NEE-140 Riverbank Road Weekly Report 4-22-2016
Weekly Monitoring Report
To: Sarah I. LaValley
Conservation, Preservation and Land Use Planner
City of Northampton
Office of Planning and Sustainability
210 Main Street, Room 11
Northampton MA, 01060
413-587-1263
slavalley@northamptonma.gov
From: Andrew Bohne, New England Environmental, Inc.
Jeffrey Dawson, New England Environmental, Inc.
Date: April 22, 2016
Project: 140 Riverbank Road Restoration
Northampton, MA
DEP Number # 246-0687
NEE Project Number – 15-4680
RE: Weekly Monitoring Report
Week Ending 4/22/2016
The following activities where completed this week for 140 Riverbank Road.
MONDAY APRIL 18, 2016
Scapes Building and Excavation (Scapes) began constructing the staircase and landing on the
bank, to connect to the proposed dock (pending Chapter 91 License approval). Scapes put the
footings and stringers for the stairs and landing in place.
www.neeinc.com 2
(Photo showing the area where the staircase and landing will be)
TUESDAY APRIL 19, 2016
Scapes Building and Excavation (Scapes) continued constructing the staircase and landing on
the bank, to connect to the proposed dock (pending Chapter 91 License approval). Scapes
finished putting the stringers and handrail posts in. Scapes began to put down the landing
decking and the staircase treads and risers.
(Photo showing the existing asphalt in the driveway being saw-cut in preparation of digging
the trench for the pipe connecting the new pump tank to the new septic field)
WEDNESDAY APRIL 20, 2016
Scapes finished putting the treads and risers on the staircase and began constructing the
hand railings.
www.neeinc.com 3
(Photo showing the new pipe out of the septic pump tank, across the driveway into the new
septic field on the north side of the cottage)
THURSDAY APRIL 21, 2016
Scapes finished constructing the staircase and landing. The hand railings were put in place
and some final structural support beams were placed underneath the structure.
(Photo showing the new staircase from the top of bank.)
www.neeinc.com 4
(Photo showing the new staircase from the constructed landing.)
ANTICIPATED TASKS FOR THE WEEK ENDING 4/29/2016
a. Re-grade back and side yard.
b. Re-seed lawn areas.
Please let me know if you have any question related to the above report.
Sincerely,
Andrew Bohne, RLA
Vice President
New England Environmental, Inc.
Email: abohne@neeinc.com
Cell: 413.687.1454
cc: Meredith Borenstein (NEE)
Scott Fisher (NEE)
Kim Urban (Home Owner)
Jerry Zanarini (Claims Adjuster)
Tim Kasulinous (Tim’s Tree Service)
John Blowers (Scapes)
Mike Gordon (Scapes)