2017_0407 LIVE 155 - MONTHLY REPORT - MARCH MONTHLY CONTROLLED CONSTRUCTION SUMMARY PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 4/5/2017 ESTIMATED % COMPLETION: 35% SCHEDULE CONFORMANCE: (SEE ATTACHED) PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS:  Coordination & Installation of relieving angles  Fabrication & Installation of wall and floor panels  Backfill site electrical conduits for building electrical service II) OBSERVATIONS:  Completion of slab allow for wall and floor panel installation to begin.  Temporary service has been installed  Snowfall & cold temps complicated site operations  Site appears to be managed well, safety protocols are emphasized & enforced by GC.  Site trailer continues to be the location for all regular job meetings.  Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS  Steel/Structural inspections  Continue installation of wall and floor panels  Envelope pre-task conference  Envelope/Fiber cement siding shop coordination and review  Site visit from L. Hasbrouck on 4/12 IV) INFORMATION/ACTION REQUIRED:  None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 3.15.17 ACCOMPLISHMENTS 1. Submittal reviews completed (Approved & AAN) a. Slab submittals b. 2nd Floor Wall Panel Shop Drawings c. Intumescent Coating d. Elevator Shop Drawings e. Fire suppression Shop Drawings & Hydraulic Calcs f. HVAC submittals (11 of 15) g. Masonry submittals h. Electrical arc flash study 2. P and FP sheets updated 3. Completed slab prep 4. Completed roof drain tie 5. Lance & Peter M. met to go through siding details GOALS 1. Clean up snow 2. Pour slab early next week 3/20 or 3/21 (depending on weather) 3. Submittal & RFI priorities a. Structural steel relieving angle shop drawings b. Wedge bolts, tension ties, and misc hardware 4. CAD files for mechanical coordination WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 3.22.17 ACCOMPLISHMENTS 1. Poured slab 03.21: over 250 cu yd 2. Poured site electrical duct bank 3. Significant submittal activity 4. Received CAD files for mechanical coordination GOALS 1. Sitework: Backfill site electrical conduits for permanent service & tie into pole 2. Install temporary service 3. Pre-construction safety meeting with framers 4. Submittal & RFI priorities a. Structural steel relieving angle shop drawings b. misc hardware 5. Envelope coordination meeting and finalizing details next Wednesday (3.29) 6. Grab bar mockup with 16 gauge material WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 3.29.17 ACCOMPLISHMENTS 1. Installed temporary service 2. Held pre-construction safety meeting with framers 3. 1st Floor Wall panels on site 4. Started installing sill plates GOALS 1. Framing: complete installation of 1st floor panels & start floor system for 2nd floor 2. Sitework: Backfill site electrical conduits for permanent service & tie into pole 3. Submittal & RFI priorities a. Structural steel relieving angle shop drawings b. Floor system hanger for 2x10 c. Window trim profile, color & shop drawings d. Elevator Louver 4. Start mechanical coordination meetings 5. Fiber cement siding planning meeting next Wednesday (4.05) 6. Envelope coordination meeting and finalizing details Wednesday (4.12) 7. Structural inspection & Northampton Building Department - Wednesday (4.12) 8. Final pricing for winter conditions IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish1HAP Housing Northampton, LIVE 155511 daysFri 3/18/16NAFri 3/18/16Fri 3/2/18429 daysFri 3/18/16Wed 11/8/172General Contractor Proposals due1 dayFri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/160 daysFri 3/18/16Fri 3/18/163HAP and PFRA+LDA proposal review and shortisted GC's notification2 daysFri 3/18/16Tue 3/22/16Fri 3/18/16Tue 3/22/166 daysFri 3/18/16Fri 3/25/164General Contractor interviews0 daysTue 3/22/16Tue 3/22/16Tue 3/22/16Tue 3/22/162 daysTue 3/29/16Wed 3/30/165HAP and PFRA+LDA deliberation and General Contractor selection8 daysTue 3/22/16Fri 4/1/16Tue 3/22/16Fri 4/1/164 daysThu 3/31/16Tue 4/5/166AIA A101-2007 negotiation/signing102 daysWed 4/20/16Fri 9/9/16Wed 4/20/16Fri 9/9/1615 daysWed 4/6/16Tue 4/26/167HAP, PFRA+LDA and General Contractor introductions and kick off mtg.1 dayWed 4/20/16Wed 4/20/16Wed 4/20/16Wed 4/20/160 daysTue 4/26/16Tue 4/26/168Pre-construction, Publish Construction Documents75 daysWed 4/20/16Wed 8/3/16Wed 4/20/16Wed 8/3/1660 daysWed 4/27/16Tue 7/19/169Resident relocations21 daysMon 8/1/16Thu 9/1/16Mon 8/1/16Thu 9/1/1615 daysWed 7/20/16Tue 8/9/1610Financial Closing1 dayWed 12/28/16Wed 12/28/16Wed 12/28/16Wed 12/28/160 days?NANA11Long Lead Items158 daysWed 8/24/16NAWed 8/24/16Fri 3/31/17110 daysWed 7/20/16Tue 12/20/1612Abatement award, submittals and regulatory notifications18 daysThu 9/8/16Mon 10/3/16Thu 9/8/16Mon 10/3/1620 daysWed 7/20/16Tue 8/16/1613Structural Steel award, shop drawing submittal (anchor bolt drawing), review and approval0 daysWed 8/24/16Thu 8/25/16Wed 8/24/16Thu 8/25/1625 daysWed 7/27/16Tue 8/30/1614Structural Steel fabrication53 daysWed 11/23/16Fri 2/3/17Wed 11/23/16Fri 2/3/1740 daysWed 8/31/16Tue 10/25/1615Concrete award, rebar shop drawing submittal, review and approval30 daysTue 10/25/16Mon 12/5/16Tue 10/25/16Mon 12/5/1620 daysWed 8/3/16Tue 8/30/1616Rebar fabrication0 daysFri 11/18/16Mon 12/5/16Fri 11/18/16Mon 12/5/1615 daysWed 8/31/16Tue 9/20/1617Wood framing award, wall panels, joists and trusses submittals, review and approval38 daysMon 12/5/16Wed 1/25/17Mon 12/5/16Wed 1/25/1735 daysWed 8/10/16Tue 9/27/1618Wall panels, joists and trusses fabrication25 daysWed 1/25/17NAWed 1/25/17Wed 3/1/1725 daysWed 9/28/16Tue 11/1/1619Elevator award, shop drawing submittal (pit dimensions and embed locations)18 daysTue 11/22/16Wed 1/4/17Tue 11/22/16Wed 1/4/1725 daysWed 8/17/16Tue 9/20/1620Award Doors, Frames and Hardware, submittals, review and approval25 daysNANATue 11/29/16Mon 1/2/1725 daysWed 8/24/16Tue 9/27/1621Electrical award, Electrical Gear and underground submittals, review and approval0 daysWed 9/28/16Thu 11/10/16Wed 9/28/16Thu 11/10/1630 daysWed 8/31/16Tue 10/11/1622Electrical Gear lead time50 daysFri 11/18/16NAFri 11/18/16Thu 1/26/1750 daysWed 10/12/16Tue 12/20/1623Plumbing award, underground submittals, review and approval32 daysMon 10/31/16Tue 12/13/16Mon 10/31/16Tue 12/13/1620 daysWed 9/7/16Tue 10/4/1624HVAC award0 daysMon 10/24/16Fri 10/28/16Mon 10/24/16Fri 10/28/165 daysWed 9/14/16Tue 9/20/1625Sprinkler award24 daysThu 11/10/16Tue 12/13/16Thu 11/10/16Tue 12/13/165 daysWed 9/21/16Tue 9/27/1626MEP Coordination Drawings40 daysMon 2/6/17NAMon 2/6/17Fri 3/31/1740 daysWed 10/12/16Tue 12/6/1627Footings, Foundations, Core and Shell325 daysFri 9/9/16NAFri 9/9/16Thu 12/7/17265 daysTue 8/9/16Tue 8/15/1728Limited Notice to Proceed (NTP) Abatement & Demolition1 dayFri 9/9/16Fri 9/9/16Fri 9/9/16Fri 9/9/160 daysTue 8/9/16Tue 8/9/1629Abatement19 daysMon 9/12/16Fri 10/7/16Mon 9/12/16Fri 10/7/160 days?NANA30Site protection and preparations for demolition15 daysTue 9/13/16Mon 10/3/16Tue 9/13/16Mon 10/3/165 daysWed 8/10/16Tue 8/16/1631Demolish and remove 1299 daysThu 10/13/16Tue 10/25/16Thu 10/13/16Tue 10/25/1620 daysWed 8/17/16Tue 9/13/1632Full Notice to Proceed (NTP)1 dayWed 12/28/16Wed 12/28/16Wed 12/28/16Wed 12/28/160 days?NANA3/22MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: 155- Project Schedule 3Date: Fri 3/24/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish33Clear and strip site, building control offsets5 daysTue 9/13/16Tue 11/1/16Tue 9/13/16Tue 11/1/165 daysWed 9/14/16Tue 9/20/1634Excavate, form, pour, strip, backfill & compact footings and foundations51 daysThu 11/17/16Thu 1/26/17Thu 11/17/16Thu 1/26/1720 daysWed 9/21/16Tue 10/18/1635Elevator pit, excavate, form, pour, strip and backfill0 daysFri 1/6/17Mon 1/23/17Fri 1/6/17Mon 1/23/1710 daysWed 10/19/16Tue 11/1/1636Plumbing underground, excavate, pipe, inspect and backfill26 daysWed 1/11/17Fri 3/3/17Wed 1/11/17Fri 3/3/1715 daysWed 11/2/16Tue 11/22/1637Electrical underground, excavate, place, inspect and backfill7 daysWed 1/11/17Mon 2/6/17Wed 1/11/17Mon 2/6/1715 daysWed 11/2/16Tue 11/22/1638Sanitary, Storm, Domestic Water and Sprinkler service29 daysWed 9/28/16Mon 11/7/16Wed 9/28/16Mon 11/7/1630 daysWed 10/19/16Tue 11/29/1639Transformer vault, utility poles and ductbank for electrical service17 daysMon 2/27/17Tue 3/21/17Mon 2/27/17Tue 3/21/1730 daysWed 10/19/16Tue 11/29/1640Slab on grade, prep, pour and finish18 daysWed 2/22/17Tue 3/21/17Wed 2/22/17Tue 3/21/175 daysWed 11/23/16Tue 11/29/1641Steel erection and inspection13 daysFri 2/10/17Tue 2/28/17Fri 2/10/17Tue 2/28/1710 daysWed 11/30/16Tue 12/13/1642Elevator shaft CMU25 daysTue 2/14/17NATue 2/14/17Mon 3/20/1715 daysWed 12/14/16Tue 1/3/1743Wood framing Level 1 and 2nd floor deck15 daysFri 3/24/17NAFri 3/24/17Thu 4/13/1710 daysWed 12/14/16Tue 12/27/1644Wood framing Level 2 and 3rd floor deck20 daysNANAFri 4/7/17Thu 5/4/1715 daysWed 12/21/16Tue 1/10/1745Wood framing Level 3 and 4th floor deck15 daysNANAFri 4/28/17Thu 5/18/1715 daysWed 1/4/17Tue 1/24/1746Wood framing Level 4 and roof deck including parapet25 daysNANAFri 5/12/17Thu 6/15/1725 daysWed 1/18/17Tue 2/21/1747Fully adhered vapor barrier on roof5 daysNANAFri 6/16/17Thu 6/22/175 daysWed 2/22/17Tue 2/28/1748Window install in all non-masonry openings10 daysNANAFri 6/16/17Thu 6/29/1710 daysWed 2/22/17Tue 3/7/1749Temporary infills at window masonry openings and future storefront10 daysNANAFri 6/16/17Thu 6/29/1710 daysWed 2/22/17Tue 3/7/1750Building tight0 daysNANAThu 6/29/17Thu 6/29/170 daysTue 3/7/17Tue 3/7/1751Polyiso insulation and fully adhered EPDM roofing15 daysNANAFri 6/23/17Thu 7/13/1715 daysWed 3/1/17Tue 3/21/1752Masonry veneer and wash25 daysNANAFri 6/16/17Thu 7/20/1725 daysWed 2/22/17Tue 3/28/1753Window install in masonry openings10 daysNANAFri 7/21/17Thu 8/3/1710 daysWed 3/29/17Tue 4/11/1754Storefront installation10 daysNANAFri 8/4/17Thu 8/17/1710 daysWed 4/12/17Tue 4/25/1755Flashing, furring and fiber cement siding50 daysNANAFri 6/30/17Thu 9/7/1750 daysWed 3/8/17Tue 5/16/1756Parapet coping and EPDM terminations20 daysNANAFri 9/8/17Thu 10/5/1720 daysWed 5/17/17Tue 6/13/1757Photovoltaic installation20 daysNANAFri 10/6/17Thu 11/2/1720 daysWed 6/14/17Tue 7/11/1758HVAC Rooftop equipment, set and connect20 daysNANAFri 10/6/17Thu 11/2/1720 daysWed 6/14/17Tue 7/11/1759Site drainage and electrical30 daysNANAFri 8/18/17Thu 9/28/1730 daysWed 4/26/17Tue 6/6/1760Grading and shaping15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/7/17Tue 6/27/1761Site concrete and hardscape15 daysNANAFri 10/13/17Thu 11/2/1715 daysWed 6/21/17Tue 7/11/1762Loam, planting and seeding15 daysNANAFri 11/3/17Thu 11/23/1715 daysWed 7/12/17Tue 8/1/1763Site signage, striping, miscellaneous10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/2/17Tue 8/15/17644th FLOOR140 daysNANAFri 6/30/17Thu 1/11/18140 daysWed 3/8/17Tue 9/19/17MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 2Project: 155- Project Schedule 3Date: Fri 3/24/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish65MEP Risers and testing20 daysNANAFri 6/30/17Thu 7/27/1720 daysWed 3/8/17Tue 4/4/1766Pre-rock 4th floor corridors and common areas5 daysNANAFri 6/30/17Thu 7/6/175 daysWed 3/8/17Tue 3/14/1767Electrical and Fire Alarm rough and fire stopping 4th floor15 daysNANAFri 7/28/17Thu 8/17/1715 daysWed 4/5/17Tue 4/25/1768Plumbing rough and fire stopping 4th floor15 daysNANAFri 7/28/17Thu 8/17/1715 daysWed 4/5/17Tue 4/25/1769HVAC rough and fire stopping 4th floor15 daysNANAFri 7/28/17Thu 8/17/1715 daysWed 4/5/17Tue 4/25/1770Sprinkler rough and fire stopping 4th floor15 daysNANAFri 7/28/17Thu 8/17/1715 daysWed 4/5/17Tue 4/25/1771MEP Rough Inspections 4th Floor5 daysNANAFri 8/18/17Thu 8/24/175 daysWed 4/26/17Tue 5/2/1772Insulation, piping and in wall5 daysNANAFri 8/25/17Thu 8/31/175 daysWed 5/3/17Tue 5/9/1773Drywall, tape, finish, prime and first coat15 daysNANAFri 9/1/17Thu 9/21/1715 daysWed 5/10/17Tue 5/30/1774Complete finishes to elevator door10 daysNANAFri 9/15/17Thu 9/28/1710 daysWed 5/24/17Tue 6/6/1775Resinous shower bases, set in place5 daysNANAFri 9/15/17Thu 9/21/175 daysWed 5/24/17Tue 5/30/1776Ceramic tile in thinset at showers15 daysNANAFri 9/15/17Thu 10/5/1715 daysWed 5/24/17Tue 6/13/1777Gypcrete placement 1"5 daysNANAFri 10/6/17Thu 10/12/175 daysWed 6/14/17Tue 6/20/1778Door frame installation10 daysNANAFri 10/13/17Thu 10/26/1710 daysWed 6/21/17Tue 7/4/1779Cabinet and countertop installation10 daysNANAFri 10/13/17Thu 10/26/1710 daysWed 6/21/17Tue 7/4/1780Epoxy bathroom floors with integral cove base10 daysNANAFri 10/20/17Thu 11/2/1710 daysWed 6/28/17Tue 7/11/1781Plumbing finishes10 daysNANAFri 10/27/17Thu 11/9/1710 daysWed 7/5/17Tue 7/18/1782Electrical and fire alarm finishes10 daysNANAFri 10/27/17Thu 11/9/1710 daysWed 7/5/17Tue 7/18/1783HVAC finishes10 daysNANAFri 10/27/17Thu 11/9/1710 daysWed 7/5/17Tue 7/18/1784Vinyl plank flooring 10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/19/17Tue 8/1/1785Wood base, door casing, and solid surface sills10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 7/26/17Tue 8/8/1786Doors, hardware, and accessories10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/2/17Tue 8/15/1787Paint final coat in units, patch and paint corridor5 daysNANAFri 12/8/17Thu 12/14/175 daysWed 8/16/17Tue 8/22/1788Carpet corridor5 daysNANAFri 12/15/17Thu 12/21/175 daysWed 8/23/17Tue 8/29/1789Pre-punchlist15 daysNANAFri 12/22/17Thu 1/11/1815 daysWed 8/30/17Tue 9/19/17903rd FLOOR120 daysNANAFri 8/11/17Thu 1/25/18120 daysWed 4/19/17Tue 10/3/1791Pre-rock 3rd floor corridors and common areas5 daysNANAFri 8/11/17Thu 8/17/175 daysWed 4/19/17Tue 4/25/1792Electrical and Fire Alarm rough and fire stopping 3rd floor15 daysNANAFri 8/18/17Thu 9/7/1715 daysWed 4/26/17Tue 5/16/1793Plumbing rough and fire stopping 3rd floor15 daysNANAFri 8/18/17Thu 9/7/1715 daysWed 4/26/17Tue 5/16/1794HVAC rough and fire stopping 3rd floor15 daysNANAFri 8/18/17Thu 9/7/1715 daysWed 4/26/17Tue 5/16/1795Sprinkler rough and fire stopping 3rd floor15 daysNANAFri 8/18/17Thu 9/7/1715 daysWed 4/26/17Tue 5/16/1796MEP Rough Inspections 3rd Floor5 daysNANAFri 9/8/17Thu 9/14/175 daysWed 5/17/17Tue 5/23/17MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 3Project: 155- Project Schedule 3Date: Fri 3/24/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish97Insulation, piping and in wall5 daysNANAFri 9/15/17Thu 9/21/175 daysWed 5/24/17Tue 5/30/1798Drywall, tape, finish, prime and first coat15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 5/31/17Tue 6/20/1799Complete finishes to elevator door10 daysNANAFri 10/6/17Thu 10/19/1710 daysWed 6/14/17Tue 6/27/17100Resinous shower bases, set in place5 daysNANAFri 10/6/17Thu 10/12/175 daysWed 6/14/17Tue 6/20/17101Ceramic tile in thinset at showers15 daysNANAFri 10/6/17Thu 10/26/1715 daysWed 6/14/17Tue 7/4/17102Gypcrete placement 1"5 daysNANAFri 10/27/17Thu 11/2/175 daysWed 7/5/17Tue 7/11/17103Door frame installation5 daysNANAFri 11/3/17Thu 11/9/175 daysWed 7/12/17Tue 7/18/17104Cabinet and countertop installation10 daysNANAFri 11/3/17Thu 11/16/1710 daysWed 7/12/17Tue 7/25/17105Epoxy bathroom floors with integral cove base10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/19/17Tue 8/1/17106Plumbing finishes10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 7/26/17Tue 8/8/17107Electrical and fire alarm finishes10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 7/26/17Tue 8/8/17108HVAC finishes10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 7/26/17Tue 8/8/17109Vinyl plank flooring 10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/9/17Tue 8/22/17110Wood base, door casing, and solid surface sills10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17111Doors, hardware, and accessories10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17112Paint final coat in units, patch and paint corridor5 daysNANAFri 12/22/17Thu 12/28/175 daysWed 8/30/17Tue 9/5/17113Carpet corridor5 daysNANAFri 12/29/17Thu 1/4/185 daysWed 9/6/17Tue 9/12/17114Pre-punchlist15 daysNANAFri 1/5/18Thu 1/25/1815 daysWed 9/13/17Tue 10/3/171152nd FLOOR120 daysNANAFri 9/1/17Thu 2/15/18120 daysWed 5/10/17Tue 10/24/17116Pre-rock 2nd floor corridors and common areas5 daysNANAFri 9/1/17Thu 9/7/175 daysWed 5/10/17Tue 5/16/17117Electrical and Fire Alarm rough and fire stopping 2nd floor15 daysNANAFri 9/8/17Thu 9/28/1715 daysWed 5/17/17Tue 6/6/17118Plumbing rough and fire stopping 2nd floor15 daysNANAFri 9/8/17Thu 9/28/1715 daysWed 5/17/17Tue 6/6/17119HVAC rough and fire stopping 2nd floor15 daysNANAFri 9/8/17Thu 9/28/1715 daysWed 5/17/17Tue 6/6/17120Sprinkler rough and fire stopping 2nd floor15 daysNANAFri 9/8/17Thu 9/28/1715 daysWed 5/17/17Tue 6/6/17121Elevator install30 daysNANAFri 9/8/17Thu 10/19/1730 daysWed 5/17/17Tue 6/27/17122MEP Rough Inspections 2nd Floor5 daysNANAFri 9/29/17Thu 10/5/175 daysWed 6/7/17Tue 6/13/17123Insulation, piping and in wall5 daysNANAFri 10/6/17Thu 10/12/175 daysWed 6/14/17Tue 6/20/17124Drywall, tape, finish, prime and first coat15 daysNANAFri 10/13/17Thu 11/2/1715 daysWed 6/21/17Tue 7/11/17125Complete finishes to elevator door10 daysNANAFri 11/3/17Thu 11/16/1710 daysWed 7/12/17Tue 7/25/17126Resinous shower bases, set in place5 daysNANAFri 10/27/17Thu 11/2/175 daysWed 7/5/17Tue 7/11/17127Ceramic tile in thinset at showers15 daysNANAFri 10/27/17Thu 11/16/1715 daysWed 7/5/17Tue 7/25/17128Gypcrete placement 1"5 daysNANAFri 11/17/17Thu 11/23/175 daysWed 7/26/17Tue 8/1/17MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 4Project: 155- Project Schedule 3Date: Fri 3/24/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish129Door frame installation5 daysNANAFri 11/24/17Thu 11/30/175 daysWed 8/2/17Tue 8/8/17130Cabinet and countertop installation10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/2/17Tue 8/15/17131Epoxy bathroom floors with integral cove base10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/9/17Tue 8/22/17132Plumbing finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17133Electrical and fire alarm finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17134HVAC finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17135Vinyl plank flooring 10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 8/30/17Tue 9/12/17136Wood base, door casing, and solid surface sills10 daysNANAFri 12/29/17Thu 1/11/1810 daysWed 9/6/17Tue 9/19/17137Doors, hardware, and accessories10 daysNANAFri 12/29/17Thu 1/11/1810 daysWed 9/6/17Tue 9/19/17138Paint final coat in units, patch and paint corridor5 daysNANAFri 1/12/18Thu 1/18/185 daysWed 9/20/17Tue 9/26/17139Carpet corridor5 daysNANAFri 1/19/18Thu 1/25/185 daysWed 9/27/17Tue 10/3/17140Pre-punchlist15 daysNANAFri 1/26/18Thu 2/15/1815 daysWed 10/4/17Tue 10/24/171411st FLOOR100 daysNANAFri 9/22/17Thu 2/8/18100 daysWed 5/31/17Tue 10/17/17142Pre-rock 1st floor corridors and common areas5 daysNANAFri 9/22/17Thu 9/28/175 daysWed 5/31/17Tue 6/6/17143Electrical and Fire Alarm rough and fire stopping 1st floor15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/7/17Tue 6/27/17144Plumbing rough and fire stopping 1st floor15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/7/17Tue 6/27/17145HVAC rough and fire stopping 1st floor15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/7/17Tue 6/27/17146Sprinkler rough and fire stopping 1st floor15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/7/17Tue 6/27/17147MEP Rough Inspections 1st Floor5 daysNANAFri 10/20/17Thu 10/26/175 daysWed 6/28/17Tue 7/4/17148Insulation, piping and in wall5 daysNANAFri 10/27/17Thu 11/2/175 daysWed 7/5/17Tue 7/11/17149Drywall, tape, finish, prime and first coat15 daysNANAFri 11/3/17Thu 11/23/1715 daysWed 7/12/17Tue 8/1/17150ACT Grid in Lobby and HAP Offices5 daysNANAFri 11/24/17Thu 11/30/175 daysWed 8/2/17Tue 8/8/17151Sprinkler heads, diffusers and recessed lighting in ACT5 daysNANAFri 12/1/17Thu 12/7/175 daysWed 8/9/17Tue 8/15/17152Resinous shower bases, set in place5 daysNANAFri 11/17/17Thu 11/23/175 daysWed 7/26/17Tue 8/1/17153Ceramic tile in thinset at showers10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 7/26/17Tue 8/8/17154Door frame installation10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/19/17Tue 8/1/17155Cabinet and countertop installation10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/2/17Tue 8/15/17156Epoxy bathroom floors with integral cove base10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/2/17Tue 8/15/17157Plumbing finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17158Electrical and fire alarm finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17159HVAC finishes10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/16/17Tue 8/29/17160Vinyl plank flooring 10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 8/30/17Tue 9/12/17MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 5Project: 155- Project Schedule 3Date: Fri 3/24/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish161Wood base, door casing, and solid surface sills10 daysNANAFri 12/29/17Thu 1/11/1810 daysWed 9/6/17Tue 9/19/17162Doors, hardware, and accessories10 daysNANAFri 12/29/17Thu 1/11/1810 daysWed 9/6/17Tue 9/19/17163Paint final coat in units, patch and paint corridor5 daysNANAFri 1/12/18Thu 1/18/185 daysWed 9/20/17Tue 9/26/17164Carpet corridor5 daysNANAFri 1/19/18Thu 1/25/185 daysWed 9/27/17Tue 10/3/17165HAP Office millwork5 daysNANAFri 12/1/17Thu 12/7/175 daysWed 8/9/17Tue 8/15/17166Polish and protect Lobby 100 concrete slab5 daysNANAFri 12/8/17Thu 12/14/175 daysWed 8/16/17Tue 8/22/17167Lobby 100 finishes, complete finishes to elevator door10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/23/17Tue 9/5/17168Pre-punchlist10 daysNANAFri 1/26/18Thu 2/8/1810 daysWed 10/4/17Tue 10/17/17169North & South Entries, STAIRS 1, 2, and 344 daysNANAFri 12/15/17Wed 2/14/1844 daysWed 8/23/17Mon 10/23/17170Stair 2 millwork and decorative railing10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/23/17Tue 9/5/17171Set storefront entrances5 daysNANAFri 12/15/17Thu 12/21/175 daysWed 8/23/17Tue 8/29/17172Install walk off entrance mats 5 daysNANAFri 12/22/17Thu 12/28/175 daysWed 8/30/17Tue 9/5/17173Video and security finishes10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 8/30/17Tue 9/12/17174Handrail install in Stairs 1 and 35 daysNANAFri 1/26/18Thu 2/1/185 daysWed 10/4/17Tue 10/10/17175Patch and paint drywall in Stairs 1,2,39 daysNANAFri 1/26/18Wed 2/7/189 daysWed 10/4/17Mon 10/16/17176Fire alarm devices and electric heater installation in Stairs 1 and 35 daysNANAFri 2/2/18Thu 2/8/185 daysWed 10/11/17Tue 10/17/17177Carpet treads and rubber nosing install in Stairs 1 and 35 daysNANAThu 2/8/18Wed 2/14/185 daysTue 10/17/17Mon 10/23/17178Equipment Start Up, Commissioning, Inspections and Close Out51 daysNANAFri 12/22/17Fri 3/2/1851 daysWed 8/30/17Wed 11/8/17179Fire alarm system programming and ring out, Record of Completion10 daysNANAFri 2/9/18Thu 2/22/1810 daysWed 10/18/17Tue 10/31/17180Rooftop Heat Pump, ERV and VRV equipment and system start up10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 8/30/17Tue 9/12/17181HVAC testing and balancing10 daysNANAFri 1/5/18Thu 1/18/1810 daysWed 9/13/17Tue 9/26/17182Water heater start up and balancing10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 8/30/17Tue 9/12/17183Substaintial Completion10 daysNANAFri 2/16/18Thu 3/1/1810 daysWed 10/25/17Tue 11/7/17184Final Plumbing Inspection2 daysNANAFri 1/5/18Mon 1/8/182 daysWed 9/13/17Thu 9/14/17185Final Electrical Inspection1 dayNANAFri 2/23/18Fri 2/23/181 dayWed 11/1/17Wed 11/1/17186Final Elevator Inspection2 daysNANAMon 2/26/18Tue 2/27/182 daysThu 11/2/17Fri 11/3/17187Final Fire Alarm Inspection2 daysNANAFri 2/23/18Mon 2/26/182 daysWed 11/1/17Thu 11/2/17188Final Building Inspection3 daysNANAWed 2/28/18Fri 3/2/183 daysMon 11/6/17Wed 11/8/17189Certificate of Occupancy and Building Turnover0 daysNANAFri 3/2/18Fri 3/2/180 daysWed 11/8/17Wed 11/8/17MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWMar 13, '16Mar 20, '16Mar 27, '16Apr 3, '16Apr 10, '16Apr 17, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 6Project: 155- Project Schedule 3Date: Fri 3/24/17