2017_1013 Monthly Report - September CONTROLLED CONSTRUCTION SUMMARY: SEPTEMBER 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 10/13/2017 ESTIMATED % COMPLETION: 60% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · 2nd and 3rd floors are being primed · Rain screen preparation is ongoing (rigid insulation, paper and furring) · Rough electrical, plumbing, HVAC, FP provisions ongoing · Masonry work is ongoing · Drywall installation is ongoing · Windows are being installed at masonry openings II) OBSERVATIONS: · All roof equipment has been craned up to roof and set in permanent location · Northern 3rd of brick is complete at Pleasant Street · Fins have been installed on south elevations · Site appears to be managed well, safety protocols are emphasized & enforced by GC · Site trailer continues to be the location for all regular job meetings · Work appears to be completed in accordance with plans and specifications III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Start installation of metal parapet cap at roof · Gyp-crete installation at west end · Continue drywall installation · Continue priming walls and ceilings · Continue masonry work · Start FCP panel installation at end of month · Install storefronts IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 9.06.17 ACCOMPLISHMENTS 1. Masonry: Pleasant Street South brick beating schedule expectations, looks fantastic 2. Rain Screen: Fabric and furring started at West End 3. Windows: Fire Rated units received and installed, AD on site addressing testing failures 4. Low Voltage: 3rd Floor sign off, 1st Floor inspection yesterday afternoon 5. Insulation: Blown in RW 2nd Floor West End complete, 3rd Floor underway 6. Drywall: 2nd Floor loaded and closing 7. Roof: Layout underway, cutting of openings weather pending 8. Interior: Stair 2 First Floor curved section rough framed 9. Retail: Ceiling insulation and drywall, enabling tie in of plumbing risers for testing GOALS 1. Rain Screen: Locate, make and seal penetrations SE corner in rain screen above South entrance canopy, in the “nook” 2. Storefronts: Button up open items for approval, release for field measure and fabrication 3. Roof: Friday, crane and set MEP dunnage, rails and miscellaneous 4. Building: Start fire stopping detail at north side of elevator shaft 5. Enabling Work: Complete installation of sign brackets over South Entry 6. Insulation: Complete blown in Rock-wool 3rd floor West end, start 1st floor 7. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 8. Rain Screen: Paper West elevation of West End, start South elevation of West End 9. Windows: Progress with corrective measures, schedule re-testing 10. Design Team priorities a. Commercial Kitchen provisions b. Hardware- storefront maglocks c. Storefront tie-in to FCP WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 9.12.17 ACCOMPLISHMENTS 1. Masonry: Pleasant Street Southern 3rd complete and washed, mobilized Center 3rd and working 2. Rain Screen: Great progress with fabric and furring South Elevation, system and pace 3. Windows: AD On site addressing root cause issues of window test failures 4. Low Voltage: 4th Floor Insulation & drywall done enabling corridor hooks, wiring underway 5. Insulation: Blown RW 3rd Floor West End complete, 1st Floor underway (will enable drywall of exterior walls and subsequent framing of in unit ceilings unique to 1st floor units). 6. Drywall: 3rd Floor loaded and closing, 2nd Floor taping and on pace for priming mid-next week 7. Roof: Dunnage picked and set, all required roof blocking, curbs, flashing etc. underway in anticipation of Equipment mid-next week 8. Building: Fire-stopping detail north side of elevator shaft underway GOALS 1. Roof: Roof Ready and crane all roof-top MEP equipment on Wed. 9/20 or Thur. 9/21 2. Storefronts: Button up open items for approval, release for field measure and fabrication 3. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 4. Rain Screen: Locate, make and seal ANY REMAINING penetrations 5. Building: Complete fire stopping detail at north side of elevator shaft 6. Enabling Work: Complete installation of sign brackets over South Entry 7. Insulation: Complete blown in Rock-wool 3rd floor West end, start 1st floor 8. Rain Screen: Complete South elevation of West End, transition to North elevation West End 9. Windows: Progress with corrective measures, schedule re-testing 10. Design Team priorities a. Commercial Kitchen provisions b. Hardware- storefront maglocks c. Storefront tie-in to FCP WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 9.20.17 ACCOMPLISHMENTS 1. Building: Fire-stopping detail north side of elevator shaft complete 2. Storefronts: Final details and hardware resolved, released for material order and fabrication 3. Roof: Ready for equipment, crane on schedule for tomorrow 4. Masonry: Pleasant Street Middle 3rd complete and washed, mobilized North 3rd and working 5. Rain Screen: Fins on site and install underway, fabric / furring going quickly and looks good 6. Low Voltage: 4th Floor rough complete and inspected, ready for blown in rock-wool 7. 1st Floor: Blown in RW complete, framing of in unit ceilings underway. 8. 2nd & 3rd Floors: Corridor ceilings framed and roughed, inspections imminent 9. 3rd Floor: Drywall loaded, closing and taping units 10. 2nd Floor: Started priming apartments GOALS 1. Roof: Crane all roof-top MEP equipment on Thur. 9/21 2. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 3. Rain Screen: Locate, make and seal ANY REMAINING penetrations. Measure and order siding for South Elevation 4. Roofing: Start metal parapet cap south, working from pinch point West 5. Enabling Work: Install sign brackets over South Entry and tie-downs for awnings 6. Insulation: Complete blown in Rock-wool 4th floor West end 7. 1st Floor: Complete water line rough in, inspect and insulate, frame ceilings 8. Rain Screen: Paper and furring North / West End, fins, field measure and order South 9. Windows: AD return to site to complete corrective measures, schedule re-testing 10. Design Team priorities a. Paint colors b. Storefront tie-in to FCP c. FCP Vent covers for dryer, kitchen & bath fan exhaust d. Stair details e. All MEP RFI’s and submittals f. Window Testing Memo Updates WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 9.27.17 ACCOMPLISHMENTS 1. Roof: Super successful crane day, all equipment on roof and set in permanent location 2. Storefronts: Revised submittal from Eastfield Glass 3. Rain Screen: First round of field measuring complete, material order placed, f&f north 4. Rain Screen: Vent shroud prototype being fabricated 5. Masonry: Pleasant Street Northern 3rd brick complete, being washed 6. Windows: R&R on site installing, break metal mock up done 7. Windows: Conference call with AD, test failures fix and testing scheduled for 10/10 8. 4th Floor: Rock-wool on schedule, kitchen and bath ceilings framed and roughed, drywall load Th 9. 4th Floor: Framing modifications for Line Set roof penetration openings 10. 1st Floor: Water rough ready for inspection, bathroom and kitchen ceilings being framed 11. 2nd & 3rd Floors: Corridors inspected and framed, being insulated 12. 3rd Floor: Priming underway GOALS 1. Storefront: Review and return revised storefront submittal 2. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 3. Rain Screen: Continue to measure and order siding (North) 4. Roofing: Start metal parapet cap south, working from pinch point West 5. 4th Floor: Load drywall and start closing, on pace for gyp-crete 10/12 6. 4th Floor: Pre-rock at Line Set Roof Penetration opening, start running lines through roof 7. 4th Floor: MEP Rough, set pace for drywall / close walls load on 10/19, all clear 10/24 8. 1st Floor: Frame kitchen and bath ceilings, sprinkler heads, set fans, wire and connect 9. Showers: Plan and coordinate work sequence for proper execution / quality control 10. Sitework: Comcast, Verizon, North Canopy drain, generator pad 11. Design Team priorities a. Generator Pad Location b. Paint colors c. Stair details d. Storefront tie-in to FCP e. All MEP RFI’s and submittals f. Window Testing Memo Updates