2021-04-23 Higgins Way Field Report1550 Main Street, Suite 400
Springfield, MA 01103
Field Report Page 1 of 5
F:\P2009\1145\C71\Construction Administration\CA Reports
Higgins Way Project Closeout Observation Log
Project Name:Higgins Way Project
Closeout
Submitted to:Carolyn Misch
Inspection Date:04/23/2021 Project Address: Higgins Way
F&O Project #:2009.1145.C71 Town: Northampton State: MA
Photos Included:4 photos Client:City of Northampton
Field Notes:
Date/Inspector/Time:04/23/2021 / Matt Taylor / 3:00-3:45 am
Weather: 65◦ F and Sunny
General Notes:
Matt Taylor of Fuss & O’Neill performed a site visit to observe construction progress.
Site Notes:
Keiter Builders (KB) on site at time of visit
o KB plans on continuing installation of sidewalk next week,
o Install of southern traffic island tentatively planned for next Tuesday
o Discussed filter strip at failing pavement edge
Site Features:
Over half of the panels have been poured
Removal of stockpiled material near basin complete
Regrading of South western trail. Awaiting install of water bars
1550 Main Street, Suite 400
Springfield, MA 01103
Field Report Page 2 of 5
F:\P2009\1145\C71\Construction Administration\CA Reports
Site Photographs:
Photo 1: Regraded at south western corner of project
1550 Main Street, Suite 400
Springfield, MA 01103
Field Report Page 3 of 5
F:\P2009\1145\C71\Construction Administration\CA Reports
Photo 2: Sidewalk install looking south.toward Ford Crossing
1550 Main Street, Suite 400
Springfield, MA 01103
Field Report Page 4 of 5
F:\P2009\1145\C71\Construction Administration\CA Reports
Photo 3: Sidewalk install looking east along north side of Higgins Way
1550 Main Street, Suite 400
Springfield, MA 01103
Field Report Page 5 of 5
F:\P2009\1145\C71\Construction Administration\CA Reports
Photo 4: Sidewalk install looking westvalong north side of Higgins Way