17A-259 Godin bathroom-2Scale
Project number
Date
Drawn by
Checked by
104 Elm Street
Northampton, MA 01060
(413) 587-3050
97 Oak Street
Florence, MA
Godin/ Petruccelli
A100
97 Oak Street
Project Number
Issue Date
Author
Checker
Project Scope:
A second floor office space will be converted into
a full bathroom with a walk in shower. The
existing brick chimney will be removed down to
the basement floor. There will be no alterations to
the exterior walls or structure.
Street View - Existing
Rear View - Existing
chimney to be removed
down to basement floor
DN
12' - 9"16' - 7"DN
Scale
Project number
Date
Drawn by
Checked by
104 Elm Street
Northampton, MA 01060
(413) 587-3050
97 Oak Street
Florence, MA
Godin/ Petruccelli
3/16" = 1'-0"
A102
2nd Floor Existing
Project Number
Issue Date
Author
Checker
3/16" = 1'-0"1 2nd floor Existing
Office
Attic / Storage
DN
12' - 9"16' - 7"9' - 9"Existing door and adjacent
wall to be removed
Existing brick chimney
to be removed down to
basement floor
Scale
Project number
Date
Drawn by
Checked by
104 Elm Street
Northampton, MA 01060
(413) 587-3050
97 Oak Street
Florence, MA
Godin/ Petruccelli
3/16" = 1'-0"
A102a
2nd Floor Demo
Project Number
Issue Date
Author
Checker
3/16" = 1'-0"1 2nd floor Demo
radiator to be moved
DN
12' - 9"16' - 7"9' - 9"15
4' x 3' walk in shower
with custom bench
1' - 6"5' - 4 1/8"Scale
Project number
Date
Drawn by
Checked by
104 Elm Street
Northampton, MA 01060
(413) 587-3050
97 Oak Street
Florence, MA
Godin/ Petruccelli
3/16" = 1'-0"
A102c
2nd Floor Proposed
Project Number
Issue Date
Author
Checker
3/16" = 1'-0"1 2nd floor Proposed
Bath
Attic/ Storage