2017_0203 LIVE 155 - Monthly Report - January MONTHLY CONTROLLED CONSTRUCTION SUMMARY PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 2/3/17 ESTIMATED % COMPLETION: 12% SCHEDULE CONFORMANCE: (SEE ATTACHED) PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA, Douglas Dick -LDa I) WORK IN PROGRESS: · Continuing installation of foundations: Footings (interior & exterior), foundation walls, foundation wall insulation, base plate/anchor bolts · Continuing installation of utilities: Gas service coordinated with utility (installation in Spring 2018), trenching for electrical, plumbing, TEL/DATA, piping/conduit runs · Foundation backfilling & subgrade prep, stormwater structures & utility vaults · Start of coordination with Pleasant St/MassWorks design team for upcoming Pleasant St improvements projects. · Steel & Wall panels are in fabrication. II) OBSERVATIONS: · Cold weather required ground thaw machines to operate on site in support of backfill/concrete/excavation activities. · Two weeks of mild temperatures enabled rapid execution of foundation walls. · Completion of foundation walls limits available site for staging/lay down areas. · Site appears to be managed well, safety protocols are emphasized & enforced by GC. · Site trailer continues to be the location for all regular job meetings. · Work appears to be completed in accordance with plans and specifications. III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Final as built foundation wall dimensions. · Fire separation detail revisions (sketch is attached separately) approval from Northampton Building Department. · TEL/DATA final design scope & subcontractor IV) INFORMATION/ACTION REQUIRED: · Northampton review/comment on fire separation detail at egress stairs. (sketch attached for review). NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 1.04.17 ACCOMPLISHMENTS 1. Project Funding and full notice to proceed 2. Two ground thaw machines are on site & working well 3. Completed concrete for foundation wall along bike path 4. Completed storm drainage along Pleasant St while backfilling the front wall GOALS 1. Continue concrete: Elevator shaft & pier footings in front section of building 2. Continue backfilling & rigid insulation installation at foundation walls 3. Start deep underslab plumbing 4. Submittal & RFI priorities a. Structural steel piece drawings, relieving angles b. Wall Panel shop drawings c. Plumbing RFIs 5. Continue buy out of key subcontracts 6. Resolution of Fire Separation Details WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 1.11.17 ACCOMPLISHMENT 1. Poured rear wall & hallway walls 2. Installed conduit ductbank for electrical room 3. Started under-slab plumbing in the front section of the building 4. Design team: Significant submittal & RFI activity a. Elevator shaft – ready to start next week b. Structural steel piece drawings – NET, AAN & R&R c. Wall Panel shop drawings – 1st floor AAN GOALS 1. Complete foundation 2. Start elevator shaft 3. Continue under-slab plumbing, electrical & tel/data 4. Submittal & RFI priorities a. Structural steel piece drawings & RFIs b. Floor System Shop Drawings c. Plumbing RFIs 5. Roof tie off system design 6. Bulletin #4 7. Resolution of Fire Separation Details at stair WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 1.18.17 ACCOMPLISHMENTS 1. Poured all interior piers, and foundation walls in the front - almost ready for structural steel 2. Installing water lines into the building (fire suppression & water service) 3. Poured footing for back wall GOALS 1. Submittal & RFI priorities a. Structural steel piece drawings & RFIs b. Elevator shaft rebar shop drawings – start next week? c. Plumbing RFIs d. Wall Panel shop drawings e. Floor System Shop Drawings 2. Pour back wall & install temp power 3. Install conduit ductbank for electrical room 4. Under-slab plumbing & electrical in the front section of the building 5. Resolution of Fire Separation Details at stair WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 1.25.17 ACCOMPLISHMENT 1. Poured rear wall & hallway walls 2. Installed conduit ductbank for electrical room 3. Started under-slab plumbing in the front section of the building 4. Design team: Significant submittal & RFI activity a. Elevator shaft – ready to start next week b. Structural steel piece drawings – NET, AAN & R&R c. Wall Panel shop drawings – 1st floor AAN GOALS 1. Complete foundation 2. Start elevator shaft 3. Continue under-slab plumbing, electrical & tel/data 4. Submittal & RFI priorities a. Structural steel piece drawings & RFIs b. Floor System Shop Drawings c. Plumbing RFIs 5. Roof tie off system design 6. Bulletin #4 7. Resolution of Fire Separation Details at stair IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish1HAP Housing Northampton, LIVE 155506 daysFri 3/18/16NAFri 3/18/16Fri 2/23/18429 daysFri 3/18/16Wed 11/8/172General Contractor Proposals due1 dayFri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/160 daysFri 3/18/16Fri 3/18/163HAP and PFRA+LDA proposal review and shortisted GC's notification2 daysFri 3/18/16Tue 3/22/16Fri 3/18/16Tue 3/22/166 daysFri 3/18/16Fri 3/25/164General Contractor interviews0 daysTue 3/22/16Tue 3/22/16Tue 3/22/16Tue 3/22/162 daysTue 3/29/16Wed 3/30/165HAP and PFRA+LDA deliberation and General Contractor selection8 daysTue 3/22/16Fri 4/1/16Tue 3/22/16Fri 4/1/164 daysThu 3/31/16Tue 4/5/166AIA A101-2007 negotiation/signing102 daysWed 4/20/16Fri 9/9/16Wed 4/20/16Fri 9/9/1615 daysWed 4/6/16Tue 4/26/167HAP, PFRA+LDA and General Contractor introductions and kick off mtg.1 dayWed 4/20/16Wed 4/20/16Wed 4/20/16Wed 4/20/160 daysTue 4/26/16Tue 4/26/168Pre-construction, Publish Construction Documents75 daysWed 4/20/16Wed 8/3/16Wed 4/20/16Wed 8/3/1660 daysWed 4/27/16Tue 7/19/169Resident relocations39 daysNANAThu 8/4/16Tue 9/27/1615 daysWed 7/20/16Tue 8/9/1610Financial Closing1 dayWed 12/28/16Wed 12/28/16Wed 12/28/16Wed 12/28/160 days?NANA11Long Lead Items136 daysWed 8/24/16NAWed 8/24/16Wed 3/1/17110 daysWed 7/20/16Tue 12/20/1612Abatement award, submittals and regulatory notifications18 daysThu 9/8/16Mon 10/3/16Thu 9/8/16Mon 10/3/1620 daysWed 7/20/16Tue 8/16/1613Structural Steel award, shop drawing submittal (anchor bolt drawing), review and approval25 daysWed 8/24/16NAWed 8/24/16Wed 10/19/1625 daysWed 7/27/16Tue 8/30/1614Structural Steel fabrication40 daysNANAThu 10/20/16Wed 12/14/1640 daysWed 8/31/16Tue 10/25/1615Concrete award, rebar shop drawing submittal, review and approval30 daysTue 10/25/16Mon 12/5/16Tue 10/25/16Mon 12/5/1620 daysWed 8/3/16Tue 8/30/1616Rebar fabrication0 daysFri 11/18/16Mon 12/5/16Fri 11/18/16Mon 12/5/1615 daysWed 8/31/16Tue 9/20/1617Wood framing award, wall panels, joists and trusses submittals, review and approval38 daysMon 12/5/16Wed 1/25/17Mon 12/5/16Wed 1/25/1735 daysWed 8/10/16Tue 9/27/1618Wall panels, joists and trusses fabrication25 daysWed 1/25/17NAWed 1/25/17Wed 3/1/1725 daysWed 9/28/16Tue 11/1/1619Elevator award, shop drawing submittal (pit dimensions and embed locations)25 daysTue 11/22/16NATue 11/22/16Fri 1/13/1725 daysWed 8/17/16Tue 9/20/1620Award Doors, Frames and Hardware, submittals, review and approval25 daysNANATue 11/29/16Mon 1/2/1725 daysWed 8/24/16Tue 9/27/1621Electrical award, Electrical Gear and underground submittals, review and approval0 daysWed 9/28/16Thu 11/10/16Wed 9/28/16Thu 11/10/1630 daysWed 8/31/16Tue 10/11/1622Electrical Gear lead time50 daysFri 11/18/16NAFri 11/18/16Thu 1/26/1750 daysWed 10/12/16Tue 12/20/1623Plumbing award, underground submittals, review and approval32 daysMon 10/31/16Tue 12/13/16Mon 10/31/16Tue 12/13/1620 daysWed 9/7/16Tue 10/4/1624HVAC award0 daysMon 10/24/16Fri 10/28/16Mon 10/24/16Fri 10/28/165 daysWed 9/14/16Tue 9/20/1625Sprinkler award24 daysThu 11/10/16Tue 12/13/16Thu 11/10/16Tue 12/13/165 daysWed 9/21/16Tue 9/27/1626MEP Coordination Drawings40 daysNANAWed 12/14/16Tue 2/7/1740 daysWed 10/12/16Tue 12/6/1627Footings, Foundations, Core and Shell320 daysFri 9/9/16NAFri 9/9/16Thu 11/30/17265 daysTue 8/9/16Tue 8/15/1728Limited Notice to Proceed (NTP) Abatement & Demolition1 dayFri 9/9/16Fri 9/9/16Fri 9/9/16Fri 9/9/160 daysTue 8/9/16Tue 8/9/1629Abatement19 daysMon 9/12/16Fri 10/7/16Mon 9/12/16Fri 10/7/160 days?NANA30Site protection and preparations for demolition15 daysTue 9/13/16Mon 10/3/16Tue 9/13/16Mon 10/3/165 daysWed 8/10/16Tue 8/16/1631Demolish and remove 1299 daysThu 10/13/16Tue 10/25/16Thu 10/13/16Tue 10/25/1620 daysWed 8/17/16Tue 9/13/1632Full Notice to Proceed (NTP)1 dayWed 12/28/16Wed 12/28/16Wed 12/28/16Wed 12/28/160 days?NANA33Clear and strip site, building control offsets5 daysTue 9/13/16Tue 11/1/16Tue 9/13/16Tue 11/1/165 daysWed 9/14/16Tue 9/20/1634Excavate, form, pour, strip, backfill & compact footings and foundations51 daysThu 11/17/16Thu 1/26/17Thu 11/17/16Thu 1/26/1720 daysWed 9/21/16Tue 10/18/1635Elevator pit, excavate, form, pour, strip and backfill15 daysFri 1/6/17NAFri 1/6/17Mon 2/13/1710 daysWed 10/19/16Tue 11/1/1636Plumbing underground, excavate, pipe, inspect and backfill25 daysWed 1/11/17NAWed 1/11/17Thu 3/2/1715 daysWed 11/2/16Tue 11/22/1637Electrical underground, excavate, place, inspect and backfill25 daysWed 1/11/17NAWed 1/11/17Thu 3/2/1715 daysWed 11/2/16Tue 11/22/1638Sanitary, Storm, Domestic Water and Sprinkler service29 daysWed 9/28/16Mon 11/7/16Wed 9/28/16Mon 11/7/1630 daysWed 10/19/16Tue 11/29/1639Transformer vault, utility poles and ductbank for electrical service30 daysNANAFri 1/6/17Thu 2/16/1730 daysWed 10/19/16Tue 11/29/1640Slab on grade, prep, pour and finish10 daysNANAFri 3/3/17Thu 3/16/175 daysWed 11/23/16Tue 11/29/1641Steel erection and inspection15 daysNANAMon 2/13/17Fri 3/3/1710 daysWed 11/30/16Tue 12/13/16MTWTFMar 13, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: 155- Project Schedule 1Date: Fri 1/27/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish42Elevator shaft CMU25 daysNANATue 2/14/17Mon 3/20/1715 daysWed 12/14/16Tue 1/3/1743Wood framing Level 1 and 2nd floor deck15 daysNANAFri 3/17/17Thu 4/6/1710 daysWed 12/14/16Tue 12/27/1644Wood framing Level 2 and 3rd floor deck20 daysNANAFri 3/31/17Thu 4/27/1715 daysWed 12/21/16Tue 1/10/1745Wood framing Level 3 and 4th floor deck15 daysNANAFri 4/21/17Thu 5/11/1715 daysWed 1/4/17Tue 1/24/1746Wood framing Level 4 and roof deck including parapet25 daysNANAFri 5/5/17Thu 6/8/1725 daysWed 1/18/17Tue 2/21/1747Fully adhered vapor barrier on roof5 daysNANAFri 6/9/17Thu 6/15/175 daysWed 2/22/17Tue 2/28/1748Window install in all non-masonry openings10 daysNANAFri 6/9/17Thu 6/22/1710 daysWed 2/22/17Tue 3/7/1749Temporary infills at window masonry openings and future storefront10 daysNANAFri 6/9/17Thu 6/22/1710 daysWed 2/22/17Tue 3/7/1750Building tight0 daysNANAThu 6/22/17Thu 6/22/170 daysTue 3/7/17Tue 3/7/1751Polyiso insulation and fully adhered EPDM roofing15 daysNANAFri 6/16/17Thu 7/6/1715 daysWed 3/1/17Tue 3/21/1752Masonry veneer and wash25 daysNANAFri 6/9/17Thu 7/13/1725 daysWed 2/22/17Tue 3/28/1753Window install in masonry openings10 daysNANAFri 7/14/17Thu 7/27/1710 daysWed 3/29/17Tue 4/11/1754Storefront installation10 daysNANAFri 7/28/17Thu 8/10/1710 daysWed 4/12/17Tue 4/25/1755Flashing, furring and fiber cement siding50 daysNANAFri 6/23/17Thu 8/31/1750 daysWed 3/8/17Tue 5/16/1756Parapet coping and EPDM terminations20 daysNANAFri 9/1/17Thu 9/28/1720 daysWed 5/17/17Tue 6/13/1757Photovoltaic installation20 daysNANAFri 9/29/17Thu 10/26/1720 daysWed 6/14/17Tue 7/11/1758HVAC Rooftop equipment, set and connect20 daysNANAFri 9/29/17Thu 10/26/1720 daysWed 6/14/17Tue 7/11/1759Site drainage and electrical30 daysNANAFri 8/11/17Thu 9/21/1730 daysWed 4/26/17Tue 6/6/1760Grading and shaping15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 6/7/17Tue 6/27/1761Site concrete and hardscape15 daysNANAFri 10/6/17Thu 10/26/1715 daysWed 6/21/17Tue 7/11/1762Loam, planting and seeding15 daysNANAFri 10/27/17Thu 11/16/1715 daysWed 7/12/17Tue 8/1/1763Site signage, striping, miscellaneous10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 8/2/17Tue 8/15/17644th FLOOR140 daysNANAFri 6/23/17Thu 1/4/18140 daysWed 3/8/17Tue 9/19/1765MEP Risers and testing20 daysNANAFri 6/23/17Thu 7/20/1720 daysWed 3/8/17Tue 4/4/1766Pre-rock 4th floor corridors and common areas5 daysNANAFri 6/23/17Thu 6/29/175 daysWed 3/8/17Tue 3/14/1767Electrical and Fire Alarm rough and fire stopping 4th floor15 daysNANAFri 7/21/17Thu 8/10/1715 daysWed 4/5/17Tue 4/25/1768Plumbing rough and fire stopping 4th floor15 daysNANAFri 7/21/17Thu 8/10/1715 daysWed 4/5/17Tue 4/25/1769HVAC rough and fire stopping 4th floor15 daysNANAFri 7/21/17Thu 8/10/1715 daysWed 4/5/17Tue 4/25/1770Sprinkler rough and fire stopping 4th floor15 daysNANAFri 7/21/17Thu 8/10/1715 daysWed 4/5/17Tue 4/25/1771MEP Rough Inspections 4th Floor5 daysNANAFri 8/11/17Thu 8/17/175 daysWed 4/26/17Tue 5/2/1772Insulation, piping and in wall5 daysNANAFri 8/18/17Thu 8/24/175 daysWed 5/3/17Tue 5/9/1773Drywall, tape, finish, prime and first coat15 daysNANAFri 8/25/17Thu 9/14/1715 daysWed 5/10/17Tue 5/30/1774Complete finishes to elevator door10 daysNANAFri 9/8/17Thu 9/21/1710 daysWed 5/24/17Tue 6/6/1775Resinous shower bases, set in place5 daysNANAFri 9/8/17Thu 9/14/175 daysWed 5/24/17Tue 5/30/1776Ceramic tile in thinset at showers15 daysNANAFri 9/8/17Thu 9/28/1715 daysWed 5/24/17Tue 6/13/1777Gypcrete placement 1"5 daysNANAFri 9/29/17Thu 10/5/175 daysWed 6/14/17Tue 6/20/1778Door frame installation10 daysNANAFri 10/6/17Thu 10/19/1710 daysWed 6/21/17Tue 7/4/1779Cabinet and countertop installation10 daysNANAFri 10/6/17Thu 10/19/1710 daysWed 6/21/17Tue 7/4/1780Epoxy bathroom floors with integral cove base10 daysNANAFri 10/13/17Thu 10/26/1710 daysWed 6/28/17Tue 7/11/1781Plumbing finishes10 daysNANAFri 10/20/17Thu 11/2/1710 daysWed 7/5/17Tue 7/18/1782Electrical and fire alarm finishes10 daysNANAFri 10/20/17Thu 11/2/1710 daysWed 7/5/17Tue 7/18/17MTWTFMar 13, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 2Project: 155- Project Schedule 1Date: Fri 1/27/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish83HVAC finishes10 daysNANAFri 10/20/17Thu 11/2/1710 daysWed 7/5/17Tue 7/18/1784Vinyl plank flooring 10 daysNANAFri 11/3/17Thu 11/16/1710 daysWed 7/19/17Tue 8/1/1785Wood base, door casing, and solid surface sills10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/26/17Tue 8/8/1786Doors, hardware, and accessories10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 8/2/17Tue 8/15/1787Paint final coat in units, patch and paint corridor5 daysNANAFri 12/1/17Thu 12/7/175 daysWed 8/16/17Tue 8/22/1788Carpet corridor5 daysNANAFri 12/8/17Thu 12/14/175 daysWed 8/23/17Tue 8/29/1789Pre-punchlist15 daysNANAFri 12/15/17Thu 1/4/1815 daysWed 8/30/17Tue 9/19/17903rd FLOOR120 daysNANAFri 8/4/17Thu 1/18/18120 daysWed 4/19/17Tue 10/3/1791Pre-rock 3rd floor corridors and common areas5 daysNANAFri 8/4/17Thu 8/10/175 daysWed 4/19/17Tue 4/25/1792Electrical and Fire Alarm rough and fire stopping 3rd floor15 daysNANAFri 8/11/17Thu 8/31/1715 daysWed 4/26/17Tue 5/16/1793Plumbing rough and fire stopping 3rd floor15 daysNANAFri 8/11/17Thu 8/31/1715 daysWed 4/26/17Tue 5/16/1794HVAC rough and fire stopping 3rd floor15 daysNANAFri 8/11/17Thu 8/31/1715 daysWed 4/26/17Tue 5/16/1795Sprinkler rough and fire stopping 3rd floor15 daysNANAFri 8/11/17Thu 8/31/1715 daysWed 4/26/17Tue 5/16/1796MEP Rough Inspections 3rd Floor5 daysNANAFri 9/1/17Thu 9/7/175 daysWed 5/17/17Tue 5/23/1797Insulation, piping and in wall5 daysNANAFri 9/8/17Thu 9/14/175 daysWed 5/24/17Tue 5/30/1798Drywall, tape, finish, prime and first coat15 daysNANAFri 9/15/17Thu 10/5/1715 daysWed 5/31/17Tue 6/20/1799Complete finishes to elevator door10 daysNANAFri 9/29/17Thu 10/12/1710 daysWed 6/14/17Tue 6/27/17100Resinous shower bases, set in place5 daysNANAFri 9/29/17Thu 10/5/175 daysWed 6/14/17Tue 6/20/17101Ceramic tile in thinset at showers15 daysNANAFri 9/29/17Thu 10/19/1715 daysWed 6/14/17Tue 7/4/17102Gypcrete placement 1"5 daysNANAFri 10/20/17Thu 10/26/175 daysWed 7/5/17Tue 7/11/17103Door frame installation5 daysNANAFri 10/27/17Thu 11/2/175 daysWed 7/12/17Tue 7/18/17104Cabinet and countertop installation10 daysNANAFri 10/27/17Thu 11/9/1710 daysWed 7/12/17Tue 7/25/17105Epoxy bathroom floors with integral cove base10 daysNANAFri 11/3/17Thu 11/16/1710 daysWed 7/19/17Tue 8/1/17106Plumbing finishes10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/26/17Tue 8/8/17107Electrical and fire alarm finishes10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/26/17Tue 8/8/17108HVAC finishes10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/26/17Tue 8/8/17109Vinyl plank flooring 10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/9/17Tue 8/22/17110Wood base, door casing, and solid surface sills10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17111Doors, hardware, and accessories10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17112Paint final coat in units, patch and paint corridor5 daysNANAFri 12/15/17Thu 12/21/175 daysWed 8/30/17Tue 9/5/17113Carpet corridor5 daysNANAFri 12/22/17Thu 12/28/175 daysWed 9/6/17Tue 9/12/17114Pre-punchlist15 daysNANAFri 12/29/17Thu 1/18/1815 daysWed 9/13/17Tue 10/3/171152nd FLOOR120 daysNANAFri 8/25/17Thu 2/8/18120 daysWed 5/10/17Tue 10/24/17116Pre-rock 2nd floor corridors and common areas5 daysNANAFri 8/25/17Thu 8/31/175 daysWed 5/10/17Tue 5/16/17117Electrical and Fire Alarm rough and fire stopping 2nd floor15 daysNANAFri 9/1/17Thu 9/21/1715 daysWed 5/17/17Tue 6/6/17118Plumbing rough and fire stopping 2nd floor15 daysNANAFri 9/1/17Thu 9/21/1715 daysWed 5/17/17Tue 6/6/17119HVAC rough and fire stopping 2nd floor15 daysNANAFri 9/1/17Thu 9/21/1715 daysWed 5/17/17Tue 6/6/17120Sprinkler rough and fire stopping 2nd floor15 daysNANAFri 9/1/17Thu 9/21/1715 daysWed 5/17/17Tue 6/6/17121Elevator install30 daysNANAFri 9/1/17Thu 10/12/1730 daysWed 5/17/17Tue 6/27/17122MEP Rough Inspections 2nd Floor5 daysNANAFri 9/22/17Thu 9/28/175 daysWed 6/7/17Tue 6/13/17123Insulation, piping and in wall5 daysNANAFri 9/29/17Thu 10/5/175 daysWed 6/14/17Tue 6/20/17MTWTFMar 13, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 3Project: 155- Project Schedule 1Date: Fri 1/27/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish124Drywall, tape, finish, prime and first coat15 daysNANAFri 10/6/17Thu 10/26/1715 daysWed 6/21/17Tue 7/11/17125Complete finishes to elevator door10 daysNANAFri 10/27/17Thu 11/9/1710 daysWed 7/12/17Tue 7/25/17126Resinous shower bases, set in place5 daysNANAFri 10/20/17Thu 10/26/175 daysWed 7/5/17Tue 7/11/17127Ceramic tile in thinset at showers15 daysNANAFri 10/20/17Thu 11/9/1715 daysWed 7/5/17Tue 7/25/17128Gypcrete placement 1"5 daysNANAFri 11/10/17Thu 11/16/175 daysWed 7/26/17Tue 8/1/17129Door frame installation5 daysNANAFri 11/17/17Thu 11/23/175 daysWed 8/2/17Tue 8/8/17130Cabinet and countertop installation10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 8/2/17Tue 8/15/17131Epoxy bathroom floors with integral cove base10 daysNANAFri 11/24/17Thu 12/7/1710 daysWed 8/9/17Tue 8/22/17132Plumbing finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17133Electrical and fire alarm finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17134HVAC finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17135Vinyl plank flooring 10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/30/17Tue 9/12/17136Wood base, door casing, and solid surface sills10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 9/6/17Tue 9/19/17137Doors, hardware, and accessories10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 9/6/17Tue 9/19/17138Paint final coat in units, patch and paint corridor5 daysNANAFri 1/5/18Thu 1/11/185 daysWed 9/20/17Tue 9/26/17139Carpet corridor5 daysNANAFri 1/12/18Thu 1/18/185 daysWed 9/27/17Tue 10/3/17140Pre-punchlist15 daysNANAFri 1/19/18Thu 2/8/1815 daysWed 10/4/17Tue 10/24/171411st FLOOR100 daysNANAFri 9/15/17Thu 2/1/18100 daysWed 5/31/17Tue 10/17/17142Pre-rock 1st floor corridors and common areas5 daysNANAFri 9/15/17Thu 9/21/175 daysWed 5/31/17Tue 6/6/17143Electrical and Fire Alarm rough and fire stopping 1st floor15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 6/7/17Tue 6/27/17144Plumbing rough and fire stopping 1st floor15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 6/7/17Tue 6/27/17145HVAC rough and fire stopping 1st floor15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 6/7/17Tue 6/27/17146Sprinkler rough and fire stopping 1st floor15 daysNANAFri 9/22/17Thu 10/12/1715 daysWed 6/7/17Tue 6/27/17147MEP Rough Inspections 1st Floor5 daysNANAFri 10/13/17Thu 10/19/175 daysWed 6/28/17Tue 7/4/17148Insulation, piping and in wall5 daysNANAFri 10/20/17Thu 10/26/175 daysWed 7/5/17Tue 7/11/17149Drywall, tape, finish, prime and first coat15 daysNANAFri 10/27/17Thu 11/16/1715 daysWed 7/12/17Tue 8/1/17150ACT Grid in Lobby and HAP Offices5 daysNANAFri 11/17/17Thu 11/23/175 daysWed 8/2/17Tue 8/8/17151Sprinkler heads, diffusers and recessed lighting in ACT5 daysNANAFri 11/24/17Thu 11/30/175 daysWed 8/9/17Tue 8/15/17152Resinous shower bases, set in place5 daysNANAFri 11/10/17Thu 11/16/175 daysWed 7/26/17Tue 8/1/17153Ceramic tile in thinset at showers10 daysNANAFri 11/10/17Thu 11/23/1710 daysWed 7/26/17Tue 8/8/17154Door frame installation10 daysNANAFri 11/3/17Thu 11/16/1710 daysWed 7/19/17Tue 8/1/17155Cabinet and countertop installation10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 8/2/17Tue 8/15/17156Epoxy bathroom floors with integral cove base10 daysNANAFri 11/17/17Thu 11/30/1710 daysWed 8/2/17Tue 8/15/17157Plumbing finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17158Electrical and fire alarm finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17159HVAC finishes10 daysNANAFri 12/1/17Thu 12/14/1710 daysWed 8/16/17Tue 8/29/17160Vinyl plank flooring 10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/30/17Tue 9/12/17161Wood base, door casing, and solid surface sills10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 9/6/17Tue 9/19/17162Doors, hardware, and accessories10 daysNANAFri 12/22/17Thu 1/4/1810 daysWed 9/6/17Tue 9/19/17163Paint final coat in units, patch and paint corridor5 daysNANAFri 1/5/18Thu 1/11/185 daysWed 9/20/17Tue 9/26/17164Carpet corridor5 daysNANAFri 1/12/18Thu 1/18/185 daysWed 9/27/17Tue 10/3/17MTWTFMar 13, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 4Project: 155- Project Schedule 1Date: Fri 1/27/17 IDTask ModeTask NameDuration Actual Start Actual Finish Start Finish Baseline1 DurationBaseline1 Start Baseline1 Finish165HAP Office millwork5 daysNANAFri 11/24/17Thu 11/30/175 daysWed 8/9/17Tue 8/15/17166Polish and protect Lobby 100 concrete slab5 daysNANAFri 12/1/17Thu 12/7/175 daysWed 8/16/17Tue 8/22/17167Lobby 100 finishes, complete finishes to elevator door10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/23/17Tue 9/5/17168Pre-punchlist10 daysNANAFri 1/19/18Thu 2/1/1810 daysWed 10/4/17Tue 10/17/17169North & South Entries, STAIRS 1, 2, and 344 daysNANAFri 12/8/17Wed 2/7/1844 daysWed 8/23/17Mon 10/23/17170Stair 2 millwork and decorative railing10 daysNANAFri 12/8/17Thu 12/21/1710 daysWed 8/23/17Tue 9/5/17171Set storefront entrances5 daysNANAFri 12/8/17Thu 12/14/175 daysWed 8/23/17Tue 8/29/17172Install walk off entrance mats 5 daysNANAFri 12/15/17Thu 12/21/175 daysWed 8/30/17Tue 9/5/17173Video and security finishes10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/30/17Tue 9/12/17174Handrail install in Stairs 1 and 35 daysNANAFri 1/19/18Thu 1/25/185 daysWed 10/4/17Tue 10/10/17175Patch and paint drywall in Stairs 1,2,39 daysNANAFri 1/19/18Wed 1/31/189 daysWed 10/4/17Mon 10/16/17176Fire alarm devices and electric heater installation in Stairs 1 and 35 daysNANAFri 1/26/18Thu 2/1/185 daysWed 10/11/17Tue 10/17/17177Carpet treads and rubber nosing install in Stairs 1 and 35 daysNANAThu 2/1/18Wed 2/7/185 daysTue 10/17/17Mon 10/23/17178Equipment Start Up, Commissioning, Inspections and Close Out51 daysNANAFri 12/15/17Fri 2/23/1851 daysWed 8/30/17Wed 11/8/17179Fire alarm system programming and ring out, Record of Completion10 daysNANAFri 2/2/18Thu 2/15/1810 daysWed 10/18/17Tue 10/31/17180Rooftop Heat Pump, ERV and VRV equipment and system start up10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/30/17Tue 9/12/17181HVAC testing and balancing10 daysNANAFri 12/29/17Thu 1/11/1810 daysWed 9/13/17Tue 9/26/17182Water heater start up and balancing10 daysNANAFri 12/15/17Thu 12/28/1710 daysWed 8/30/17Tue 9/12/17183Punchlist10 daysNANAFri 2/9/18Thu 2/22/1810 daysWed 10/25/17Tue 11/7/17184Final Plumbing Inspection2 daysNANAFri 12/29/17Mon 1/1/182 daysWed 9/13/17Thu 9/14/17185Final Electrical Inspection1 dayNANAFri 2/16/18Fri 2/16/181 dayWed 11/1/17Wed 11/1/17186Final Elevator Inspection2 daysNANAMon 2/19/18Tue 2/20/182 daysThu 11/2/17Fri 11/3/17187Final Fire Alarm Inspection2 daysNANAFri 2/16/18Mon 2/19/182 daysWed 11/1/17Thu 11/2/17188Final Building Inspection3 daysNANAWed 2/21/18Fri 2/23/183 daysMon 11/6/17Wed 11/8/17189Certificate of Occupancy and Turnover0 daysNANAFri 2/23/18Fri 2/23/180 daysWed 11/8/17Wed 11/8/17MTWTFMar 13, '16TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 5Project: 155- Project Schedule 1Date: Fri 1/27/17