2017_1215 Monthly Report - November CONTROLLED CONSTRUCTION SUMMARY: NOVEMBER 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 12/15/2017 ESTIMATED % COMPLETION: 74% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Douglas Dick – LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Roof parapet metal cap installation is ongoing · Rain screen fiber cement panel installation is near completion at the south elevation and the north elevation is underway. · Rough electrical, plumbing, HVAC, FP provisions ongoing · Drywall installation is ongoing · Door frame installation underway at west end II) OBSERVATIONS: · Brick masonry is complete · Window installation complete · PV panel installation complete until other roof work is complete · Rain screen panels are being installed smoothly · Site appears to be managed well, safety protocols are emphasized & enforced by GC · Site trailer continues to be the location for all regular job meetings · Work appears to be completed in accordance with plans and specifications III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Begin elevator installation · Continue laying tile in bathrooms · Finish installation of metal parapet cap at roof · Continue drywall installation · Continue priming and painting walls and ceilings · Continue installation of FCP panels (complete north elevation at courtyard) · Continue installation of frames and begin installing doors. · Install gypcrete at east end IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11.1.17 ACCOMPLISHMENTS 1. Rain Screen: First shipment installation going smoothly, order placed for nook, pinch point & North side with anticipated delivery 11/7 2. Masonry: ½ way up last wing wall at NE despite multiple rain outs 3. Windows: AD completed installation of taller snubber tracks, retest scheduled for 11/9 4. Roof: PV Squared successful crane day on Saturday, installation underway 5. Roof: Lower metal complete on small parapets 6. Unit Tile: Waterproofing started on 3rd Floor 7. Elevator: Delivered, requirements for installation to begin being addressed 8. East End: Plumbing rough ahead of schedule on 2nd and 3rd floors 9. HVAC: Equipment on West and Center racks piped and brazed, on final 15 at East rack GOALS 1. Windows: Approval of alternate handle, retest scheduled next week 11/9 2. Rain Screen: Complete installation of panels on South Elevation, prepare to rcv 11/7 shipment 3. Mason: Finish final NE elevation and column at South canopy, off site by end of next week 4. 4th Floor: Continue with bathroom waterproofing, water test this week, start mud set 5. 4th Floor: Complete Laundry Room MEP rough 6. 2nd & 3rd Floors: Plumbing inspection Monday 7. 1st Floor: West end MEP rough, insulation and fire caulking 100% by end of week 8. Solar: Steady progress toward goal of installation complete for end of Nov 9. Sitework: Learn lead time on CE soil and granite, reorganize Pleasant Street and start grading 10. Design Team priorities a. All RFIs b. Submittals – grout, cabinet, appliances, sitework materials c. Bulletin 8 WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11.15.17 ACCOMPLISHMENTS 1. Masonry: brick installation is complete 2. Windows: Installation is complete, A/D on site 11/9 for pre-testing 3. Rain Screen: Most of South Elevation is complete above 12’ band. Next shipment anticipated 11/16 4. Roof: PV Squared installation progressing rapidly 5. Roof: Lower metal complete on small & medium parapets, large parapet underway 6. Unit Tile: Water testing completed on 3rd floor. Tile installation underway in 1 bathroom for approval 7. Elevator: Crystalline waterproofing underway 8. East End: Plumbing rough complete on 2nd and 3rd floors 9. HVAC: Charging rooftop condensers & installing West End minisplits, ceiling heaters & ERVs GOALS 1. Windows: Approval of alternate handle, retest scheduled 11/17 and 11/20 with SGH 2. Rain Screen: Complete installation of panels on South Elevation, then move to North Elevation in courtyard 3. 4th Floor West End: Finish trims and cabinets arriving next week 4. 4th Floor: Complete Laundry Room & Janitor’s closet MEP rough 5. 1st Floor: West end MEP rough, insulation and fire caulking 100% by end of week 6. Solar: Steady progress toward goal of installation complete for end of Nov 7. Sitework: Start work along Pleasant St, South side by bike path & prep for binder course by trailer 8. Design Team priorities a. All RFIs & Submittals b. Stair 2 fire suppression system details c. Finalize Lobby Changes 2-4 WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11.22.17 ACCOMPLISHMENTS 1. Windows: SGH on site 11.17 and 11.20 for window testing 2. Rain Screen: Started running bond installation in the “Nook” and the “Pinch Point” 3. Roof: PV Squared maximized the array size 4. Unit Tile: Tile installation mockup approved & installation is underway 5. Elevator: Crystalline waterproofing complete in elevator pit 6. East End: Installing drywall on 3 & 2. Painting on 4 7. West End: Cabinets arrived today for 4th floor & ½ of 3rd 8. HVAC: Charging rooftop condensers 9. Sitework: Prep’d for binder course by trailer 10. Submittals: Design team has responded quickly to critical finish submittals GOALS 1. Windows: Clear deliverables for A/D and eliminate WB coordination requirements moving forward 2. Rain Screen: Complete installation of panels on South Elevation, then move to North Elevation in courtyard 3. West End: 4th floor Mockup of cabinets and finish trims in Studio & 1 bedroom next week 4. 1st Floor: West end completion of insulation and fire caulking 5. Complete Laundry Room & Janitor’s closet MEP rough 6. Gypcrete East End: 12/14-15 7. Solar: Steady progress toward goal of installation complete for end of Nov 8. Elevator Installation: starting 12/4 9. Sitework: Binder course by trailer next week. Start work along Pleasant St and South side by bike path 10. Design Team priorities a. All RFIs b. Countertop and Sill Submittals c. Finalize Lobby Changes 2-4 & Stair 2 FP details WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11.29.17 ACCOMPLISHMENTS 1. West End Finishes: started jambs/trims for barn doors on 4th floor, casing mockup approved 2. Rain Screen: Started installation on the North side, ordered material for rear section of the building 3. Metal Window Panning: completed installation on the North Side 4. East End: Painting on 4, taping drywall on 3, completing installation on 2 5. HVAC: Charging rooftop condensers 27 of 30 units charged on west end 6. Solar: complete for now. A few panels need to be installed after all other roof work is complete 7. Sitework: Started work along Pleasant St GOALS 1. Windows: SGH reports & clear deliverables for A/D by end of week 2. Rain Screen: Complete installation of panels North Elevation in courtyard 3. West End Finishes: get missing kitchen cabinet & start 4th floor Mockup of cabinets and finish trims in Studio & 1 bedroom next week, door delivery next week 4. 1st Floor: West end completion of drywall 5. Gypcrete East End: 12/14-15 6. Complete Laundry Room & Janitor’s closet MEP rough, inspections by end of week 7. Lobbies & Corridors: Complete rough & install ceiling drywall before gypcrete 8. Elevator Installation: starting 12/4 9. Sitework: Binder course by trailer next week. Start work along South side by bike path 10. Design Team priorities a. Highlighted RFIs b. Solid Surface submittal c. Quick responses on finishes questions (kitchen cabinets, counters, trims, etc) d. Finalize Lobby Changes 2-4 & Stair 2 FP details