2017_0803 Monthly Report - July CONTROLLED CONSTRUCTION SUMMARY: JULY 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 8/3/2017 ESTIMATED % COMPLETION: 51% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Framing on miscellaneous details ongoing · Window installation is underway · Rough electrical, plumbing, HVAC, FP provisions ongoing · Masonry work has started · The building is starting to be wrapped with rigid insulation II) OBSERVATIONS: · Roof system installation almost complete · Framing is almost complete · Permanent power has been installed on site · Many rough inspections have been completed · Site appears to be managed well, safety protocols are emphasized & enforced by GC. · Site trailer continues to be the location for all regular job meetings. · Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Complete framing · Rough for MEP/FP to continue · Continue masonry installation · Finish window installation IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 7.12.17 ACCOMPLISHMENTS 1. Roof: 75% complete. 2. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, siding, mason. 3. Mason on site. Precast installation and layout underway. 4. Exterior door frames released. 5. Window delivery. Layout complete. 6. Metal and trims in fabrication. 7. New telcom contractor on board. GOALS 1. Framing: continue work on misc details 2. Roofing: complete installation 3. Mechanical subs: continue rough 4. Mobilize mason to start brick work 5. Install windows and survey building 6. Mock up water test. Order FCP. 7. Finalize counter and finish millwork scope. 8. Finalize acoustical ceiling layout. 9. Design Team priorities a. Condensing Rack b. “Shaft” behind the elevator c. MEP/FP coordination d. Laundry Room e. Brick Details – ERV penetrations & art/canopy brackets f. FCP Details – ERV hoods & WC-6 g. Doors & Hardware- storefront maglocks WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 7.19.17 ACCOMPLISHMENTS 1. Roof: 95% complete. 2. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, siding, mason, steel. 3. 1st Batch of Windows: Installation almost compete 4. Mason: started setting pre-cast 5. Mechanical Coordination: sign off on 2nd floor coordination drawings 07.18 6. Carlisle CCW-705: Approval for 30 day extension GOALS 1. Framing: continue work on misc details 2. Mechanical subs: continue rough 3. Continue masonry installation 4. Finish installation of 1st batch of windows & start the next 40 windows 7/24 5. Water Test on 2 FCP windows 7/28 6. Finalize counter and finish millwork scope. 7. Finalize acoustical ceiling layout. 8. Design Team priorities a. “Shaft” behind the elevator b. MEP/FP coordination c. Brick Details – Signage & canopy details d. FCP Details – Kitchen, Bath & dryer exhaust e. Doors & Hardware- storefront maglocks WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 7.26.17 ACCOMPLISHMENTS 1. Permanent Power: inspections complete, waiting for National Grid 2. Numerous rough inspections complete 3. Trades on site: framers, plumbing, electrical, HVAC, FP, roofers, drywall, building wrap, masons. 4. 2nd Batch of Windows arrived & installation is underway 5. Mason: started installing brick at South elevation 6. Started wrapping the building with rigid insulation 7. Valley Communications on site today GOALS 1. Start rough for tel/data 2. Framing: continue work on misc details 3. Mechanical subs: continue rough & pre-rock 4. Continue masonry installation 5. Finish installation of 2nd batch of windows 6. Water Test on 2 FCP windows 7/31 7. Mockup 8. Design Team priorities a. “Shaft” behind the elevator b. MEP/FP coordination c. Membrane details: penetrations & at base of sheathing d. Brick Details – Signage & canopy details e. FCP Details – Kitchen, Bath & dryer exhaust f. Doors & Hardware- storefront maglocks