2018_0504 Monthly Report - MARCH
CONTROLLED CONSTRUCTION SUMMARY: MARCH 2018
PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 05/04/2018
ESTIMATED % COMPLETION: 95% SCHEDULE CONFORMANCE: YES
PRESENT ON SITE: Peter Makrauer - LDa, Douglas Dick – LDa, Peter Frothingham – PFRA
I) WORK IN PROGRESS:
· Rain screen fiber cement panel installation is almost complete
· Forbo flooring and tile installations are ongoing
· Unit finish work is ongoing
· Finish site work is ongoing
· Dumpster enclosure work is underway
II) OBSERVATIONS:
· Appliance installation is near completion
· All units are near completion and ready for punch list
· Exterior elevations are near completion and ready for punch list
· Site appears to be managed well, safety protocols are emphasized & enforced by GC
· First floor retail space is the current location for all regular job meetings
· Work appears to be completed in accordance with plans and specifications
III) ANTICIPATED WORK IN THE NEXT 4 WEEKS
· Finish installation of FCP panels
· Install missing cabinets and replace warped doors
· Continue all finish work
· Create punch list of all units and common spaces
IV) INFORMATION/ACTION REQUIRED:
· None at this time
NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED
WITH THIS DOCUMENT.
PREPARED BY: Peter Makrauer - Project Manager - LDa
WEEKLY CONSTRUCTION ACTIVITY SUMMARY
PROJECT: LIVE 155
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 3.15.18
ACCOMPLISHMENTS
1. Pre-liminary punchlisting activities Complete: 4th floor & exterior
2. Roof: final crane day 03.12, cleaned off the roof
3. Fall Protection System: Testing & Training completed 03.15
4. Site work: poured curved path, started excavation for bike shelter & dumpster enclosure
5. DAFS: prep work is complete, ceiling areas tented for heat
6. Rain Screen: Significant progress below 12’ band on South, West & North Elevations
7. Store Front: air & water testing: passed air, failed water
8. Fire Alarm pre-testing complete on 3rd & 4th floors
9. Appliances: 30 units installed, 4th & 3rd floor laundries installed
10. Solid Surface: almost complete on 3rd & 2nd
11. Forbo: repairs complete on 4th & 3rd. Installing flooring in Corridors & Lobbies. Expect to be
complete on 2nd through 4th floor by the end of the week.
12. Room Entry Doors & Hardware are getting installed
13. Working with the city on CO – hardscape must be complete
GOALS
1. 1st Floor Flooring: make a decision on the path forward (Forbo vs Kinetex product)
2. Fire Alarm full testing on 2, 3 & 4 next week
3. Storefront: field test again next week 03.19
4. FCP: complete installation of materials on site, prep remaining areas & place final order
5. Finish all work requiring lifts
a. Exterior Caulking: Brick/FCP joint
b. Washing windows & installing screens
6. Won-Door and Smoke Curtain coordination
7. Design Team priorities:
a. Foundation insulation details where hardscape is adjacent to building
b. Stormwater O&M Plan (GZA)
c. Louis Hasbrouck requested info
d. A/D: review documents produced to date. Issue memo.
e. Issues which could keep us from getting the CO
WEEKLY CONSTRUCTION ACTIVITY SUMMARY
PROJECT: LIVE 155
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 3.27.18
ACCOMPLISHMENTS
1. Site work: poured pads for bike shelter & dumpster enclosure
2. DAFS: ceiling areas tented are complete
3. Rain Screen: Almost ready for final order
4. Store Front: water re-testing improved: passed AMMA, failed ASTM (1 location only)
5. Slab at Retail: poured 03.26
6. Charging unit mini-splits: ¾ of 4 & ½ of 3 complete
7. 2nd, 3rd, & 4th floor units: pre-punchlisting
8. Public Restrooms: installing bath accessories
9. Appliances: 60 units installed, 2nd thru 4th floor laundries installed
10. Forbo: working on punchlist repairs
11. Way Finder Open House for affordable units on 03.22 & 03.24
GOALS
1. FCP: complete installation of materials on site, prep remaining areas & place final order
2. Finish all work requiring lifts
a. Clean FCP
b. Washing windows & installing screens
3. Cabinets: install missing cabinets, get replacements for all warped doors
4. 1st Floor Flooring: installation of Kinetex to start Wednesday
5. Final Plumbing Inspections: 2 hr block this week
6. 1st Floor Ceiling Electrical Inspections: this week
7. Public Restrooms: complete installation of bath accessories & partitions
8. Won-Door installation later this week
9. Smoke Curtains arriving 04.09
10. Design Team priorities:
a. A/D: review documents produced to date. Issue memo.
b. Stormwater O&M Plan (GZA): must be signed by mayor & recorded
c. Plan for granite seat walls/transition at Hampton Court
d. Louis Hasbrouck requested info for CO
i. CBAC approved drawings: 2016 update
ii. Lighting Plans from PB approval (A109 & A209 dated 10/14/2014) & certification by
design engineer that it meets the plans
iii. Architectural punch list w/ final inspections by MEPS (in XLS format)
iv. Completion affidavits by all disciplines
v. Letter of substantial completion