NEE-140 Riverbank Road Weekly Report 12-11-2015-Final.pdf
Weekly Monitoring Report
To: Sarah I. LaValley
Conservation, Preservation and Land Use Planner
City of Northampton
Office of Planning and Sustainability
210 Main Street, Room 11
Northampton MA, 01060
413-587-1263
slavalley@northamptonma.gov
From: Andrew Bohne, New England Environmental, Inc.
Jeffrey Dawson, New England Environmental, Inc.
Date: December 11, 2015
Project: 140 Riverbank Road Restoration
Northampton, MA
DEP Number # 246-0687
NEE Project Number – 15-4680
RE: Weekly Monitoring Report
Week Ending 12/11/2015
The following activities where completed this week for 140 Riverbank Road.
FRIDAY DECEMBER 4TH, 2015
While Scapes Building and Excavation (Scapes) was excavating the area for the new Septic
tank, we discovered and old concrete foundation and slab around 40” below grade. Based on
the dimensions for the proposed new septic tank, Scapes had to saw-cut and air hammer the
area of the exposed old concrete foundation and slab away to make room for the new septic
tank. The portion of the old foundation was cut, air hammered and removed from the site.
During the excavation of the area for the new septic tank, it was also discovered that the
water line from the street was not in the location as shown on the septic plans. This water
line runs from the street to the northwest corner of the main house and then from the main
house, and then a waterline runs from the northwest corner of the main house to the south
west corner of the cottage.
www.neeinc.com 2
(Photo showing the concrete slab and footing discovered while excavating the area needed for
the installation of the new septic tank.)
(Photo showing the concrete slab and footing that had to be saw-cut, air hammered and
removed from the site to be able to set the new septic tank to the correct elevation.)
www.neeinc.com 3
(Photo showing the water line on the western edge of the new septic tank that runs from the
main house and feeds the cottage)
SATURDAY DECEMBER 5TH, 2015
The new septic tank was delivered to the site and set in the excavated area adjacent to the
existing functioning septic tank to minimize homeowners and tenant’s disruption of sewer
services. The exterior of the new tank partially backfilled and site was stabilized for the
remainder of the weekend.
www.neeinc.com 4
(Photo showing the new septic tank being set in the excavated area adjacent to the current
septic tank-in foreground of picture)
MONDAY NOVEMBER 7TH, 2015
Scapes Building and Excavation (Scapes) excavated the area for the new septic pump tank.
The base was filled with washed stone as specified for a setting bed for the new pump tank.
www.neeinc.com 5
(Photo showing the excavated area for the septic pump tank)
TUESDAY DECEMBER 8TH, 2015
New septic pump tank was installed and set in place as shown on the septic design plans.
During the excavation of the trenches for the new alignment of the septic lines running to the
new septic tank, it was discovered an additional foundation wall was in the path on the new
pipe alignment coming from the cottage structure to the new septic tank. Again, we had to
saw-cut this exposed old concrete foundation, air hammer the concrete and removed the
debris from the site. Asphalt in driveway was saw-cut in preparation of connecting the new
pump tank to the new septic field.
www.neeinc.com 6
(Photo showing the installed septic pump tank installed to the west side of the newly
installed septic tank)
(Photo showing the old foundation wall unearthed while excavation the new trench for the
septic pipe from the cottage to the new septic tank. Old foundation needed to be saw-cut,
air hammered and removed from the site to allow for proper pipe alignment to new tank)
www.neeinc.com 7
(Photo showing the existing asphalt in the driveway being saw-cut in preparation of digging
the trench for the pipe connecting the new pump tank to the new septic field)
WEDNESDAY DECEMBER 9, 2015
Pipe connecting the new pump tank to the new septic field was installed and backfilled.
Septic pump was installed and wired by a licensed electrician.
(Photo showing the new pipe out of the septic pump tank, across the driveway into the new
septic field on the north side of the cottage)
www.neeinc.com 8
THURSDAY DECEMBER 10, 2015
Northampton Electrical Inspector came to the site to approve the new electrical work for the
septic pump. Upon inspection, the inspector noted that the service to the house and the
existing electrical box located in the basement does not meet code and needs to be updated.
The service from the pole to the house will need to be updated and the circuit box in the
basement will need to be relocated out of the floodplain. This work is being coordinated and
will be completed as soon as possible. The inspector allowed the electrician to temporarily
hook up the new septic pump until the updates for the electrical work can be completed.
Scapes disconnected to old lines feeding the old septic tank and installed the new pipes
connected to the new septic system and field.
(Photo showing the new pipe out of the cottage conned to the new septic system)
FRIDAY DECEMBER 11, 2015
Septic designer completed the final septic inspection and approved the system. Scapes filled
around all the new septic connection, tanks, and features. Scapes pumped down the old
septic tank and will filled it with flow-able fill, to properly decommission the old system next
week.
www.neeinc.com 9
(Photo showing the new septic system partially back filled prior to final inspection by septic
designer)
ANTICIPATED TASKS FOR THE WEEK ENDING 11-18-2015
a. Install road to top of bank along the Ct. River
b. Begin slope preparation and toe of slope stabilization
Please let me know if you have any question related to the above report.
Sincerely,
Andrew Bohne, RLA
Vice President
New England Environmental, Inc.
Email: abohne@neeinc.com
Cell: 413.687.1454
cc: Meredith Borenstein (NEE)
Scott Fisher (NEE)
Kim Urban (Home Owner)
Jerry Zanarini (Claims Adjuster)
Tim Kasulinous (Tim’s Tree Service)
John Blowers (Scapes)
Mike Gordon (Scapes)