2018_0316 Live 155 - Monthly Report - February
CONTROLLED CONSTRUCTION SUMMARY: FEBRUARY 2018
PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 03/16/2018
ESTIMATED % COMPLETION: 92% SCHEDULE CONFORMANCE: YES
PRESENT ON SITE: Peter Makrauer - LDa, Douglas Dick – LDa, Peter Frothingham – PFRA
I) WORK IN PROGRESS:
· Rain screen fiber cement panel installation is almost complete
· Plumbing fixtures are being installed
· Unit appliances are being installed
· Unit doors, trim, forbo flooring and tile installations are ongoing
· Unit finish painting is ongoing
· Finish site grading underway
II) OBSERVATIONS:
· 4th floor units are near completion and ready for punch list
· Exterior elevations are near completion and ready for preliminary punch list
· Storefront installation at retail area is complete
· All cabinets have been installed
· Site appears to be managed well, safety protocols are emphasized & enforced by GC
· First floor office space is the current location for all regular job meetings
· Work appears to be completed in accordance with plans and specifications
III) ANTICIPATED WORK IN THE NEXT 4 WEEKS
· Finish installation of FCP panels
· Continue installation of all finishes
· Prepare all units for punch list
IV) INFORMATION/ACTION REQUIRED:
· None at this time
NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED
WITH THIS DOCUMENT.
PREPARED BY: Peter Makrauer - Project Manager - LDa
WEEKLY CONSTRUCTION ACTIVITY SUMMARY
PROJECT: LIVE 155
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 2.13.18
ACCOMPLISHMENTS
1. Site work planning meeting with subs & design team last week
2. Rain Screen: Installation above the 12’ band 99% complete.
3. Forbo flooring complete on units in 4W & 3W, 4E underway.
4. Counters: Vanities installed on 4W, 3W & 2W, Kitchens complete on 4W, started on 4E & 3W
5. Kitchen cabinets: all cabinets on site, installations underway on 2E, then 1W & WF kitchen
6. Plumbing Fixtures: installations complete where possible all over the building
7. Elevator: Installation nearing completion
8. Working with the city on CO – hardscape must be complete
GOALS
1. Forbo – increase capacity to 20+ units per week
2. Windows: field test next week
3. Elevator: Complete installation
4. FCP: more materials being delivered tomorrow
5. Finish all work requiring lifts
a. Exterior Caulking: Brick/FCP joint
b. FCP installation above 12’
c. Material deliveries
6. Complete 10 units on 4W, ready for punch list
7. Won-Door and Smoke Curtain coordination
8. Fire alarm system testing – start 03.06
9. Design Team priorities:
a. A/D: review documents produced to date. Issue memo.
b. FP system soffit details
c. Stair 2 – finalizing details
d. Details where hardscape is adjacent to building
e. Stormwater O&M Plan (GZA)
f. Issues which could keep us from getting the CO
WEEKLY CONSTRUCTION ACTIVITY SUMMARY
PROJECT: LIVE 155
ARCHITECT’S PROJECT #: 201420
DATE ISSUED: 2.27.18
ACCOMPLISHMENTS
1. Site work restarted, pouring concrete base for pavers at South Entry
2. Rain Screen: Installing below 12’ band. Almost complete along South side
3. Forbo: higher quality & productivity crew on site, completed 20 units last week
4. Solid Surface: Complete on 4, except 417 ADA
5. Kitchen cabinets: all cabinets installed except WF kitchen
6. Plumbing Fixtures: installations complete where possible all over the building
7. Elevator: Flooring installed
8. Working with the city on CO – hardscape must be complete
9. A/D Window Testing complete – extended warranty required
10. Final electrical & data inspections on 4th floor apartments & above ceiling & 3rd floor
apartments
GOALS
1. Storefront: field test next week 03.01
2. Punch list 4th Floor Units next week 03.06
3. Fire alarm system pre-testing – start 03.06
4. FCP: complete installation of materials on site
5. Finish all work requiring lifts
a. Exterior Caulking: Brick/FCP joint
b. FCP installation above 12’
c. Material deliveries
6. Won-Door and Smoke Curtain coordination
7. Design Team priorities:
a. Foundation insulation details where hardscape is adjacent to building
b. Details in “Unassigned” storage space under Stair 3
c. Stormwater O&M Plan (GZA)
d. Louis Hasbrouck requested info
e. A/D: review documents produced to date. Issue memo.
f. Issues which could keep us from getting the CO