleaning of the inside of the trailer on a weekly basis. Repairs to the trailer shall be made from time to time as directed by the Engineer. G. The Contractor shall pay the regular monthly service charges and all telephone/tel-data costs. H. The Engineer’s field office shall be delivered to the site and fully set-up as described above within ten calendar days of the Owner’s issuance of the TEMPORARY FACILITIES Northampton Drainage Relocation AND CONTROLS 20164277.003A 01500 - 10 Notice to Proceed. No work will be performed on site until this office is established to the satisfaction of the Engineer. I. At the time the field office is made available to the Engineer, the Contractor shall furnish evidence to the Engineer that insurance in the amount of $50,000 (non-deductible) has been obtained which will protect the City of Northampton, the Engineer, and/or its employees or agents against loss of property in the event of fire, theft, vandalism, storm or flood. The insurance will be kept in effect during the entire period of occupancy. J. In case of loss or damage all equipment involved shall be repaired or replaced by the Contractor within 48 hours. In the event the field office is destroyed or rendered untenable for any reason, it shall be replaced within 5 calendar days. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01500 EROSION CONTROL, Northampton SEDIMENTATION AND CONTAINMENT Drainage Relocation OF CONSTRUCTION MATERIALS 20164277.003A 01568 - 1 SECTION 01568 EROSION CONTROL, SEDIMENTATION AND CONTAINMENT OF CONSTRUCTION MATERIALS PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. Provide all work and take all measures to control soil erosion resulting from construction operations, prevent flow of sediment from construction site, and contain construction materials (including excavation and backfill) within protected working area as to prevent damage to any stream or wetlands. 1.3 REFERENCE A. All work shall be performed in accordance with the Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas, latest edition. 1.4 QUALITY ASSURANCE A. Use acceptable procedures, including use of water diversion structures, diversion ditches, settling basins, and sediment traps. B. Operations restricted to areas of work indicated on drawings and area which must be entered for construction of temporary or permanent facilities. C. If construction materials are washed away during construction, remove materials from fouled areas. D. Stabilize diversion outlets by means acceptable to Engineer. E. Engineer has authority to limit surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations and to direct immediate permanent or temporary pollution control measures to prevent contamination of any stream or wetlands, including construction of temporary berms, dikes, dams, sediment basins, sediment traps, slope drains, EROSION CONTROL, Northampton SEDIMENTATION AND CONTAINMENT Drainage Relocation OF CONSTRUCTION MATERIALS 20164277.003A 01568 - 2 and use of temporary mulches, mats, or other control devices or methods as necessary to control erosion. PART 2 – PRODUCTS 2.1 FIBER ROLLS A. Straw or other suitable material acceptable to Engineer. 1. Twine for straw bales shall be biodegradable. 2.2 WOOD STAKES A. As indicated in attached drawings. 2.3 SILT FENCE A. Provide silt fence conforming to the requirements specified in Section 02273. PART 3 – EXECUTION 3.1 GENERAL A. Do not discharge chemicals, fuels, lubricants, bitumen, raw sewage and other harmful waste into or alongside any body of water or into natural or man- made channels. 3.2 INSTALLATION A. Install sedimentation barriers in all locations as directed, surrounding base of all deposits of stored excavated material outside of disturbed area, and where directed by the Engineer. B. Install sedimentation barriers immediately after site is cleared and before trench excavation. Locate sedimentation barriers surrounding stored material approximately 6 ft. from material. C. Construct earth berms or diversions to intercept and divert runoff water from critical areas. D. Discharge silt-laden water from excavations onto filter fabric mat, filter bag, and/or sediment traps to ensure that only sediment-free water is returned to watercourses. EROSION CONTROL, Northampton SEDIMENTATION AND CONTAINMENT Drainage Relocation OF CONSTRUCTION MATERIALS 20164277.003A 01568 - 3 E. Do not place excavated soil material adjacent to water-course in manner that will cause it to wash away by high water or runoff. F. Prevent damage to vegetation from excessive watering or silt accumulation in the discharge area. G. Prevent damage to vegetation adjacent to or outside of construction area limits. H. Do not dump spoiled material into any streams, wetlands, surface waters, or unspecified locations. I. Prevent indiscriminate, arbitrary, or capricious operation of equipment in streams, wetlands or surface waters. J. Do not pump silt-laden water from trenches or excavations into surface waters, streams, wetlands, or natural or man-made channels leading thereto. K. Do not dispose of trees, brush, debris, paints, chemicals, asphalt products, concrete curing compounds, fuels, lubricants, insecticides, washwater from concrete trucks or hydroseeders, or any other pollutant in streams, wetlands, surface waters, or natural or man-made channels leading thereto, or unspecified locations. L. Do not alter flow line of any stream unless indicated or specified. M. Clean and dispose of debris from sedimentation barriers on a weekly basis. N. Upon completion of work and upon approval by Engineer, remove and dispose of sedimentation barriers. END OF SECTION 01568 EROSION CONTROL, Northampton SEDIMENTATION AND CONTAINMENT Drainage Relocation OF CONSTRUCTION MATERIALS 20164277.003A 01568 - 4 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation CONTROL OF MATERIALS 20164277.003A 01600 - 1 SECTION 01600 CONTROL OF MATERIALS PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 APPROVAL OF MATERIALS A. Unless otherwise specified, only new materials and equipment shall be incorporated in the Work. All materials and equipment furnished by the Contractor shall be subject to the inspection and approval of the Engineer. No material shall be delivered to the worksite without prior approval of the Engineer. B. As specified in Section 01300, the Contractor shall submit to the Engineer, data relating to materials and equipment he proposes to furnish for the work. Such data shall be in sufficient detail to enable the Engineer to identify the particular product and to form an opinion as to its conformity to the specifications. C. Facilities and labor for handling and inspection of all materials and equipment shall be furnished by the Contractor. If the Engineer requires, either prior to beginning or during the progress of the work, the Contractor shall submit additional samples or materials for such special tests as may be necessary to demonstrate that they conform to the specifications. Such samples shall be furnished, stored, packed, and shipped as directed at the Contractor's expense. Except as otherwise noted, the Owner will make arrangements for and pay for the tests. D. Any delay of approval resulting from the Contractor's failure to submit samples or data promptly shall not be used as a basis of a claim against the Owner or the Engineer. E. In order to demonstrate the proficiency of workmen or to facilitate the choice among several textures, types, finishes, and surfaces, the Contractor shall provide such samples of workmanship or finish as may be required. F. The materials and equipment used on the work shall correspond to the approved samples or other data. Northampton Drainage Relocation CONTROL OF MATERIALS 20164277.003A 01600 - 2 1.3 REJECTED MATERIALS AND DEFECTIVE WORK A. Materials furnished by the Contractor and condemned by the Engineer as unsuitable or not in conformity with the specifications shall forthwith be removed from the work by the Contractor, and shall not be made use of elsewhere in the work. Any errors, defects or omissions in the execution of the work or in the materials furnished by the Contractor, even though they may have been passed or overlooked or have appeared after the completion of the work, discovered at any time before the final payment is made hereunder, shall be forthwith rectified and made good by and at the expense of the Contractor and in a manner satisfactory to the Engineer. The Contractor shall reimburse the Owner for any expenses, losses or damages incurred in consequence of any defect, error, omission or act of the Contractor or his employees, as determined by the Engineer, occurring previous to the final payment. PART 2 - PRODUCTS (NOT USED) PAGE 3 - EXECUTION (NOT USED) END OF SECTION 01600 DELIVERY, STORAGE Northamtpon Drainage Relocation AND HANDLING 20164277.003A 01610 - 1 SECTION 01610 DELIVERY, STORAGE AND HANDLING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section specifies the general requirements for the delivery, handling, storage and protection for all items required in the construction of the work. Specific requirements, if any, are specified with the related item. 1.3 TRANSPORTATION AND DELIVERY A. Transport and handle items in accordance with manufacturer's printed instructions. B. Schedule delivery to reduce long term on-site storage prior to installation and/or operation. Under no circumstances shall equipment be delivered to the site more than one month prior to installation without written authorization from the Engineer. C. Coordinate delivery with installation to ensure minimum holding time for items that are hazardous, flammable, easily damaged or sensitive to deterioration. D. Deliver products to the site in manufacturer's original sealed containers or other packing systems, complete with instructions for handling, storing, unpacking, protecting and installing. E. All items delivered to the site shall be unloaded and placed in a manner which will not hamper the Contractor's normal construction operation or those of subcontractors and other contractors and will not interfere with the flow of necessary traffic. F. Provide equipment and personnel to unload all items delivered to the site. G. Promptly inspect shipment to assure that products comply with requirements, quantities are correct, and items are undamaged. For items furnished by DELIVERY, STORAGE Northamtpon Drainage Relocation AND HANDLING 20164277.003A 01610 - 2 others (i.e. Owner, other Contractors), perform inspection in the presence of the Engineer. Notify Engineer verbally, and in writing, of any problems. 1.4 STORAGE AND PROTECTION A. Store and protect products in accordance with the manufacturer's printed instructions, with seals and labels intact and legible. Storage instruction shall be studied by the Contractor and reviewed with the Engineer by him. Instructions shall be carefully followed and a written record of this kept by the Contractor. Arrange storage to permit access for inspection. B. Store loose granular materials on solid flat surface in a well-drained area. Prevent mixing with foreign matter. C. Cement and lime shall be stored under a roof and off the ground and shall be kept completely dry at all times. All structural, miscellaneous and reinforcing steel shall be stored off the ground or otherwise to prevent accumulation of dirt or grease, and in a position to prevent accumulations of standing water and to minimize rusting. Beams shall be stored with the webs vertical. Precast concrete shall be handled and stored in a manner to prevent accumulations of dirt, standing water, staining, chipping or cracking. Brick, block and similar masonry products shall be handled and stored in manner to reduce breakage, cracking and spalling to a minimum. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01610 Northampton Drainage Relocation CONTRACT CLOSEOUT 20164277.003A 01700 - 1 SECTION 01700 CONTRACT CLOSEOUT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section specifies administrative and procedural requirements for project closeout, including but not limited to: 1. Closeout procedures. 1.3 CLOSEOUT PROCEDURES A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review. B. Provide submittals to Engineer that are required by governing or other authorities. C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payment, and sum remaining due. D. Submit all warranties. E. Submit written notice that all subcontractors and suppliers have been paid in full. F. Submit written notice showing the disparition of all insurance filings and claims. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 01700 Northampton Drainage Relocation CONTRACT CLOSEOUT 20164277.003A 01700 - 2 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation WARRANTIES AND BONDS 20164277.003A 01740 - 1 SECTION 01740 WARRANTIES AND BONDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section specifies general administrative and procedural requirements for warranties and bonds required by the Contract Documents, including manufacturer’s standard warranties on products and special warranties. 1.3 RELATED WORK A. Refer to General Conditions of the Contract for the general requirements relating to warranties and bonds. B. General closeout requirements are included in Section 01700 – CONTRACT CLOSEOUT. C. Specific requirements for warranties for the Work and products and installations that are specified to be warranted. D. Certifications and other commitments and agreements for continuing services to Owner are specified elsewhere in the Contract Documents. 1.4 SUBMITTALS A. Submit written warranties to the Owner prior to the date fixed by the Engineer for Substantial Completion. If the Certificate of Substantial Completion designates a commencement data for warranties other than the date of Substantial Completion for the Work, or a designated portion of the Work, submit written warranties upon request of the Owner. B. When a designated portion of the Work is completed and occupied or used by the Owner, by separate agreement with the Contractor during the construction period, submit properly executed warranties to the Owner within fifteen days of completion of that designated portion of the Work. Northampton Drainage Relocation WARRANTIES AND BONDS 20164277.003A 01740 - 2 C. When a special warranty is required to be executed by the Contractor, or the Contractor and a subcontractor, supplier or manufacturer, prepare a written document that contains appropriate terms and identification, ready for execution by the required parties. Submit a draft to the Engineer for approval prior to final execution. D. Refer to individual sections for specific content requirements, and particular requirements for submittal of special warranties. E. At Final Completion, compile two copies of each required warranty and bond properly executed by the Contractor, or by the Contractor, subcontractor, supplier, or manufacturer. Organize the warranty documents into an orderly sequence based on the table of contents of the Project Manual. F. Bind warranties and bonds in heavy-duty, commercial quality, durable 3-ring vinyl covered loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-in. by 11-in. paper. G. Table of Contents: Neatly typed, in the sequence of the Table of Contents of the Project Manual, with each item identified with the number and title of the specification Section in which specified, and the name of the product or work item. H. Provide heavy paper dividers with celluloid covered tabs for each separate warranty. Mark the tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product, and the name, address and telephone number of the installer, supplier, and manufacturer. I. Identify each binder on the front and the spine with the typed or printed title "WARRANTIES AND BONDS," the Project title or name, and the name, address, and telephone numbers of the Contractor and equipment supplier. J. When operating and maintenance manuals are required for warranted construction, provide additional copies of each required warranty, as necessary, for inclusion in each required manual. K. Schedule of Special Warranties: None 1.5 WARRANTY REQUIREMENT A. Related Damages and Losses: When correcting warranted Work that has failed, remove and replace other Work that has been damaged as a result of such failure or that must be removed and replaced to provide access for correction of warranted Work. B. Reinstatement of Warranty: When Work covered by a warranty has failed and been corrected by replacement or rebuilding, reinstate the warranty by written Northampton Drainage Relocation WARRANTIES AND BONDS 20164277.003A 01740 - 3 endorsement. The reinstated warranty shall be equal to the original warranty with an equitable adjustment for depreciation. C. Replacement Cost: Upon determination that Work covered by a warranty has failed, replace or rebuild the Work to an acceptable condition complying with requirements of Contract Documents. The Contractor is responsible for the cost of replacing or rebuilding defective Work regardless of whether the Owner has benefited from use of the Work through a portion of its anticipated useful service life. D. Owner's Recourse: Written warranties made to the Owner are in addition to implied warranties, and shall not limit the duties, obligations, rights and remedies otherwise available under the law, nor shall warranty periods be interpreted as limitations on time in which the Owner can enforce such other duties, obligations, rights or remedies. E. Rejection of Warranties: The Owner reserves the right to reject warranties and to limit selections to products with warranties not in conflict with requirements of the Contract Documents. F. The Owner reserves the right to refuse to accept Work for the Project where a special warranty, certification, or similar commitment is required on such Work or part of the Work, until evidence is presented that entities required to countersign such commitments are willing to do so. G. Disclaimers and Limitations: Manufacturer's disclaimers and limitations on product warranties do not relieve the Contractor of the warranty on the Work that incorporates the products, nor does it relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with the Contractor. 1.6 DEFINITION A. Standard Product Warranties are pre-printed written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to the Owner. B. Special Warranties are written warranties required by or incorporated in the Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for the Owner. PART 2 - PRODUCTS - (NOT USED) PART 3 - EXECUTION - (NOT USED) END OF SECTION 01740 Northampton Drainage Relocation WARRANTIES AND BONDS 20164277.003A 01740 - 4 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 1 SECTION 01850 TRAFFIC MANAGEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Pedestrian and vehicular traffic and other safety control devices, requirements and management for the protection of the traveling public and working personnel during construction and related operations, as approved by the Owner. 2. The design, application, and installation of all devices required by this section shall conform to the requirements of the Manual on Uniform Traffic Control Devices (MUTCD) and Part VI Latest Edition, published by the U. S. DOT, latest edition, American Disabilities Act (ADA), and the Commonwealth of Massachusetts, Highway Department (MHD), Standard Specifications for Highways and Bridges, Section 850, except as modified herein. 3. Traffic control during construction and maintenance operations includes installing and maintaining temporary pedestrian and construction facilities, furnishing, installing, inspecting, resetting, and removing channelization devices necessary to maintain pedestrian and vehicular traffic during construction and fencing of excavations as required. 4. “Approved by the Owner” throughout this Section shall mean the approval of the City of Northampton, Massachusetts. 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 – SUBMITTAL PROCEDURES: 1. Safety Signing for Construction Operations. Where not indicated on Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 2 the Contract Drawings, the Contractor shall submit a temporary pedestrian and construction facilities plan and sign placement and sign size sketches showing the proposed sign setups intended for use to provide the necessary traffic control and protection during the progress of the work, plus the sign and legend size and layout. These sketches shall be submitted to the Owner for review and approval before work begins. 2. The Contractor shall submit to the Owner the information required by this section a minimum of 14 working days prior to the start of construction and prior to the start of construction at any new location throughout the duration of work under this contract. 3. Before starting any work under this Contract, the Contractor shall prepare, and submit to the Engineer for approval, a plan that indicates the traffic routing proposed by the Contractor during the various stages and time periods of the work, and the temporary pedestrian and construction facilities, temporary barricades, signs, drums, and other traffic control devices to be employed during each stage and time period of the work, to maintain traffic and access to abutting properties. Particular care shall be taken to establish and maintain methods and procedures that will not create unnecessary or unusual hazards to public safety. Traffic control devices required only during working hour operations shall be removed at the end of each working day. 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400. 1.5 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610 and as specified. B. No material shall be stored within the work area or on adjacent roadways or residential streets except which is needed to complete the work for that day. 1.6 SYSTEM DESCRIPTION A. Materials required for the work of this Section need not be new, but must be in first-class condition and acceptable to the Owner. Any materials that in the judgment of the Owner are unsatisfactory in appearance or performance shall be removed and immediately replaced by acceptable units. B. Signs, portable barricades, and drums shall have “Type III High Intensity Encapsulated Lens Reflective Sheeting” in accordance with Section M9.30.0 Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 3 of the 1995 MHD Standard Specifications for Highways and Bridges and MUTCD requirements. C. Safety Signing for Construction Operations shall be fabricated in accordance with the provisions of subsection M9.30.0, Type III or IV High Intensity, of the MHD Standard Specifications for Highways and Bridges, where these colors are specified. D. Portable Type III Barricades shall conform with Standard Plate No. 406.2.0 of the MHD Construction and Traffic Standard Details (Metric Edition). Reflectorized sheeting to conform to Section M9.30.0 Type III or IV, of the MHD Standard Specifications for Highways and Bridges. E. Precast concrete median barrier shall conform with Standard Plate No. 401.15.0 of the MHD Construction and Traffic Standard Details. F. Traffic Drums shall conform to Standard Plate No. TR.7.1 of the MHD Construction and Traffic Standard Detail and provided in the type and quantity required by the standards specified herein. G. Temporary pavement markings and devices shall be used as required by MUTCD and ADA standards for traffic control and pedestrian safety. H. The Contractor shall provide necessary access for fire apparatus and other emergency vehicles through the work zones to abutting properties at all times. I. At the end of each working period, trenches in areas of public travel shall be covered with steel plates, each edge of the plates shall be either beveled or protected by a bituminous concrete ramp at a slope of two feet horizontally to 1-inch vertically. Any temporary patching material may be used to construct the ramps. The cost of necessary patching materials, and their maintenance and removal, will be considered incidental to the work being performed with no separate payment. J. Sweeping and cleaning of surfaces beyond the limits of the project required to clean up material caused by spillage or vehicular tracking during the various phases of the work shall be considered as incidental to the work being performed under the Contract and there will be no additional compensation. Sweeping and cleaning shall be done daily. 1.7 UTILITIES A. The Contractor shall be responsible for the coordination of his/her work with all utility work being performed by utility owners in relation to this project or projects adjacent to this project. The Contractor shall phase all work in a Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 4 manner that will provide positive and safe through movement of traffic passing the construction site. 1.8 TEMPORARY LIGHTING A. The Contractor shall provide all the temporary lighting to properly illuminate the work area and approaches in the event of nighttime work. 1.9 EXCAVATIONS A. Open excavations adjacent to the traveled way or shoulders shall not remain open through non-work hours unless adequately steel plated for the passage of heavy vehicles and specifically authorized by the Engineer. 1.10 PERMITS A. The Contractor shall be responsible for obtaining all permits to perform the work. 1.11 ACCESS TO PROPERTIES A. At least one serviceable driveway access to all residences and businesses within the project shall be maintained at all times. 1.12 HAULING A. The Contractor is advised that all roads and bridges within or adjacent to the project shall be subject to legal loads and vehicles. B. The Contractor is advised that no agreements have been made by the City of Northampton or the MHD with surrounding cities or towns to relieve the Contractor of liability for damage to local roads and bridges caused by the Contractor’s operation. The Contractor shall contact appropriate officials of the surrounding cities or towns concerning hauling over city or town roads and bridges. 1.13 TRAFFIC CONTROL STANDARDS AND SPECIFICATIONS A. The following standards and specifications are to be considered to be part of the Traffic Control Plan: 1. Section 850 of the Standard Specifications. 2. Manual on Uniform Traffic Control Devices, current edition including all revisions, amendments and addenda. Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 5 1.14 BARRICADES, WARNING SIGNS AND OTHER PROTECTIVE DEVICES A. Install, inspect, remove and rest all temporary construction elements in accordance with an approved construction staging sequence and traffic management plan. B. Regulatory and warning devices shall be subject to removal, replacement, and repositioning as often as necessary, and as directed by the Owner. C. Maintenance of Construction and Regulatory Signing 1. Safety signing for construction operations shall consist of furnishing, positioning, repositioning, inspecting, maintaining, and removing regulatory, warning, and guide signs and temporary bus stop signs and taxi stop signs and their supports as approved by the City of Northampton. 2. Replace all signs which are damaged or are missing from their location without additional compensation. 3. Maintain all signs in a satisfactory manner including the removal of dirt or road film that cause a reduction in sign reflective efficiency. E. Portable Barricades 1. Furnish, install, relocate, remove, re-install, and maintain portable barricades in accordance with MHD and MUTCD requirements or as directed by the Owner. 2. Barricades shall be maintained in good and serviceable condition throughout the duration of the Contract. 3. Temporary pedestrian and construction facilities shall be kept clean and freshly painted as required. F. Signs, Covered 1. Cover any existing regulatory and warning sings as necessary and as directed by the Owner. 2. Use a cover approved by the Owner, which shall be securely fastened to the existing sign and shall completely cover the legend of the existing sign. The cover shall remain in place as long as necessary at which time it shall be promptly removed. 3. Signs shall be covered without causing any damage to the existing Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 6 sign. G. Temporary Precast Concrete Median Barrier 1. Temporary precast concrete median barrier shall be furnished and installed as shown on the traffic management plans and where required by the Engineer to protect work zones and excavations, which cannot be completed and backfilled within a daily work period. Barriers shall be removed when no longer required. 2. Temporary precast barrier for use for temporary pedestrian and construction facilities shall have three (3) shelves cast in the barrier to receive a post for panel and fence installations. H. Temporary Safety Fencing 1. Temporary orange plastic safety fencing, 4 feet high, shall be erected at work zones abutting pedestrian travel paths and at work zones hazardous to pedestrians. 1.15 TRAFFIC OFFICERS SERVICE A. Uniformed officers shall be utilized to maintain safe traffic flow throughout the construction period. B. The Contractor shall be responsible for scheduling police details with the Northampton Police Department and adherence to its policies for such. Contractor is required to use as many police details as needed to ensure the safety of pedestrians and traffic at all times. Additional police details shall be provided at the Owner’s request. 1.16 PEDESTRIAN TRAFFIC A. Pedestrian detours and pedestrian and construction facilities shall be constructed as needed to maintain pedestrian traffic and business access, as shown on the plans or as ordered. B. Pedestrian access will be provided to abutting land uses such as residences and businesses at all times, as approved by the Owner and in accordance with MUTCD and ADA requirements. C. Temporary pedestrian walkways shall be separated from roadway and constructed areas by barricades as approved by the Owner. Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 7 1.17 TRAFFIC CONTROL REQUIREMENTS A. The Contractor shall meet the following conditions, unless otherwise specifically approved by the Engineer: 1. All work shall be prosecuted with proper regard for the convenience of the public and in a manner to permit unimpeded traffic flow whenever possible. The interruption of traffic will not be permitted unless specifically allowed by the Engineer and in accordance with the requirements of the Owner and in conformance with MUTCD requirements. 2. The Contractor shall be responsible for coordination with the Owner’s departments affected by the project. 3. Traffic control devices and signs shall be removed, demounted or properly covered for those periods of the day not in use. 4. The DPW shall be notified of any re-routing of traffic 72 hours in advance. Approval must be obtained from the Owner prior to any rerouting of traffic (except emergencies). Coordination with other city agencies or departments will be by the Contractor. 5. The Contractor shall coordinate the work with the schedules of delivery trucks to the adjacent property owners so as not to impede their access. 6. No operations shall be conducted, including the loading or unloading of vehicles, on or near the traveled lanes or road shoulders without first erecting warning signs and channelizing devices as directed. These precautions shall be maintained at all times while work is in progress. 7. Construction signs and channelizing devices shall be used to separate traffic from the work areas and for traffic control. Placement, other than as shown in the plans or the MUTCD, will require prior approval. 8. Temporary signs and channelizing devices shall not be set up until there is adequate visibility or appropriate construction lighting. The Contractor shall schedule his work so that temporary signs and channelizing devices are removed and traffic is returned to its normal pattern before the end of the work period. 9. Work requiring overnight lane closures shall not begin until all materials required for the completion of each nights work are Northampton Drain Relocation TRAFFIC MANAGEMENT 20164277.003A 01850 - 8 delivered or available to the project site, unless otherwise approved by the Engineer. 10. Accesses to residences and businesses shall be maintained at all times. 11. Work operations shall not be performed on the roadway in such a manner that traffic is obstructed or endangered simultaneously from both sides of the roadway. 12. The Contractor shall keep all roadway areas open to traffic as clear as possible at all times. Materials shall not be stored on any roadway area or within 10 ft. of the traveled way. Material shall be delivered to the installation areas as they are needed to provide a continuous installation. Location of storage areas shall be subject to approval. 13. The Contractor shall remove all equipment and construction vehicles from the traveled way and shoulders open to traffic during non-work hours. Vehicles shall be parked no closer than 10 feet from the traveled way in pre-approved areas unless specifically permitted. 14. The Contractor shall furnish 60” x 30” approved signs reading “CONSTRUCTION VEHICLE - DO NOT FOLLOW” to be used on trucks hauling to the project, when necessary. The color, type of sheeting and size of lettering shall conform to that of the permanent construction signs. 15. Each driver of any vehicle used on this contract shall be furnished written instructions concerning the manner of operation for that vehicle. Specifically, these instructions shall warn against stopping on the traveled portions of the roadway, against passing other vehicles, and against traveling in close proximity to other vehicles. A copy of these instructions shall be given to the Engineer. 16. Temporary signs and channelizing devices shall not be set up in inclement weather. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01850 Northampton Drainage Relocation SUBSURFACE INVESTIGATION 20164277.003A 02010 - 1 SECTION 02010 SUBSURFACE INVESTIGATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. The Contractor acknowledges that he has satisfied himself as to the nature and location of the work, the general and local conditions, particularly those bearing upon transportation, disposal, handling, and storage of materials, availability of labor, water, electric power, roads and uncertainties of weather, groundwater table or similar physical conditions at the site, the conformation of subsurface materials to be encountered, the character of equipment and facilities needed prior to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this Contract. Any failure by the Contractor to acquaint himself with all available information concerning these conditions will not relieve him from responsibility for estimating properly the difficulty or cost of successfully performing the work. B. The Contractor's attention is directed to Article 4 of Section 00710 - GENERAL CONDITIONS pertaining to Subsoil Investigation. 1.3 SUBSURFACE DATA A. The location of borings and/or probes are shown on the Drawings and the logs of borings and/or probes are included in Appendix A. Such data is offered in good faith solely for the purpose of placing the Contractor in receipt of all information available. The Contractor must interpret such data according to his own judgment and acknowledges that he is not relying upon the same as accurately describing the subsurface conditions which may be found to exist. The Contractor further acknowledges that he assumes all risk contingent upon the nature of the subsurface conditions, to be actually encountered by him in performing the work covered by the Contract, even though such actual conditions may result in the Contractor performing more or less work than he originally anticipated. END OF SECTION 02010 Northampton Drainage Relocation SUBSURFACE INVESTIGATION 20164277.003A 02010 - 2 THIS PAGE INTENTIONALLY LEFT BLANK GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 1 SECTION 02015 GEOTECHNICAL INSTRUMENTATION AND MONITORING PART 1 – GENERAL 1.1 DESCRIPTION OF WORK A. Work in this Section shall include, but not be limited to, all materials, equipment, labor, and services required to install, protect, replace, monitor and report on geotechnical instrumentation specified herein. B. The work included in this section includes the following: 1. Furnish, install, protect, replace, monitor and report on the following instrumentation: a. Deformation monitoring points installed on structures, utilities, and railroad tracks, at the approximate locations described herein and indicated on the Drawings to measure vertical and horizontal displacement of these points during the Work. b. Shoring monitoring points on the top of temporary excavation support systems, spaced at about 20-feet along both sides, to measure horizontal displacements of these points during the Work. c. Crack gauges following identification of existing cracks in the station structure during the Pre- Construction Condition Survey. The Engineer will assist the Contractor in determining the final locations. d. Groundwater observation wells to measure for changes in the water level outside the excavation during dewatering. 2. Continuously monitor vibrations during installation of the support of excavation system, earth excavation, rock removal, and backfill and compaction activities. Two seismographs shall monitor vibrations at two separate locations per a crew; one adjacent to the work and one adjacent to the nearest building. 3. The Contractor’s registered Independent Surveyor Consultant or the Contractor’s Geotechnical Monitoring Consultant shall monitor the instrumentation. Monitoring frequency shall be as noted herein during installation of the support of excavation system, earth excavation, rock removal, and backfill and compaction activities unless otherwise directed by the Engineer. 4. Furnish, install, protect, replace, monitor and report on additional geotechnical instrumentation as requested by the Engineer at no additional cost to the City. 5. Replace instrumentation damaged or made inaccessible by the construction operations at no additional cost to the City. 6. Furnish the City final reports for all phases of the demolition and construction activities. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 2 C. Related Work: The following items are not included in this Section and will be performed under the designated Sections: 1. Section 02140 – DEWATERING 2. Section 02160 – EXCAVATION SUPPORT AND PROTECTION 3. Section 02210 – EARTH EXCAVATION 1.2 SUBMITTALS A. Submit the following in accordance with Section 01300 – SUBMITTAL PROCESURES. 1. Shop drawings that indicate the instrumentation and monitoring point locations, sizes, material types, manufacturers’ data and specifications, installation procedures, and other data. Provide description of work and materials. 2. Contractor submittals shall be acceptable to the Engineer prior to undertaking the work. The Contractor shall forward submittals in advance considering that resubmittals may be required. B. The Contractor shall submit initial baseline survey data on a plan indicating locations and elevations of all deformation monitoring points, and observation wells to the Engineer at least three days prior to beginning of construction. Baseline data shall include measurements at all monitoring locations on at least 3 separate days prior to the start of construction. C. Qualification Data: For Surveyor and Geotechnical Monitoring Consultant D. The Contractor shall submit subsequent survey data on all deformation monitoring points to the Engineer prior to the beginning of work the following day. A faster turnaround of data reporting may be required by the Engineer if threshold or limiting response values, as specified in this Section, are approached or exceeded. Data shall be tabulated and depicted graphically on movement versus time plots acceptable to the engineer, and show incremental and cumulative movement since the start of monitoring. Final reports shall be submitted to the City. E. A mitigation plan shall be submitted to the Engineer by the Contractor prior to any demolition, construction, excavation, installation of the excavation support system, or dewatering. The mitigation plan shall detail the Contractor’s course of action in the event threshold or limiting response values are met or exceeded. Such mitigation plan shall be revised as appropriate for each instance threshold and/or limiting values are reached. 1.3 QUALITY CONTROL A. Retain the services of an Independent Surveyor Consultant to monitor the deformation monitoring points and establish the location instruments installed by the Contractor. The Independent Surveyor Consultant shall be registered in the State of Massachusetts and shall have demonstrated at least 5 years’ experience and at least three (3) projects of similar type, size, and complexity including installation and monitoring of surface settlement and lateral deformation points. The Independent Surveyor Consultant shall be approved by the Engineer and must be approved two weeks prior to mobilization for construction. The Contractor’s Independent Surveyor Consultant shall adhere to all methods and standards described in this Specification. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 3 B. Retain the services of a Geotechnical Monitoring Consultant to monitor observation wells, and vibrations. The Geotechnical Monitoring Consultant shall have demonstrated at least 5 years’ experience and at least three (3) projects of similar type, size, and complexity including monitoring and reporting on the types of geotechnical instruments to be utilized on this project. The Geotechnical Monitoring Consultant shall be approved by the Engineer and must be approved two weeks prior to mobilization for construction. The Contractor’s Geotechnical Monitoring Consultant shall adhere to all methods and standards described in this Specification. C. The Contractor shall provide sufficient notice to the Engineer to allow the Engineer to be present to observe the Work. Cooperate with the Engineer in all respects to facilitate any testing or observations. D. The Contractor may conduct additional testing or monitoring for its own information, at no additional cost to the City. E. The presence of the Engineer (including observations and review of test results) shall not relieve the Contractor of its sole responsibility to perform the work in accordance with the Contract Documents, nor shall they be construed to relieve the Contractor from full responsibility for the means and methods of construction and for safety on the construction site. F. Work not in conformance with the specified requirements shall be improved, or removed and replaced, at no additional cost to the City. All costs related to testing of nonconforming Work or materials shall be paid for by the Contractor, at no additional cost to the City. G. Measure and report all data on movements of all instrumentation monitoring points to the nearest 0.01 ft. (.003m). H. A factory calibration shall be conducted on all seismographs at the manufacturer's facility prior to shipment. Calibration shall be conducted within 1 year of use. Each factory calibration shall include a calibration curve with data points clearly indicated, and a tabulation of the data. Each instrument shall be marked with a unique identification number. PART 2 – PRODUCTS 2.1 DEFORMATION MONITORING POINTS A. Building deformation monitoring points (BMPs) and shoring monitoring points (SMPs) shall consist of : 1. Type 1: ¼-inch-diameter, stainless steel carriage bolts drilled 1.5 inches into the structure surface and extending approximately 1.5 inches from the structure face, 2. Type 2: 2-inch long surveyors' “PK” nails, securely nailed in place, or 3. Type 3: an observable point punch marked on the top horizontal surface of the structure. The surface within 3 inches of the point shall be cleaned by wire brush to permit easy identification of the exact point. The points shall be clearly identified using fluorescent spray paint adjacent to the point. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 4 B. Utility Monitoring Points (UMP) shall be used to monitor the condition of existing utilities during the Work. 1. UMPs shall be placed at the centerline of the existing utilities at the approximate locations indicated on the Contract Drawings, or as directed by the Engineer. 2. Provide 3-inch PVC casing, threaded and coupled, as-needed. 3. Provide ¼ inch steel bar, threaded and coupled, as-needed. 4. Provide centralizers spaced at 3-feet maximum. 5. Installation borehole shall be backfilled with cement-bentonite grout. 6. Install a road box at the ground surface to protect the instrument and provide access for monitoring. C. Track Monitoring Points 1. Provide high quality precision optical survey prisms in conjunction with fully automated motorized total stations under computer control to provide deformation monitoring of the railroad tracks at locations identified on the Contract Drawings. The system shall provide the means to remotely monitor vertical movement of precision targets on the track. 2. The monitoring system shall provide vertical displacement vectors for all the survey prisms with a measurement precision of plus or minus 0.01 feet for sight distances up to 300 feet. 3. The monitoring system shall have been proven to have the performance and precision specified herein for monitoring deformation at a minimum of one project. 4. System shall consist of: a. Monitorized total station(s) including mounting cages, brackets, and protective arrangements. b. High quality precision optical survey prisms. c. High quality precision optical reference prisms. d. Means to provide the data to the Engineer on a daily basis. 5. The monitoring stations shall be installed on sturdy structures. 6. A minimum of three control targets for each total station shall be set up at sturdy structures that are outside the “zone of influence”, as defined by the MBTA Railroad Operations Directorate Section VII “Temporary Sheeting and Shoring”, dated May 1994. The control targets shall be read by the total stations for each cycle of monitoring and the monitoring data shall be automatically corrected for self-movement of the total stations. 7. The monitoring system shall be capable of providing temperature readings that coincide with the instrument readings, and shall take into account temperature and pressure variations so that it is GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 5 insensitive to the effects of refraction. 8. The monitoring system shall incorporate a limited search window and a limited time for searching for a survey prism so that if the search is unsuccessful because of prism damage or other causes, the system will pass to the next prism in the cycle. In this event, the result for the missing prism shall be identified as “no result”. If the system is unable to find and read this prism during the following cycle, the system shall send an alarm message indicating that the prism is missing. 9. The monitoring system shall be capable of retaining setup information and measurements in memory for a minimum of 72 hours in case of power failure or power interruption. 2.2 CRACK GAUGES A. Crack gauges shall be installed by the Contractor on existing cracks identified during the preconstruction condition survey and new cracks which develop during construction and shall be monitored using a device such as: · Standard Tell-Tale by Avongard Products of Waukegan, IL · Crack Monitor by East Palestine, OH · Standard Crack Gauge by Humboldt of Elgin, IL, · or approved equal. 2.3 OBSERVATION WELLS A. Provide solid and slotted 2-inch PVC casing, threaded and coupled as needed. B. Provide sand filter around the well screen and bentonite seal. C. Provide locking well cap and 6-inch diameter road box 2.4 VIBRATION MONITORING A. Construction vibrations shall be monitored by the Contractor in terms of peak particle velocity using a seismograph with continuous recording capability. The vibration sensors shall be capable of recording three (3) orthogonal components of vibration. PART 3 – EXECUTION 3.1 GENERAL REQUIREMENTS A. Do not install any instruments until the City and the Engineer have been notified. 3.2 INSTALLATION A. Deformation Monitoring Points 1. Building monitoring points (BMPs) shall be installed at the approximate locations indicated on the Contract Drawings. BMPs shall have the horizontal as-built location determined to an accuracy 0.02-feet and the elevation to an accuracy of 0.01-feet. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 6 2. Shoring monitoring points (SMPs): a. SMPs shall be installed along the both sides of the support of excavation system as noted on the Contract Drawings. b. SMPs shall be spaced at about 20 feet along the top of each wall. c. All temporary excavation support wall monitoring points shall have the horizontal as-built location determined to an accuracy of 0.02-feet and the elevation to an accuracy of 0.01-feet. 3. Utility monitoring points (UMPs) shall be installed as directed by the Engineer. a. Where necessary, the Contractor shall install the UMPs by the use of vacuum excavation exercising due diligence not to disturb or damage the utility being monitored and to minimize disruption and damage to adjacent areas. b. The location of the utility in plan shall be determined and the borehole advanced to within a maximum of 2-feet above the utility. The Contractor shall be responsible for any damage to the utility during installation of the utility monitoring points. Drill casing may be used during the installation. c. After completion of installation, the as-built location of the UMPs in horizontal position shall be determined to an accuracy of 0.02-foot and in elevation to an accuracy of 0.01-feet. 4. Track Monitoring Points (TMP) a. Install track monitoring points in accordance with the requirements of the MBTA Railroad Operations Directorate Section VII “Temporary Sheeting and Shoring”, dated May 1994. Points shall be spaced at 15-½ foot intervals within the limits indicated on the drawings. Monitoring of each track is required for any excavation within the “zone of influence” of the track, as defined in the directorate. b. TMPS shall be installed, including establishing the formal initial reading (FIR), at least two (2) weeks prior to the start of work related to installation of the support of excavation system. c. All track monitoring points shall have the horizontal as-built location determined to an accuracy of 0.02-feet and the elevation to an accuracy of 0.01-feet. B. Observation Wells 1. Groundwater observation wells shall be installed at the approximate locations indicated on the drawings. 2. After completion of installation, the as-built location of the observation wells in horizontal position shall be determined to an accuracy of 0.5-foot and in elevation to an accuracy of 0.01-feet. 3. Well as-builts will be submitted after observation well installation. 4. Wells shall be properly developed by a licensed driller to ensure adequate connection to the aquifer. Confirm adequate aquifer connection by pneumatic displacement testing or bail down testing and GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 7 recovery to demonstrate that the observation wells are functioning properly. 5. Repair or replace, within 48 hours, observation wells that become inactive, damaged, or destroyed. Suspend construction activities in areas where observation wells are not functioning properly until reliable observations can be made. 6. Following completion and acceptance of the work, the observation wells shall be decommissioned in accordance with state and local regulations. C. Crack Gauges 1. Locations of existing building cracks shall be identified during the Pre-Construction Condition Survey. The base bid allows for a minimum of 10 existing and new cracks to be monitored. D. Seismographs 1. A seismograph shall be installed each day for each crew during installation of the support of excavation system, earth excavation, rock removal, and backfill and compaction activities. The seismographs shall be installed adjacent to existing structures within 25 feet of the work. If there are no existing structures within 25 feet, the seismograph shall be installed on a firm surface 25 feet from the work zone. 2. Vibration sensors shall be firmly mounted on the surface of concrete or asphalt, or firmly set in undisturbed soil. 3. The daily reports shall clearly describe the location of the seismograph relative to the work zone and the work performed on that date. E. Formal Initial Readings 1. Obtain formal initial readings (FIRs) on all installed instruments for use as the baseline reference for the instrument. Before establishing the FIR for each instrument, a minimum of three readings shall be performed that demonstrate that changes resulting from the installation process have ceased. The three readings demonstrating that the installation has stabilized shall be performed on different days and may be used to establish the FIR. 2. The FIR for a deformation monitoring point (BMP, SMP, UMP, and TMP) will consist of the average of two survey measurements of elevation or horizontal offset with two independent set-ups. Where applicable, the FIR shall be taken after allowing sufficient time for the grout or epoxy to set. Each reading other than the FIR shall consist of a single set of survey measurements. Reference all elevation readings to a deep benchmark. Reading accuracy shall be +/-0.01 foot. Report elevations to the nearest 0.001 foot. 3. The FIR for a crack monitor will be the reading of the cross hairs on the crack monitor when the tape connecting the two plates is cut after the monitor has been installed and/or the epoxy has set. Reading accuracy shall be +/-0.5 mm. 4. The FIR for an observation well shall consist of the average of three independent readings of groundwater level measurements taken within one hour. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 8 5. The FIR (background reading) for a seismograph shall be performed prior to any vibration-producing construction activities to document background vibrations. Background reading shall be collected continuously for at least one week prior to the start of construction. Vibration data shall also be performed at the start of vibration-producing construction activities to establish the maximum energy which can be used without surpassing acceptable vibration and overpressure levels at nearby facilities. The Contractor shall notify the City at least 24 hours prior to starting a new vibration- producing construction task. Monitoring during pile driving, rock drilling, pavement breaking, demolition, excavation, and other vibration-producing construction activity shall consist of recording single-component peak particle velocities, which shall be printed on a strip chart. Continuous monitoring and full waveform data shall be recorded and submitted. During all monitoring of vibration-producing construction activities the Contractor shall document all events that are responsible for the measured vibration levels, and submit the documentation to the City with the data. 3.3 MONITORING A. Obtain the FIRs on building, utility, and track deformation monitoring points; observation wells; and crack gauges at least seven days prior to the start of demolition of the existing structures. B. Obtain background readings for the seismograph at least one week prior to the start of construction. C. Prior to the start of excavation within the support of excavation system, SMPs shall be established on each side of the system to monitor horizontal displacement. Obtain the FIRs prior to starting excavation. D. The Contractor’s Geotechnical Monitoring Consultant and Independent Surveyor Consultant shall monitor all instrumentation specified. Instrumentation data obtained by the Geotechnical Monitoring Consultant shall be provided to the Engineer, in a format acceptable to the Engineer. E. Monitoring Frequencies: 1. Building and utility monitoring points (BMP and UMPs) shall be monitored twice a week during construction activities until the work is backfilled up to original surface grade. 2. Track monitoring points (TMPs) shall be monitored in accordance with the requirements of the MBTA Railroad Operations Directorate Section VII “Temporary Sheeting and Shoring”, dated May 1994. 3. Shoring monitoring points (SMPs) shall be monitored at a minimum daily during all excavation, construction, backfill, and compaction activities unless otherwise directed by the Engineer or specified. 4. Observation wells shall be monitored daily for the first two weeks of dewatering activities. Monitoring shall continue once per week for four weeks following construction of the permanent structure unless otherwise directed by the Engineer. 5. Crack gauges within 25 feet of construction activities shall be monitored twice a week. Crack gauges between 25 and 100 feet of construction activities shall be monitored once a week. 6. Vibration monitoring shall be performed continuously during all excavation, backfill, and GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 9 compaction, and installation of temporary earth support. 7. Monitoring frequency may be increased as directed by the Engineer for some or all of the monitoring points if the threshold or limiting response values are approached or exceeded during the Work, at no additional cost to the City. F. Reporting Data: 1. A plan showing location and numbering system for all instrumentation shall be submitted to the Engineer prior to start of construction along with results of the FIR and initial baseline data. 2. After each set of readings is obtained, the data shall be sent to the Engineer within 24 hours, where the data will be reviewed and interpreted. The Contractor shall make its own interpretations for the data. The Contractor shall monitor and interpret data from additional instrumentation that it deems necessary to ensure the safety of its work. The Engineer is not responsible for the safety of the work based on its review of the instrumentation data. 3. Deformation monitoring point data (BMP, SMP, UMP, and TMP): a. Tables and plots of results of surveys shall be submitted prior to the beginning of work the following day. b. The table of survey results shall include the initial measurement, the current measurement, and the amount of movement since start of excavation. c. Plots of survey data shall show date versus the amount of change between the FIR and the current reading. 4. Observation Well Data: a. Tables and plots of results of water level readings shall be submitted daily for the first two weeks of dewatering activity, then weekly prior to the beginning of work the following day. b. The table of water level readings shall include the initial measurement, the current measurement, and the amount of changes relative to the initial measurement. c. Plots of water level data shall show date versus the amount of change between the FIR and the current reading. 5. Plots of crack meter data shall show absolute deformation versus time. 6. Plots of seismograph data shall be full waveform plots consisting of a graphical display of the three component peak particle velocities and overpressure levels during the entire course of the vibration- producing activity. Seismograph submittals shall include a summary log for each day of work indicating the seismograph serial number, location, general description of construction activities; maximum vibration reading magnitude and time; explanation if any readings exceeded the “threshold” or “limiting” values. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 10 G. Criteria for "threshold" and "limiting" response values have been established as provided in the following table. Instrument Monitoring “Threshold” Value “Limiting” value BPM Vertical or horizontal movement 0.25 inches 0.5 inches Angular distortion between adjacent points 1/1000 1/750 SMP within railroad zone of influence or 25 feet of existing buildings horizontal movement 0.25 inches 0.5 inches SMP outside railroad zone of influence or beyond 25 feet of station structure horizontal movement 0.5 inches 0.75 inches TMP Vertical movement 0.25 inches 0.5 inches Crack Meter Change in crack size 1/8 inch 1/4 inch Observation wells Change in groundwater level (drawdown) 4 inches 8 inches Seismograph Vibrations in peak particle velocity 0.3 inches per second at frequencies of 60 Hz or less 0.5 inches per second at frequencies of 60 Hz or less Notes: 1. Angular distortion is defined as the ratio of the differential elevation between any two points over the horizontal distance between those points. H. The Contractor shall immediately notify the Engineer and shall take immediate steps to control further movement by revising construction procedures, providing supplemental bracing or other measures (such as working extended hours as approved or temporarily terminating work in the area of movement if necessary) as required if any of the following occur: 1. Field measurements indicate that any of the "threshold" movement criteria are reached or exceeded. 2. Field measurements or observations indicate that significant or sustained wall movements, beyond those reasonably expected, are occurring (total movement may be less than the "Limiting" movement criteria). Movements of the station structure are detected. I. If "Limiting" movements are being approached or reached, the City may require the Contractor to temporarily terminate the work in the area where such movement is occurring and implement all necessary mitigation measures which are satisfactory to the Engineer, to arrest the movements, at no cost to the City. J. Work in the area where the “Limiting” values had been reached shall not be permitted until the results of optical surveys indicate no increase in lateral movement of the earth support system and adjacent surface and station structure settlement for the one-week period immediately prior to the start of construction. K. These criteria are intended to establish a minimum basis for the Contractor's design and procedures and do not relieve the Contractor of its responsibility for preventing detrimental movements and damage to adjacent structures, utilities or other work. GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 11 L. In the event the Contractor does not comply with the approved mitigation plan, or continues to work in violation of threshold or limiting values being reached or exceeded, the Contractor shall not be allowed to continue work until proper mitigation procedures and corrections have been made as determined by the City and Engineer. M. The Contractor shall be responsible for repairing all property damage caused by construction activities. 3.4 PROTECTION OF INSTRUMENTATION A. Protect all instruments during the course of the Work. Any damage or loss of function caused by the Contractors operations, or by any other cause, to new or existing instrumentation devices, shall be immediately repaired or the equipment replaced at no additional cost to the City. END OF SECTION 02015 GEOTECHNICAL INSTRUMENTAITON Northampton Drainage Relocation AND MONITORING 20164277.003A 02015 - 12 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation DEMOLITION AND ABANDONMENT 20164277.003A 02051 - 1 SECTION 02051 DEMOLITION AND ABANDONMENT PART 1 – GENERAL 1.1 RELATED DOCUMENTS A.Drawings and general provisions of the Contract, including Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A.This section includes the following: 1.Demolish, remove and abandon existing facilities as indicated on drawings, as specified, and as directed by Engineer. B.Related sections include the following: 1.Section 02100 - Site Preparation 2.Section 02210 - Earth Excavation, Backfill, Fill and Grading. 1.3 SUBMITTALS A.Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1.Submit to Engineer for review, a demolition plan describing proposed sequence, methods, and equipment for demolition and disposal of each structure. 1.4 QUALITY ASSURANCE A.Provide in accordance with Section 01400 and as specified. B.Demolish and remove existing construction, utilities, equipment, and appurtenances without damaging integrity of existing structures, equipment, and appurtenances that are to remain. C.Store equipment to be salvaged for relocation where directed by Engineer, and if necessary, protect from damage during work. Northampton Drainage Relocation DEMOLITION AND ABANDONMENT 20164277.003A 02051 - 2 D.Repair or remove items that are damaged. Repair and install damaged items at no additional compensation and to condition at least equal to that which existed prior to start of work. E.Exercise all precautions for fire prevention. Make acceptable fire extinguishers available at all times in areas where demolition work by burning torches is being done. Contractor shall not burn demolition debris on or near site. F.Protect persons and property throughout progress of work. Proceed in such manner as to minimize spread of dust and flying particles and to provide safe working conditions for personnel. G.Maintain circulation of traffic within area at all times during demolition operations. H.Obtain permission from Engineer before abandoning or removing any existing structures, materials, equipment and appurtenances. I.Make arrangements with and perform work required by utility companies and municipal departments for discontinuance or interruption of utility services due to demolition work. PART 2 - PRODUCTS (NOT USED) PART 3 – EXECUTION 3.1 REFERENCES A.Provide three reference points for each survey marker and monument removed, established by a licensed civil engineer or land surveyor and record locations and designations of survey markers and monuments prior to removal. B.Any disturbed property markers shall be restored upon completion of work. Reestablish disturbed survey markers and monuments shall be in conformance with recorded reference points and shall be performed by a registered land surveyor in the Commonwealth of Massachusetts. Forward letter to Engineer signed by licensed land surveyor verifying reestablishment of survey markers and monuments. C.Confine apparatus, storage of materials, demolition work, new construction, and operations of workmen to areas that will not interfere with continued use and operation of entire facility. Provide and maintain lights, barriers, and temporary passageways for free and safe access. D.Wet down work during demolition operations to prevent dust from arising. Provide maximum practicable protection from inclement weather for materials, Northampton Drainage Relocation DEMOLITION AND ABANDONMENT 20164277.003A 02051 - 3 equipment, and personnel located in partially dismantled structures. Provide shoring or bracing where necessary to prevent settlement or displacement of existing or new structures. E.Cap or plug with brick and mortar, as indicated, pipes and other conduits abandoned due to demolition. 3.2 SALVAGE A.Materials, equipment, and appurtenances removed, that are not designated for relocation, or future use by Owner shall become property of Contractor. Haul from site and dispose of at no additional compensation. B.Salvage manhole frame and covers for future use by Owner. Deliver frame and covers to the City of Northampton as directed by the engineer. 3.3 UTILITY SERVICES A.Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition, modification and abandonment operations. B.Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to authorities having jurisdiction. C.Provide at least 72 hours notice to Owner if shutdown of service is required during changeover. D.Utility Requirements: Locate, identify, disconnect, and seal or cap off indicated utilities serving areas to be selectively demolished or abandoned. E.If utility services are required to be removed, relocated, or abandoned, before proceeding with selective demolition or proposed construction, provide temporary utilities that bypass area of selective demolition, relocation or abandonment, and that maintain continuity of service to other parts of building. 3.4 DEMOLITION AND ABANDONMENT PROCEDURES A.Disposal of all materials shall be performed in compliance with applicable local, state, and federal codes and requirements. Provide labor, equipment, and materials to perform work as specified and indicated. B.The Contractor shall flush all pipe and structures to be removed or abandoned to remove solids and objectionable material prior to commencing demolition, modification, or abandonment. Northampton Drainage Relocation DEMOLITION AND ABANDONMENT 20164277.003A 02051 - 4 C.When existing pipe is removed, the Contractor shall plug all resulting abandoned connections whether or not shown. Where removed piping is exposed, the remaining piping shall be fitted with a removable cap or plug, or bulk headed. Where existing piping is to be abandoned, the Contractor shall cut back the abandoned pipe for a distance of 5 feet from any connecting structures to remain. Pipes to be abandoned in structures to be abandoned may be capped, plugged or bulk headed from inside the structure. All holes at the existing structures shall be repaired. Abandoned pipe shall be filled with Controlled Density Fill (CDF) prior to being capped, plugged, or bulk headed and backfilling unless otherwise noted. Each pipe reach to be abandoned with CDF shall be filled with CDF from the up gradient end of the pipe reach wherever possible. The CDF shall completely fill each pipe reach and flow out the other end. The Contractor shall aid the flow of the CDF in the pipe by providing at least one temporary structure at the access point to build up head or by pumping the CDF and by providing vibration in the pipe reach or access points. The Contractor shall provide documentation to the City and to the Engineer that demonstrates the existing culverts have been completely filled without voids. Existing culverts shall not be warranted as completely abandoned until the City and the Engineer approve the documentation submitted demonstrating the culverts are completely filled. The Requirements for Controlled Density Fill are described in Section 02210 – EARTH EXCAVATION, BACKFILL, FILL AND GRADING. D.Where existing drainage structures such as catch basins and drain manholes are to be abandoned in place, the Contractor shall remove the frames, grates, and covers and cut the structures down a minimum of 2 feet below final grade. The Contractor shall put a minimum of four, 2-inch diameter drainage holes in the invert of each structure and then backfill the structure with flowable fill as specified and as approved by the Engineer. Backfill around the structure shall be in accordance with Section 02210 – EARTH EXCAVATION, BACKFILL, FILL AND GRADING. E.Permanent plugs shall be constructed of Class B concrete, brick or other material approved by the engineer. 3.5 MASONRY PLUGS AND BULKHEADS A.Shall be installed by a qualified mason having experience in the construction of temporary and permanent masonry plugs and bulkheads of the same general nature of those specified and proposed. 3.5 CONTRACT CLOSEOUT A.Provide in accordance with Section 01700. END OF SECTION 02050 Northampton Drainage Relocation SITE PREPARATION 20164277.003A 02100 - 1 SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A.Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A.This section includes the following: 1.Provision of labor, material, tools and equipment to prepare site as indicated and specified. 2.Protection of existing trees and vegetation outside the limit of work and specifically designated trees and vegetation within the limit of work. 3.Removal of trees, stumps and other vegetation, if required. 4.Topsoil stripping, if required. 5.Clearing and grubbing. B.Related sections include the following: 1.Section 02210: Earth Excavation, Backfill, Fill and Grading 1.3 PROJECT CONDITIONS A.Traffic: Conduct site clearing operations to ensure minimum interference with roads, streets, walks, and other adjacent occupied or used facilities. Do not close or obstruct streets, walks or other occupied or used facilities without permission from authorities having jurisdiction. B.Protection of Existing Improvements: Provide protection necessary to prevent damage to existing improvements indicated to remain in place or outside of the limit of work. Existing trees and shrubbery to remain shall be protected from injury. Except as otherwise directed, cutting and trimming of existing trees will not be permitted. Existing trees to remain, and which are liable to be damaged by construction operations, shall be boxed and protected as directed. Protection shall be maintained until completion of the work of the Contractor, unless otherwise directed. Northampton Drainage Relocation SITE PREPARATION 20164277.003A 02100 - 2 1.Protect improvements on adjoining properties and on Owner's property. 2.Restore improvements damage by Contractors clearing activities to their original condition, at no additional expense to the Owner. C.Protection of Existing Trees and Vegetation: Protect existing trees and other vegetation indicated to remain in place or outside of the clearing/grading limit lines indicated on the drawings. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION 3.1 EXISTING TREES AND VEGETATION A.Existing trees and shrubbery to remain shall be protected from injury. Except as otherwise directed, cutting and trimming of existing trees will not be permitted. Existing trees to remain, and which are liable to be damaged by construction operations, shall be boxed and protected as directed. Protection shall be maintained until completion of the work of the Contractor, unless otherwise directed. B.Avoid cutting or injuring trees and vegetation outside easement lines and outside areas to be cleared. C.Accept responsibility for damages outside these lines. D.Remove trees within permanent and temporary easements as indicated on the plans and designated by the Engineer. E.Contractor shall flag trees that are required to be removed and notify the Owner. No trees shall be removed without approval from the Owner. 3.2 EXISTING STRUCTURES AND PROPERTY A.Remove and reset at completion of project existing signs, posts, catch basin frames and grates, manhole frames and covers, and granite curbing within construction path unless directed otherwise. B.Store at a site designated by Owner, items in reusable condition as determined by Engineer. C.Approximately 60’ of the existing wooden fence inside the work zone and adjacent the 274 Pleasant Street parking lot, shall either be: removed during site preparation, stockpiled, and then re-installed during restoration or shall be Northampton Drainage Relocation SITE PREPARATION 20164277.003A 02100 - 3 supported during construction, in a way that maintains the functionality of the existing fence and does not endanger any persons on site. D.For work in loamed areas, strip loam to one side to avoid mixing with excavation materials. Do not take loam from site. 3.3 CLEARING A.No clearing operations shall begin until the limits of clearing have been determined in the field by the Engineer and Contractor. B.Areas within the excavation shall remove trees, brush, and other vegetation matter such as snags, bark and refuse, from areas to be cleared, except as specified or indicated otherwise. Remove such items elsewhere on site as specifically indicated. Clear ground to width of permanent easement unless otherwise directed. C.Cut trees, stumps, and stubs to be cleared, except where clearing done by machinery, as close to ground surface as practicable, but no more than 6 in. above ground surface for small trees and 12 in. for larger trees. D.Carefully and cleanly cut roots and branches of trees indicated to be left standing, where such roots and branches obstruct new construction. Use only hand methods for grubbing inside drip line of trees indicated to be left standing. E.Bury elm bark, at least 1 ft. deep, or burn in incinerators off site with anti- pollution controls and fire prevention controls, to prevent spread of Dutch Elm disease as required by applicable laws. 3.4 CLEARING IN WOODED AREAS A.Chip and stockpile wood cleared at location directed by Owner. Do NOT PERMIT use of elm wood and elm bark as wood chips. B.Chip and spread wood cleared at locations and cover as directed by the Engineer. Do NOT PERMIT use of elm wood and elm bark as wood chips. C.Supply and spread wood chips. 3.5 GRUBBING, STRIPPING, DISPOSAL A.All stumps shall be removed in their entirety, unless otherwise specified. Roots and matted roots shall be grubbed out to at least 30 inches below the existing grades shown on the Drawings. B.Strip stumps, roots, foreign matter, topsoil, loam and unsuitable earth from ground surface. Topsoil shall be carefully removed, to the depths directed, over all areas to be excavated and over all other areas to be disturbed as a Northampton Drainage Relocation SITE PREPARATION 20164277.003A 02100 - 4 result of the Contractor's operations in the performance of the Contract work. Utilize topsoil and loam insofar as possible for finished surfacing. Do not take loam from site. Stripping operations shall be completed prior to excavation, trenching, or grading operations. C.Promptly remove material from clearing and grubbing not reused or stockpiled from Owner's property and dispose of off site. In doing so, observe all applicable laws, ordinances, rules and regulations. Waste materials shall include but not be limited to timber, brush, refuse, stumps, roots, vines, debris and other objectionable matter. All timber designated in the field to not be disposed of by the Contractor shall be stored at a nearby location for ultimate disposal by the Owner. Timber to be stored shall be de-branched, cut into six foot lengths and stacked as directed. Do not consider work completed until final cleaning, unless otherwise directed. 3.6 STOCKPILES A.The topsoil shall be transported and deposited in storage piles convenient to the areas which are subsequently to receive the application of topsoil, separate from other excavated materials, and in approved locations. The topsoil shall be stockpiled free of roots, stones and other undesirable material. The Contractor shall take all necessary precautions to prevent other excavated material or other objectionable material from becoming intermixed with the topsoil, either before or after the stripping and stockpiling operation. Stockpiles shall be neatly trimmed and graded to provide drainage from surfaces and to prevent depressions where water may become impounded. All construction operations shall be performed so as not to cause mixing of objectionable materials with the topsoil, and stockpiles shall be protected and shall not be disturbed except for subsequent operations for replacing topsoil. The location of stockpiles shall be approved by the Owner and the Engineer. 3.7 EXCESS TOPSOIL A.Topsoil which has been stripped and stockpiled, but is not needed after the completion of all final topsoiling and grassing shall be stockpiled on site in a location to be approved by the Engineer and shall remain the property of the Owner. 3.8 CONTRACT CLOSEOUT A.Provide in accordance with Section 01700. END OF SECTION 02100 Northampton Drainage Relocation DEWATERING 20164277.003A 02140-1 SECTION 02140 DEWATERING PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. B. Examine all Drawings and all other Sections of the Specifications for requirements therein affecting the work of this Section. 1.2 SUMMARY A. This section includes the following: 1. Design, furnish, operate, maintain, and remove temporary dewatering systems to control groundwater and surface water to maintain stable, undisturbed subgrades, and allow work to be performed under dry and stable conditions: and comply with permit and other regulatory requirements. 2. Work to be done as part of dewatering includes, but is not limited to: a. Lower the groundwater level within excavations to at least 18 inches below the bottom of the excavation. b. Minimize groundwater drawdown outside the excavations to the levels indicated in Specification Section 02015- Geotechnical Instrumentation and Monitoring. c. Prevent surface water from entering the excavation during construction. d. Implement effective `erosion and sedimentation control measures for disposing of discharge water. e. Provide system to treat/settle all water removed from excavations, except water that is re-infiltrated to the ground on site in a manner that does not result in negative on- or off- site impacts. f. Provide an Dewatering Specialist/Field Representative (hereinafter referred to as the Dewatering Professional) who Northampton Drainage Relocation DEWATERING 20164277.003A 02140-2 will be responsible for dewatering, reinfiltration, treatment and discharge of dewatering flows as specified and in compliance with all applicable permits and regulations. 3. Water removed from excavations shall be reinfiltrated to the ground if feasible. If reinfiltration is not feasible, water shall be directly or indirectly discharged to a surface water in accordance with a National Pollutant Discharge Elimination System (NPDES) permit issued by the U.S. Environmental Protection Agency (EPA). If contaminated groundwater is identified, discharge shall be conducted under a Remediation General Permit (RGP). If no sheen or other evidence of contamination, including the results of laboratory analysis, is present, discharge shall be conducted under a Construction General Permit or Dewatering General Permit, as applicable. In no case shall dewatering flows be directly or indirectly released to surface waters or storm drains prior to settling of suspended solids and appropriate additional treatment. If discharge to a separated drainage system is not feasible, discharge shall be to a municipal sewer system under an appropriate discharge permit. The Contractor is responsible for acquiring all the proper permitting required for the chosen method of discharge. 1.3 SUBMITTALS A. Shop Drawing: Submit the following in accordance with Section 01300 – SUBMITTALS: 1. Qualification of both the Contractor’s dewatering specialist or firm's qualifications (installation) and the Dewatering Professional (all other responsibilities) a minimum of four (4) weeks prior to execution of any dewatering. The submittal shall include, but not be limited to: a. Qualifications of specialist or firm's Registered Professional Engineer as specified below. b. Qualifications of the Dewatering Professional who shall oversee the installation, operation and maintenance of the dewatering system. 2. Submit a dewatering plan including design calculations at least four (4) weeks prior to start of any dewatering operation. The submittal will be only for the information of the Owner and third parties for an overall understanding of the project relating to access, maintenance of existing facilities and proper utilization of the site. The Contractor shall remain responsible for the adequacy and safety of the means, methods and sequencing of construction. The plan shall include the following items as a minimum: Northampton Drainage Relocation DEWATERING 20164277.003A 02140-3 a. Dewatering plan and details stamped and signed by a Massachusetts Registered Professional Engineer that conforms to the requirements of the dewatering permit(s), and all other applicable regulations and permits including, but not limited to, requirements for equipment, monitoring, sampling and reporting. b. Certificate of Design c. A list of equipment including, but not limited to, pumps, prime movers, and standby equipment. d. A description of the proposed method of dewatering; water reinfiltration; containment; treatment and discharge; and installation, maintenance, and system removal procedures. e. A groundwater monitoring plan shall be developed by the Professional Engineer retained by the Contractor and that designs the dewatering system. The monitoring plan shall address groundwater control within the excavations and methods for monitoring drawdown outside of the excavations f. A description of erosion/sedimentation control measures, and methods of disposal of pumped water. g. List of all applicable laws, regulations, rules, and codes to which dewatering design conforms. 3. Data for the required discharge reports shall be collected by the Contractor’s Dewatering Professional. It shall consist of periodic sampling and analysis of system influents, midfluents and/or effluents and discharge quantities and other requirements of the relevant permits. The Contractor’s Dewatering Professional shall also coordinate analysis of samples at an appropriately certified analytical laboratory and shall comply with all permit reporting requirements. 4. A modified dewatering plan within 24 hours, if open pumping from sumps and ditches results in boils, loss of fines or softening of the ground. 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400 and as specified. B. Employ the services of a Dewatering Professional and a Massachusetts Registered Professional Engineer in firms having the following Northampton Drainage Relocation DEWATERING 20164277.003A 02140-4 qualifications: 1. The Massachusetts Registered Professional Civil Engineer shall have completed the design of at least five (5) successful dewatering projects of equal size and complexity and with equal systems within the last five (5) years consisting of deep wells, shallow dewatering wells, well points, vacuum well points, and sump pumping for heavy Civil projects of similar size, type, and complexity in developed areas with trench box or steel/timber sheeting support of excavation systems. 2. The dewatering systems installer supervisor shall have a minimum of 5 years experience in installation of well points, deep wells, shallow dewatering wells, recharge systems, or equal systems. 3. The Dewatering Professional responsible for day to day operation of the system shall have the following minimum qualifications: a. Completion of at least 5 successful dewatering projects of equal size and complexity with equal systems within the last five (5) years consisting of system operation and troubleshooting, collection of readings, maintenance of logs and other required documents, collection of samples, coordination of analysis of samples, and compliance with reporting requirements during pumping for heavy Civil projects of similar size, type, and complexity in developed areas. b. Valid certification from DEP to operate the proposed treatment system. C. If subgrade soils are disturbed or become unstable due to dewatering operation or an inadequate dewatering system, notify the Engineer, stabilize the subgrade, and modify system to perform as specified at no additional cost to the Owner. D. If oil and/or other hazardous materials are encountered after dewatering begins, immediately notify the Engineer. 1.5 PROJECT/SITE CONDITIONS A. Subsurface Investigations: Refer to Section 02010. PART 2 – PRODUCTS 2.1 MATERIALS Northampton Drainage Relocation DEWATERING 20164277.003A 02140-5 A. Provide groundwater observation wells in accordance with the submitted dewatering plan or as specified. B. Provide casings, well screens, piping, fittings, pumps, power and other items required for dewatering system. C. Provide sand and gravel filter around the well screen. Wrapping geotextile fabric directly around the well screen shall not be allowed. D. When deep wells, well points, or vacuum well points are used, provide pumping units capable of maintaining high vacuum and handling large volumes of air and water at the same time. E. Provide and store auxiliary dewatering equipment, consisting of pumps and hoses on the site in the event of breakdown, at least one (1) pump for every five (5) used. F. Provide dewatering equipment, including an appropriately sized settling tank, and maintain erosion/sedimentation control devices as indicated or specified and in accordance with the dewatering plan. G. Provide temporary pipes, hoses, flumes, channels, crushed stone, geotextile fabric, sedimentation barriers, or any combination of the above for the transport of discharge water over-ground to the discharge location. H. Provide cement grout having a water cement ratio of 1 to 1 by volume. I. Refer to 02761 “Stormwater Bypass Flow Handling, section 2.2, for the materials to be used when bypassing the 60”x68” existing culvert for the upstream and downstream tie-in connections. PART 3 – EXECUTION 3.1 GENERAL A. Execution of any earth excavation, installing support of excavation systems, and dewatering shall not commence until the related submittals have been submitted, and the Dewatering Professional is on site and has begun the duties specified herein. B. Furnish, install, operate, and maintain dewatering, reinfiltration, treatment and discharge systems as indicated or specified and in accordance with the dewatering plan. As no dewatering flows shall be discharged to surface waters either directly or indirectly without appropriate settling, at a minimum, the Contractor shall provide a settling tank with a capacity of 10,000 gallons, so that if pumping rates exceed discharge rates, sufficient storage capacity is available. Delays due to insufficient storage capacity will Northampton Drainage Relocation DEWATERING 20164277.003A 02140-6 be at no additional cost to the Owner. The Contractor is responsible to evaluate available data and determine the necessary storage capacity so as not to impede construction activities. C. Carry out dewatering program in such a manner as to prevent undermining or disturbing foundations of existing structures or of work ongoing or previously completed. D. Monitor groundwater levels outside of excavations and minimize drawdown as indicated in Specification Section 02015- Geotechnical Instrumentation and Monitoring D. Do not excavate until the dewatering system is operational. E. Unless otherwise specified, continue dewatering uninterrupted until all structures, pipes, and appurtenances below groundwater level have been completed such that they will not be floated or otherwise damaged by an increase in groundwater elevation. F. Discontinue open pumping from sumps and ditches, if such pumping is resulting in boils, loss of fines, softening of the ground, or instability of the slopes. Modify dewatering plan and submit to the Engineer at no additional cost to the Owner. G. Where subgrade materials are disturbed or become unstable due to dewatering operations, remove and replace the materials in accordance with Section 02210 at no additional cost to the Owner. 3.2 DEWATERING DISCHARGE A. Water to be infiltrated need not be treated. Contractor shall provide infiltration that complies with relevant local, state and federal regulations. B. Transport pumped or drained water to discharge location in compliance with applicable permits and without interference to other work; damage to or contamination of pavement, other surfaces, or property; erosion; or siltation. C. Provide separately controlled pumping lines. D. Immediately notify the Engineer if groundwater is encountered that is suspected to be contaminated with substances other than those for which the treatment system has been designed. Do not pump water found to be contaminated with oil or other hazardous material to the discharge locations. 3.3 COMPLIANCE WITH DEWATERING AND RELATED PERMITS AND REGULATIONS Northampton Drainage Relocation DEWATERING 20164277.003A 02140-7 A. Should dewatering activities be required the Contractor shall be prepared to store, treat and discharge the water in accordance with applicable permits and regulations. Periodic sampling, as may be required to demonstrate treatment effectiveness and compliance with discharge and/or pretreatment standards specified in any local, state, or federal discharge permit required shall be the responsibility of the Contractor and its Dewatering Professional. Discharge Water is anticipated to be discharged to the existing culvert system. The Contractor shall be responsible for seeking coverage under the appropriate construction dewatering permit. At a minimum, the Contractor shall be prepared to comply with the permit influent/effluent testing requirements. The Dewatering Plan shall include a description of procedures and information related to the collection of readings, maintenance of logs and other required documents. At a minimum, the dewatering plan shall describe compliance with relevant provisions of the EPA/NPDES Dewatering General Permit for construction dewatering and the EPA/NPDES Remediation General Permit. B. The Contractor, through its Dewatering Professional: 1. Shall furnish all labor, equipment and materials necessary to obtain accurate representative samples of the groundwater and for analysis for the set of analytical parameters specified above and as required by local, state and federal permits and regulations. 2. Shall coordinate sampling activities with the Engineer. The Engineer reserves the right to sample treated and untreated dewatering flows at any time. 3. Shall take readings from the treatment system in accordance with the dewatering plan. 4. Shall collect an initial sample of untreated and treated groundwater at the beginning of dewatering activities within the construction area. 5. Shall prepare and keep in proper order all records required by regulatory authorities and permits. 6. Shall maintain logs and other records in accordance with the Specifications, regulatory agency and permit requirements, and the Dewatering Plan. 7. Shall coordinate analysis of samples by an appropriately certified analytical laboratory in accordance with the Specifications, regulatory agency and permit requirements, and the Dewatering Plan, and ensure that laboratory detection limits meet permit requirements. 8. Shall comply with reporting requirements in a timely manner and in Northampton Drainage Relocation DEWATERING 20164277.003A 02140-8 the format required by the relevant permit. Reporting in compliance with permit requirements includes, but is not limited to, notification to the appropriate regulators and the Owner and Engineer prior to discharge; submittal of laboratory analytical reports for each sampling event; submittal of reports for each reporting period during which no discharge occurs; notification of non-compliant discharges; notification of termination of discharge; and response to permit- related questions posed by regulators or the Owner and Engineer. a. If water will be discharged under a National Pollutant Discharge Elimination System (NPDES) permit, submit notifications and reports to both the Environmental Protection Agency (EPA) and the appropriate regional office of the Massachusetts Department of Environmental Protection (DEP). Comply with pre-discharge notification, discharge reporting, notification of no discharge, and termination of discharge notification requirements; and respond to inquiries or correspondence from EPA or DEP regarding permit issues. b. If water will be discharged under a local permit, submit notifications and reports as required in the permit. c. For monthly or less frequent reporting deadlines, provide the Engineer with copies of all reports fourteen (14) days prior to the reporting deadline, and submit reports to the appropriate agency(ies). Provide copies of other dewatering documents to the Engineer immediately. 9. Install and maintain erosion/sedimentation control devices at the point of discharge as indicated or specified and in accordance with the dewatering plan. 10. The Contractor shall obtain all federal, state, county, and local permits and variances to allow transport of materials on public roadways, should such transport be necessary. 11. The Contractor shall dispose of all wastes resulting from construction dewatering activities in accordance with local, federal and state regulations. 12. The Contractor is solely responsible for the implementation of the permit requirements, and is solely responsible for any punitive action resulting from any violation of the permit. The actual permit issued shall become part of this Contract by either addendum or by change order. If the actual permit is included by change order, no additional costs for implementing the permit will be considered by the Owner, when the actual permit is issued. Northampton Drainage Relocation DEWATERING 20164277.003A 02140-9 3.4 REMOVAL A. Do not remove the dewatering system without written approval from the Engineer. B. Backfill and compact sumps or ditches with crushed stone wrapped with geotextile fabric in accordance with Section 02210. C. All dewatering wells shall be abandoned in accordance with state and local regulations upon completion of the work, and completely backfilled with cement grout. END OF SECTION 02140 Northampton Drainage Relocation DEWATERING 20164277.003A 02140-10 THIS PAGE INTENTIONALLY LEFT BLANK TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-1 SECTION 02160 TEMPORARY SUPPORT OF EXCAVATION SYSTEMS PART 1 – GENERAL 1.1 SUMMARY A.This section is not applicable to the support of excavation system for the proposed box culvert. Information related to that system are provided on the drawings. B.This section includes the following for excavations other than that required for the proposed box culvert: 1.Design, furnish and install temporary support of excavation systems as required to maintain lateral support, prevent loss of ground, limit soil movements to the allowable limits indicated, and protect from damage existing and proposed improvements including, but not limited to, pipelines, utilities, structures, roadways, and other facilities. 2.The location, configuration, design, construction, and maintenance of the temporary support of excavation walls and internal bracing shall be the sole responsibility of the Contractor. 3.The temporary support of excavation system to be used on this project may include trench boxes, singular or multiple stages comprised of internally braced timber or steel sheeting, soldier piles and timber lagging, or trench boxes. 4.A temporary support of excavation system is, at a minimum, required at excavation locations within 25 feet of building walls, and where buried utilities are located within the soil wedge extending from the base of the excavation, upward to the ground surface at a slope of 2 horizontal to 1 vertical. 5."Sheeting" as used in this section or on the Contract Drawings shall refer to steel soldier piles and timber lagging or steel and timber sheeting support systems. 6.Construction of the temporary support of excavation system shall not disturb the existing structures or the completed proposed structures. The Contractor, at no additional cost to the Owner, shall repair damage to such structures. TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-2 7.The Contractor shall bear the entire cost and responsibility of correcting any failure, damages, subsidence, upheaval or cave-ins as a result of improper installation, maintenance or design of the temporary support of excavation systems. The Contractor shall pay for all claims, costs and damages that arise as a result of the work performed at no additional cost to the Owner. 8.Monitoring movement of the support of excavation systems by optical survey techniques is required by an independent geotechnical monitoring consultant per Specification 02015 until installation and backfilling is complete. Additional survey monitoring may be required if movement (lateral or vertical) is measured following backfilling to the existing grade. a.In addition, Existing utilities exposed within the trench shall be monitored for movement and/or settlement for the entire time exposed. 9.If, in the Engineers judgment, the performance of the support of excavation system is unacceptable, the Owner may instruct the Contractor to stop work and implement remedial measures to arrest further movements or restore groundwater levels to pre-construction levels. The Contractor shall take immediate steps to implement the remedial measures designed by the Contractor and reviewed by the Engineer. The costs for these measures shall be at no additional cost to the Owner. 10.Temporary support of excavation systems shall be designed and installed in accordance with OSHA excavation safety standards. 1.2 SUBMITTALS A.Shop Drawings: Submit the following in accordance with Section 01300 – SUBMITTALS. 1.Submit the following qualifications at least three weeks prior to the start of construction: a.Qualifications of Contractor’s temporary support of excavation system designer as specified below. b.Qualifications of Contractor’s temporary support of excavation system installer as specified below. 2.Submit a temporary support of excavation plan stamped and signed by a Professional Civil Engineer registered in the Commonwealth of Massachusetts at least two weeks prior to start of the construction. Submit design calculations for review that will be TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-3 only for the information of the Owner and third parties for an overall understanding of the project relating to access, maintenance of existing facilities and proper utilization of the site. The Contractor shall remain responsible for the adequacy and safety of the means, methods and sequencing of construction. The plan shall include the following items as a minimum: a.Drilled or hydraulically pushed in place support of excavation system details, location, layout, depths, extent of different types of support relative to existing features and the permanent structures to be constructed, and methods and sequence of installation and removal. b.Certificate of Design c.Requirements of dewatering during the construction. d.Minimum lateral distance from the edge of the support of excavation system for use for vehicles, construction equipment, and stockpiled construction and excavated materials. e.List of equipment used for installing the support of excavation systems. f.Estimates of the lateral and vertical displacements of the excavation lateral support systems under applied loads at critical stages. 3.Plans for preventing movement of the existing utilities adjacent to, or exposed within the trench including, but not limited to, the 12- inch cast iron water main. It is anticipated that the 4-inch cast iron gas main will be abandoned and the 8-inch gas main will be relocated prior to the start of construction. The telecom duct bank has been abandoned. Contractor shall confirm prior to the start of work and notify the Engineer of their findings. Lateral support systems shall not come in contact with existing utilities. In addition, in accordance with Specification Section 02015, the Contractor shall propose and submit for the Engineer’s approval no less than 30 days prior to the start of excavation, the methods to be used to monitor movement and/or settlement of exposed utilities. 4.Submit a Construction Contingency Plan specifying the methods and procedures to maintain support of excavation system stability if the allowable movement of the adjacent ground and adjacent structures is exceeded. 5.For support of excavation systems left in place, submit the following TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-4 as-built information prior to backfilling and covering the support of excavation systems: a.Type of the temporary support of excavation system. b.Surveyed coordinates of the ends and points of change in direction. c.Elevations of top and bottom 1.3 QUALITY ASSURANCE A.Provide in accordance with Section 01400 – QUALITY CONTROL and as specified. B.Conform to the requirements of the OSHA Standards and Interpretations: "Part 1926 Subpart P - Excavation, Trenching, and Shoring", and all other applicable laws, regulations, rules, and codes. C.All welding shall be performed in accordance with AWS D1.1. D.Prepare design, including calculations and drawings, under a Professional Civil Engineer registered in the Commonwealth of Massachusetts and having the following qualifications: 1.Not less than five years experience in the design of the proposed temporary support of excavation systems in urban areas of comparable type, size, and complexity as this project. 2.Completed not less than five successful projects utilizing proposed temporary support of excavation system in urban areas of comparable type, size, and complexity as this project within the last five years. E.Temporary Support of excavation System Installer's Qualifications: 1.Not less than five years’ experience in the installation of temporary support of excavation systems in urban areas of comparable type, size, and complexity as this project. 2.Completed not less than five successful temporary support of excavation system projects in urban areas of comparable type, size, and complexity as this project within the last five years. F.Install all temporary support of excavation system under the supervision of a supervisor having the following qualifications: 1.Not less than five years’ experience in installation of temporary support of excavation systems in urban areas of comparable type, TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-5 size, and complexity as this project. 2.Completed not less than five successful temporary support of excavation system projects in urban areas of comparable type, size, and complexity as this project within the last five years. G.Notify the Engineer immediately if any settlement or movement is detected on any adjacent structures. If the settlement or movement is deemed by the Engineer to be related to the temporary support of excavation system, take actions to protect the adjacent structures and submit a modified temporary support of excavation plan to the Engineer within 24 hours. Implement the modified plan and repair any damage incurred to the adjacent structures at no additional cost to the Owner. 1.4 DESIGN CRITERIA A.Design of temporary support of excavation systems shall meet the following minimum requirements: 1.Support systems shall be designed for earth pressures, hydrostatic pressure, equipment, traffic, temporary stockpiles, construction loads, and other surcharge loads in accordance with the current AASHTO (American Association of State Highway and Transportation Officials) Design Criteria. 2.Contractor shall at a minimum comply with the requirements of the MBTA Railroad Operations Directorate, dated May 1994. Refer to Section VII “Temporary Sheeting and Shoring” of the Directorate for temporary sheeting and shoring requirements. 3.Design internal bracing as needed to provide sufficient reaction to maintain stability. 4.Limit movement of buildings, ground, and buried utilities adjacent to the support of excavation system to be within the allowable ground deformation as specified in Section 02015 – GEOTECHNICAL MONITORING AND INSTRUMENTATION. 5.Design the embedment depth below bottom of excavation to minimize lateral and vertical earth movements and provide bottom stability. Toe of unbraced temporary support of excavation systems shall not be less than 5 feet below the bottom of the excavation. 6.Design temporary support of excavation system shall withstand an additional 3 feet of excavation below proposed bottom of excavation without redesign except for the addition of lagging and/or bracing. 7.Maximum width of pipe trench excavation shall be as indicated on the Drawings. TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-6 8.Permanent structure walls shall not be directly cast against support of excavation walls. 1.5 DELIVERY, STORAGE AND HANDLING A.Provide support of excavation in accordance with Section 01600 – PRODUCTS, MATERIALS AND EQUIPMENT and as specified. B.Store sheeting and bracing materials to prevent sagging, which would produce permanent deformation. Keep concentrated loads, which occur, during stacking or lifting below the level which would produce permanent deformation of the material. 1.6 PROJECT/SITE CONDITIONS A.Subsurface investigation data are provided in Section 02010 – SUBSURFACE INVESTIGATIONS. The geotechnical data is made available to the Contractor for informational purposes only and shall not be interpreted as a warranty of subsurface conditions whether interpreted from written text, boring logs, or other data. B.Prior to submitting a bid, the Contractor shall review and understand the information contained in the geotechnical data and all Contract Documents. C.The Contractor shall draw their own conclusions regarding site conditions based upon site visit(s) and from available sources, for which the Owner and its Consultants assume no responsibility. The Contractor shall assume that subsurface conditions outside of subsurface exploration locations could differ from conditions shown in the records of the explorations. D.The Contractor shall notify the Engineer immediately if obstructions are determined to conflict with the location of the support of excavation system. Cobbles and boulders within dense well-bonded soils or other competent naturally deposited soils will not be considered obstructions. E.The Contractor shall protect adjacent structures above ground and buried from damage associated with lateral support of excavation operations and other operations. Damage due to lateral support of excavation operations or other Contractor activities shall be repaired immediately by the Contractor at his own expense. PART 2 – PRODUCTS 2.1 MATERIALS A.Structural Steel: All soldier piles, wales, rakers, struts, wedges, plates, waterstop and accessory steel shapes shall conform to ASTM A36. TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-7 B.Timber Lagging: Structural grade having a nominal thickness of 3 inches and a minimum allowable working stress of 1100 psi. C.Timber Sheeting: Structural grade having a nominal thickness of 4 inches and a minimum allowable working stress of 1100 psi. D.Other Materials 1.Tamping tools adapted for backfilling voids after removal of the support of excavation system. 2.Hydraulic, pneumatic or screw-jack shoring systems (Speed Shores) used to support excavations shall be in good working order and shall conform to all of the manufacturer’s requirements for new equipment; bent or otherwise damaged supports, leaking hydraulic cylinders, or damaged sheeting shall not be used, and the Contractor shall immediately remove such damaged materials/equipment from the work site. PART 3 – EXECUTION 3.1 GENERAL A.Installation of the temporary support of excavation systems shall not commence until the Engineer has reviewed the related earth excavation and dewatering submittals with all Engineers’ comments satisfactorily addressed. B.The Contractor shall take all precautions against excessive vibrations in all areas. The Contractor shall be solely responsible for any damages caused directly or indirectly to structures, utilities, and shall repair any such damage occurring due to his operations to the requirements of the Owner. C.Install support of excavation system in accordance with the Contractor’s temporary support of excavation plan. D.Carry out program of temporary support of excavation in such a manner as to prevent undermining or disturbing foundations of existing structures and utilities, and of work ongoing or previously completed. E.Perform preparatory work to discover, protect, maintain and restore, or remove utilities, foundations or other facilities located in close proximity of the proposed temporary support of excavation system. F.Conduct pre-excavation as necessary to remove obstructions and identify exiting utilities along the alignment of the temporary support of excavation system which will interfere with installation in accordance with Specification Section 02210 - EARTH EXCAVATION, BACKFILL, FILL AND GRADING. Pre-excavation shall not extend greater than 4 feet in depth, and shall not extend within a 2 horizontal to 1 vertical (2H:1V) envelope below TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-8 existing utilities or structures to remain. G.The Contractor shall provide fully equipped rig(s) and appropriate tools in full-time operation at the site during the work, and shall mobilize additional equipment, if necessary, to complete the work on schedule. H.Excavation shall not proceed more than 2 ft below the bracing level, anywhere within the support of excavation limits, until the entire level of bracing is completely installed, including prestressing. I.Notify utility owners if existing utilities interfere with the temporary support of excavation system. Modify the existing utility with the utility owner’s permission or have the utility owner make the modifications at no additional cost to Owner. J.All trench support shall be installed and maintained so it is in continuous contact with the earthen trench walls being supported. K.Installation, maintenance and removal of the temporary support of excavation shall be coordinated with the exposure and support of existing utilities indicated on the plans. L.Contractor shall control the rate of the trench excavation and removal of the support system to minimize the movement of permanent structures and the adjacent ground surface. 3.2 SOLDIER PILES AND TIMBER LAGGING A.Install steel soldier piles before starting excavation. If used, drilled methods shall prevent loss of ground around the hole. Each soldier pile shall be installed in its drilled hole within 2 hours after drilling is completed to the required depth. B.The Contractor shall have equipment on-site able to advance the drilled hole for installation of the soldier piles through sand below the water table, through concrete, and through large boulders and other obstructions which may be encountered. C.Space soldier piles at intervals indicated on the Shop Drawings. Accurately align exposed faces of flanges to vary not more than 2 inches from a horizontal line and not more than 1:120 out of vertical alignment. D.Within the same day of seating the soldier piles in the drilled holes, encase the piles with MHD (1995) M4.08.0 – Controlled Density Fill, Type 1E from the tip elevations to the currently existing ground surface. Crushed stone or other granular materials are not acceptable. E.Where the support of excavation is to be left in place, soldier piles shall be cut off 5 feet below the final ground surface prior to completion of the final TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-9 backfilling operations. F.Install wood lagging within flanges of soldier piles as excavation proceeds. Trim excavation as required to install lagging. As installation progresses, backpack the voids between the excavation face with sand and on-site soils to establish a tight contact. Pack louver openings between lagging with hay or other porous material to allow free drainage of groundwater without loss of retained soil or backpacking. In no case shall the louvered openings be allowed to exceed 1-inch. G.Beginning at the top of the soldier piles, the maximum permissible height of unlagged face of excavation shall not exceed 1-foot in all soil types encountered at the site. If water is flowing from the face of the excavation, or if soil to be retained moves toward the excavation, the maximum height of unlagged face shall not exceed 8-inches. H.If unstable ground is encountered, take suitable measures (grouting behind the lagging or other approved method) to retain the material in place and prevent loss of ground or movements, which may cause damage to adjacent structures or utilities. 3.3 INSTALLATION – STEEL OR TIMBER SHEETING A.Length Markings: Before installation is started each steel or timber section shall be marked so that the depth of the tip can be readily determined. This shall be accomplished by a method that is approved by the Engineer. B.All sheeting shall be protected from damage during installation. C.All sheeting shall be hydraulically pushed to its full depth ahead of the excavation so as to avoid the loss of material from behind the sheeting; where voids occur outside of the sheeting, they shall be filled immediately with structural fill and thoroughly compacted. D.The Contractor shall provide all inspection equipment to determine whether the sheeting has been started in their planned location, are vertical, and are within the allowable tolerance for position after installation. E.Requirements for the sheeting include the following: 1.Install sheeting in the plumb position. 2.Install sheeting such that the piling is in direct contact with the material to be retained. 3.Install sheeting to the depths indicated on approved Shop Drawings. 4.Methods and equipment used in pushing, setting, cutting and splicing shall conform to approved Shop Drawings. TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-10 5.Use templates or other temporary alignment facilities to maintain piles plumb and on line. 6.Control vibrations and noise associated with installation. 7.Pre-excavate as necessary to remove existing structures along alignment of the sheeting. 8.Sheeting shall be positioned within 3 inches of the design plan location along its length from top down to bottom of excavation grade. Design plan locations are to be established by the Contractor’s Professional Engineer and submitted to the Engineer for review. 3.4 INTERNAL LATERAL WALL BRACING (WALES AND STRUTS A.Use walers and struts as necessary to provide internal support of the temporary support of excavation system as required. Include web stiffeners, plates, brackets, or angles as required to prevent rotation, crippling or buckling of connections and points of bearing between structural steel members. All for eccentricities due to fabrication and assembly. Consider effects of temperature changes. B.Install and maintain all support members in continuous tight contact with each other and with the earth wall being supported. C.Coordinate locations of all bracing and components thereof for temporary lateral support of excavation with locations of permanent structures. D.Control rate of excavation and installation of support members to minimize movement of adjacent ground surface. E.Excavation shall proceed in accordance with the detailed sequence submitted by the Contractor and reviewed by the Engineer. It shall be the responsibility of the Contractor to schedule and sequence the work accordingly. 3.5 MONITORING A.As proposed by the Contractor and approved by the Engineer. B.In the event the monitoring system proposed by the Contractor proves ineffective, the Contractor shall implement additional measures as required by the Engineer at no additional cost to the Owner. 3.6 REMOVAL OF SUPPORT OF EXCAVATION SYSTEM A.Where sheeting cannot be removed without damage to existing utilities or work recently installed or other facilities it shall be left in place with the TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-11 exception of the top 5 feet of support of excavation system below final grades, which shall be removed, unless otherwise approved by the Engineer. B.Remove support of excavation in a manner that will maintain support as excavation is backfilled and will not leave voids in the backfill. C.Do not begin the removal of the support of excavation system until it can be safely removed damage to existing facilities, completed work or adjacent property. D.Fill any void left by the shoring system or voids created by the removal of the shoring system to provide soil support between the trench backfill and the native soil. E.Sheet piling removal must be performed in a manner that will avoid “vibro- consolidation” (densification) of sandy or granular material below or adjacent to the excavation that could lead to settlement and damage of the pipeline, existing utilities, other works of construction and adjacent property. END OF SECTION 02160 TEMPORARY SUPPORT OF Northampton Drainage Relocation EXCAVATION SYSTEMS 20164277.003A 02160-12 [THIS PAGE INTENTIONALLY LEFT BLANK] EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-1 SECTION 02210 EARTH EXCAVATION, BACKFILL, FILL AND GRADING PART 1 – GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. B. Examine all Drawings and all other Sections of the Specifications for requirements therein affecting the work of this Section. 1.2 SUMMARY A. This section includes the following: 1. The Work shall consist of excavation of all materials within the limits of the Contract in accordance with the Specifications and in close conformity with the lines, grades, thickness and cross sections shown on the plans or established by the Engineer. 2. The Work shall include abandonment of existing brick arch culvert by backfilling with Controlled Density Fill (CDF). 3. Provide materials for backfilling excavations as indicated and specified. 4. Grade surfaces to meet finished grades indicated. Grade roadway and site as to maintain them in a level unrutted condition and to eliminate puddling of surface and subsurface water. 5. The Contractor shall monitor existing utilities and structures for movement during excavation and backfilling as indicated on the Contract Drawings. 6. The Contractor shall bear the entire cost and responsibility of correcting any failure, damages, subsidence, upheaval or cave-ins as a result of improper excavation, maintenance or backfill of excavation. The Contractor shall pay for all claims, costs and damages that arise as a result of the work performed at no additional cost to the Owner. B. Blasting shall not be permitted for this project. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-2 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 – SUBMITTALS: 1. Submit an Excavation, Backfilling, Grading and Compaction plan at least two weeks prior to start of any earth moving activities. The review will be only for the information of the Owner and third parties for an overall understanding of the project relating to access, maintenance of existing facilities and proper utilization of the site. The Contractor shall remain responsible for the adequacy and safety of the means, methods and sequencing of construction. The plan shall include, but not be limited to the following items: a. Detailed sequence of work. b. General description of construction methods. c. Numbers, types, and sizes of equipment proposed to perform excavation, backfilling, grading and compaction. d. Details of dust control measures. e. Proposed locations of stockpiled excavation and/or backfill materials. f. Proposed surplus excavated material off-site disposal areas and required permits. g. Erosion and sedimentation control measures, which will prevent erosion and sedimentation during the earth moving and soil stockpile activities. B. Backfill Materials: Submit a grain size analysis and moisture density curve performed in accordance with AASHTO T311 and AASHTO T180, respectively, for each proposed source and type of backfill, imported material, and on-site material to be reused for review by the Engineer at least, one week prior to use of the material. The grain size analysis shall indicate that the backfill material conforms to the gradation requirements specified. 1. In addition, a certification statement and analytical results shall accompany each physical sample of earth materials to be imported onto the site, including but not limited to crushed stone, loam, bedding sand, gravel sub-base, common fill and structural backfill. At a minimum the certification shall state the point of origin and that the material is free of contaminants. The certification shall include representative sample analysis from each point of origin of backfill to be used on the site. The sample(s) shall be analyzed by a certified laboratory for RCRA 8 metals, volatile organic compounds (EPA EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-3 Method 8260), semi-volatile organic compounds (EPA Method 8270), petroleum hydrocarbons (EPA Method 8100), and Total PCBs and pesticides (EPA Method 8081 and 8082). On-site soils defined as suitable for reuse in this Section and in Section 02080 – SOIL AND WASTE MANAGEMENT can be used as backfill without providing the certification required above. 2. All sampling of soils for chemical testing shall be performed by a person experienced in sample collection and shall be either: 1) a Licensed Site Professional registered in the Commonwealth of Massachusetts; 2) a Professional Engineer registered in the Commonwealth of Massachusetts; 3) a Professional Geologist registered in the Commonwealth of Massachusetts; 4) a certified groundwater/environmental professional; or 5) an authorized representative of the one of the persons listed above. Samples of each material shall be submitted to a chemical analytical laboratory, certified by the Massachusetts Department of Environmental Protection. 3. Submit additional geotechnical and analytical test data and certifications for every 1000 cubic yards (every 200 cubic yards for moisture density curves) of material imported or reused on-site or anytime consistency of material changes in the opinion of the Engineer. Submit associated chemical laboratory data on the imported materials throughout the course of the Work, if requested by the Engineer, to evaluate the consistency of the source or process, at no additional cost to the Owner. C. Controlled Density Fill Mix Design: Prior to beginning the work the Contractor shall submit for review, controlled density fill mix designs which shall show the proportions and gradations of all materials proposed for each class and type of controlled density fill specified herein. D. Filter Fabric: Submit shop drawings and product data sheets. E. During Construction, submit written confirmation of fill lift thickness, in- place soil moisture content, and percentage of compaction to the Engineer before placing the next lift or constructing foundations. F. Submit Qualifications of the Contractor’s Independent Testing Laboratory as specified in Paragraph 1.7.C, three weeks prior to the execution of any earth excavation, backfilling, filling, or compaction process. 1.4 DEFINITIONS A. Suitable Material: Material which does not contain organic silt or organic clay; peat; vegetation; wood or roots; stones or rock fragments over 6-inch in diameter; porous biodegradable matter; loose or soft fill; excavated pavement; EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-4 or refuse. Material for backfill shall conform to the gradation requirements specified herein. B. Unsuitable Materials: Materials that do not comply with the requirements for the acceptable material or which cannot be compacted to the specified or indicated density. C. Percentage of compaction is defined as the ratio of the field dry density, as determined by AASHTO T310 or AASHTO T191, to the maximum dry density determined by AASHTO T180, multiplied by 100. D. Proof Roll: Compaction with a minimum of four passes of a vibratory steel drum roller. Vibratory plate compactors shall be used in small areas where a vibratory steel drum roller cannot be used. 1.5 EXCAVATION CLASSIFICATIONS A. Earth Excavation or "Excavation" consists of removal of materials encountered to the subgrade elevations indicated and subsequent reuse or disposal of the materials removed. All excavation is classified as earth excavation unless it otherwise meets the classifications provided below for unauthorized excavation, additional excavation, or rock excavation. B. Unauthorized Excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of the Engineer. Unauthorized excavation, as well as remedial work directed by the Engineer, shall be at Contractor's expense. 1. Under footings, foundations bases, concrete slabs, retaining walls or other structures, fill unauthorized excavations to the proper elevations with material as directed by Engineer. Elsewhere, backfill and compact unauthorized excavations as specified for excavations of the same class, unless otherwise directed by the Engineer. C. Additional Excavation: 1. When excavation has reached required subgrade elevations, notify the Engineer who will review subgrade conditions. 2. If unsuitable bearing materials are encountered at required subgrade elevations, carry excavations deeper and replace excavated material as directed by the Engineer. 3. Removal of unsuitable material and its replacement as directed will be paid on the basis of contract conditions relative to changes in work or as provided for under the unit rates for this classification. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-5 D. Rock Excavation: 1. Rock excavation in trenches and pits includes removal and disposal of materials and obstructions encountered which cannot be excavated with a 1.0 cubic yard (heaped) capacity, 42-inch wide bucket on track-mounted power excavator equivalent to Caterpillar Model 215, rated at not less than 90HP flywheel power and 30,000 lb. drawbar pull. Trenches in excess of 10 foot 0-inches in width and pits in excess of 30 feet 0-inches in either length or width are classified as open excavation. 2. Rock excavation in open excavations includes removal and disposal of materials and obstructions encountered which cannot be dislodged and excavated with modern track-mounted heavy-duty excavating equipment without drilling, blasting or ripping. Rock excavation equipment is defined as Caterpillar Model No. 973 or No. 977K, or equivalent track-mounted loader, rated at not less than 170HP flywheel power and developing 40,000 lb. break-out force (measured in accordance with SAE J732C). 3. Determination of rock excavation classification shall be made by the Engineer. Typical of materials classified as rock are boulders 1.0 cu. yd. or more in volume, solid rock, rock in ledges, and rock-hard cementitious aggregate deposits. Intermittent drilling, blasting or ripping performed to increase production and not necessary to permit excavation of material encountered will be classified as earth excavation. Do not perform rock excavation work until material to be excavated has been cross-sectioned and classified by Engineer. Visual observation of the completed excavation may be made by the Engineer to modify the excavation classifications. Removal of rock excavation prior to classification by the Engineer shall be considered as earth excavation unless accepted by the Engineer in writing. Such excavation will be paid on the basis of contract unit rates for this classification. 1.6 REGULATIONS A. The Contractor shall be solely responsible for making all excavations in a safe manner. All excavation, trenching, and related sheeting, bracing, etc. shall comply with the requirements of OSHA excavation safety standards (29 CFR Part 1926 Subpart P) and State requirements. Where conflict between OSHA and State regulations exists, the more stringent requirements shall apply. B. The Contractor shall comply with all applicable laws, rules, ordinances, and EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-6 general regulations of the Federal Government, the Commonwealth of Massachusetts, the City of Northampton, the Northampton Department of Public Works, DEP, EPA, OSHA, and other regulatory agencies having jurisdiction over the Work. 1.7 QUALITY ASSURANCE A. Provide and maintain dewatering and groundwater control as specified in Section 02140 - DEWATERING. B. Excavations shall be performed in the dry, and kept free from standing water, snow and ice during construction. C. Provide and maintain temporary support of excavation systems as specified in Section 02160 – TEMPORARY EXCAVATION SUPPORT SYSTEMS. D. Do not excavate or fill until the Engineer has reviewed all the required submittals. E. Dig test pits considered separate to the normal excavation as required to locate underground utilities, obstructions or water table. F. Employ an independent testing laboratory to perform particle size and gradation analyses in accordance with AASHTO T311, laboratory compaction testing per AASHTO T180, and in-place density and moisture content per AASHTO T310 or AASHTO T191. The independent testing laboratory shall have the following qualifications: 1. Be accredited by the American Associates of State Highway and Transportation Officials (AASHTO) Accreditation Program; 2. Have three years’ experience in sampling, testing and analysis of soil and aggregates, and monitoring field compaction operations; 3. Able to provide three references from previous work. 1.8 AVAILABLE INFORMATION A. Prior to submitting his bid, the Contractor shall review and understand all available information. Subsurface exploration data is made available to the Contractor for informational purposes only and shall not be interpreted as a warranty of subsurface conditions whether interpreted from written text, boring logs, or other data. The subsurface data represent conditions only at the sampling locations at the times the explorations were conducted. B. Neither the Owner nor Engineer shall be liable for any error or discrepancy in the subsurface information provided, nor for the Contractor’s use or interpretation of the information. Additional test borings, test pits or other EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-7 exploratory operations may be made by the Contractor with the written approval of the Owner, at no additional cost to the Owner. 1.9 CONSTRUCTION TOLERANCES A. Construct finished surfaces to plus or minus 0.5 inches of the elevations indicated. Provide the Engineer with adequate survey information to verify compliance with above tolerances. 1.10 FIELD TESTING A. Field Testing and Inspections: By Contractor’s independent testing laboratory, acceptable to the Engineer, at Contractor's expense as specified. Location of tests shall be mutually acceptable to testing laboratory and the Engineer or as required by the Engineer. In the event compacted material does not meet specified in-place density, recompact material and retest this area until specified results are obtained at no additional cost to the Owner. B. Methods of Field Testing: In-Place Density and Moisture Content shall be determined by AASHTO T310 or AASHTO T191. C. Testing Frequency: Crushed stone and Sand Borrow shall be compacted as specified and indicated. For other backfill and fill materials, minimum test frequency shall be as follows, and no less than two tests per lift: 1. Trenches under structures, sidewalks, or roadways subbase: Every 30 lin. ft. per lift. 2. Trenches in areas without structures or roadways: Every 50 lin. ft. per lift. 3. Under Structure: Every 100 sq. ft. per lift. 4. Around Structures: Every 100 sq. ft. per lift. PART 2 – PRODUCTS 2.1 SAND BORROW A. The Sand Borrow shall conform to Massachusetts Department of Transportation (MassDOT) 1988 Standard Specifications section, M1.04.1. 2.2 CRUSHED STONE A. Crushed stone shall conform to the requirements of MassDOT 1988 Standard Specifications section M2.01.4 for ¾-inch crushed stone. B. Crushed stone shall be wrapped in filter fabric for separation, placed in maximum 6-inch thick layers, loose measure, and compacted with a minimum of four passes of a vibratory plate or roller compactor. The crushed EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-8 stone shall be uniformly blended. 2.2 ORDINARY BORROW: A. Ordinary Borrow shall consist of sand and gravel consisting of hard durable particles, and free from trash, ice and snow, tree stumps, roots and other organic matter, and shall conform to MassDOT 1988 Standard Specifications section M1.01.0, and the following gradation requirements: Sieve Size Percent Finer by Weight 6-inch (152.4mm) 100 No. 4 30-80 No. 40 30-50 No. 200 0-25 B. On-site excavated material may be used as Ordinary Borrow, provided it meets the requirements specified herein and can be compacted to the required degree. 2.3 CONTROLLED DENSITY FILL (CDF) A. Controlled density fill shall consist of a cementitious excavatable mixture of aggregate, Portland Cement, and air entraining admixtures. The material shall be of the type specified in MassDOT 1995 Standard Specifications for Highway and Bridges, as amended, Type 2E. B. Controlled density fill placed in contact with ductile iron pipe shall utilize a non-fly ash mix design. 2.4 GRAVEL BORROW A. Gravel Borrow shall conform to the requirements of MassDOT 1988 Standard Specifications section M1.03.0 for Type b Gravel Borrow. 2.5 GRAVEL SUBBASE A. Gravel Subbase shall conform to the requirements of MassDOT 1988 Standard Specification section M1.03.1. 2.6 FILTER FABRIC A. Filter Fabric, shall consist of a nonwoven fabric made from polypropylene or polyethylene filaments or yarns. The fabric shall be inert to organic chemicals commonly encountered in the soil. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-9 B. Filter fabric shall meet the requirements specified in AASHTO M 288: Standard Specification for Geotextile Specification for Highway Applications for subsurface drainage, separation, stabilization, or permanent erosion control as appropriate for the intended application. C. Edges and ends of filter fabric shall overlap a minimum of two feet. PART 3 – EXECUTION 3.1 GENERAL A. Execution of any earth excavation shall not commence until the related dewatering, soil and fill management, excavation support systems, and required backfill and fill materials submittals are reviewed by the Engineer and all Engineers’ comments addressed. B. Cut pavement and all surface materials to the top of the existing fill material with a saw to prevent damage to remaining pavement without extra compensation. Surface materials may include concrete slabs, cobblestones, rails and other miscellaneous materials. Where pavement is removed in large pieces, dispose of pieces before proceeding with excavation. C. Formulate excavation, backfilling, and filling schedule and procedures to eliminate possibility of undermining or disturbing foundations of partially and completed structures, pipelines and embankments or existing structures and pipelines. D. During progress of work, conduct earth-moving operations and maintain work site so as to minimize the creation and dispersion of dust. E. Roadway and Site Leveling: Grade roadway and site as to maintain them in a level unrutted condition and to eliminate puddling of surface and subsurface water. 3.2 TRENCH EXCAVATION A. Excavate to widths that give adequate working space for constructing structures or laying and jointing piping, and to allow for safety of personnel. B. Excavate to lines and elevations indicated in an orderly and continuous program. C. Excavate trench by machinery to, or just below designated subgrade. Excavate deeper, as required by the Engineer, to remove unsuitable subgrade material. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-10 D. Exercise care to preserve material below and beyond the lines of excavations. If material remaining at the bottom of the trench is disturbed, recompaction shall be required. E. Excavations shall be performed in the dry, and kept free from standing water, snow and ice during construction. F. Maintain groundwater levels a minimum of 2 feet below the bottom of the trench during excavation and subgrade preparation. Dewatering systems shall be provided and maintained as specified in Section 02140 - DEWATERING. G. Excavation Around Existing Structures or Utilities: 1. Discontinue digging by machinery when excavation approaches pipes, conduits, or other underground structures. Excavate using only hand tools when within 3 feet horizontally of exposed structures or utilities, and within a soil wedge delineated by a downward line at 45 degree angle drawn from the springline of exposed utilities. Include such manual excavation in work to be done when incidental to normal excavation and under items involving normal excavation. 2. Excavations to remove unsuitable material shall not extend within a 2 horizontal to 1 vertical (2H:1V) envelope below existing structures to remain, except when excavation is supported by an approved shoring system designed and installed in accordance with Specification Section 02160. 3. Excavate test pits when determination of exact location of pipe utilities or other underground structures is necessary for doing work properly. 3.3 REUSE OF EXCAVATED MATERIAL A. Carefully remove material from excavated areas and store separately for further use as backfill material or for disposal or immediately reuse at the area of excavation as backfill. B. In general, the material used for backfilling trench excavations within the zone around and above structures and more than 6 inches above pipe crowns shall be material removed from the excavation, provided that the reuse of these materials result in the required trench compaction and the material meets the requirements specified herein for Ordinary Borrow. C. All excess excavated material not approved for re-used as part of the project shall be the sole responsible of the Contractor to removal, transport and legally disposed of the material offsite at an acceptable facility in accordance with all federal, state and local regulations. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-11 3.4 SUBGRADE PREPARATION AND PROTECTION A. Proof compact the exposed subgrade to a firm and unyielding condition with a vibratory plate compactor or double drum roller (minimum of 4 passes) prior to backfilling and filling operation, or placing pipe or structure bedding. Proof rolling shall be performed in the presence of the Engineer. B. As required by the Engineer, over-excavate any unstable or unsuitable materials below the subgrade. The overexcavation shall be backfilled with Crushed Stone wrapped in filter fabric or Gravel Borrow and compacted as specified herein. C. Use excavating equipment equipped with a toothless or smooth edged, excavating bucket to expose the pipe trench subgrade to avoid disturbance of the bearing surface. Do not plow, scrape or dig by machinery near to finished subgrade in a manner that would result in disturbance of subgrade. D. In areas where the bottom of the excavation is in silt and clay, and is below the groundwater table, a working mat and drainage layer of 12 inches of compacted crushed stone wrapped in filter fabric may be placed. 3.6 BACKFILL PLACEMENT A. The trenches shall be backfilled as soon as practicable with the material specified herein. All trench backfilling shall be done with special care, in the following manner and as required by the Engineer. B. All fill shall be placed in horizontal layers. Fill shall not be placed following the natural contours of the ground. Fill shall be placed starting in the lowest areas working up to finish grades in horizontal layers in the manner specified herein. C. Place backfill in maximum loose lift thickness of 9 inches, except where used as pipe bedding, and compact to the degree specified herein. D. Backfill material for pipe bedding shall be deposited across the entire width of the trench, uniformly on both sides of the pipe simultaneously to ensure that all loads applied to the utility by the backfill are properly balanced and that they do not exceed the safe load carrying capacity of the utility at any time as indicated on the drawings. 1. Sand borrow bedding shall be placed by hand shovels, in layers not more than 4-inches thick in loose depth, and each layer shall be thoroughly and evenly compacted by tamping on each side of the pipe to provide uniform support around the pipe, free from voids. 2. Crushed stone bedding material shall be placed in layers not more than 6-inches thick in loose measure, and compacted with at least 4 passes using a vibratory plate compactor. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-12 E. The trench shall be backfilled with compacted Ordinary Borrow from above the pipe or structure bedding up to bottom of topsoil or pavement base course. F. Backfill shall be placed in appropriately sized lifts and on both sides of the utility simultaneously to ensure that all loads applied to the utility by the backfill are properly balanced and that they do not exceed the safe load carrying capacity of the utility at any time. G. All trench backfilling shall be done with special care and must be carefully placed so as not to disturb the work at any time. If necessary, timber grillage or other suitable method shall be used to break the fall of material. The moisture content of the backfill material shall be such that proper compaction will be obtained. Backfill shall be made to grades required to establish the proper subgrade for the placement of topsoil or pavement base courses. H. In no case shall fill be placed in standing water, over unsuitable material, or material that is frozen. Water shall not be allowed to rise upon or flow over the bedding and backfill material. I. No fill material shall be placed, spread or rolled during unfavorable weather conditions. When work is interrupted by heavy rains, fill operations shall not be resumed until the moisture content and the density of the previously placed fill are as specified. J. Any trenches or excavations improperly backfilled or where settlement occurs, shall be reopened to the depth required for proper compaction, then refilled and compacted with the surface restored to the required grade and condition, at no additional expense to the Owner. K. During filling and backfilling operations, pipelines will be checked by the Engineer to determine whether any displacement of the pipe has occurred. Pipelines observed to display poor alignment, displacement, or other defects shall be remedied to meet Engineer and Owner requirements at no additional cost to the Owner. L. After backfilling trenches and excavations, the Contractor shall maintain the surfaces of backfill area in good condition so as to present a smooth surface at all times level with adjacent surfaces. The Contractor shall repair any subsequent settling over backfilled area immediately, in a manner satisfactory to the Engineer, and such maintenance shall be provided by the Contractor for the life of this Contract, at no additional expense to the Owner. M. The finished subgrade of the fills and filled excavations upon which topsoil is to be placed or pavements are to be constructed, shall not be disturbed by traffic of other operations, and shall be maintained in a satisfactory condition until the finished courses are placed. The storage or stockpiling of materials on finished subgrade will not be permitted. N. Backfilling around structures should not commence until after the satisfactory EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-13 completion of leakage tests and of any other required work in connection with the structures. O. Symmetrical backfill loading shall be maintained around structures. Special care shall be taken to prevent any wedging action or eccentric loading upon or against the structures. P. The Contractor shall conduct his compacting and other operations in a manner to prevent damage to structures due to passage of heavy equipment over or adjacent to structures, and any damage thereto shall be remedied by the Contractor at no additional expense to the Owner. 3.7 BRICK ARCH CULVERT ABANDONMENT A. The existing brick arch culvert shall be backfilled with quick-set CDF to 2 feet above the crown of any utility crossing the trench in areas where compaction cannot be achieved using mechanical compaction equipment. B. CDF backfill shall be placed in a manner which ensures that voids will not remain within the culvert. 3.8 COMPACTION REQUIREMENTS A. Compaction equipment: 1. The compaction equipment shall be selected by the Contractor, and shall be capable of consistently achieving the specified compaction requirements. 2. The selected compaction equipment shall meet the following minimum requirements. a. Manually operated vibratory plate compactors weighing no less than 200 pounds with vibration frequency no less than 1600 cycles per minute b. Vibratory steel drum roller weighing at least 12,000 pounds. c. Water jetting and puddling will not be allowed EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-14 B. The degree of compaction is expressed as a percentage of the maximum dry density at optimum moisture content as determined by AASHTO T180. The required degrees of compaction are as follows: Area ASTM Density Degree of Compaction Natural subgrade Proof roll Crushed stone As specified herein Sand Borrow As specified herein Gravel subbase 95% Trench backfill - below pavements - below landscaped areas 95% 92% Other areas 92% C. Moisture Control: Maintain backfill material with a uniform moisture content, with no visible wet or dry streaking, between plus 2 percent or minus 3 percent of optimum moisture content. 1. Fill that is too wet for proper compaction shall be desiccated, harrowed, or otherwise dried to a proper moisture content to allow compaction to the required density. If fill cannot be dried within 24 hours of placement, it shall be removed and replaced with drier fill at no additional cost to the Owner. 2. Fill that is too dry for proper compaction shall receive water uniformly applied over the surface of the loose layer. Sufficient water shall be added to allow compaction to the required density D. Compaction Control: In-place density tests shall be made at the Contractor’s expense in accordance with AASHTO T310 or AASHTO T191 as the work progresses, to determine the degree of compaction being attained by the Contractor. Any corrective work required as a result of such tests, such as additional compaction, or a decrease in the thickness of layers, shall be performed by the Contractor at no additional expense to the Owner. E. In freezing weather, a layer of fill shall not be left in an uncompacted state at the close of the day’s operations. Prior to terminating work for the day, the final layer of compacted fill shall be rolled with a smooth wheeled roller to eliminate ridges of soil left by compaction equipment. F. The Engineer’s duties do not include supervision or direction of the actual work by the Contractor, his employees or agents. Neither the presence of the Engineer nor any observation and testing performed by him shall excuse the Contractor from defects discovered in his work at that time or subsequent to the testing. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-15 3.9 CDF QUALITY CONTROL TESTING DURING CONSTRUCTION A. Slump: ASTM C143; one test at point of discharge for each day’s placement; additional tests when CDF consistency seems to have changed. B. Compression Test Specimen: ASTM C31; one set of four (4) standard cylinders for each compression strength test, plus additional sets for each 100 cu yds more than the first 50 cu yds placed in any one day unless otherwise required. C. Compressive Strength Tests: ASTM C39; one set for each day’s pour plus additional sets for each 100 cu. yds more than the first 50 cu. yds placed in any one day; two specimens tested at 28 days, and two specimens tested at 90 days. D. Test results will be reported in writing to Engineer, Ready-Mix Producer, and Contractor within 24 hours after tests. Reports of compressive strength tests shall contain the project identification name and number, date of placement, name of testing service, fill type and class, location of fill batch along route, design compressive strength limits at 28 days and 90 days, fill mix proportions and materials, compressive breaking strength, and type of break for both 28 day tests and 90 day tests. 3.10 REMOVAL OF SUBSURFACE OBSTRUCTIONS A. Remove indicated or approved subsurface structures and related obstructions to complete the work. B. Promptly notify the Engineer when any unexpected subsurface facilities are encountered during excavation such as utility lines and appurtenances, walls and foundations. 3.11 UNAUTHORIZED EXCAVATION A. When the bottom of any excavation is excavated beyond limits indicated or specified, backfill with crushed stone wrapped with non-woven geotextile fabric. No additional payment will be made for the excavation of backfill or unauthorized excavation. 3.12 CARE AND RESTORATION OF PROPERTY A. Restore all surfaces damaged by the Contractor's operations, including paved surfaces damaged by the treads of the Contractor’s equipment, to a condition at least equal to that in which they were found immediately before work commenced. Use suitable materials and methods for such restoration. EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-16 3.13 POLLUTION CONTROL A. During progress of work, conduct earth-moving operations and maintain work site so as to minimize the creation and dispersion of dust. B. Separation of Excavated Material for Reuse: Remove only existing pavement and all other surface materials, which may include concrete slabs, cobblestones, rail ties, by saw cutting that is necessary for prosecution of work. END OF SECTION 02210 EARTH EXCAVATION, Northampton Drainage Relocation BACKFILL, FILL, AND GRADING 20164277.003A 02210-17 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 1 SECTION 02431 CATCH BASINS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Providing and constructing catch basins as indicated, specified, and consisting of: a. Base: Precast concrete. Tops accurately shaped by ring forms to suit riser sections b. Walls: Precast concrete riser sections. c. Top of Cone: Precast reinforced concrete riser rings (not to exceed 6 in. or 12 in.). d. Frames and Grates: As indicated and specified. B. Related sections include the following: 1. Section 02210 - Earth Excavation, Backfill, Fill and Grading 2. Section 03346 - Cast-in-Place Concrete 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Submit manufacturer's specifications and product data. 2. Submit buoyancy calculations as specified herein. Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 2 1.4 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610. PART 2 - PRODUCTS 2.1 MATERIALS A. Portland Cement: ASTM C150, Type II B. Hydrated Lime: ASTM C207, Type S C. Sand: ASTM C33, Fine Aggregate, except all passes No. 8 sieve. D. Water: Potable E. Brick: ASTM C32, Grade SS, except that the mean of five tests for absorption shall not exceed eight percent by weight. F. Frames and Grates: Cast Iron, minimum Class 25 conforming to ASTM A48, and as follows: 1. Castings to be free from scale, lumps, blisters, sandholes. 2. Machine contact surfaces to prevent rocking. 3. Thoroughly clean and hammer inspect. 4. Capable of withstanding AASHTO H-20 loading unless otherwise indicated or specified. 5. Frames and grates shall conform to Section M8.03.0 of the Commonwealth of Massachusetts Department of Public Works Standard Specifications for Highways and Bridges. 6. Frames and grates shall be: a. Model No. LF248-2, Lebaron Foundry, Inc., Brockton, MA. b. Model No. R-3405, Neenah Foundry Co., Albany, NY c. Model No. 2815, Campbell Foundry Co., North Haven, CT d. Or approved equal. G. Riser rings: Precast reinforced concrete. H. Outlet Hoods: All catch basin shall be fitted with hoods over the outlet pipe. The proposed hoods shall be the Eliminator model as manufactured by Ground Water Rescue, Inc of Quincy, MA or approved equal. Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 3 2.2 CURB INLETS A. Granite curb inlets: Section M9.04.5 of Commonwealth of Massachusetts Department of Public Works Standard Specifications for Highways and Bridges. 2.3 PRECAST CONCRETE SUMPS AND RISER SECTIONS A. Precast concrete: ASTM C478, and following requirements: 1. Wall section not less than 6 in. thick. 2. Use Type II cement except as otherwise permitted. 3. Cured by saturated steam at temperature between 100 and 130 deg. F. for period of not less than 12 hours or, when necessary, for such additional time as needed to enable sections to meet strength requirements. 4. Allow no more than two lift holes cast or drilled in each sump and riser section. 5. Accept sumps and riser section on basis of material tests and inspection of completed product. 2.4 MIXES A. Concrete: Section 03346. B. Mortar for Brickwork: Mix portland cement, hydrated lime and sand. Volume of sand not to exceed three times sum of volumes of cement and lime. Proportion cement and lime as directed; may vary from 1:1/4 for dense, hard burned brick to 1:3/4 for softer brick. Generally mix mortar in proportion of 1:1/2 : 4-1/2. Use sufficient water to form a workable mixture. C. Mortar for Plugging Lift Holes: Mix portland cement and sand 1:1/2, with sufficient water to make mortar damp, just short of "balling". PART 3 - EXECUTION 3.1 SETTING PRECAST SECTIONS A. Set verticals with sections and steps in alignment. Set bases true to line and elevation. B. Install Butyl rubber-based sealants in joints between sections. Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 4 C. Plug holes for handling with mortar. Hammer mortar into hole until dense and excess of paste appears, then smooth flush with adjoining surface. 3.2 LAYING BRICKWORK A. Use clean units. B. Moisten bricks by suitable means, until neither dry as to absorb water from mortar nor wet as to be slippery when laid. C. Do not moisten concrete masonry units. D. Lay each brick in full bed and joint of mortar without requiring subsequent grouting, flushing or filling; bond thoroughly. E. Lay each masonry unit in full bed of mortar; bond thoroughly. Fill vertical keyways, completely, with mortar. 3.3 PLASTERING AND CURING BRICK MASONRY A. Plaster outside faces with mortar 1/4-in. to 3/8-in thick. B. Moisten brick masonry before application of mortar, if required. C. Spread and trowel plaster carefully. D. Check for bond and soundness after hardening, by tapping. E. Remove and replace unbonded and unsound plaster. F. Protect from too rapid drying by use of moist burlap or other approved means. G. Protect from weather and frost. 3.4 SETTING CURB INLETS, GRATES AND FRAMES A. Set inlets and frames with tops conforming accurately to finished ground or pavement surface as indicated and directed. B. Set circular frames concentric with top of masonry. C. Set frames in full bed of mortar to fill and make watertight completely the space between top of concrete or plastic riser rings and bottom flange of the frame. Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 5 D. Place a thick ring of mortar extending to the outer edge of masonry, around bottom flange. Finish mortar smoothly and give a slight slope to shed water away from the frame. E. Place grates in the frames on completion of other work at the catchbasin. 3.5 PLUGGING LIFT HOLES IN PRECAST SECTIONS A. Plug lift holes in sumps, used for handling, with mortar. Hammer mortar into holes until dense and excess of paste appears, then smooth flush with adjoining surface. 3.6 ADJUSTMENT TO GRADE OF EXISTING CATCHBASIN A. Adjust existing catchbasin tops to line and grade as indicated on drawings or as directed by Engineer. B. Use only new brick for adjustment. 3.7 REBUILDING OF EXISTING CATCHBASIN A. Cut suitable openings into existing structures to make connections to drains. Confine cutting to smallest amount possible consistent with good workmanship. B. After installing drains, carefully fit mortar around, close up, and repair structures watertight. 3.8 ABANDONMENT OF EXISTING CATCHBASIN A. Remove entire top of structure, including all tapered or domed portions of walls. Securely plug with Class B concrete, pipes or conduits in remaining portions of structure then fill with acceptable material thoroughly compacted by tamping, as specified for backfill under Section 02210. B. Salvage and clean cast-iron frames, covers, and traps removed from abandoned catchbasins. Deliver salvaged castings to Owner. Castings remain property of Owner. 3.9 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02431 Northampton Drainage Relocation CATCH BASINS 20164277.003A 02431 - 6 THIS PAGE INTENTIONALLY LEFT BLANK CHAIN LINK FENCE AND GATE 02444 - 1 Northampton Drainage Relocation 20164277.003A SECTION 02444 CHAIN-LINK FENCE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Providing chain-link fence, gates and accessories as indicated and specified. 2. Design Criteria: a. Fence heights as indicated with top rail and bottom tension wire. b. Fence heights as indicated with top rail, bottom tension wire. B. Related sections include the following: 1. Section 03300 - Cast-in-Place Concrete 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Submit manufacturer's specifications, drawings, details and fence layout with appurtenances. 2. Submit two samples of fencing materials. Mark or tag each sample and submit 30 days prior to erection of fence. 3. Submit certified test reports with results of tests for fence finish. 4. Submit shop drawings, samples and certificates simultaneously as one complete package. CHAIN LINK FENCE AND GATE 02444 - 2 Northampton Drainage Relocation 20164277.003A 1.4 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610. PART 2 - PRODUCTS 2.1 GENERAL A. Galvanized steel. B. Steel pipe dimensions and weights: ASTM A53, Schedule 40. Dimensions specified are nominal pipe sizes. C. Dimensions and weight tolerances: Plus or minus five percent. D. Zinc Coating: Minimum 2.0 ounces per sq. ft. E. Provide posts with tops of same material, and designed to fit securely over post and carry top rail. Carry apron around outside of post at base of top fitting. F. Ferrous metal fittings, posts, fence, gate framework, and accessories galvanized with heavy coating of 2.0 oz. pure zinc spelter per sq. ft., use hot- dip process. Thinner zinc coatings, electro-galvanizing, zinc paint or cold galvanizing compounds shall not be used as substitute for hot-dipped galvanized finish. G. Fabricate and weld before hot-dip galvanizing. Weld conforming to American Welding Society standards. H. Hot-dip galvanized gate frame, after welding, if bolted or riveted corner fittings not used. j. Single and double leaf swing gates with center bolt, center stop, and automatic backstops. 2.2 FENCE FABRIC A. Galvanized steel chain-link fabric conforming to ASTM A392, with Class 2 zinc coating (2.0 oz. of zinc per sq. ft. of uncoated wire surface); Fabric CHAIN LINK FENCE AND GATE 02444 - 3 Northampton Drainage Relocation 20164277.003A woven in 2-in. mesh from No.9 gage wire in a 6-ft. height with barbed selvages top and bottom. 2.3 TENSION WIRE A. No. 7-gage coil spring steel wire with galvanized finish having minimum of 0.80 oz. of zinc coating per sq. ft. of uncoated wire surface. 2.4 TIE WIRES A. Tie wires, for fastening fence fabric to line posts and rails, not less than No. 6 gage aluminum wire. 2.5 LINE POSTS: A. 2-3/8 in. outside diameter steel pipe weighing not less than 3.65 lb. per ft., or 1-7/8 in. high carbon steel H-beams weighing not less than 2.70 lb. per ft. 2.6 END, CORNER, AND PULL POSTS A. 2-7/8 in. outside diameter steel pipe weighing not less than 5.79 lb. per ft., or 2-1/2 in. square steel tube weighing not less than 5.14 lb. per ft., or 3-1/2 in. by 3-1/2 roll-formed, steel corner section weighing not less than 5.14 lb. per ft. 2.7 GATE POSTS A. 2-7/8 in. outside diameter steel pipe and gate posts, for gate leaves up to and including 6 ft. wide, weighing not less than 5.79 lb. per ft., or 2-1/2 in. square steel tube weighing not less than 5.14 lb. per ft., or 3-1/2 in. by 3-1/2 in. roll- formed, steel corner section weighing not less than 5.14 lb. per ft. B. 4 in. outside diameter steel pipe, gate posts for gate leaves over 6 ft. wide and up to and including 13 ft. wide and weighing not less than 9.10 lb. per ft. C. 6-5/8 in. outside diameter steel pipe, gate posts for gate leaves over 13 ft. wide and up to and including 18 ft. weighing not less than 18.97 lb. per ft. 2.8 RAILINGS A. 1-5/8 in. outside diameter steel pipe with minimum weight of 2.27 lb. per ft. or 1-5/8 in. by 1-1/4 in., 14-gage roll-form section, for top railing and railings for top middle and bottom braces between terminal posts and adjacent line posts. CHAIN LINK FENCE AND GATE 02444 - 4 Northampton Drainage Relocation 20164277.003A 2.9 TRUSS A. 2-7/8 in. diameter steel rod diagonal truss braces between terminal and adjacent line posts and for gate framework. 2.10 FITTINGS A. Heavy-duty malleable iron or pressed steel fittings of suitable size to produce strong construction. 2.11 STRETCHER BARS A. Flat bars with minimum cross section dimensions of 1/4 in. by 3/4 in, full height of fabric, secured with bar bands of minimum 11-gage sheet steel, spaced approximately 15 in. on centers and bolted with 3/8 in. diameter bolts, for attaching fabric to terminal posts. 2.12 GATE LEAF FRAMEWORK A. 1-7/8 in. outside diameter steel pipe weighing 2.72 lb. per ft, minimum. 2.13 GATE HINGES A. Heavy pattern of adequate strength for gate size, with large bearing surfaces for clamping or bolting in position. 2.14 LATCH A. Gates with suitable latch, accessible from both sides and with provision for padlocking. 2.15 GATE PADLOCKS A. Manufacturers: 1. Eaton Corp. Lock & Hardware Div., Yale Marketing Dept., Charlotte, NC; 2. P&F Corbin, Div. of Emhart Corp., Berlin, CT; 3. Best Universal Lock Co., Inc., Indianapolis, IN; 4. Or acceptable equivalent product. B. Solid brass cases, hardened steel shackles, removable core cylinders, and galvanized steel chains attached to shackle by a clevis. CHAIN LINK FENCE AND GATE 02444 - 5 Northampton Drainage Relocation 20164277.003A C. Provide pad locks for each gate. 2.16 CONCRETE FOOTINGS A. Class A concrete, conforming to Section 03300 Cast-In-Place Concrete. 2.17 GROUT A. One part Portland cement and three parts of clean, sharp, well-graded sand with minimum water for proper workability for posts set in solid rock. PART 3 - EXECUTION 3.1 GENERAL A. Examine conditions under which fence and gates are to be installed. Notify Engineer, in writing, of improper conditions of work. B. Do not proceed with work until unsatisfactory conditions have been corrected. C. Verify measurements at site. D. Check location of underground work to make sure fence footings clear utilities and drainage work. E. Do not install fence until final grading is complete and finish elevations are established. F. Do not drive equipment on areas to be landscaped, except as approved by ENGINEER. Areas not accessible from roads shall be protected with heavy wood planking. Remove barricades and protection at completion of project. Repair damaged landscape surfaces. 3.2 INSTALLATION A. Footings: 1. Maintain vertical sides to minimize up-lift. Dispose of excavated material in accordance with Section 02210. 2. Rod and compact concrete around posts. Slope top of footings above level of adjacent grade, and trowel finish. 3. Size: CHAIN LINK FENCE AND GATE 02444 - 6 Northampton Drainage Relocation 20164277.003A a. 6 in. minimum diameter, plus outside dimension of post. b. Set corner, end, pull, and gate posts 42 in. into concrete. c. Set line posts set 36 in. into concrete. d. Total depth of concrete 6 in. greater than required for post embedment. 4. Time of Set: 48-hrs before rails are erected or before fabric is applied or stretched. B. Framing: 1. Install line posts not more than 10 ft. apart. 2. Install pull posts not more than 600 ft. apart where a straight run of fence exceeds 600 ft. and where fence line changes direction by more than 15o but less than 30o. 3. Install corner posts where the fence line changes direction by more than 30o. 4. Set posts in concrete footings, plumb and true to line. 5. Brace and truss end, pull, corner, and gate posts to adjacent line posts. Provide brace to match top rail spaced midway between top rail and tension wire and extending to adjacent line posts. Provide brace to match top rail spaced midway between top rail and tension wire and extending to adjacent line post. Truss diagonally with 5/16 in. dia tension rod with turnbuckle. 6. Fasten top rail to end, pull, gate and corner posts. Pass top rail through fittings of line posts. 7. Provide expansion and contraction joints in top rail for each 100- linear foot of fence. 8. Fasten bottom tension wire to end, pull, gate, corner, and line posts. 9. Maximum area of unbraced fence shall not exceed 1500 square feet. 10. When rock is encountered, set posts into rock a minimum depth of 12 in. for line posts and 18 in. for terminal posts. If solid ledge is encountered without overburden of soil. Provide post holes at least 1 in. greater in diameter than post, fill post holes with concrete work CHAIN LINK FENCE AND GATE 02444 - 7 Northampton Drainage Relocation 20164277.003A post into hole taking care not to cause voids, remove excess concrete and crown remainder at top to shed water. Where solid rock is covered by overburden, do not exceed total setting depth required for setting in earth, grout posts into rock as described. C. Fabric: 1. Place fabric on outside of posts and stretch to avoid bulging or buckling. 2. Fasten at line posts, top rail, and bottom tension wire with aluminum ties. Space ties not more than 15 in. apart on line posts and not more than 24 in. apart on rail and tension wire. 3. Fasten at terminal posts at intervals not exceeding 15 in. using flat or beveled galvanized steel bands with 5/16 in. x 1-1/4 in. galvanized carriage bolts and nuts. 4. Make tie connections on interior side of fence. 5. Provide steel angle metal closures where finished ground surface is more than two inches below bottom tension wire. Bolt steel angle to fence posts, and install reinforcing rods and bracing members as approved. Install rods of accepted length vertically where drainage ditches cross fence line, provide concrete ditch lining and steel reinforcing bar grill. 6. Install gates plumb, level, and secure for full width of opening and hardware adjusted for smooth operation. 3.3 TOUCH-UP AND REPAIR WORK A. Remove and replace fencing which is improperly located or is not true to line, grade and plumb within tolerances as indicated. B. Repair damaged vinyl-coated components as recommended by manufacturer. 3.4 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02444 CHAIN LINK FENCE AND GATE 02444 - 8 Northampton Drainage Relocation 20164277.003A THIS PAGE INTENTIONALLY LEFT BLANK RESTORATION OF Northampton Drainage Relocation DISTURBED AREAS 20164277.003A 02498-1 SECTION 02498 RESTORATION OF DISTURBED AREAS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary General Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. Provide all plant, labor, equipment, appliances and materials, and in performing all operations in connection with restoration to preconstruction conditions of all areas affected by work under this Contract, complete in accordance with the drawings and specifications. 1.3 GENERAL A. Remove and reset or replace all fencing, guardrails, trees, shrubs, lawns, posts, curbing, signs, and other items which interfere with the progress of the work. Shore or guy any utility pole as required by the utility company. B. Contractor shall make arrangements and notify property owners for any work which will affect their properties and indicate what will be done to restore the area after construction is completed. C. Contractor shall notify all utility companies and local, state and federal authorities which will be affected by his work. D. Wherever streets, lawns, or sidewalks within or outside the contract limit lines have been excavated in fulfilling the work required under this Contract, the Contractor shall furnish and install all materials necessary to bring finished surfaces level with the existing adjacent surfaces. E. If, during the progress of the contract work, any water pipe, sewer, conduit, gas line, drain, or other construction is damaged as a result of operations under this Contract, the Contractor shall repair all such damage and restore work to its original condition. F. The Contractor shall restore all disturbed and damaged areas upon completion of the work in the affected area or prior to commencing work on an additional street. Failure to perform such restoration shall be cause for the Owner to RESTORATION OF Northampton Drainage Relocation DISTURBED AREAS 20164277.003A 02498-2 engage outside work forces to do the required work and all related costs shall be deducted from payments due to the Contractor for work performed under this Contract. G. Contractor shall take careful ties to location of bollards (located on north side of 300 Pleasant St) prior to removal. These bollards are more or less located along the existing property line and will need to be restored to the exact same location. H. Any and all property markers that are disturbed or removed by construction shall be replaced and re-set by a land surveyor registered in the Commonwealth of Massachusetts. This work shall be at no cost to the Owner. 1.4 TRENCHES NOT IN PAVED AREAS A. Where the trench occurs adjacent to paved streets in shoulders, sidewalks, or in cross-country areas, the Contractor shall thoroughly consolidate the backfill and shall maintain the surface as the work progresses. If settlement takes place, Contractor shall immediately deposit additional fill to restore the level of the ground. In areas adjacent to streets and highways which are not to be loam and seeded, the top 12-inch layer of trench backfill shall consist of compacted dense-blend gravel borrow or sand and gravel as required to match existing conditions. Trench backfill in unpaved roadways shall have the top 12-inch layer of backfill consist of compacted processed gravel. B. If in the opinion of the Engineer, the top 12-inch layer is unsuitable for use as base course, he may order the Contractor to remove this layer and to provide material that meets specifications. C. Loam and seed or sod work shall be performed as specified on the Drawings. END OF SECTION 02498 PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 1 SECTION 02525 PAVING, SIDEWALKS AND CURBING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. B. Reference is made herein to the Commonwealth of Massachusetts, Department of Public Works, Massachusetts Highway Department, latest edition, hereinafter referred to as the “Massachusetts Highway Department”. All references to method of measurement, basis of payment, and payment items in the standard specifications are hereby deleted. References made to particular sections or paragraphs in the standard specifications shall include all related articles mentioned therein. 1.2 SUMMARY A. In general, the following pavement repairs shall be made: 1. Removal of existing bituminous pavement for trenches. 2. Installation of temporary pavement. 3. Installation of trench pavement repairs. 4. Removal, replacement, and installation of bituminous curb. 5. Milling of bituminous concrete. 6. Placing bituminous concrete overlay. B. Related sections include the following: 1. Section 02210 - Earth Excavation, Backfill, Fill and Grading 1.3 SUBMITTALS PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 2 A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES. 1. Product Data: Submit complete data on materials to be used in construction, including gradation tests for granular base. 2. Design Data: Submit design mix for bituminous base, binder and top course. 3. Material Certificates: Provide copies of materials certificates signed by material producer and Contractor, certifying that each material item complies with, or exceeds, specified requirements. 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400 and as specified. B. Laboratory Testing Required: 1. The density of the Bituminous Concrete Pavement will be determined by using either the following tests; Nuclear Density Gauge Method ASTM D2950 or the Bulk Specific Gravity Method AASHTO-T166. C. Thickness: Test in-place asphalt concrete courses for compliance with requirements for thickness. Repair or remove and replace unacceptable paving as directed by Engineer. In-place compacted thickness will not be acceptable if exceeding following allowable variation from required thickness: 1. Binder Course: 1/4-inch, plus no minus. 2. Surface Course: 1/4-inch, plus no minus. 1.5 PROJECT SITE CONDITIONS/PROJECT DESCRIPTION A. Environmental Requirements: 1. Do not place materials when underlying surface is muddy, frozen, or has frost, snow, or water thereon. 2. Do not place concrete when air temperature at time of placement, or anticipated temperature for following 24 hours, is lower than 40°F or higher than 90°F. 3. Apply prime and tack coats when ambient temperature is above 50 PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 3 deg.F (10 deg.C), and when temperature has not been below 35 deg.F (1 deg.C) for 12 hours immediately prior to application. 4. Base course may be placed when air temperature is above 30 deg.F (-1 deg.C) and rising. 1.6 ROAD PLATES A. Use of steel plates require the Contractor to notify the Owner’s Public Works Department prior to use. If approved, steel plates shall be recessed into the roadway and welded as required. PART 2 - PRODUCTS 2.1 MATERIALS A. Asphalt: 1. Ensure that asphalt replacement conforms to Class I Bituminous Concrete, Type I-1, MHD - 460. 2. Asphalt mixtures shall be within the composition limits for courses in accordance with MHD M3.11.03, and Table A. B. Gravel Subbase 1. Sub-grade material shall be new processed stone conforming to MHD specification M2.01.7 “Dense Graded Crushed Stone for Sub-Base”. PART 3 - EXECUTION 3.1 PREPARATION A. Protection: 1. Existing Roadway: a. Saw cut existing pavement to required width and depth to avoid damage to adjacent pavement, curbs, gutters, or other structures and as indicated on the drawings. B. Surface Preparation: 1. Pavement Subbase: a. The subbase to be placed under pavement shall be of thickness PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 4 shown on Drawings after compaction. Subbase shall be evenly spread and thoroughly compacted in accordance with the Contract Documents. b. The subbase shall be spread in layers not more than 8 - inches thick except the last layer of gravel shall be 4-inches thick, compacted measure. All layers shall be compacted to not less than 95 percent of the maximum dry density of the material as determined by ASTM D1557 Method C at optimum moisture content. c. Complete subbase preparation, including dynamic compaction, for full width before placing surfacing materials. 2. Subgrade: a. Prepare subgrade in accordance with Section 02210. b. Complete subgrade preparation, including dynamic compaction, for full width before placing surface materials. c. Stabilize subgrades in accordance with Section 02210 so that loaded construction vehicles do not cause rutting or displacement when depositing materials. 3. Raising and Adjusting Castings: a. Prior to top course paving, all existing municipally owned catch basin and manhole castings and curb and valve boxes shall be raised, if necessary, to the proper grade by the Contractor. The Contractor shall replace all gate valve boxes which are adjusted with boxes meeting the municipality standards unless the City agrees that the salvaged box is acceptable for reuse. b. Castings owned by private utilities shall be raised by the responsible utility. The Contractor shall be responsible for coordinating this work. Contractor shall provide at least 3 week notification to the private utilities. c. The method of adjusting these castings shall be as follows: Cut around catch basin or manhole castings a minimum of 8 inches from casting. Excavate and if required rebuild up to 12 inches of masonry below the bottom of the casting. Backfill with suitable material and compact to bottom of casting. Place high, early strength cement concrete collar, as directed by the Authority, to approximately 1½ inches below the raised casting grade. Masonry work shall conform to Section 02601 Sewer PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 5 Manholes. d. The method of raising valve boxes shall be as follows: Cut around valve box a minimum of 8 inches from valve box. Excavate as required and raise the valve box. Pour high early strength cement or bituminous concrete collar, as directed, to approximately 1½ inches below the top of the valve box. e. Castings which need to be raised or adjusted to complete final top course full-width paving shall be done immediately prior to paving. 3.2 INSTALLATION A. General 1. Pavement depths shall be as shown on the drawings or as specified herein. B. Permanent Bituminous Pavement: 1. Repair asphalt roads, shoulders, and private driveways or streets, cut by line of trench or otherwise damaged during construction operations. 2. Compact and finish pavement replacement to provide a smooth transition between new and existing surfaces. 3. Where new pavement abuts existing pavement outside the limits of work, saw cut existing pavement full depth for a smooth, regular edge so that new pavement in-fill or new adjoining areas create a neat, straight seam with no feathering. 4. The bituminous paving mixture, equipment, methods of mixing and placing, and the precautions to be observed as to weather, condition of base, etc., shall be in accordance with MHD 460. 5. All paving thicknesses are measured after rolling. Permanent surface courses shall be evenly spread and rolled with a power roller having a minimum weight of 5 tons. 7. Top Course Pavement: a. The top course shall be placed as shown on the drawings or as specified. b. Prior to placement of the top course, the entire surface which PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 6 the top course or modified top course is to be placed shall be broom cleaned and tack coated. c. Prior to placing full width top course a 4 foot wide transition keyway shall be cold planed where transitioning to existing pavement. 8. Pavement Placement: a. Unless otherwise permitted by the Engineer for particular conditions, only machine methods of placing shall be used. Methods other than machine methods may be used, at no additional cost to the Owner. The equipment for spreading and finishing shall be mechanical, self-powered pavers, capable of spreading and finishing the mixture true to line, grade, width and crown. The mixtures shall be placed and compacted only at such times as to permit proper inspection and checking by the Engineer. b. After the paving mixtures have been properly spread, initial and intermediate compaction shall be obtained by the use of steel wheel rollers having a weight of not less than 240 pounds per inch width of tread. c. Final rolling of the pavement shall be performed by a steel wheel roller weighing not less than 285 pounds per inch width of tread at a mix temperature and time sufficient to allow for final smoothing of the surface and thorough compaction. d. Immediately after placement of the new pavement, all joints between the existing and new pavements shall be sealed with bitumen RS-1 and sanded. e. Where there is no backing for the edges of the pavement, the Contractor shall provide a gravel transition. The gravel transition shall be installed immediately after the pavement is placed, shall be feathered and extend a minimum of 18 inches, and shall be compacted using the same equipment as for pavement compaction. The gravel shall be uniformly graded material with a maximum size of 3/8 to ½ inch. The backing installation will be considered incidental to the pavement installation. f. The Contractor shall furnish and install paving to provide transition or aprons for driveways and walkways impacted by new pavement installation. PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 7 C. Pavement Markings: 1. The Contractor shall replace all pavement markings removed or covered-over in carrying out the work, and as directed by the Engineer, no later than 48 hours after completion of overlay pavement. All replacement markings shall match existing markings and shall conform to the latest standards of the municipality or agency having jurisdiction over the roadway. The markings shall be thermoplastic markings, 4-inches wide, white or yellow, single or double lines as required. 2. The Contractor shall provide temporary markings on the temporary pavements where existing markings are removed at no additional cost to the Owner. D. Curb and Gutter Replacement 1. Replace curb and gutter with same material to pre-construction lines and curb sections; except where concrete curb shall be replaced with bituminous concrete curb, unless directed otherwise. Reset granite curb to pre-construction line and grade. 2. Removal and replacement of curbing shall be done in accordance with Sections 501 and 580, as applicable of the MHD Specifications for Highways and Bridges. 3. Provide expansion joints at each intersection with existing curb sections. 4. Use expansion joints one inch wide. a. Fill with expansion joint material and cut to shape of curb section. E. Sidewalk and Driveway Replacement: 1. Gravel sidewalks: a. Gravel sidewalks shall be restored to a condition at least equal to that existing immediately before the work was started. 2. Bituminous concrete sidewalks and driveways: a. Construct in accordance with MHD Section 701, Sidewalks, Wheelchair Ramps and Driveways. b. The subgrade shall be shaped parallel to the proposed surface PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 8 of the sidewalk or driveway and shall be thoroughly rolled and tamped. All depressions occurring shall be filled with suitable material and again rolled or tamped until the surface is smooth and hard in order for a gravel foundation to be placed upon it. c. The sidewalk or driveway shall be a minimum of 2-1/2 compacted inches thick, laid in two equal courses. d. Sidewalk cross slopes cannot exceed 2 percent as required by the Americans with Disabilities Act (ADA). The Contractor shall merge new sidewalk slopes into existing sidewalk slopes as required by ADA. 3. General: a. Valve boxes, manhole frames, and all other castings shall be carefully set to the proposed finished grades. F. Berms and Waterways: 1. Bituminous curbing shall be replaced as directed by the Engineer. Curbing shall be machine layed and conform to grade of roadway and adjacent curb areas. 2. Bituminous berms shall be replaced as directed by the Engineer. Berms shall be machine layed and conform to the grade of the roadways. Berms shall be placed in accordance with MHD Specification 470.20 3. Bituminous waterways which have been disturbed by construction operations shall be repaired or replaced. The waterways shall be repaired and constructed in accordance with the applicable requirements of Section 280 of the MHD Specifications. Waterways shall be placed in two 1-1/2-inch thick courses on a prepared gravel base. Material shall be compacted by tamping or rolling. 3.3 PROTECTION A. Protect replacement work with barricades or other devices as approved by Engineer so that no damage occurs as a result of subsequent construction operations. 1. Repair damages or other irregularities to satisfaction of Engineer, at no additional cost to the Owner, before final acceptance by the Engineer. PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 9 3.4 GUARANTEE A. During the one year guarantee period, the Contractor shall maintain the surfacing and shall promptly fill with similar material any depressions and holes that may occur so as to keep the surfacing in a safe and satisfactory condition for traffic. 3.5 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02525 PAVING, SIDEWALKS Northampton Drainage Relocation AND CURBING 20164277.003A 02525 - 10 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 1 SECTION 02604 DRAIN MANHOLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Providing and constructing manholes as indicated and specified. 2. Base: Precast concrete. Tops accurately shaped by ring forms to suit riser sections. 3. Walls (Risers and Cones): Precast Concrete 4. Top of Cone: Brickwork or reinforced concrete grading rings for adjusting frame to match finished surface not to exceed [12 inch]. 5. Inverts: Provide formed invert channels of concrete. Conform to adjoining pipes size. Curve side inverts and lay out main inverts (where direction changes) in smooth curves of longest possible radius tangent to adjoining pipelines centerline. 6. Frames and Covers: Cast-iron, as indicated or specified. B. Related sections includes the following: 1. Section 02210 - Earth Excavation, Backfill, Fill and Grading 2. Section 03300: Cast-in Place Concrete 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Submit manufacturer's specifications and product data. Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 2 2. Submit manufacturer's written instruction for installing resilient connector. 1.4 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610. PART 2 - PRODUCTS 2.1 MATERIALS A. Precast Concrete: 4000 psi @ 28 days B. Portland Cement: ASTM C150, Type II C. Hydrated Lime: ASTM C207, Type S D. Sand: ASTM C33, Fine Aggregate, except all passes No. 8 sieve. E. Water: Potable F. Brick: ASTM C32, Grade SS, except that mean of five tests for absorption not to exceed eight percent by weight. G. Frames and Covers: Cast Iron minimum Class 25 conforming to ASTM A48, and as follows: 1. Castings to be free from scale, lumps, blisters and sandholes. 2. Machine contact surfaces to prevent rocking. 3. Thoroughly clean and hammer inspect. 4. Frames and grates shall conform to Massachusetts Highway Department Standard Specifications for Highways and Bridges Section M.8.03.0. 5. Capable of withstanding AASHTO H-20 loading unless otherwise indicated or specified. H. Standard Manhole Frames and Covers: 1. Manhole frame and cover shall be Pamrex, ERGO Access Assembly or approved equal. Frame and cover shall be manufactured from Ductile Iron and be 3rd party certified and ISO 9000 approved. Product shall be fully tested in road conditions for a period of at least 2 years. Product design will require that covers are hinged and incorporate a 90-degree blocking system to prevent accidental closure. Cover will allow automatic release Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 3 of back pressure. Frame shall come complete with an open hinge box and a hinge infiltration plug. Covers shall be one-man operable using standard tools and shall be capable of withstanding a test load of 120,000 lbs. Frames shall be circular and shall incorporate a seating ring capable of withstanding surface water inflow and absorbing shock from routine traffic. Product will be available in a 30-inch clear opening. The frame depth shall not exceed 4 inches, and the flange shall incorporate bedding slots and bolt holes. Covers shall have “DRAIN” cast in top. I. Bituminous Waterproofing Material: 1. Refer to Section 07160 for complete information. J. Plastic Coated Steel Steps. Minimum dimensions: Step width 14 inches, distance from manhole wall 5 inches after installation. Equal to: PS2-PF-SL Manhole Steps made by M.A. Industries, Inc., Peachtree City, GA. 1. The copolymer polypropylene conforming to ASTM D4101-82 PP200B33454 with a minimum carbon black content of 1/2% by weight or other demonstrated equivalent sunlight protection system. K. Steps capable of resisting following loads without loosening or damaging: 1. Minimum horizontal pull out load 1600 pounds (800 pounds per leg). 2. Minimum vertical load 800 pounds. 2.2 PRECAST CONCRETE SECTIONS A. The precast bases shall be supported on a compacted level foundation of crushed stone at least 6-inches thick. B. The precast bases shall be manufactured to contain wall openings of the minimum size, to receive the ends of the pipes and such openings shall be accurately set to conform with line and grade of the sewer. Subsequent cutting or tampering in the field, for the purpose of creating new openings or altering existing openings, will not be permitted. Connection of sewer pipe to manholes shall be made using the mechanical connections. C. Precast bases shall be at least 8-inches thick for 6-foot diameter manholes. D. Base to have integral buoyancy collar designed to resist buoyancy forces assuming groundwater depth at rim elevation. Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 4 2.3 PRECAST CONCRETE SECTIONS A. All precast concrete sections shall conform to the ASTM "Tentative Specifications for Precast Reinforced Concrete Manhole Sections," Designation C478 with the following exceptions and additional requirements: 1. The barrel shall be at least 48-inches inside diameter with not less than 6-inch thick wall, or as indicated. 2. Cement: ASTM C150, Type II, otherwise as directed by Engineer. 3. Joints between sections: Butyl rubber-based sealants. 4. Cure by subjecting to saturated steam at temperature between 100 and 130 degrees F. for 12 hours or more. Do not ship sections until at least 5 days after having they have been cast. 5. Cast or drill only two lift holes in each section. 6. Clearly mark date of manufacture and name or trademark of manufacturer on insides of walls on all sections. 7. The concrete for precast manhole risers and tops shall have an average strength of 4,000 psi at 28 days. Strength shall be determined by tests on 6-inch by 12-inch vibrated test cylinders cured in the same manner as the manhole risers and tops, cores cut from the manhole risers and tops, or by other approved methods. Not less than two concrete strength tests shall be made for each 100 linear feet of manhole risers and tops and the test results submitted to the Engineer. Testing may be conducted at the manufacturer's plant or at an approved testing laboratory and shall be the responsibility of the Contractor, at no additional expense to the Owner. 8. Accept on basis of material tests and product inspection. 9. For the precast concrete sections being used, the tops of the bases shall be suitably shaped by means of accurate bell-ring forms to receive the barrel sections. 10. The top conical section shall have a wall thickness not less than 6-inches at the bottom and wall thickness of 8-inches at the top. The conical section shall taper from a minimum of 72-inches diameter to 30-inches diameter at the top. 11. Flat tops and landing platforms shall have a minimum thickness of 8-inches and shall have tongue and groove joints. Reinforcement for flat tops shall be designed for H-20 loading. Shop Drawings showing reinforcement shall be submitted to the Engineer for review. Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 5 12. The Engineer reserves the right to reject any precast section which does not meet these requirements. 13. Manhole top section openings shall be 30-inch diameter. B. Cones and Conical Transitions similar in design and construction to riser sections. Use flat slab tops only where indicated. C. Cast and build into bases during manufacture: 1. Resilient connectors for pipe connections 2. Holes for future pipe connections 3. Buoyancy collar. D. Set steps accurately as indicated. 2.4 JOINTS A. Ends of each length of manhole riser sections and the bottom end of manhole tops, of the cone type, shall be provided with tongue-and-groove ends of concrete formed on machined rings to insure accurate joint surfaces. The joints shall be the type using a butyl-rubber polymer gasket for sealing the joints. All joints shall be provided so as to be watertight under all conditions of service. The ends of risers and cones to be jointed using petroleum resistant joints which shall be designed to enclose the gasket on four surfaces when the joint is in its final position. B. Gaskets: Gaskets for sealing joints shall be of petroleum resistant materials of a special composition having a texture to assure a watertight and permanent seal. The joint sealing gasket shall be of a composition and texture which shall be resistant to sewage, industrial wastes, petroleum products (oil, gasoline, etc) and groundwater, and which will endure permanently under the conditions likely to be imposed by this use. A 6-inch sample of gasket shall be submitted to the Engineer for review. C. Between precast sections: Butyl rubber-based sealants per Type B, AASHTO M198, but no bitumen content. D. Resilient connectors for pipes to precast sections: ASTM C923, and to manufacturer's standards. Do not use connectors using castings and bolts with non- resilient bearing. E. Rubber ring waterstops for use in pipe-to-manhole joints: Rings of resilient material that will fit snugly over pipes, held firmly against pipe surface by means of a mechanical take-up device which when tightened will compress resilient material or by a stretch fit. Waterstop designed and installed so that leakage between pipe and manhole is minimized. Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 6 1. Materials and manufacture of waterstops: ASTM C923. F. Non-shrink mortar for pipe connections to existing manholes: 1. Masterflow 713 Grout made by Master Builders, Cleveland, OH. 2. Five Star Grout made by U.S. Grout Corp., Old Greenwich, CT. 3. Upcon made by Upco Co., Cleveland, OH. 4. Or acceptable equivalent product. 2.5 MIXES A. Mortar for Brickwork: Mix portland cement, hydrated lime and sand. Volume of sand not to exceed three times sum of volumes of cement and lime. Proportion cement and lime; may vary from 1:1/4 for dense, hard burned brick to 1:3/4 for softer brick. Generally mix mortar in proportion of 1:1/2:4-1/2. Use sufficient water to form a workable mixture. PART 3 - EXECUTION 3.1 SETTING PRECAST SECTIONS A. Manhole risers and tops shall be installed using approved butyl-rubber polymer type gasket for sealing joints of manhole risers and tops; jointing shall be performed in accordance with the manufacturer's recommendations, and as approved. Manhole risers and tops shall be installed level and plumb. Water shall not be permitted to rise over newly made joints, nor until after inspection as to their acceptability. All jointing shall be done in a manner to insure watertight joints. Openings shall be provided in the precast concrete manhole risers to receive entering pipes and these openings shall be made at the place of manufacture. Connection of pipes to manholes shall be by means of a flexible manhole sleeve cast into the manhole wall. Sleeves shall be resistant to sewage, industrial wastes, petroleum products, and groundwater. The serrated flange is cast into the manhole base and/or wall to form a tight waterstop. The pipe is secured in the sleeve using a stainless steel strap, clamp, draw bolt and nut. B. Care shall be taken to assure that the openings are made to permit setting of the entering pipe at its correct elevation as indicated or directed. Manhole risers and tops shall be installed so that the manhole steps shall be in alignment. C. All holes in sections used for handling shall be thoroughly plugged with non-shrink grout. Hammer mortar into hole until dense and excess of paste appears, then smooth flush with adjoining surface. Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 7 3.2 LAYING BRICKWORK AND GRADING RINGS A. Moisten bricks, before laying. Moistening grading rings NOT PERMITTED. B. Lay bricks and grading rings in full bed and joint of mortar without subsequent grouting, flushing or filling; bond thoroughly. 3.3 PLASTERING AND CURING BRICK MASONRY A. Plaster outside faces with mortar for brick: 1/4 in. to 3/8 in. thick. B. Moisten brick masonry before application of mortar. C. Spread and trowel plaster carefully. D. Check after hardening by tapping for bond and soundness. E. Remove and replace unbonded and unsound plaster. F. Protect from too rapid drying by moist burlap or as approved. G. Protect from weather and frost. 3.4 JOINTING AND CONNECTIONS A. Use joints between precast sections, and between pipes and precast sections conforming to related standards and manufacturer's instruction. B. Hold rubber ring water stops for pipe-to-manhole firmly against pipe surface by mechanical take-up device to compress resilient material when tightened. Install to minimize leakage. C. Apply non-shrink mortar according to manufacturer's instruction. D. Close openings for future connection with brick masonry bulkhead. 3.5 COATING A. Apply two heavy coats of bituminous waterproofing material to exterior surfaces, by brush or spray according to manufacturer's instructions. 3.6 SETTING FRAMES AND COVERS Northampton Drainage Relocation DRAIN MANHOLES 20164277.003A 02604 - 8 A. Manhole frames shall be set with tops conforming accurately to the grade of the pavement or finished ground surface or as indicated on the Drawings. Frames shall be set concentric with the top of the manhole and in a full bed of mortar so that the space between the top of the brick and mortar and the bottom flange of the frame shall be completely filled and made watertight. A thick ring of mortar extending to the outer edge of the concrete shall be placed all around the bottom flange. The mortar shall be smoothly finished to a height of 4-inches above the flange. B. Manhole covers shall be left in place in the frame on completion of other work at the manholes. 3.7 STUBS IN MANHOLES A. Stubs placed as specified and indicated on the Drawings shall be 3 feet long. The stubs, regardless of size, shall be identical to the adjacent sewer pipe, sealed with a watertight cap. Stubs shall be set accurately to the required line and elevation and be placed in the manhole as indicated on the Drawings. Pipe materials shall correspond to the Specifications for the adjacent installed sewer pipe. 3.8 INSTALLING STEPS A. Embed plastic coated steel steps during casting or attach after casting: Drive into holes formed during casting, or into embedded plastic inserts. 3.9 REJECTED BRICKS A. Remove immediately from work. 3.10 BITUMINOUS WATERPROOFING A. Apply two heavy coats of bituminous waterproofing material to exterior surfaces by brush or spray according to manufacturer's instructions. 3.11 CLEANING A. All excess material including dirt, loose concrete, bricks, grit, stones and any other material, shall be removed from all manholes prior to final review by the Engineer. 3.12 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02601 PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 1 SECTION 02715 PRECAST REINFORCED CONCRETE BOX CULVERT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Furnish all plant, labor, materials and equipment required to construct precast reinforced concrete box culvert complete in place, within the limits and to the lines and grades indicated. 2. Provide design certification, prepared by a Massachusetts Registered Structural Engineer, for the culverts. B. Related sections include the following: 1. Section 02210 Earth Excavation, Backfill and Grading 2. Section 02140 Dewatering 3. Section 02761 Stormwater Bypass Flow Handling 4. Section 03346 Cast-in-place Concrete. 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Submit, prior to fabrication of the box culvert sections, Shop Drawings, a schedule of section lengths, key information for the project. All precast sections furnished under this Contract shall be fabricated in full accordance with the approved Shop Drawings. 2. Submit, prior to fabrication of the precast box culvert, design drawings and calculation stamped by a professional structural PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 2 engineer registered in the Commonwealth of Massachusetts to the Engineer for review. 3. Certificate of Design. 1.4 REFERENCE STANDARDS A. American Society for Testing and Materials (ASTM): 1. ASTM C33 – Standard Specification for Concrete Aggregates. 2. ASTM C150 – Standard Specification for Portland Cement. 3. ASTM C789 – Standard Specification for Precast Reinforced Concrete Box Sections for Culverts, Storm Drains and Sewers. B. Where reference is made to one of the above standards, the revision in effect at the time of bid opening shall apply. 1.5 QUALITY ASSURANCE A. Provide in accordance with Section 01400. 1.6 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610. PART 2 - PRODUCTS 2.1 MATERIALS A. Precast Box Culvert 1. The precast reinforced box culvert shall be made up of sections of monolithically cast concrete. The box sections shall have internal dimensions as indicated and shall have a male and female end with overlap to allow 1-inch diameter neoprene gasket or a joint sealant to be cemented to the joint surface. Successive sections shall be bolted together on the inside surface with a minimum of three 7/8-inch diameter equally spaced and recessed bolts. Bolt holes shall be grouted over after assembly so as to maintain a smooth inside wall surface and in no way restrict the flow in the completed installation. The precast concrete sections shall conform to ASTM C789 and shall be designed for a minimum of HS20 live loading and earth loading as indicated. Lateral pressure shall be taken as 0.50 times the vertical soil pressure in addition to hydrostatic pressure resulting from maximum external water table assumed at finished road surface. PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 3 2. Non-air-entraining Portland cement conform to ASTM C150, Type II or III shall be used. Water reducing admixture shall be used. The use of other admixtures will not be permitted. 3. Fine aggregate shall consist of washed inert natural sand conforming to the requirements of ASTM C33, except for gradation, with a maximum loss of 8.0 percent when subjected to 5 cycles of the soundness test using magnesium sulfate. 4. Coarse aggregate shall consist of well-graded crushed stone or washed gravel conforming to the requirements of ASTM C33, except for gradation, with a maximum loss of 8.0 percent when subjected to 5 cycles of the soundness test using magnesium sulfate. 5. The 28-day compressive strength of the concrete, as indicated by cores cut from the culvert and headwalls shall not be less than 4000 psi. The concrete mass shall be dense and uniform. Minimum reinforcement in the box culvert shall be as required by ASTM C789. 6. The quality of all materials and the finished culvert and headwalls shall be subject to inspection and approval by the Engineer. Such inspection may be made at the place of manufacturer, or on the Work after delivery or at both places and the culvert and headwalls shall be subject to rejection at any time on account of failure to meet any of the specification requirements, even though sample culverts may have been accepted as satisfactory at the place of manufacture. Units rejected after delivery shall be marked for identification and shall be removed from the job at once and replaced at no additional cost to the City. The Contractor shall require the manufacturer’s cooperation in these inspections. 7. The Engineer shall have the right to cut cores from finished culvert for inspection and testing. Cores shall be obtained, capped and sealed in conformity with ASTM C789. Core drilling and filling shall be performed by the precast manufacturer at no additional cost to the City. 8. The Engineer will inspect all precast sections for quality and compliance with ASTM C789 and with the approved manufacturer’s drawings. The Contractor shall inspect all joints for uniformity and ends for squareness and provide a notarized affidavit stating all precast sections meet the requirements of ASTM C789, this Section and the joint design with respect to square ends and uniform joint surfaces. PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 4 9. Pits, blisters, rough spots, breakage and other imperfections may be repaired at no additional cost to the City, subject to the approval of the Engineer, after demonstration that strong and permanent repairs result. Repairs shall be carefully inspected before final approval. Non-shrink cement mortar used for repairs shall have a minimum compressive strength of 4000 psi at the end of 7 days and 6000 psi at the end of 28 days, when tested in 3-inch cylinders. 10. Unsatisfactory or damaged precast sections will be either permanently rejected or returned for repairs. Only that culvert or headwall actually conforming to the specifications and accepted will be listed for approval and shipment. Approved materials will be so stamped or stenciled on the inside before it is shipped. All materials which have been damaged after delivery will be rejected and if such materials have already been installed, they shall be removed and replaced, at no additional cost to the City. Culvert may be rejected for any of the reasons indicated in ASTM C789. 11. The precast box culvert shall be placed on a 12-inch bed of crushed stone. The stone shall be spread upon the prepared subgrade and compacted to the required thickness by rollers, crawler tractors or mechanical tampers subject to the approval of the Engineer. Compaction shall continue until the surface is even and true to the proposed lines and grades. 12. Joints for concrete box culvert shall conform to ASTM C789. The ends of the box sections shall be so formed that when the sections are laid together they will make a continuous line of box sections with a smooth interior free of appreciable irregularities in the flow line. 13. Joint sealant shall conform to Fed. Spec. SS-S-00210. 14. Dampproofing requirements refer to Section 07160 for additional information. PART 3 - EXECUTION 3.1 INSTALLATION A. Crushed stone shall be placed and compacted to give complete vertical and lateral support for the lower section of the culvert as indicated. Before the culvert is lowered into the trench, the ends of the box sections shall be clean and free from dirt. The box culvert shall be installed in full accordance with the manufacturer’s instructions. The box culvert shall be properly aligned in the trench to avoid any possibility of contact with the side of the trench and to permit feeding the gasket. As soon as the tongue is centered in the groove of the box culvert, the section shall be connected, drawn and held together using PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 5 the three 7/8-inch diameter bolts supplied by the manufacturer. Under no circumstances shall crowbars alone be used nor shall any motor-driven equipment be used for the purpose of drawing culvert sections together. Provide a representative of the manufacturer on site at all time during installation to supervise the installation of the culvert. B. Prior to Final Completion of the Work, clean all of the new culvert to remove all dirt, stones, pieces of wood or other material. C. Coat outer surfaces of precast box culvert with two coats of dampproofing, in accordance with manufacturer’s instructions. 3.2 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02715 PRECAST REINFORCED CONCRETE Northampton Drainage Relocation BOX CULVERT 20164277.003A 02715 - 6 THIS PAGE INTENTIONALLY LEFT BLANK STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 1 SECTION 02761 STORMWATER BYPASS FLOW HANDLING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Furnishing all plant, labor, equipment and materials, as well as performing all operations associated with handling bypass flows from the existing system around the work indicated on the Drawings in accordance with these Specifications. 2. Maintaining flow from main pipelines without interruption of service, and maintaining flow in lateral connections with minimal interruption of service. 3. Performing the work in a sequence that is the least disruptive to vehicular and pedestrian traffic and in a manner that shall protect the public from damage to persons and property. B. Related Sections include the following: 1. Section 02210 – Earth Excavation, Backfill, Fill and Grading 2. Section 02140 – Dewatering C. Contractor shall design the bypass flow handling system. 1.3 SUBMITTALS A. Submit the following in accordance with Section 01300– SUBMITTALS PROCEDURES: 1. Shop drawings and/or manufacturer’s descriptive literature indicating materials, equipment and methods to complete bypass flow handling operations. 2. Work plan including the following items: STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 2 a. Location, configuration and cross-country routing of bypass flow handling pipes. b. Staging area(s) for pumps and other equipment. c. Upstream flow collection location and/or bulkheads. d. Downstream discharge location. e. Method of protecting structures that accept discharge flows. f. Locations of individual bypass flow handling systems. g. Sample notification of property owner service shutdown. h. Traffic management plan. i. Roadway crossing details including hose ramps or trench details. j. Noise pollution abatement plan. 3. List of 24-hour emergency telephone numbers at which the Contractor may be reached. B. Contractor shall submit a Certificate of Design (refer to SECTION 01300 – SUBMITTAL PROCEDURES) for the bypass flow handling system and shall be responsible for the design of the following system components: 1. Pumps. (including Redundant Pump required for Culvert Bypass). 2. Generators and power sources. 3. Suction and discharge piping. 4. Temporary pipe supports and anchoring. 5. Pipe plugging and bulkheads. 6. Noise control equipment. 7. Calculation of average and maximum daily flows. 8. Calculations of static lift, friction losses, flow velocity and flow rate. 9. Systems testing and start-up. 10. Maintenance of system for off-construction hours. STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 3 11. Contingency plan and equipment for system failures. C. Contractor shall submit complete documentation of qualifications as specified herein. 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400 and as specified. B. The Contractor designing and installing the bypass flow handling system shall have completed at least five (5) projects of similar size and complexity as this project in the United States within the past three (3) years. Contractor may employ the services of a subcontractor that specializes in this work to fulfill this requirement. C. Rejection of any subcontractor and/or manufacturer by the Engineer due to insufficient qualifications shall not be grounds for modifications to the Contract Documents such as change in scope, time of completion or contract amount. 1.5 DELIVERY, STORAGE AND HANDLING A. Provide in accordance with Section 01610. PART 2 - PRODUCTS 2.1 EQUIPMENT A. The bypass flow handling equipment shall be of sufficient size and material to convey existing flows from one access structure to at least the next access structure immediately downstream of the work without overflow, spillage or discharge to the surrounding environment. a. Brick Culvert base flow (dry weather) is anticipated to range from 0 cfs to 23 cfs. The Brick Culvert peak flow discharge anticipated under a 1-yr (24-hr) & 2-yr (24-hr) storm event is 103 cfs and 133 cfs, respectively. B. Contractor shall be fully equipped to operate and respond to any repair or replacement of the system (24 hours per day and 7 days per week) while the bypass flow handling system is in use. C. Contractor shall incorporate noise reduction equipment to minimize impact on the surrounding environment. Such measures shall include insulated enclosures, hospital grade silencers or mufflers, equipment modifications and/or special equipment to limit noise to eighty (80) dBA at seven (7) feet or sixty (60) dBA at the nearest residence or business. STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 4 D. As part of the bypass flow handling system, special requirements shall apply to the materials used for flow diversion to keep the work zones in the dry when connecting to both the upstream and downstream tie in locations of the existing culvert known as Market Street Brook and labeled as 60” x 68” Brick Arch Culvert within the plan set. Refer to the next section 2.2. 2.2 SPECIAL REQUIREMENTS FOR BYPASS OF EXISTING 60”x68” CULVERT A. Contractor shall refer to Appendix C for the requirements presented in the Army Corp. of Engineers (ACOE) permit approval. Contractor shall comply with all requirements stated in the ACOE permit. B. Contractor shall be limited to the following materials when by-passing the existing flow in the existing 60”x68” culvert: · Metal or wood materials not limited to Steel Sheeting, pressure treated wood lumber, bolts, bracing, brackets, plates, and other components necessary to secure the temporary means of diverting existing flow. · Membrane, rubber, and or tarp materials to supplement the metal and wood materials in order to provide a dry working condition to the maximum extent feasible. · Inflatable Geomembrane Plug (Upstream connection only). C. Contractor shall not be allowed to use the following materials when temporarily diverting the existing flow in the existing 60”x68” culvert: · Sand Bags · Jersey Barriers or concrete obstructions · Any other materials that are considered to be an activity having the effect of fill based on the United States EPA Clean Water Act, Section 404. D. The contractor shall submit a specific plan detailing the by-pass system and a list of materials to be included for the by-pass system intended to be used when temporarily diverting the existing flow in the existing 60”x68” culvert at least four (4) weeks prior to the by-pass. PART 3 – EXECUTION 3.1 PREPARATIONS A. Contractor shall perform all work in accordance with municipal, state and federal requirements. B. Contractor shall obtain relevant permits required to perform work prior to the commencement of construction at no additional cost to the Owner. STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 5 C. Prior to the commencement of construction, Contractor shall perform all possible preparatory work. The Contractor shall, at all times, conduct operations to interfere as little as possible with existing flows. D. Contractor shall verify flow conditions in the existing system prior to the commencement of construction. The Contractor shall have no claim for additional compensation by reason of delay or inconvenience in adapting its operations to the need for maintaining existing flows. E. Prior to start-up of bypass flow handling system, Contractor shall notify, in writing, the Owner within seven (7) days prior to the shut down and twenty- four (24) hours prior to the shut-down. 3.2 GENERAL A. Contractor shall design the layout and routing of the bypass flow handling system to minimize disturbance to public and private land and to maintain access for pedestrians and traffic. B. The Contractor shall maintain traffic throughout the duration of bypass flow handling in accordance with the requirements of the “Manual on Uniform Traffic Control Devices”, latest edition. C. If excavation is required across roadways, all work shall be performed in accordance with municipal and/or state requirements. D. Contractor shall furnish, install, maintain and operate all temporary facilities such as dams, pumping equipment, conduits and all other labor and equipment necessary to intercept the flow before it reaches points where it would interfere with the work. E. Contractor may utilize pipelines in an existing parallel system as an alternative to installing a full bypass flow handling system pending approval by the Engineer and the Owner. Contractor shall submit a Certificate of Design prior to utilizing the parallel system and shall restore the parallel system to pre- construction conditions upon completion of construction. F. Contractor shall design, furnish and install individual bypass flow handling systems for flowing lateral connections. · 24-hr Peak Discharge Stormwater Flows for 1-yr & 2-yr Storm: o DMH-3 to Existing Culvert – 1-yr (8.02 cfs) / 2-yr (9.17 cfs) o CB-4 to Existing Culvert – 1-yr (2.75 cfs) / 2-yr (3.50 cfs) o CB7 to Existing Culvert – 1-yr (1.81 cfs) / 2-yr (2.32 cfs) G. Upon completion of construction, the Contractor shall remove plugging and/or bulkheads in a manner that permits the existing flows to slowly return to pre- construction conditions and prevent surcharging, flooding or causing any other disturbances downstream. STORMWATER Northampton Drainage Relocation BYPASS FLOW HANDLING 20152193.001 02761 - 6 3.3 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 02761 Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 1 SECTION 03346 CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes the following: 1. Specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mix design, placement procedures, and finishes. Headwall slabs, cut-off walls, and wherever cast-in-place concrete is indicated. 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Product Data: For each type of manufactured material and product indicated. 2. Design Mixes: For each concrete mix. 3. Steel Reinforcement Shop Drawings: Include material, grade, bar schedules, stirrup spacing, bent bar diagrams, arrangement, and supports of concrete reinforcement. 4. Material Certificates: Signed by manufacturers certifying that each of the following items complies with requirements: a. Cementitious materials and aggregates. b. Form materials and form-release agents. c. Steel reinforcement and reinforcement accessories. d. Admixtures. e. Curing materials. f. Ready-mix concrete producer. g. Repair materials. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 2 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400 and as specified. B. Ready Mix Producer Qualifications: A firm experienced in manufacturing ready- mixed concrete products complying with ASTM C 94 requirements for production facilities and equipment. C. Testing Agency Qualifications: Contractor shall employ a testing agency, acceptable to the Engineer and qualified according to ASTM C 1077 and ASTM E 329 to conduct the testing indicated, as documented according to ASTM E 548. D. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, each aggregate from one source, and each admixture from the same manufacturer. E. ACI Publications: Comply with the following, unless more stringent provisions are indicated: 1. ACI 301, "Specification for Structural Concrete." 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." 1.5 DELIVERY, STORAGE, AND HANDLING A. Provide in accordance with Section 01610 and as specified. B. Deliver, store, and handle steel reinforcement to prevent bending and damage. PART 2 - PRODUCTS 2.1 FORM-FACING MATERIALS A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit. C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 x 3/4 inch minimum. D. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces. E. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber- reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 3 2.2 STEEL REINFORCEMENT A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed. B. Plain-Steel Wire: ASTM A 82, as drawn. C. Plain-Steel Welded Wire Fabric: ASTM A 185, fabricated from as-drawn steel wire into flat sheets. 2.3 REINFORCEMENT ACCESSORIES A. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire fabric in place. Manufacture bar supports according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast concrete or fiber-reinforced concrete of greater compressive strength than concrete. 2.4 CONCRETE MATERIALS A. Portland Cement: ASTM C 150, Type II. B. Normal-Weight Aggregate: ASTM C 33, uniformly graded. C. Water: Potable and complying with ASTM C 94. 2.5 ADMIXTURES A. General: Admixtures certified by manufacturer to contain not more than 0.1 percent water-soluble chloride ions by mass of cementitious material and to be compatible with other admixtures and cementitious materials. Do not use admixtures containing calcium chloride. B. Air-Entraining Admixture: ASTM C 260. C. Water-Reducing Admixture: ASTM C 494, Type A. D. High-Range, Water-Reducing Admixture (Superplasticizer): ASTM C 494, Type F. E. Water-Reducing and Accelerating Admixture: ASTM C 494, Type E. F. Water-Reducing and Retarding Admixture: ASTM C 494, Type D. 2.6 CURING MATERIALS A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete. This product shall not be used as a substitutiom for curing compounds. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 4 B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth weighing approximately 9 oz./sq. yd. dry. C. Moisture-Retaining Cover: ASTM C 171, polyethylene film. D. Clear, Waterborne, Membrane-Forming Curing and Sealing Compound: ASTM C 1315, Type 1, Class A. 2.7 CONCRETE MIXES A. Prepare design mixes for each type and strength of concrete determined by either laboratory trial mix or field test data bases, as follows: 1. Proportion normal-weight concrete according to ACI 211.1 and ACI 301. 2. Fly ash shall not be used. B. Concrete mixes shall be designed for the classes indicated below and in accordance with the requirements indicated. Design Mix Schedule Class Specified Compressive Strength (psi) Minimum Cement Content (lb/cy) *Maximum Water/ Cementitious Ratio % Air Entrainment A 4,000 565 0.50 5.5+/-1 B 2,000 N/A 0.76 N/A * Total water in mix at time of mixing, including free water in aggregates. 1. Mix Classifications: The design mix classes indicated above shall be used as indicated on the Drawings and as follows: Class A: Use in all areas, unless Class B is indicated. Class B: Whereever low strength concrete fill is indicated. C. Slump Limits: Proportion and design mixes to result in concrete slump at point of placement of 1” to 4”. D. Admixtures: Subject to Engineer’s approval, use admixtures according to manufacturer's written instructions. 2.8 CONCRETE MIXING A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94 and ASTM C 1116, and furnish batch ticket information. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 5 PART 3 - EXECUTION 3.1 FORMWORK A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until concrete structure can support such loads. Tolerance limits shall be per ACI 117 and surface irregularities per ACI 347R. B. Fabricate forms for easy removal without hammering or prying against concrete surfaces. C. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete. D. Retighten forms and bracing before placing concrete, to prevent mortar leaks and maintain proper alignment. E. Coat contact surfaces of forms with form-release agent. 3.2 EMBEDDED ITEMS A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. 3.3 REMOVING AND REUSING FORMS A. General: Formwork, for sides of beams, walls, columns, and similar parts of the Work, that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 48 hours after placing concrete provided concrete is hard enough to not be damaged by form-removal operations and provided curing and protection operations are maintained. B. Clean and repair surfaces of forms to be reused in the Work. 3.4 SHORES AND RESHORES A. Comply with ACI 318, ACI 301, and recommendations in ACI 347R for design, installation, and removal of shoring and reshoring. 3.5 STEEL REINFORCEMENT A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement. B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials. C. Accurately position, support, and secure reinforcement against displacement. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 6 D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces. E. Install welded wire fabric in longest practicable lengths on bar supports spaced to minimize sagging and lap edges and ends of adjoining sheets at least one mesh spacing. 3.6 JOINTS A. General: Construct joints true to line with faces perpendicular to surface plane of concrete. B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer. 1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints, unless otherwise indicated. 2. Form using bulkhead forms with keys, unless otherwise indicated. 3.7 CONCRETE PLACEMENT A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed. B. Do not add water to concrete during delivery, at Project site, or during placement, unless approved in writing by Engineer. C. Deposit concrete continuously or in layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as specified. Deposit concrete to avoid segregation. D. Deposit concrete in forms in horizontal layers to avoid cold joints. 1. Limit drop height of concrete off of chute to 60-inches (1500mm). 2. Use equipment and procedures for consolidating concrete recommended by ACI 309R. E. Cold-Weather Placement: Comply with ACI 306.1. F. Hot-Weather Placement: Place concrete according to recommendations in ACI 305R. 3.8 FINISHING FORMED SURFACES A. The finish of formed surfaces shall proceed concurrently with, or immediately after the repair of surface defects. The selection of finishes shall be as indicated in the table below. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 7 Concrete Finishes (Formed Surfaces)Location Finish Concrete surfaces not exposed to view Rough-Formed Finish Concrete surfaces exposed to view. Smooth-Formed Finish B. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defective areas repaired and patched. C. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defective areas. Remove fins and other projections exceeding 1/8 inch in height. 3.9 CONCRETE PROTECTION AND CURING A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and with recommendations in ACI 305R for hot-weather protection during curing. B. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing by one or a combination of the following methods: C. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, by one or a combination of the following methods: 1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials: a. Water. b. Continuous water-fog spray. c. Absorptive cover, water saturated, and kept continuously wet. Cover concrete surfaces and edges with 12-inch lap over adjacent absorptive covers. 2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture- retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. 3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 8 3.10 CONCRETE SURFACE REPAIRS A. Defective Concrete: Repair and patch defective areas. Submit proposed methods of repair to Engineer for review and approval. Remove and replace concrete that cannot be repaired and patched to Engineer's approval. 3.11 FIELD QUALITY CONTROL A. Testing Agency: Contractor shall employ qualified independent testing and inspecting agency to sample materials, perform tests, and submit test reports during concrete placement according to requirements specified in this Article. B. Testing Services: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements: 1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete, plus one set for each additional 50 cu. yd. or fraction thereof. 2. Slump: ASTM C 143; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mix. 3. Air Content: ASTM C 231, pressure method, for normal-weight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mix. 4. Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 40 deg F and below and when 80 deg F and above, and one test for each composite sample. 5. Unit Weight: ASTM C 567, fresh unit weight of structural lightweight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mix. 6. Compression Test Specimens: ASTM C 31/C 31M; cast and laboratory cure one set of four standard cylinder specimens for each composite sample. 7. Compressive-Strength Tests: ASTM C 39; test one laboratory-cured specimen at 7 days, two at 28 days, and one at 56 days. C. Test results shall be reported in writing via FAX to Engineer, Owner, concrete manufacturer, and Contractor within 48 hours of testing. D. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Engineer. Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 9 3.12 CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 03346 Northampton Drainage Relocation CAST-IN-PLACE CONCRETE 20164277.003A 03346 - 10 THIS PAGE INTENTIONALLY LEFT BLANK Northampton Drainage Relocation BITUMINOUS DAMPPROOFING 20164277.003A 07160 - 1 SECTION 07160 BITUMINOUS DAMPPROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This section includes all operations in connection with the furnishing and application of bituminous dampproofing, including surface preparation and appurtenant work, complete in place. B. Bituminous Dampproofing shall be applied to all exterior concrete surfaces of precast concrete manholes and precast concrete structures. 1.3 SUBMITTALS A. Shop Drawings: Submit the following in accordance with Section 01300 - SUBMITTAL PROCEDURES: 1. Product data for each type of product specified, including data substantiating that materials comply with requirements for each dampproofing material specified. 2. For informational purposes only submit manufacturer’s written and recommended method of application, recommended primer, specified number of coats, coverage or thickness, and recommended protection course. 3. Certification by dampproofing manufacturer that products supplied comply with local regulations controlling use of volatile organic compounds (VOCs). 1.4 QUALITY ASSURANCE A. Provide in accordance with Section 01400 and as specified. Northampton Drainage Relocation BITUMINOUS DAMPPROOFING 20164277.003A 07160 - 2 1.5 PROJECT CONDITIONS A. Substrate: Proceed with dampproofing only after substrate construction and penetrating work have been completed. B. Weather Limitations: Proceed with dampproofing only when existing and forecasted weather conditions will permit work to be performed according to manufacturer's recommendations and warranty requirements. PART 2 - PRODUCTS 2.1 BITUMINOUS DAMPPROOFING MATERIAL A. Bituminous dampproofing materials shall conform to Federal Specification SS-A-701 and shall be Dehydratine 4 as manufactured by W.R. Grace & Company; Tremco; Hydrocide 648 as manufactured by Sonneborn; or approved equal. 2.2 MISCELLANEOUS MATERIALS A. Primer: Asphalt primer complying with ASTM D 41, for asphalt-based dampproofing. B. Glass Fabric: Woven glass fabric, treated with asphalt, complying with ASTM D 1668, Type I. C. Protection Course, Board Type: Premolded, 1/8-inch- (3-mm-) thick, multi- ply, semirigid board, consisting of a mineral-stabilized asphalt core sandwiched between layers of asphalt-saturated felt, and faced on one side with polyethylene film. 1. Available Products: Subject to compliance with requirements, products that may be incorporated in the Work include, but are not limited to, the following: a. Protection Course II; ChemRex, Inc.; Sonneborn Building Products Div. b. Bituthene Asphaltic Hardboard; Grace: W.R. Grace & Co. c. PC-2 Protection Course; Meadows: W.R. Meadows, Inc. d. Or equal. D. Protection Course, Roll Roofing Type: Smooth-surfaced roll roofing, complying with ASTM D 224, Type II. Northampton Drainage Relocation BITUMINOUS DAMPPROOFING 20164277.003A 07160 - 3 PART 3 - EXECUTION 3.1. APPLICATION A. Bituminous dampproofing shall be applied in strict accordance with the printed instructions of the approved manufacturer. The surface must be clean and free of all foreign matter. Do not apply over a frost-covered surface. All cracks, voids, honeycombs, etc., shall be filled and repaired with mortar to provide a sound structural surface. No heating or thinning is required. If thinning is absolutely necessary, use a small amount of mineral spirits. Apply by brush or spray in a continuous unbroken film free from pinholes or other surface breaks. All surfaces to be dampproofed shall receive two coats. Each coat shall dry a minimum of 20 to 24 hours before application of the next coating. The second coat shall be applied perpendicular to the first. Allow a minimum of 48 hours for drying before backfilling. Each coat shall be applied at a rate of 65 square feet per gallon. 3.2. CONTRACT CLOSEOUT A. Provide in accordance with Section 01700. END OF SECTION 07160 Northampton Drainage Relocation BITUMINOUS DAMPPROOFING 20164277.003A 07160 - 4 THIS PAGE INTENTIONALLY LEFT BLANK APPENDIX A Boring Logs PLATE 1Pleasant St Drain Relocation 256 Pleasant St Northampton, MA KLEINFELDER - 215 First Street, Suite 320 | Cambridge, MA 02142 | PH: 617.497.7800 | FAX: 617.498.4630 | www.kleinfelder.com The report and graphics key are an integral part of these logs. All data and interpretations in this log are subject to the explanations and limitations stated in the report. Lines separating strata on the logs represent approximate boundaries only. Actual transitions may be gradual or differ from those shown. No warranty is provided as to the continuity of soil or rock conditions between individual sample locations. Logs represent general soil or rock conditions observed at the point of exploration on the date indicated. In general, Unified Soil Classification System designations presented on the logs were based on visual classification in the field and were modified where appropriate based on gradation and index property testing. Fine grained soils that plot within the hatched area on the Plasticity Chart, and coarse grained soils with between 5% and 12% passing the No. 200 sieve require dual USCS symbols, ie., GW-GM, GP-GM, GW-GC, GP-GC, GC-GM, SW-SM, SP-SM, SW-SC, SP-SC, SC-SM. If sampler is not able to be driven at least 6 inches then 50/X indicates number of blows required to drive the identified sampler X inches with a 140 pound hammer falling 30 inches._ SILTY SANDS, SAND-GRAVEL-SILT MIXTURES CLAYEY SANDS, SAND-GRAVEL-CLAY MIXTURES SW-SM CLAYEY SANDS, SAND-SILT-CLAY MIXTURES CL CL-ML > < < SANDS WITH 5% TO 12% FINES SANDS WITH > 12% FINES SANDS (More than half of coarse fraction is smaller than the #4 sieve)WELL-GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE FINES Cu 4 and/ or 1 Cc 3> CLEAN GRAVEL WITH <5% FINES GRAVELS WITH 5% TO 12% FINES OL CH CLAYEY GRAVELS, GRAVEL-SAND-CLAY MIXTURES GRAVELS WITH > 12% FINES > Cu 4 and 1 Cc 3 >_ _ STANDARD PENETRATION SPLIT SPOON SAMPLER (2 in. (50.8 mm.) outer diameter and 1-3/8 in. (34.9 mm.) inner diameter) _ GM GC GW GP GW-GM GW-GC __ _ INORGANIC CLAYS OF LOW TO MEDIUM PLASTICITY, GRAVELLY CLAYS, SANDY CLAYS, SILTY CLAYS, LEAN CLAYS GRAPHICS KEY < SAMPLE/SAMPLER TYPE GRAPHICS > < < > CLEAN SANDS WITH <5% FINESGRAVELS (More than half of coarse fraction is larger than the #4 sieve)Cu 6 and/ or 1 Cc 3 Cu 6 and/ or 1 Cc 3 > Cu 6 and 1 Cc 3 SC-SM Cu 4 and 1 Cc 3 <_ ORGANIC SILTS & ORGANIC SILTY CLAYS OF LOW PLASTICITY SILTS AND CLAYS (Liquid Limit less than 50) SILTS AND CLAYS (Liquid Limit greater than 50) WELL-GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE OR NO FINES POORLY GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE OR NO FINES MH OH ML GC-GM COARSE GRAINED SOILS (More than half of material is larger than the #200 sieve)UNIFIED SOIL CLASSIFICATION SYSTEM (ASTM D 2487) < Cu 6 and 1 Cc 3 GP-GM GP-GC _ __< > < < > SP SP-SM SP-SC SM SC <_< > WELL-GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE OR NO FINES POORLY GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE OR NO FINES WELL-GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE FINES WELL-GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE CLAY FINES POORLY GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE FINES POORLY GRADED GRAVELS, GRAVEL-SAND MIXTURES WITH LITTLE CLAY FINES SILTY GRAVELS, GRAVEL-SILT-SAND MIXTURES CLAYEY GRAVELS, GRAVEL-SAND-CLAY-SILT MIXTURES WELL-GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE CLAY FINES POORLY GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE CLAY FINES SW SW-SC POORLY GRADED SANDS, SAND-GRAVEL MIXTURES WITH LITTLE FINES Cu 4 and/ or 1 Cc 3> >FINE GRAINED SOILS(More than half of materialis smaller thanthe #200 sieve)INORGANIC SILTS AND VERY FINE SANDS, SILTY OR CLAYEY FINE SANDS, SILTS WITH SLIGHT PLASTICITY ORGANIC CLAYS & ORGANIC SILTS OF MEDIUM-TO-HIGH PLASTICITY INORGANIC CLAYS OF HIGH PLASTICITY, FAT CLAYS INORGANIC SILTS, MICACEOUS OR DIATOMACEOUS FINE SAND OR SILT INORGANIC CLAYS-SILTS OF LOW PLASTICITY, GRAVELLY CLAYS, SANDY CLAYS, SILTY CLAYS, LEAN CLAYS GROUND WATER GRAPHICS OBSERVED SEEPAGE WATER LEVEL (level after exploration completion) WATER LEVEL (level where first observed) WATER LEVEL (additional levels after exploration) NOTES DRAWN BY: CHECKED BY: DATE: REVISED:-PLOTTED: 08/09/2016 11:23 AM BY: SBridgesPROJECT NO.: 20164277 gINT FILE: PROJECTWISE: Pleasant St Drain.gpjgINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2016.GLB [GEO-LEGEND 1 (GRAPHICS KEY) WITH USCS] 2 PLATE CALIFORNIA SAMPLER (# blows/ft) MODIFIED CA SAMPLER (# blows/ft) SPT-N60(# blows/ft) Pleasant St Drain Relocation 256 Pleasant St Northampton, MA KLEINFELDER - 215 First Street, Suite 320 | Cambridge, MA 02142 | PH: 617.497.7800 | FAX: 617.498.4630 | www.kleinfelder.com SOIL DESCRIPTION KEY Boulders Cobbles coarse fine Gravel Sand Fines GRAIN SIZE >12 in. (304.8 mm.) 3 - 12 in. (76.2 - 304.8 mm.)Fist-sized to basketball-sized 3/4 -3 in. (19 - 76.2 mm.)Thumb-sized to fist-sized 0.19 - 0.75 in. (4.8 - 19 mm.)Pea-sized to thumb-sized 0.079 - 0.19 in. (2 - 4.9 mm.)#10 - #4 0.017 - 0.079 in. (0.43 - 2 mm.) #200 - #40 coarse fine medium SIEVE SIZE APPROXIMATE SIZE Larger than basketball-sized>12 in. (304.8 mm.) 3 - 12 in. (76.2 - 304.8 mm.) 3/4 -3 in. (19 - 76.2 mm.) #4 - 3/4 in. (#4 - 19 mm.) Rock salt-sized to pea-sized #40 - #10 Sugar-sized to rock salt-sized 0.0029 - 0.017 in. (0.07 - 0.43 mm.)Flour-sized to sugar-sized Passing #200 <0.0029 in. (<0.07 mm.)Flour-sized and smaller DESCRIPTION Secondary Constituent is Fine Grained Secondary Constituent is Coarse Grained CONSISTENCY <2 >30 Very Soft SPT - N60(# blows / ft) Soft Medium Stiff Very Stiff Hard 2 - 4 4 - 8 8 - 15 15 - 30 VISUAL / MANUAL CRITERIA <500 >8000 4000 - 8000 500 - 1000 1000 - 2000 2000 - 4000 Thumb will penetrate more than 1 inch (25 mm). Extrudes between fingers when squeezed. Thumb will penetrate soil about 1 inch (25 mm). Remolded by light finger pressure. Thumb will penetrate soil about 1/4 inch (6 mm). Remolded by strong finger pressure. Can be imprinted with considerable pressure from thumb. Thumb will not indent soil but readily indented with thumbnail. Thumbnail will not indent soil. UNCONFINED COMPRESSIVE STRENGTH (Qu)(psf) Alternating layers of varying material or color with the layer less than 1/4-in. thick, note thickness. NAME Blue Green Red Green Green Yellow Yellow Yellow Red ABBR GY Y YR Black Purple Purple Blue Red Purple Blue N RP BG G R P PB B NAME ABBR Term of Use <5% With Modifier 5 to <15% 15% Trace <15% 15 to <30% 30% AMOUNT DESCRIPTION Dry Moist Wet FIELD TEST Damp but no visible water Visible free water, usually soil is below water table Absence of moisture, dusty, dry to the touch Rounded Subrounded DESCRIPTION FIELD TEST Moderately Strongly Crumbles or breaks with considerable finger pressure. Will not crumble or break with finger pressure. Crumbles or breaks with handling or slight finger pressure.Weakly None Particles have nearly plane sides but have well-rounded corners and edges. Angular Particles have sharp edges and relatively plane sides with unpolished surfaces. DESCRIPTION Fissured Slickensided Blocky Lensed CRITERIA Weak Strong No visible reaction Violent reaction, with bubbles forming immediately DESCRIPTION FIELD TEST Some reaction, with bubbles forming slowly Stratified Laminated Fracture planes appear polished or glossy, sometimes striated. Alternating layers of varying material or color with layers at least 1/4-in. thick, note thickness. Breaks along definite planes of fracture with little resistance to fracturing. Cohesive soil that can be broken down into small angular lumps which resist further breakdown. Inclusion of small pockets of different soils, such as small lenses of sand scattered through a mass of clay; note thickness. Subangular Particles have smoothly curved sides and no edges. Particles are similar to angular description but have rounded edges. DESCRIPTION CRITERIA A 1/8-in. (3 mm.) thread cannot be rolled at any water content.NPNon-plastic The thread can barely be rolled and the lump or thread cannot be formed when drier than the plastic limit.< 30Low (L) The thread is easy to roll and not much time is required to reach the plastic limit. The thread cannot be rerolled after reaching the plastic limit. The lump or thread crumbles when drier than the plastic limit. It takes considerable time rolling and kneading to reach the plastic limit. The thread can be rerolled several times after reaching the plastic limit. The lump or thread can be formed without crumbling when drier than the plastic limit. 30 - 50 > 50 Medium (M) High (H) RELATIVE DENSITY (%) APPARENT DENSITY 30 - 50 10 - 30 4 - 10 <4 >60 35 - 60 12 - 35 5 - 12 <4 >70 40 - 70 15 - 40 5 - 15 85 - 100 65 - 85 35 - 65 15 - 35 <5 0 - 15 Very Dense Dense Medium Dense >50 Loose Very Loose FROM TERZAGHI AND PECK, 1948 LLDESCRIPTION FIELD TEST MOISTURE CONTENT CONSISTENCY - FINE-GRAINED SOIL FROM TERZAGHI AND PECK, 1948; LAMBE AND WHITMAN, 1969; FHWA, 2002; AND ASTM D2488 SECONDARY CONSTITUENT MUNSELL COLOR ANGULARITY CEMENTATION STRUCTURE REACTION WITH HYDROCHLORIC ACID PLASTICITYAPPARENT / RELATIVE DENSITY - COARSE-GRAINED SOIL GRAIN SIZE DRAWN BY: CHECKED BY: DATE: REVISED:-PLOTTED: 08/09/2016 11:24 AM BY: SBridgesPROJECT NO.: 20164277 gINT FILE: PROJECTWISE: Pleasant St Drain.gpjgINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2016.GLB [GEO-LEGEND 2 (SOIL DESC KEY) REV 072616] GROUNDWATER LEVEL INFORMATION: Groundwater was observed at approximately 9 ft. below ground surface during drilling. GENERAL NOTES: The exploration location and elevation are approximate and were estimated by Kleinfelder. 5" Bituminous pavement over 2" subbase. S1:FILL Poorly graded SAND with Silt (SP-SM): fine-grained, brown, moist, dense, frequent brick, glass and concrete fragments S2a: Top 5" similar to S1 with frequent coal and slag. S2b:Silty SAND (SM): fine-grained, brown, moist S3 Poorly graded SAND (SP): fine-grained, gray, moist, loose, trace silt S4a: Top 9" Poorly graded SAND (SP): fine-grained, mottled gray and reddish brown, moist, medium dense, occasional roots and organic material S4b: Bottom 5" Well-graded SAND with Gravel (SW): fine to coarse-grained, gray, wet, medium dense, subrounded to subangular fine gravel. 1" silt in spoon tip. S5a: Top 11"Silty SAND (SM): fine-grained, gray, wet, loose S5b: Bottom 4" Poorly graded SAND (SP): fine-grained, gray, wet, loose S6: INTERBEDDED SILT and CLAY (CL-ML): medium plasticity, gray, wet, very soft, with occasional fine sand varves. S7: Similar to S6. The boring was terminated at approximately 22 ft. below ground surface. The boring was backfilled with auger cuttings and patched at surface on July 01, 2016. BC=17 18 9 8 BC=2 2 3 3 BC=5 5 4 6 BC=3 6 7 3 BC=2 3 3 2 BC=WOH 1 1 1 BC=WOH WOH WOH 2 17" 10" 9" 14" 15" 24" 24" BORING LOG B-1 PLATE B-1 1 of 1 BORING LOG B-1 LABORATORY RESULTS Lithologic Description PAGE: FIELD EXPLORATION Pleasant St Drain Relocation 256 Pleasant St Northampton, MA KLEINFELDER - 215 First Street, Suite 320 | Cambridge, MA 02142 | PH: 617.497.7800 | FAX: 617.498.4630 | www.kleinfelder.comDry Unit Wt. (pcf)Passing #4 (%)Passing #200 (%)Approximate Ground Surface Elevation (ft.): 119.00 Surface Condition: Bituminous Pavement Logged By: Date Begin - End: Hor.-Vert. Datum: Weather: Drill Crew: Not Available Mobile B-53 D. Feeley / D. Griffen Seaboard 140 lb. Auto - 30 in. -90 degreesPlunge: Drilling Company: Drilling Method: Drilling Equipment: 7/01/2016 4.25 in. I.D.Sunny, 60º F Auger Diameter: B. Straley Hammer Type - Drop: Hollow Stem Auger Additional Tests/RemarksBlow Counts(BC)=Uncorr. Blows/6 in.Liquid LimitPlasticity Index(NP=NonPlastic)Depth (feet)5 10 15 20 25ApproximateElevation (feet)115 110 105 100 95 90 Graphical LogRecovery(NR=No Recovery)USCSSymbolWaterContent (%)CHECKED BY:TF DATE:7/26/2016 DRAWN BY:BJS REVISED:-gINT FILE: PROJECTWISE: Pleasant St Drain.gpjgINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2016.GLB [KLF_BORING/TEST PIT SOIL LOG]PLOTTED: 08/09/2016 11:24 AM BY: SBridgesPROJECT NO.: 20164277Sample Type GROUNDWATER LEVEL INFORMATION: Groundwater was observed at approximately 9.5 ft. below ground surface after drilling completion. GENERAL NOTES: The exploration location and elevation are approximate and were estimated by Kleinfelder. Sand Bentonite Chips Sand 2" SCH 40 Solid PVC Riser 2" SCH 40 Slotted 0.010 PVC Screen 2" Bituminous Pavement S1a: Top 6" FILL Well-graded SAND with Gravel (SW): fine to coarse-grained, brown, moist, subrounded to subangular gravel, one black sand lense. S1b: Bot 7" Poorly graded SAND (SP): fine-grained, reddish brown, moist, with occasional lean clay pockets S2:Silty SAND (SM): brown mottled reddish brown, moist, loose S3a: Similar to S2 except brown S3b: Well-graded SAND (SW): fine to medium-grained, brown, wet, loose, trace coarse sand S4: Poorly graded SAND (SP): fine-grained, gray, wet, loose, trace silt S5: Similar to S4. S6:INTERBEDDED SANDY SILT and CLAY (CL-ML): gray, wet, soft, fine sand S7: INTERBEDDED SILT and CLAY (CL-ML): medium plasticity, gray, wet, very soft, frequent fine sand varves S8: Similar to S7, except soft, and some sand layers are reddish brownmedium plasticity The boring was terminated at approximately 27 ft. below ground surface. The boring was backfilled with on July 01, 2016. BC=10 8 6 6 BC=3 3 3 3 BC=2 2 3 3 BC=2 3 2 4 BC=4 6 7 7 BC=2 2 2 3 BC=WOH WOH 2 2 BC=WOH 2 1 1 13" 14" 12" 16" 12" 13" 24" 24" BORING LOG B-2 PLATE B-2 1 of 1 BORING LOG B-2 LABORATORY RESULTS Lithologic Description PAGE: FIELD EXPLORATION Pleasant St Drain Relocation 256 Pleasant St Northampton, MA KLEINFELDER - 215 First Street, Suite 320 | Cambridge, MA 02142 | PH: 617.497.7800 | FAX: 617.498.4630 | www.kleinfelder.com Completion Method: Flush mount cap in concrete MONITORING WELL CONSTRUCTION*Dry Unit Wt. (pcf)Passing #4 (%)Passing #200 (%)Approximate Ground Surface Elevation (ft.): 120.00 Surface Condition: Bituminous Pavement Logged By: Date Begin - End: Hor.-Vert. Datum: Weather: Drill Crew: Not Available Mobile B-53 D. Feeley / D. Griffen Seaboard 140 lb. Auto - 30 in. -90 degreesPlunge: Drilling Company: Drilling Method: Drilling Equipment: 7/01/2016 4.25 in. I.D.Sunny, 70º F Auger Diameter: B. Straley Hammer Type - Drop: Hollow Stem Auger Blow Counts(BC)=Uncorr. Blows/6 in.Liquid LimitPlasticity Index(NP=NonPlastic)Depth (feet)5 10 15 20 25ApproximateElevation (feet)115 110 105 100 95 Graphical LogRecovery(NR=No Recovery)USCSSymbolWaterContent (%)CHECKED BY:TF DATE:7/26/2016 DRAWN BY:BJS REVISED:-gINT FILE: PROJECTWISE: Pleasant St Drain.gpjgINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2016.GLB [KLF_BORING/TEST PIT SOIL LOG]PLOTTED: 08/09/2016 11:24 AM BY: SBridgesPROJECT NO.: 20164277Sample Type GROUNDWATER LEVEL INFORMATION: Groundwater was observed at approximately 13 ft. below ground surface during drilling. GENERAL NOTES: The exploration location and elevation are approximate and were estimated by Kleinfelder. 3" Bituminous Pavement S1a: Top 4"FILL Poorly graded SAND with Silt (SP-SM): brown, moist S1b: 7" Poorly graded SAND (SP): reddish brown, moist, trace silt, trace gravel S1c: 4"CLAY (CL): medium plasticity, gray, moist S1d: Bottom 4" Well-graded SAND (SW): fine to coarse-grained, reddish brown, moist, trace silt, trace gravel S2: Poorly graded SAND (SP): fine-grained, reddish brown, moist, very loose S3: Similar to S2. S4a: Top 6" similar to S2. S4b: Bottom 11" SILT (ML): non-plastic, olive brown, moist, trace sand S5a: Top 5" similar to S4b with frequent dark brown organic silt pockets.trace sand S5b: Bottom 15" Sandy SILT (ML): non-plastic, black, moist, fine grained sand, organic odor. S6a: Top 10" similar to S5b grading to Silty SAND with Gravel (SM): fine-grained, dark brown, wet, occasional wood S6b: 1" gray poorly graded fine sand (SP) over 1" Sandy SILT (ML): low plasticity, mottled red brown and gray, wet S7: Poorly graded SAND (SP): fine-grained, gray and reddish brown, wet, loose, with occasional lean clay lenses S8:INTERBEDDED SILT and CLAY (CL-ML): medium plasticity, gray, dark gray and reddish brown, wet, soft, with interbedded lenses of fine sand The boring was terminated at approximately 22 ft. below ground surface. The boring was backfilled with auger cuttings and patched at surface on July 01, 2016. BC=3 6 5 4 BC=2 1 1 2 BC=2 1 2 1 BC=1 2 1 1 BC=WOH 1 2 2 BC=3 5 3 3 BC=3 4 3 4 BC=2 2 2 1 19" 12" 16" 17" 20" 12" 15" 24" BORING LOG B-3 PLATE B-3 1 of 1 BORING LOG B-3 LABORATORY RESULTS Lithologic Description PAGE: FIELD EXPLORATION Pleasant St Drain Relocation 256 Pleasant St Northampton, MA KLEINFELDER - 215 First Street, Suite 320 | Cambridge, MA 02142 | PH: 617.497.7800 | FAX: 617.498.4630 | www.kleinfelder.comDry Unit Wt. (pcf)Passing #4 (%)Passing #200 (%)Approximate Ground Surface Elevation (ft.): 122.00 Surface Condition: Bituminous Pavement Logged By: Date Begin - End: Hor.-Vert. Datum: Weather: Drill Crew: Not Available Mobile B-53 D. Feeley / D. Griffen Seaboard 140 lb. Auto - 30 in. -90 degreesPlunge: Drilling Company: Drilling Method: Drilling Equipment: 7/01/2016 4.25 in. I.D.Sunny, 80º F Auger Diameter: B. Straley Hammer Type - Drop: Hollow Stem Auger Additional Tests/RemarksBlow Counts(BC)=Uncorr. Blows/6 in.Liquid LimitPlasticity Index(NP=NonPlastic)Depth (feet)5 10 15 20 25ApproximateElevation (feet)120 115 110 105 100 95 Graphical LogRecovery(NR=No Recovery)USCSSymbolWaterContent (%)CHECKED BY:TF DATE:7/26/2016 DRAWN BY:BJS REVISED:-gINT FILE: PROJECTWISE: Pleasant St Drain.gpjgINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2016.GLB [KLF_BORING/TEST PIT SOIL LOG]PLOTTED: 08/09/2016 11:24 AM BY: SBridgesPROJECT NO.: 20164277Sample Type LOG OF BORING NL-1 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/2/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 27' GROUND SURFACE ELEV. 122.5' B-53 Truck Mounted Rig TYPE BIT Roller Bit SIZE &TYPE OF CORE BARREL CASING 3" N/A DISTURBED 7 FIRST COMPL. HR. CASING HAMM. WEIGHT 300 lbs. DROP -- UNDISTURBED None -- -- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION North of existing 2-1/2 story brick building SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 7/12/7/14 10/24 S-1 2" ASPHALT ASPHALT (0-2') Top 1": Medium dense, dark gray, fine SAND, little medium sand, trace(+) silt, FINE SAND trace gravel, dry Bottom 9": Medium dense, brown, fine SAND, little medium sand, trace(-) silt, moist 2/2/12/14 10/24 S-2 Top 5": Medium dense, gray, fine SAND and SILT, trace medium sand, damp (2-4") Bottom 5": Medium dense, brown, fine to medium SAND, trace coarse sand, trace(-) silt, moist 5 12/9/12/26 9/24 S-3 Medium dense, brown, fine to medium SAND, trace(+) coarse sand, trace(-) silt, dry (5-7') 10 1 9/10/15/17 9/24 S-4 Medium dense, brown, fine to medium SAND, trace coarse sand, trace silt (10-12') 15 9/13/23/37 12/24 S-5 Dense, brown, fine SAND, some medium sand, trace(-) silt (15-17') 20 20' 2/1/3/4 24/24 S-6 Soft, gray, varved SILT and CLAY, trace fine sand VARVED 0.20 tsf (TV) (20-22')SILT AND CLAY 0.203 tsf (PP) 25 1/2/1/2 18/24 S-7 Soft, gray, varved SILT and CLAY, trace fine sand 0.17 tsf (TV) (25-27')0.156 tsf (PP) End of exploration at 27' Remarks: 1. Started drilling with roller bit and wash at 10'. O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety 12/2/2014 SAMPLES DESCRIPTION LOG OF BORING NL-2 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/2/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 22' GROUND SURFACE ELEV. 122' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 7 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None 20'1 SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION East of existing 2-1/2 story brick building SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 15/15/15/15 12/24 S-1 2" ASPHALT ASPHALT (0-2') Dense, red-brown, fine to medium SAND, trace coarse sand, trace(+) silt, dry FILL 5/5/3/4 10/24 S-2 Loose, red-brown, fine to medium SAND, trace(+) coarse sand, trace(-) silt, dry (3-5')1 5 2/3/3/3 7/24 S-3 Loose, red-brown, fine to medium SAND, trace coarse sand, trace(-) silt, dry (5-7') 3/3/4/4 11/24 S-4 Loose, red-brown, fine to medium SAND, trace coarse sand, trace(-) silt, dry (7-9') 10 10' 3/7/9/10 14/24 S-5 Medium dense, dark gray-brown, SILT and ORGANICS (roots, wood), damp ORGANICS 2 (10-12') 12' FINE SAND 15 12/21/27/42 0/24 S-6 NO RECOVERY (15-17') 23/33/33/20 9/24 S-7 Very dense, brown, fine SAND, trace(+) silt, damp (17-19') 19' 3 VARVED 20 SILT AND CLAY 4/3/2/2 12/24 S-8 Medium, gray, varved SILT and CLAY, trace fine sand, wet 0.12 tsf (TV) (20-22')0.169 tsf (PP) End of exploration at 22' 25 Remarks: 1. Concrete encountered at 4'. Offset drilling by ~12'. 2. Approximate 1" thick sand layer near bottom of sample S-5. 3. Drilling became easier at 19'. Likely beginning of clay layer. Safety DESCRIPTION 12/2/2014 SAMPLES O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) 8.5' LOG OF BORING NL-3 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/2/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 24' GROUND SURFACE ELEV. 122.5' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 10 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None 12.5 -- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION East of concrete pad (building foundation/remains) SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FILL 8/22/12/10 11/24 S-1 Dense, brown, fine SAND, trace medium to coarse sand, trace(-) silt, moist (1-3') 6/7/5/7 14/24 S-2 Medium dense, brown, fine SAND, trace medium to coarse sand, trace(-) silt, moist (3-5') 5 4/4/4/5 8/24 S-3 Top 6": Loose, brown, fine SAND, trace medium to coarse sand, trace(-) silt, moist (5-7') Bottom 2": Medium, gray, SILT and CLAY, trace medium sand, moist 3/4/5/6 8/24 S-4 Top 7": Stiff, gray, SILT and CLAY, trace medium sand, trace(-) coarse sand, moist (7-9') Bottom 1": Loose, light brown, fine SAND, little silt, trace(-) organics (roots), moist 10 3/3/5/7 18/24 S-5 Top 12": Medium, gray with rust blotches, SILT and CLAY, trace(-) organics (roots), (10-12') moist Bottom 6": Loose, dark gray, SILT, some organics (roots), moist 11.5' SILT AND SAND, 5/6/7/9 17/24 S-6 Top 4": Medium dense, dark gray, SILT, little fine sand, trace organics (roots), moist SOME ORGANICS (12-14') Bottom 13": Medium dense, gray, fine SAND, little organics (roots & wood), 13' trace silt, wet FINE SAND 15 5/10/8/7 9/24 S-7 Top 4": Medium dense, gray-brown, fine SAND and SILT, wet (15-17') Bottom 5": Medium dense, gray-brown, medium SAND, little fine sand, trace coarse sand, trace gravel, trace(-) silt, wet 5/10/30/30 12/24 S-8 Dense, gray, fine SAND, trace(-) silt, wet (17-19')1 20 3/4/5/5 18/24 S-9 Top 5": Loose, gray, fine SAND, trace silt, wet 0.10 tsf (TV) (20-22') Bottom 13": Stiff, gray, varved SILT and CLAY, trace fine sand, wet 21' 0.231 tsf (PP) VARVED SILT AND CLAY 3/3/4/4 20/24 S-10 Medium, gray, varved SILT and CLAY, trace fine sand, wet 0.20 tsf (TV) (22-24')0.225 tsf (PP) End of exploration at 24' 25 Remarks: 1. Approximately 1" thick clay varves near center of sample 12/2/2014 Safety SAMPLES DESCRIPTION O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- LOG OF BORING NL-4 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/2/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 22' GROUND SURFACE ELEV. 121' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 7 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None 10'-- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Eastern portion of site SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FINE SAND 6/12/15/15 14/24 S-1 Medium dense, orange-brown, fine SAND, trace medium to coarse sand, trace silt, (1-3') moist 12/12/10/10 16/24 S-2 Medium dense, orange-brown, fine SAND, trace(+) coarse sand, trace medium sand, (3-5') trace silt, moist 5 5/5/5/8 12/24 S-3 Medium dense, brown, fine SAND, little medium sand, trace(+) coarse sand (5-7') trace(-) silt, moist 10 10' 4/10/15/18 9/24 S-4 Medium dense, brown, medium to coarse SAND, little fine gravel, trace fine sand, MEDIUM TO (10-12') trace(-) silt, wet COARSE SAND 1 2 15 15' 5/10/14/8 10/24 S-5 Medium dense, gray, fine SAND, trace silt, wet FINE SAND (15-17') 17' 5/4/7/7 14/24 S-6 Stiff, gray, varved SILT and CLAY, trace fine sand, wet VARVED 0.20 tsf (TV) (17-19')SILT AND CLAY 0.194 tsf (PP) 20 1/1/2/2 14/24 S-7 Soft, gray, varved SILT and CLAY, trace fine sand, wet 0.10 tsf (TV) (20-22')0.219 tsf (PP) End of exploration at 22' 25 Remarks: 1. Dark brown silt cuttings encountered from 12' to 13'. 2. Gravel and dark brown silt cuttings encountered from 13' to 14.5'. SAMPLES DESCRIPTION 12/2/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety LOG OF BORING NL-5 Page 1 OF 4 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 102' GROUND SURFACE ELEV. 121.5' B-53 Truck Mounted Rig TYPE BIT Roller Bit SIZE &TYPE OF CORE BARREL CASING 4" N/A DISTURBED 18 FIRST COMPL. HR. CASING HAMM. WEIGHT 300 lbs. DROP -- UNDISTURBED 2 -- -- SAMPLER: 2" O.D. Split Spoon Rod N (2 3/8" O.D.)BORING LOCATION Approximate center of site SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FILL 15/16/13/14 12/24 S-1 Top 4": Medium dense, dark brown, fine SAND, little debris (ash, coal), trace silt, damp (1-3') Bottom 8": Medium dense, brown, fine SAND, trace medium sand, trace(-) coarse sand, trace(-) silt, damp 14/8/7/5 6/24 S-2 Medium dense, brown, fine SAND, trace medium sand, trace fine gravel, (3-5') trace(-) coarse sand, trace(-) silt, damp 5 3/4/3/4 8/24 S-3 Loose, brown, fine SAND, trace medium to coarse sand, trace silt, damp (5-7') 10 1 2/6/7/6 10/24 S-4 Top 6": Medium dense, brown, fine SAND, trace medium sand, trace silt, (10-12') trace(-) fine gravel Bottom 4": Medium dense, gray-brown, SILT, trace fine sand 12' 6/10/14/14 11/24 S-5 Top 4": Medium dense, brown-gray, fine SAND, trace silt, FINE SAND (12-14') trace(-) organics (roots, leaves) Next 4": Medium dense, gray, fine SAND, trace medium sand, trace silt Bottom 3": Medium dense, brown with rust blotching, fine and medium SAND, trace silt 15 7/10/7/8 11/24 S-6 Medium dense, gray, fine SAND, some silt (15-17') 13/22/13/13 0/24 S-7 NO RECOVERY (17-19') 20 20' 1/2/2/3 24/24 S-8 Soft, gray, varved SILT and CLAY, trace fine sand VARVED 0.10 tsf (TV) (20-22')SILT AND CLAY 0.203 tsf (PP) 25 WOH for 24/24 S-9 Very soft, gray, varved SILT and CLAY, trace fine sand 0.15 tsf (TV) 18"/3 (25-27')0.109 tsf (PP) Remarks: 1. Started drilling with roller bit and wash at 10'. 2. Started open-hole drilling at 30'. 3. Shelby tube samples taken at 35-37' (S-12) and 50-52' (S-16). 12/4/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety SAMPLES DESCRIPTION LOG OF BORING NL-5 Sheet 2 of 4 Project No. 69-08-01 SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6IN. VARVED SILT AND CLAY 30 2 N/A 0/24 S-10 Shelby Tube - NO RECOVERY (30-32') WOH for 24/24 S-11 Very soft, gray, varved SILT and CLAY, trace fine sand 0.12 tsf (TV) 12"/2/4 (32-34')0.15 tsf (PP) 35 N/A 24/24 S-12 Shelby Tube 3 (35-37') WOH for 24/24 S-13 Very soft, gray, varved SILT and CLAY, trace fine sand 0.15 tsf (TV) 24" (37-39')0.172 tsf (PP) 40 2/3/4/4 24/24 S-14 Medium, gray, varved SILT and CLAY, trace fine sand 0.09 tsf (TV) (40-42')0.088 tsf (PP) 45 WOH for 24/24 S-15 Stiff, gray, varved SILT and CLAY, trace fine sand 0.02 tsf (TV) 6"/3/3/4 (45-47')0.063 tsf (PP) 50 N/A 24/24 S-16 Shelby Tube 3 (50-52') WOH for 24/24 S-17 Medium, gray, varved SILT and CLAY, trace fine sand 0.14 tsf (TV) 6"/4/4/6 (52-54')0.109 tsf (PP) 55 60 WOR for 24/24 S-18 Very soft, gray, varved SILT and CLAY, trace fine sand 0.15 tsf (TV) 12"/2/4 (60-62')0.181 tsf (PP) O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS SAMPLES DESCRIPTION LOG OF BORING NL-5 Sheet 3 of 4 Project No. 69-08-01 SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6IN. VARVED SILT AND CLAY 65 70 WOR for 24/24 S-19 Very soft, gray, varved SILT and CLAY, trace fine sand 0.09 tsf (TV) 24" (70-72')0.156 tsf (PP) 75 80 WOR for 24/24 S-20 Very soft, purple-gray, varved SILT and CLAY, trace fine sand 0.20 tsf (TV) 24" (80-82')0.175 tsf (PP) 85 90 WOR for 24/24 S-21 Very soft, purple-gray, varved SILT and CLAY, trace fine sand 0.17 tsf (TV) 24" (90-92')0.20 tsf (PP) 95 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS SAMPLES DESCRIPTION LOG OF BORING NL-5 Sheet 4 of 4 Project No. 69-08-01 SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6IN. VARVED SILT AND CLAY 100 WOR for 24/24 S-22 Very soft, brown-gray, varved SILT and CLAY 0.15 tsf (TV) 24" 100-102'0.231 tsf (PP) End of exploration at 102' 105 110 115 120 125 130 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS SAMPLES DESCRIPTION LOG OF BORING NL-6 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 22' GROUND SURFACE ELEV. 122' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 8 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None 17'-- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Approximate center portion of site SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 6/9/8/6 12/24 S-1 Top 6": Medium dense, red-brown, fine SAND, trace medium to coarse sand, FILL (0-2') trace silt, moist Bottom 6": Medium dense, yellow-brown, fine SAND, trace medium sand, trace silt, moist 6/10/10/8 14/24 S-2 Top 6": Medium dense, yellow-brown, fine SAND, trace medium sand, trace silt, moist (2-4') Bottom 8": Medium dense, red-brown, fine SAND, trace silt, moist 5 2/2/3/4 14/24 S-3 Top 11": Loose, brown, fine SAND and SILT, trace debris (brick), moist (5-7') Bottom 3": Loose, red-brown, fine SAND, trace medium sand, trace silt, moist 6.5' FINE SAND 3/3/3/4 15/24 S-4 Loose, red-brown, fine SAND, trace medium sand, trace silt, moist (7-9') 10 3/5/5/5 12/24 S-5 Loose brown-red, fine SAND, trace medium sand, trace silt, trace(-) coarse sand, damp (10-12') 15 4/5/6/11 14/24 S-6 Medium dense, gray, fine SAND, trace silt, trace(-) medium to coarse sand, wet (15-17') 10/10/11/9 20/24 S-7 Top 10": Medium dense, gray, fine SAND, trace silt, trace(-) medium sand, wet (17-19') Bottom 10": Medium dense, brown-gray, fine and medium SAND, trace coarse sand, 18' trace(-) silt, wet FINE AND MEDIUM SAND 20 20' 1/1/1/2 20/24 S-8 Soft, gray, varved SILT and CLAY, trace fine sand, wet VARVED 0.25 tsf (TV) (20-22')SILT AND CLAY 0.125 tsf (PP) End of exploration at 22' 25 Remarks: DESCRIPTION O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety 12/3/2014 SAMPLES LOG OF BORING NL-7 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 17' GROUND SURFACE ELEV. 119.5' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 6 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None 12'-- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Southern edge of property SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 3" ASPHALT ASPHALT FILL 22/27/25/30 12/24 S-1 Very dense, red-brown, fine SAND, trace medium sand, trace fine gravel, (1-3') trace silt, moist 23/10/8/7 20/24 S-2 Medium dense, red-brown, fine SAND, trace(+) coarse gravel, trace silt, (3-5') trace(-) medium sand, moist 5 1/10/5/3 8/24 S-3 Top 4": Medium dense, red-brown, fine SAND, trace silt, trace(-) medium sand, moist (5-7') Bottom 4": Medium dense, brown, fine SAND and coarse GRAVEL, little medium sand, trace(+) silt, moist 3/2/2/4 22/24 S-4 Top 3": Very loose, brown, fine and medium SAND, trace coarse gravel, (7-9') trace(+) silt, moist Next 14": Very loose, gray-brown with rust mottling, SILT, trace fine sand, moist Bottom 5": Very loose, dark brown with rust mottling, SILT, trace fine sand, trace organics (roots), trace debris (ash), moist 10 10' 10/16/21/17 14/24 S-5 Dense, gray, fine SAND, trace(+) silt, trace organics (roots), wet FINE SAND 1 (10-12') 15 15' 2/1/2/2 18/24 S-6 Soft, gray, varved SILT and CLAY, trace fine sand, wet VARVED 0.15 tsf (TV) (15-17')SILT AND CLAY 0.169 tsf (PP) End of exploration at 17' 20 25 Remarks: 1. Organics present only in bottom 4" of sample. SAMPLES DESCRIPTION 12/3/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety LOG OF BORING NL-8 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 5' GROUND SURFACE ELEV. 123' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 1 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None -- -- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Pleasant Street right of way entrance SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FILL 10/10/8/9 18/24 S-1 Top 11": Medium dense, dark brown, SILT, trace fine sand, moist (1-3') Next 4": Medium dense, red-brown, fine SAND, trace medium sand, trace(-) silt, moist Bottom 3": Medium dense, brown, SILT, trace fine sand, moist 9/12/14/12 14/24 S-2 SAMPLE NOT RETAINED 1 (3-5') 5 End of exploration at 5' 10 15 20 25 Remarks: 2. Drilling terminated at 5' due to complaint from owner of adjacent property. Sample not retained. SAMPLES DESCRIPTION 12/3/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety LOG OF BORING NL-9 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 9' GROUND SURFACE ELEV. 123.5' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 4 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None -- -- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Northeast corner of property, by existing lumber storage shed SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FILL 6/14/16/14 16/24 S-1 Top 4": Medium dense, brown, fine SAND, little silt, trace coarse sand, moist 1 (1-3') Next 8": Medium dense, brown-dark brown, fine SAND, some silt, moist Bottom 4": Medium dense, red-brown, fine SAND, trace medium sand, trace silt, moist 8/6/5/4 14/24 S-2 Top 9": Medium dense, red-brown, fine SAND, trace medium sand, trace silt, moist (3-5') Bottom 5": Medium dense, gray-brown, SILT, trace organics (roots), trace(-) fine sand, wet 5 4/4/4/5 14/24 S-3 Loose, gray-brown, SILT, some fine sand, wet (5-7') 5/5/5/6 10/24 S-4 Top 2": Loose, gray-brown, SILT and CLAY, little fine sand, wet (7-9') Bottom 8": Loose, gray-brown, SILT, little fine sand, trace(-) organics (roots), wet 2 End of exploration at 9' 10 15 20 25 Remarks: 1. Infiltration test performed adjacent to bore hole. 2. Organics present only in bottom 2" of sample. SAMPLES DESCRIPTION 12/3/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety LOG OF BORING NL-10 Page 1 OF 1 PROJECT : Northampton Lumber Yard LOCATION: Northampton, MA PROJECT NO. : 69-08-01 DRILLING CONTRACTOR FOREMAN Mike DATE STARTED 12/3/2014 DATE FINISHED Seaboard Environmental Drilling HELPER Doug DRILLING EQUIPMENT COMPLETION DEPTH 9' GROUND SURFACE ELEV. 121.5' B-53 Truck Mounted Rig TYPE BIT Hollow Stem Auger SIZE &TYPE OF CORE BARREL CASING N/A N/A DISTURBED 4 FIRST COMPL. HR. CASING HAMM. WEIGHT N/A DROP N/A UNDISTURBED None -- -- SAMPLER: 2" O.D. Split Spoon Rod A (1 5/8" O.D.)BORING LOCATION Eastern portion of site, proposed parking area SAMPLER HAMMER WEIGHT DROP 140 lbs. 30" (Wire Line) ENGINEER/GEOLOGIST Dustin Humphrey SAMPLES DEPTH PENETR. REC. TYPE/SOIL REMARKS FT. RESIST. IN. NO.DESCRIPTION BL/6 IN. 2" ASPHALT ASPHALT FILL 10/17/9/7 17/24 S-1 Top 1": Medium dense, orange-brown, fine SAND, trace coarse sand, trace silt, moist 1 (1-3') Bottom 16": Medium dense, yellow-brown, fine SAND, some silt, moist 6/5/4/4 7/24 S-2 Loose, yellow-brown, fine SAND, some silt, moist (3-5') 5 3/3/6/10 16/24 S-3 Top 6": Loose, yellow-brown, fine SAND, some silt, moist (5-7') Bottom 10": Loose, brown, fine SAND, some silt, trace organics (roots), trace debris (ash), moist 6/8/9/9 18/24 S-4 Top 2": Medium dense, brown, fine SAND, some silt, moist (7-9') Bottom 16": Medium dense, brown, fine SAND, trace(+) silt, trace coarse sand, moist 2 End of exploration at 9' 10 15 20 25 Remarks: 1. Infiltration test performed adjacent to bore hole. 2. Coarse sand present only in bottom 2" of sample. SAMPLES DESCRIPTION 12/3/2014 O'REILLY, TALBOT & OKUN ASSOCIATES, INC. ENVIRONMENTAL AND GEOTECHNICAL ENGINEERING CONSULTANTS No. OF SAMPLES WATER LEVEL (FT.) -- Safety BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.0 1 5 2 5-10' 0.1 10 3 10-15' 0.0 15 4 15-20' 0.1 2 20 25 30 35 40 NA (Geoprobe) 4" grayish-brown gravel and coarse sand; 10" medium brown coarse sand, wet; 12" medium brown fine sand with gravel, wet; 2" gray silty sand, wet Sand pack 2. Two-inch diameter monitoring well installed. 10' of slotted screen 10 to 20' and 10' of solid PVC riser to surface. Finished with flush mount road box. Native Fill Bentonite seal Well screen SOIL BORING and MONITORING WELL INSTALLATION LOG Soil Descriptions NA (Geoprobe) NA (Geoprobe) NA (Geoprobe) SB-1/MW-1 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC 7/11/2013 Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Well As Built 7" asphalt; 6" medium to dark brown coarse sand with gravel; 4" dark brown, fine-medium sand; 22" light brown fine sand and silt 60/37" 60/31" 60/28" 60/37" End of borehole 20 feet 12" medium brown medium sand; 4" medium brown silty sand; 15" brown/gray/white gravel with rocks and coarse sand Gray silty sand with some clay, wet 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. Groundwater table BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.0 1 5 2 5-10' 0.0 10 3 10-15' 0.0 15 4 15-20' 0.0 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-3/MW-2 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/32" NA (Geoprobe) 4" asphalt; 16" medium to dark brown gravel; 12" damp, medium brown coarse sand 60/18" NA (Geoprobe) 18" medium brown, medium-coarse sand, damp 60/20" NA (Geoprobe) 4" medium brown, medium-coarse sand, damp; 3" wood framents; 6" wet gray silt; 7" wet brownish-gray silt 60/36" NA (Geoprobe) 12" coarse brown sand and gravel, wet; 24" grayish- brown fine sand, wet End of borehole 20 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Two-inch diameter monitoring well installed. 10' of slotted screen 10 to 20' and 10' of solid PVC riser to surface. Finished with flush mount road box. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.1 1 5 2 5-10' 0.0 10 3 10-15' 0.1 15 4 15-20' 0.2 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-5/MW-3 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/31" NA (Geoprobe) 7" asphalt and rocks with dark brown coarse sand and gravel; 2" light grayish-brown coarse sand and gravel; 5" medium-dark brown coarse sand with gravel and rocks; 17" light brown coarse sand with rocks 60/24" NA (Geoprobe) Light brown with bands of orange coarse sand 60/26" NA (Geoprobe) 6" light brown and orange coarse sand, damp; 2" light brown gravel; 8" gray silty sand with clay, wet; 10" light to dark gray fine sand with silt, 1" of gravel at bottom 60/34" NA (Geoprobe) 10" light brownish-gray coarse sand, damp; 12" light brownish-gray fine-medium sand, wet; 10" light brown fine-medium sand; 2" gray silty clay, wet End of borehole 20 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Two-inch diameter monitoring well installed. 10' of slotted screen 10 to 20' and 10' of solid PVC riser to surface. Finished with flush mount road box. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.1 1 5 2 5-10' 0.0 10 3 10-15' 0.1 15 4 15-20' 0.1 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-6/MW-4 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/36" NA (Geoprobe) 4" asphalt; 4" light brown coarse sand with rocks; 2" light and dark brown coarse sand; 26" light brown fine- medium sand with some silt 60/35" NA (Geoprobe) 7" light and medium brown fine sand; 10" brown medium sand with silt, damp; 2" medium brown sand with peat and gray silt; 12" light brown fine sand with grayish-brown silt, damp 60/30" NA (Geoprobe) 12" light browish-gray coarse sand and gravel; 5" brownish-gray silt and fine sand, wet; 13" rocks with medium brown fine sand and gravel, damp 60/34" NA (Geoprobe) 6" medium brown medium sand, damp; 14" brown, gray and orange fine sand with silt, wet; 14" gray silty clay, wet; 2" gray sandy silt, wet End of borehole 20 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Two-inch diameter monitoring well installed. 10' of slotted screen 10 to 20' and 10' of solid PVC riser to surface. Finished with flush mount road box. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 11-12'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.0 1 5 2 5-10' 0.0 10 3 10-15' 0.1 15 4 15-20' 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-8/MW-5 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/25" NA (Geoprobe) 4" asphalt; 8" medium brown gravel; 13" medium brown fine-medium sand and gravel, damp 60/34" NA (Geoprobe) 8" medium brown coarse sand and silt with gravel, damp; 6" medium brown silt with gravel; 20" brownish- gray silt with mottling 60/36" NA (Geoprobe) 21" wet gray silt; 12" gray and orange silt with coarse sand and gravel, wet; 60/0" NA (Geoprobe) Well screen Sand pack End of borehole 18' No recovery 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Two-inch diameter monitoring well installed. 10' of slotted screen 10 to 20' and 10' of solid PVC riser to surface. Finished with flush mount road box. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.1 1 5 2 5-10' 0.1 10 3 10-15' 0.1 15 4 15-20' 0.0 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-2 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/38" NA (Geoprobe) 4" asphalt; 12" brown coarse sand and gravel; 6" brownish-gray coarse sand with brick fragments; 14" light brown fine sand with silt, damp 60/24" NA (Geoprobe) 12" light brownish-gray fine sand and silt; 12" light gray coarse sand with gravel 60/32" NA (Geoprobe) 8" damp brown medium sand with gravel; 24" wet brown coarse sand with gravel 60/36" NA (Geoprobe) 12" brownish-orange coarse sand and gravel; 6" brown medium sand and gravel; 8" wet gray silty sand with some clay End of borehole 20 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.8 1 5 2 5-10' 0.0 10 3 10-15' 0.0 15 4 15-20' 0.0 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-4 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/26" NA (Geoprobe) 4" light brown fine sand; 3" asphalt; 3" medium brown medium-coarse sand; 16" medium and dark brown coarse sand, damp 60/9" NA (Geoprobe) 4" brick fragments; 5" medium brown coarse sand, damp 60/14" NA (Geoprobe) 10" medium brown coarse sand, damp; 4" gray coarse sand with silt, damp 60/24" NA (Geoprobe) End of borehole 20 feet Well screen Sand pack 8" wet brownish-gray coarse sand with gravel; 6" wet grayish-brown silt with fine sand; 10" wet gray silt with some clay 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) 14-15'INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.0 1 5 2 5-10' 0.0 10 3 10-15' 0.0 15 4 15-20' 0.0 2 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-7 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/17" NA (Geoprobe) Orange-brown fine to coarse sand with silt 60/42" NA (Geoprobe) 2" orange-brown fine sand, damp; 4" dark gray coarse sand; 36" orange-brown fine to coarse sand with silt 60/30" NA (Geoprobe) 12" dark brown peat and silt, damp; 18" gray sand with silt; 6" wet coarse sand with orange gravel 60/43" NA (Geoprobe) 15" wet grayish-brown silty sand; 27" wet gray silt with some clay End of borehole 20 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.4 1 5 2 10 15 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-A 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/33" NA (Geoprobe) 7" asphalt; 4" brown medium sand with rocks; 18" brown medium sand; 6" gray sandy clay, damp End of borehole 5 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.0 1 5 2 10 15 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-B 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/32" NA (Geoprobe) 6" brown gravelly topsoil; 2" orange to dark brown medium sand; 9" light brown coarse sand; 2" medium to dark brown coarse sand; 13" light orangish-brown coarse sand End of borehole 5 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 1.0 1 5 2 10 15 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-C 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/30" NA (Geoprobe) 1" topsoil with brick fragments; 4" dark brown gravel with rocks; 25" light to medium brown coarse sand End of borehole 5 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.2 1 5 2 10 15 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-D 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/36" NA (Geoprobe) 4" medium brown sand, moist; 12" light grayish-brown coarse sand with asphalt; 2" dark brown coarse sand with rocks, moist; 2" brick fragments; 16" orange- brown coarse sand with some fine sand, moist End of borehole 5 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal BORING NO.: Environmental Compliance Services, Inc.DOCUMENT NO.: 588 Silver Street, Agawam, Massachusetts 01001 SHEET OF 1 BORING COMPANY: JOB NUMBER: PROJECT NAME: FOREMAN:PROJECT ADDRESS: ECS INSPECTOR:CLIENT NAME: GROUNDWATER OBSERVATIONS CASING SAMPLER CORE BARREL Date Depth Stabilization Time TYPE Casing Elevation (ft.) INSIDE DIAMETER PVC Elevation (ft.) HAMMER WEIGHT Surface Elevation (ft.) HAMMER FALL Date Started NOTES:Date Completed Depth Sample Number Sample Depths Penetration/ Recovery Blows per 6" penetration Strata Changes Field Testing Notes 0 1 0-5' 0.1 1 5 2 10 15 20 25 30 35 40 SOIL BORING and MONITORING WELL INSTALLATION LOG SB-E 1 LOCATION Crawford Drilling Services LLC 01-220303 See Site Plan BORING COMPANY ADDRESS:Westminster, MA Northampton Lumber Al 256 Pleasant St, Northampton, MA Amy Butler/Ela Soja Valley CDC Direct Push Geoprobe Drilling Equipment 7/11/2013 7/11/2013 Soil Descriptions Well As Built 60/33" NA (Geoprobe) 5" asphalt; 12" brown coarse sand with rocks; 5" orange-brown and dark brown coarse sand; 3" brick fragments; 3" orange coarse sand with rocks; 12" light brown fine sand with trace silt End of borehole 5 feet Well screen Sand pack 1. Field testing values = total organic vapors measured using MassDEP jar headspace methods with a Phocheck Tiger photoionization detector (PID) in parts per million. 2. Soil boring only, no monitoring well installed. Native Fill Groundwater table Bentonite seal APPENDIX B Wage Rates APPENDIX C USACE Permitting Documentation APPENDIX D Notice of Intent and Order of Conditions Documentation