2017_0623 LIVE 155 - MONTHLY REPORT - MAY CONTROLLED CONSTRUCTION SUMMARY: MAY 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 6/23/2017 ESTIMATED % COMPLETION: 45% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Fabrication & Installation of wall and floor panels – 4rd floor panel work is complete. · Roof framing ongoing · Rough electrical & plumbing provisions ongoing II) OBSERVATIONS: · Roof system installation ongoing. · Site appears to be managed well, safety protocols are emphasized & enforced by GC. · Site trailer continues to be the location for all regular job meetings. · Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Complete roof framing & canopy framing · Complete building wrap, roofing preparation. · Rough for MEP/FP to continue. · Complete elevator shaft IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 5.10.17 ACCOMPLISHMENTS 1. Framing: 3rd floor floor system complete & 3rd floor wall panels over 50% installed 2. Structural inspection 05.03.2017 3. Completed plumbing rough in an apartment 4. Started mechanical coordination meetings. Conf call with BER 05.09 GOALS 1. Framing: Complete 3rd floor wall panels & start 4th floor floor system 2. Continue plumbing rough 3. Start electrical rough 4. Continue elevator shaft to 4th floor 5. Complete installation of relieving angle 6. Submittal & RFI priorities a. Stair 2 Framing & fire separation details b. Window shop drawings c. Roofing d. FCP products & shop drawings e. Plumbing fixtures f. Fire suppression system (wall depth at fire valve cabinets) 7. Shower drain, tile coordination meeting 05.10 WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 5.17.17 ACCOMPLISHMENTS 1. Framing: 3rd floor panels complete & 4th floor floor system in process 2. Completed elevator shaft to 4th floor 3. Completed installation of relieving angle at 1st floor & height adjustment of beam for S canopy 4. Started installation of air barrier 5. Resolution on kitchen countertop seams 6. Shower drain & tile coordination 05.10 GOALS 1. Framing: Start 4th floor wall panels 2. Continue plumbing rough 3. Start electrical rough 4. Submittal & RFI priorities - needed by 05.23 a. Fire separation details – stair 2 & complete separation at hallway shear walls b. Window shop drawings c. Roofing d. Plumbing fixtures e. RFIs for framing & mechanical coordination f. Fire suppression system (wall depth at fire valve cabinets) g. FCP shop drawings h. Roof condenser rack design – MJM generating comments WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 5.24.17 ACCOMPLISHMENTS 1. Framing: 4th floor panels in process 2. Columbia Gas installed gas line from street to building 05.24 3. Trades on site: plumbing, electrical, intumescent paint, accufab, membrane installers, crane, mason 4. High level of support on submittal and RFI activity 5. Design team met with Louis Hasbrouck and got approval on stair 2 design GOALS 1. Framing: continue 4th floor wall panels 2. Submittal & RFI priorities - needed by 05.30 a. Fire separation details – stair 2 & complete separation at hallway shear walls b. Roofing c. RFIs for framing & mechanical coordination d. Fire suppression system (wall depth at fire valve cabinets) e. Roof condenser rack design – MJM generating comments f. FCP shop drawings 3. Bulletin #6 – public art above main entry, building envelope details, misc SKs WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 5.31.17 ACCOMPLISHMENTS 1. Framing: roof framing package craned up this morning 2. Trades on site: plumbing, electrical, intumescent paint, accufab, membrane installers, crane, mason 3. High level of support on submittals, RFIs and design issues 4. Mockup framing complete GOALS 1. Framing: Complete roof system framing 2. Submittal & RFI priorities - needed by 06.06 a. Roofing b. Roof condenser rack design c. Envelope air sealing details d. Framing questions e. MEP/FP coordination f. Brick g. FCP 3. Bulletin #6 a. public art above main entry b. building envelope details c. stem wall details d. condenser rack design e. numerous SKs and plan sheet updates