2017_0523 LIVE 155 - MONTHLY REPORT - APRIL CONTROLLED CONSTRUCTION SUMMARY: APRIL 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 5/23/2017 ESTIMATED % COMPLETION: 40% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · Fabrication & Installation of wall and floor panels – 3rd floor panel work is complete. · Elevator shaft construction ongoing · Rough electrical & plumbing provisions ongoing II) OBSERVATIONS: · Wall panel and floor system installation ongoing. · Site appears to be managed well, safety protocols are emphasized & enforced by GC. · Site trailer continues to be the location for all regular job meetings. · Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Continue installation of wall and floor panels · Complete roof framing & canopy framing · Begin building wrap, roofing preparation. · Rough for MEP/FP to continue. IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 4.12.17 ACCOMPLISHMENTS 1. 1st Floor wall panel installation complete 2. Critical submittals approved – structural steel & 2x10 hallway hangers 3. Started stick framing front section of 1st floor 4. Envelope coordination meeting and finalize details – morning of 04.12 GOALS 1. Framing: complete 1st floor stick framing & floor system for 2nd floor. Start 2nd floor wall panels on Friday 2. Restart elevator shaft construction 3. Submittal & RFI priorities a. Window shop drawings b. Roofing c. Insulation 4. 04.19 Structural inspection & Hardware Coordination Meeting 5. Bulletin #5: Updates to P, FP & E drawings, bathroom details (especially valve locations), Vulkem spec, roof rack design 6. Final pricing for winter conditions WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 4.19.17 ACCOMPLISHMENTS 1. Framing: Stick framing front section of 1st floor & finishing up floor system for 2nd floor 2. Completed 2nd floor section of elevator shaft 3. Hardware coordination meeting – morning of 04.19 GOALS 1. Framing: complete 1st floor stick framing & floor system for 2nd floor. Start 2nd floor wall panels 2. Pre-rock plan & start rough mechanical installation 3. Submittal & RFI priorities a. Framing RFIs: Fire separation framing at stairs, web stiffeners, window framing details b. Window shop drawings c. FCP products & shop drawings d. Roofing 4. Bulletin #5: Updates to P, FP & E drawings, bathroom details (especially valve locations), Vulkem spec, roof rack design 5. 05.03 Structural inspection WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 4.26.17 ACCOMPLISHMENTS 1. Framing: 2nd floor floor system complete & 2nd floor wall panels over 50% installed 2. Bulletin #5 issued GOALS 1. Framing: Complete 2nd floor wall panels & start 3 floor floor system 2. Start plumbing rough 3. Start mechanical coordination meetings 4. Submittal & RFI priorities a. Fire separation framing at stairs b. DensGlass Type X for Pre-Rock c. Window shop drawings d. Roofing e. FCP products & shop drawings f. Stem wall framing & finish details 5. 05.03 Structural inspection