2017_0803 Monthly Report - June CONTROLLED CONSTRUCTION SUMMARY: JUNE 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8/3/2017 ESTIMATED % COMPLETION: 47% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Framing ongoing · Roof installation ongoing · Rough electrical, plumbing, HVAC, FP provisions ongoing · Pre-rock ongoing II) OBSERVATIONS: · Roof system installation ongoing. · Framing is almost complete. · Closed cell insulation at parapets and sound insulation at top of hallways installed for pre- rock. · Site appears to be managed well, safety protocols are emphasized & enforced by GC. · Site trailer continues to be the location for all regular job meetings. · Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Complete framing · Complete building wrap, roofing preparation · Rough for MEP/FP to continue · Brick work to begin · Begin window installation IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 06.07.17 ACCOMPLISHMENTS 1. Framing: completed 4th floor walls, working on the roof & stairs 2. Roofing: materials on the roof 3. Trades on site: framers, plumbing, electrical, roofers GOALS 1. Framing: complete roof & misc details 2. Start installation of roofing vapor barrier 3. Complete elevator shaft 4. Design Team priorities - needed by 06.13 a. Parapet framing details b. Elevator Louver Details c. Fire separation details at end of hallways (Stair 1 & 3) d. Roof condenser rack design & framing changes e. Misc Framing Questions f. Envelope air sealing details & membrane installation at all transitions/openings g. MEP/FP coordination h. Brick Details i. FCP Details 5. Bulletin #6 a. public art above main entry b. building envelope details c. stem wall details d. condenser rack design e. numerous SKs and plan sheet updates 6. Mockup: continue with envelope WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 06.14.17 ACCOMPLISHMENTS 1. Framing: roof deck complete 2. Roofing: vapor barrier complete 3. Masons: Elevator shaft CMU complete 4. Intumescent Paint: majority of columns are complete 5. Trades on site: framers, plumbing, electrical, HVAC, roofers, masons GOALS 1. Framing: complete parapets & misc details 2. Roofing: start installing roof on back half of the building 3. Mechanical subs: start installing hangers (for pre-rock) 4. Insulation: closed cell at parapets & sound insulation at top of hallways (for pre-rock) 5. Design Team priorities - needed by 06.20 a. Misc Framing Questions b. Roofing c. MEP/FP coordination d. Envelope air sealing details & membrane installation at all transitions/openings/flashings e. FCP Details – ERV hoods & WC-6 f. Doors & Hardware g. Brick Details 6. Bulletin #6 a. public art above main entry b. building envelope details c. stem wall details d. condenser rack design e. numerous SKs (qty 34) and plan sheet (qty 8) updates 7. Mockup: modify for new parapet & coping details, install vapor barrier, start brick 8. MassWorks Project WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 06.21.17 ACCOMPLISHMENTS 1. Framing: almost complete 2. Started insulation at top of hallways & pre-rock 3. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, insulators, drywall 4. 1st Floor Mechanical Coordination – Signed off by trades 5. Bulletin #6 issued 6. Very quick turn around on critical RFIs & Submittals GOALS 1. Framing: misc details 2. Roofing: start installing roof on back half of the building 3. Mechanical subs: continue installing hangers (for pre-rock) & plumbing 4. Insulation: closed cell at parapets & sound insulation at top of hallways (for pre-rock) 5. Design Team priorities - needed by 06.27 a. Misc Framing Questions b. Roofing c. MEP/FP coordination d. Laundry Room e. FCP Details – ERV hoods & WC-6 f. Doors & Hardware g. Brick Details 6. Mockup: complete brick, install windows, insulation, building wrap & furring 7. MassWorks Project WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 06.28.17 ACCOMPLISHMENTS 1. Framing: almost complete, fire separation at stair 1 & 3 complete 2. Roof: over 1/3 complete 3. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, insulators, drywall 4. Insulation: closed cell at parapets & sound insulation at top of hallways (for pre-rock) 5. Pre-rock complete for the next 2 weeks 6. MassWorks project work in front of our site is complete 7. Mockup brick work is complete GOALS 1. Framing: continue work on misc details 2. Roofing: continue installation 3. Mechanical subs: continue rough in the back half of the building 4. Mobilize mason to start brick work 5. Window delivery anticipated 07.05 6. Design Team priorities - needed by 07.05 a. Misc Framing Questions b. MEP/FP coordination c. Laundry Room d. Brick Details – ERV penetrations & art/canopy brackets e. FCP Details – ERV hoods & WC-6 f. Doors & Hardware