012900Proj. No. 10105 Residence Conversions October 7, 2011 58 Kensington, 57 Dryads Green, 72 Dryads Green Smith College, Northampton, MA PAYMENT PROCEDURES Page 1 of 4 012900 SECTION 012900 -PAYMENT PROCEDURES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A.Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A.This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment. 1.3 DEFINITIONS A.Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 1.4 SCHEDULE OF VALUES A.Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule. 1.Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following: a.Application for Payment forms with Continuation Sheets. b.Submittals Schedule. c.Contractor's Construction Schedule. 2.Submit the Schedule of Values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment. Proj. No. 10105 Residence Conversions October 7, 2011 58 Kensington, 57 Dryads Green, 72 Dryads Green Smith College, Northampton, MA PAYMENT PROCEDURES Page 2 of 4 012900 B.Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section. 1.Identification: Include the following Project identification on the Schedule of Values: a.Project name and location. b.Name of Architect. c.Contractor's name and address. d.Date of submittal. 2.Submit draft of AIA Document G703 Continuation Sheets. 3.Round amounts to nearest whole dollar; total shall equal the Contract Sum. 4.Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. a.Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option. 5.Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum. 1.5 APPLICATIONS FOR PAYMENT A.Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner. 1.Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements. Proj. No. 10105 Residence Conversions October 7, 2011 58 Kensington, 57 Dryads Green, 72 Dryads Green Smith College, Northampton, MA PAYMENT PROCEDURES Page 3 of 4 012900 B.Payment Application Times: Progress payments shall be submitted to Architect by the fifth day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month. C.Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment. D.Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action. 1.Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made. 2.Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application. E.Transmittal: Submit 3 signed and notarized original copies of each Application for Payment to Architect. One copy shall include waivers of lien and similar attachments if required. F.Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following: 1.List of subcontractors. 2.Schedule of Values. 3.List of Contractor's staff assignments. 4.Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. 5.Certificates of insurance and insurance policies. G.Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. H.Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following: Proj. No. 10105 Residence Conversions October 7, 2011 58 Kensington, 57 Dryads Green, 72 Dryads Green Smith College, Northampton, MA PAYMENT PROCEDURES Page 4 of 4 012900 1.Evidence of completion of Project closeout requirements. 2.Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. 3.Updated final statement, accounting for final changes to the Contract Sum. 4.AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims." 5.AIA Document G706A, "Contractor's Affidavit of Release of Liens." PART 2 -PRODUCTS (Not Used) PART 3 -EXECUTION (Not Used) END OF SECTION 012900