Loading...
32A-172 (14) 3( A - I- -- Metcalfe Associates Architecture gli 142 Main St. Northampton, MA, 01060 Tristram W. Metcalfe III, Ma. Reg.5393 Phone number> 413 586 5775 Cell number> 413 695 8200 REC. i —- Email >twm34rcn.com NCARB, NYS,MA,CT registrations at - 2 ytr 2 W MAIA 1 AIA June 26, 2012 Louis Hasbrouck, 1413 587 12401 Building Inspector City of Northampton, Puchalski Municipal Building, 212 Main Street Northampton, MA 01060 RE; Building permit progress report -- for; 11-15 Bridge St. Norwood Hotel Town Houses FOR; Silvia Woicekoski,57 Bridge St Northampton Ma WITH; William Turomisha, Construction Manager Dear Louis, This is a report on progress to date; We have completed most of the structural repairs we found in existing and new frame modifications. We still need to support the new load on the east rear roof where a living room is enlarged to meet code minimum area. It also extends support to the existing stair addition there, which has sagged probably due to under design. The list of repair work below the roof attic work zone previously mentioned is as follows; Installation of microlam beams to add support to existing and new floor structure at the 2nd and 3 rd floors. Based as specified in April thru May. UNIT #3; 2 12x 14ft LVL for floor frame UNIT #5 & UNIT #4; 1- 6X 14ft for new stairs to carry 3rd flr load off 2nd floor into bearing UNIT #2;2-9"x 22ft to support floor joists direction change UNIT #1; I- 9"x 20ft to support attic floor I- 9"x 14ft to support 3rd floor Re-hang all floor joists that change directions and have missing connections on both 2nd & 3 rd floors. The foundation to the new entry enclosure tower at existing stairway for the residences is now back filled. We are redesigning the main entry vestibule to allow for unforeseen foundation and steel plus brick plus wood supports causing wheelchair lift reorientation, We will submit drawings once they are resolved for construction. Respectfully Submitted, Tris Metcalfe MA RA #5393