CONSTRUCTION MEETING MINUTES
MEETING NO. 25
PROJECT: Smith College Crew House
PROJECT NO: 15038
DATE: 07/27/2017
PRESENT Gary Hartwell, (GH), Smith College
Jim Culliton, (JC), Allegrone
Bruce Belisle, (BB), Allegrone
Ben Kleiner, (BK), Allegrone
Chris Farley, (CF), KRA
WEATHER: Raining, 70’s
In accordance with 780 CMR107.6, I have completed field visits and observed the following work:
Progress as reported by Contractor:
Upper sidewalk concrete poured
Site Light by sidewalk installed
All interior doors and trim installed in Addition
Tile and grout complete
Exterior wood shingles 97% complete
Exterior painting for Entry Addition is on-going
Interior painting and stain is on-going
Schedule:
Schedule shows building and upper walkway complete by 12 Sep. 2017.
GH confirms Fall semester check in is 1 Sep. 2017.
Submittals / Shop Drawings:
Exhaust Fan submittal outstanding
Roller Shades to be provided by Smith College
RFI’s/ASI’s/SK’s/PR/COP/CO:
BK provided RFI and submittal logs for the record
Requisition for Payment:
NA
Reports:
NA
Page 2 of 5
OLD BUSINESS
2.01 01/12/17 – Lighting Review
Please see previous minutes for complete history of this item.
05/04/17 – GH is awaiting a delivery date from Theatrix for
specified fixtures and will contact BW and arrange for
temporary fixtures to be installed by 16 May for events on 19
May 2017.
05/11/17 – GG will provide a price for dimmers and interface
for specified theatrical lights.
06/15/17 – CF will provide an ASI for the dimmer mods. JC
will contact GG for pricing.
06/29/17 – CH will check with Bruce Wallace on fixtures
07/13/17 – BK will check with GG on dimmer submittal. BW
confirms fixtures will be available around mid-July.
07/27/17 – GH to contact BW.
On-going
08/10/17 GH
2.06 01/12/17 – At-Grade Walkway Construction –
Please see previous minutes for complete history of this item.
04/20/17 – Final layout and location of at-grade walk will be
confirmed after cleaning of sanitary line in June 2017.
07/13/17 – CF will discuss details with JS and a sketch will be
issued.
On-going
08/10/17 CF, JS
14.06 04/06/17 – Condenser Screening Fence –
Please see previous minutes for complete history of this item.
05/11/17 – JC will contact DD and ask the heat pump support
stand to be rebuilt to match the footprint of unit. Fencing to
have 5/4 wood cap at top.
06/15/17 – DD confirmed the support will be re-built per GH
sketch during the week of 19-23 June. TJC site foreman will
review with GH prior to work being done.
07/13/17 – Fencing scheduled around 21 July.
07/27/17 – Fencing scheduled around 28 July.
On-going
Reminder
18.03 05/04/17 – Mech. Rm. Lighting – GH asks for three ceiling-
mount fixtures to be installed in Mech. Rm. 104 after all MEP
work is complete, fixtures to be same as Dock Rm. lights. Type
“A” fixture (round and heavy) scheduled for Mech. Rm. to be
installed on ceiling of Vestibule 101.
On-going
Reminder
20.02 05/25/17 – Stone Retaining Wall – Allegrone will provide a
stone (boulder) retaining wall to the NE of the building where
the bank has been cut. Mike Marion will source and provide
local boulders for this. Extent of wall and details to be reviewed
with GH in the field at the next job meeting.
06/08/17 – Team will discuss at next job meeting.
06/15/17 – Details for the retaining wall, paving, and drainage
Reminder
Page 3 of 5
were reviewed. CF/JS will provide an SK for review by GH for
next meeting.
06/29/17 – Sketch provided by CF. CF clarifies curve of wall at
north end to be smooth and tangent to straight section east of
building. JC & MM to review and comment.
07/13/17 – Wall to be installed after lower site work complete.
On-going
20.05 05/25/17 – Card Readers – Smith College has requested card
readers at the two exterior doors to the building. JC will discuss
with GH and will contact Chad Gagnon at the College to
discuss options and to coordinate with new hardware package.
06/08/17 – GH will discuss with CG and JC will contact Gregg
Lewis at BSAH for coordination. CF will issue ASI when design
is clarified.
06/29/17 – ASI issued. JC to confirm specs with BSAH.
07/27/17 – Card Readers (if used) to be provided by Smith
College, all prep by Allegrone
On-going
Reminder
22.01 06/15/17 – Threshold Rm 204 – Due to floor level change,
Storage Room 204 will have a canted wood threshold.
07/27/17 – Raised floor to be installed in Storage Room and
canted threshold to be eliminated. CF will issue ASI.
On-going
07/28/17 CF
23.01 06/29/17 – Screening Panels under Deck – Allegrone will
submit info on what they’re carrying in their bid and CF will
provide clarification/detail of panels.
07/27/17 – Screening panels to match detailing of Condenser
Screen.
On-going
08/10/17 JC, BB
23.02 06/29/17 – New Fiber Optic Line – Hogan will install new FO
line using existing steam tunnel. Detail at existing concrete
headwall TBD.
07/13/17 – JC will request scope and pricing from Hogan for
this work. Raceway will be provided by Orchard Elec.
On-going
07/27/17 JC
24.01 07/13/17 – ADA/AAB Interior Signage – GH confirms he’ll
provide the AAB required interior signage and Allegrone will
install. CF to forward GH list of interior signs. GH will also ask
Laura Rauscher (LR) Director of Disability Services for SC to
review.
07/27/17 – GH will provide signs for install by Allegrone.
On-going
08/10/17 GH
24.03 07/13/17 – Baby-Changing in Acc. Restroom #208 – JC/BK
will provide submittal on Baby-Changing station to be installed
under north window, KOALA or EQ.
07/27/17 – Window may be too low for unit. BK to submit on
unit and CF to review for placement.
On-going
08/10/17 BK, CF
Page 4 of 5
24.04 07/13/17 – Entry Slab at Boat House – GH requests JC
provide a price proposal for removing and pouring a new conc.
Slab at the entry to the Boat House. Exist. Perimeter conc.
Curb to remain.
07/27/17 – CF will issue ASI.
On-going
07/28/17 CF
24.05 07/13/17 – Ice Board Work @ South Boat Doors – GH will
discuss work to be done on the south boat doors with BB.
On-going
07/27/17 GH, BB
24.06 07/13/17 – Dance Lab “D” Fixture – GH requests a price
proposal for painting aircraft support cables and power cords
and canopies black.
07/27/17 – CF will issue ASI.
On-going
08/10/17 CF
24.07 07/13/17 – Door @ Storage Rm #201 – GH requests a price
proposal for installing wider, double doors at Rm #201. CF will
issue an ASI for this work.
07/27/17 – ASI issued, JC/BK to provide pricing.
On-going
08/10/17 JC/BK
24.08 07/13/17 – Pull-down Stair – CF will issue an ASI for pull-
down stair in Hall #207. (post mtg note; a pull-down stair is
spec’ed in DIV 11. BK to provide a submittal as spec’ed).
07/27/17 – Spec’ed stair is too big for space given skylight
install. Rainbow unit to be used, submittal to be provided.
On-going
08/10/17 BK
24.09 07/13/17 – Parallam Bearing DTL – CF to provide a DRAFT
SK showing the desired downhill parallam bearing DTL at
transverse steel beam.
07/27/17 – BK to check on status of fabricated steel and CF to
forward DTL to BK for review.
On-going
07/28/17 BK, CF
24.10 07/13/17 – Box-Out DTL @ Baseboard Heaters – GH
requests a box-out DTL below baseboard heaters in Entry
Addition. CF will review baseboard box-out detail with DD and
provide an ASI.
07/27/17 – Box-out complete, baseboard heaters to be installed
as submitted.
On-going
08/10/17 BB
24.11 07/13/17 – Sewer Manhole Repairs #5, #6, #7 – GH confirms
bidding for manhole #5, #6, and #7 repairs will take place in
about 4-6 weeks.
07/27/17 – Re-building of manholes may be complete as early
as 21 August.
On-going
08/10/17 GH
Page 5 of 5
NEW BUSINESS
Item
No.
Text Due Date Responsibility
25.01 07/27/17 – Coat Hook Spec – GH approves coat hook spec
provided by CF. CF to forward details to BK.
On-going
08/10/17 CF, BK
25.02 07/27/17 – Layout for Separation of Piers and Sanitary Line –
MM will be on site on 31 July to layout piers and BB will
measure the distance between piers and the existing sanitary
sewer pipe.
On-going
07/31/17 MM, BB
25.03 07/27/17 – New Door #101 on Lower Level – BK will provide
a PCCOR to GH for review for the proposed new door on the
lower level.
On-going
08/10/17 BK
25.04 07/27/17 – Pier DTL at Lower Walkway – GH requests CF
explore revised details for the concrete piers at the lower
walkway in order to avoid having to draw down the pond. CF
will review with JS and RH.
On-going
08/10/17 CF
25.05 07/27/17 – Condensate Drip Pipe – GH asks BB for the new
condensate drip pipe to be lowered to be approx. 24” above
grade and that gravel be provided at grade.
On-going
08/10/17 BB
25.06 07/27/17 – Light in Attic – GH requests a light and
convenience outlet be added in the attic. CF will issue an ASI.
On-going
08/10/17 CF
Next Meeting: Thursday, August 10, 2017, 2:00pm, Crew House
Respectfully Submitted:
7 August 2017
Chris Farley
KUHN RIDDLE ARCHITECTS
Email Copies: All attendees
Louis Hasbrouck
Jim Culliton
Ryan Hellwig
Dino D’Angelo
Jeff Squire
Charles Roberts