2017_0907 Monthly Report - August CONTROLLED CONSTRUCTION SUMMARY: AUGUST 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 9/7/2017 ESTIMATED % COMPLETION: 54% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Storefront openings framing is underway · Rain screen preparation is underway (rigid, paper and furring) · Rough electrical, plumbing, HVAC, FP provisions ongoing · Masonry work is ongoing · Blown in Rock-wool insulation is underway at 2nd floor · Drywall is being installed on the 1st floor II) OBSERVATIONS: · All windows on site have been installed · Masonry is complete at 15/N · Permanent power is live to switch · Site appears to be managed well, safety protocols are emphasized & enforced by GC · Site trailer continues to be the location for all regular job meetings · Work appears to be completed in accordance with plans and specifications III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Prepare roof openings · Blown in Rock-wool insulation at 3rd and 4th floors · Continue rain screen preparations · Continue masonry work · Install drywall at 2nd, 3rd and 4th floors IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8.2.17 ACCOMPLISHMENTS 1. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, building wrap, masons. 2. Received 40 windows on 7/31 3. Window Test 7/31 – 2 mulled Single Hungs in FCP, glazing leaks 4. LDa on site 2 Tuesdays GOALS 1. Start rough for tel/data 2. Permanent Power: waiting for National Grid 3. Framing: continue work on misc details 4. Mechanical subs: continue rough & pre-rock 5. Continue masonry installation 6. Finish installation of 3rd batch of windows 7. Resolution of water leakage issues 8. Mockup: complete FCP, DAFS & Parapet Metal 9. Design Team priorities a. MEP/FP coordination – Range Hoods b. Misc framing issues c. FCP Details – Kitchen, Bath & dryer exhaust, ERV d. Brick Details – Canopy Blocking Requirements & electrical requirements for signs e. Hardware- storefront maglocks 10. Bulletin #7 WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8.9.17 ACCOMPLISHMENTS 1. Finished Brick on South Face 2. Complete membrane installation 3. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, building wrap, masons, tel/data, window installers, PV 4. Started tel/data rough 5. National Grid has connected permanent power GOALS 1. PV Squared starting installation – submittals required? 2. Equipment startup/testing for permanent power 3. Resolution of water leakage issues on single hung windows 4. Window Testing on casements 8/17 5. Mockup: complete FCP & Parapet Metal 6. Design Team priorities a. Fire separation at North side of elevator shaft b. MEP/FP coordination - submittals, curb design c. Misc framing issues – South Canopy details d. Tel/com questions e. FCP – shop drawings, camera mounting details, vent hood design f. Brick Details – Electrical requirements for signs g. Hardware- storefront maglocks WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8.16.17 ACCOMPLISHMENTS 1. Finished Brick on South Face 2. Complete membrane installation 3. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, building wrap, masons, tel/data, window installers, PV 4. Started tel/data rough 5. National Grid has connected permanent power GOALS 1. PV Squared starting installation – submittals required? 2. Equipment startup/testing for permanent power 3. Resolution of water leakage issues on single hung windows 4. Window Testing on casements 8/17 5. Mockup: complete FCP & Parapet Metal 6. Design Team priorities a. Fire separation at North side of elevator shaft b. MEP/FP coordination - submittals, curb design c. Misc framing issues – South Canopy details d. Tel/com questions e. FCP – shop drawings, camera mounting details, vent hood design f. Brick Details – Electrical requirements for signs g. Hardware- storefront maglocks WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8.23.17 ACCOMPLISHMENTS 1. Windows: great progress with installation, delivery received and off loaded yesterday 2. Windows: Tested casements and fixed units (were failures that Lynne is working on with AD) 3. Masonry: Walls at 10/M full height and 9/J.5 ground floor complete and washed. Setting base at future storefront to align framing, setting up at 15/N 4. Electric: Permanent power should be live to switch today 5. Coordination: Mason and Roofer coordinated transition at South Entrance Canopy. 6. Coordination: Questions on vent locations answered, line set penetrations means and methods detailed. GOALS 1. Enabling Work: Complete installation of canopy and sign brackets 2. Building: Start shaft wall and fire stopping detail at north side of elevator shaft 3. Plumbing: Get vents through the roof, cut openings for line sets 4. Masonry: Complete full height wall at 15/N, mobilize and start laying brick 1 Line Southernmost 1/3rd 5. Sprinkler: test Floors 2,3 and 4 6. Insulation: Kick of blown in Rock-wool 2nd floor West end (set pace of 1 week / floor) 7. Rain Screen: Complete all penetrations, sealing and rigid on West end North side 8. Masonry: Complete wing wall at 15/N, open up for parapet metal and cement siding from Bike Path 9. Windows: Progress with resolution of water leakage issues on single hung windows 10. Design Team priorities a. Brick Details – Confirm horiz & vertical location for awning brackets, public art & signage lighting b. Tel/com questions c. Hardware – storefront maglocks WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8.30.17 ACCOMPLISHMENTS 1. Windows: All windows on site are installed, includes SE “nook” in masonry 2. Masonry: Full height at 15/N complete, awning brackets installed Pleasant South 1/3 underway 3. Rain Screen: Rigid insulation North side of West End, SE “nook” substantially complete 4. Insulation: Blown in RW 2nd Floor West End underway, 3rd Floor LV inspection imminent 5. Roof: Crane day, roof prep and steel work coordinated, confirmed for 9/8 6. Retail: Storefront openings framing underway, ceiling insulation (drywall and plumbing follow) 7. Power: Live to main switch, electric rooms each floor getting drywall and paint, equipment built GOALS 1. Roof: Prepare roof openings, crane and set MEP dunnage, rails and miscellaneous 2. Enabling Work: Complete installation of sign blocking and brackets 3. Building: Start fire stopping detail at north side of elevator shaft 4. Storefronts: Button up open items for approval, release for field measure and fabrication 5. Insulation: Low Voltage inspection, blown in Rock-wool 3rd floor West end, 1st floor 9/6 6. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 7. Rain Screen: Final check and confirm of lighting and security locations, through wall provisions 8. Rain Screen: Paper and furring South Elevation, West End 9. Rain Screen: Locate, make and seal penetrations SE corner in rain screen above entrance canopy 10. Windows: Doug Nowlin on site 9/4 – 9/8 - Progress with resolution of water leakage issues 11. Design Team priorities a. Rooftop Layout – PV, mechanical equipment, chases, railing system b. Brick Details – Confirm horiz & vertical location for signage& lighting c. Tel/com questions d. Hardware- storefront maglocks e. Storefront tie-in to FCP