Village hill Enforcement wetlands enforcement April 7 2017Northview, Village Hill, April 4, 2017 Rain Event (0.65 inches of rain 3 am to 12 noon) Figure 1. The entire sloped site has been stripped and sediment is eroded during rain storms and flows to the small detention basin and the low spot of the proposed roadway near the underground infiltration basin. Figure 2. Small Detention Basin Figure 3. Low spot graded for the proposed roadway. Water and sediment appears to flow through gravel mounds into the catch basin and to the underground infiltration system Figure 4. Water and sediment flow from the piped system to the large detention area and flow out the lower outlet control structure to the right. Figure 5. Water and sediment flows out the outfall, through the rip rap, scours and erodes the slope below the rip rap and flows along the silt fence. Figure 6. Storm flows and fine sediment flow through silt fence and coir logs at the lowest section. An additional silt fence has been added but does not filter the fine sediment. Figure 7. Storm flows and sediment continue flowing across the path and down into the wetland area Figures 8 and 9. Sediment continues to flow to a brook and to the Mill River