120106 - Dewey - Program and ScopePage 1 January 6, 2012 Summarized Program and Scope of Work Renovations and Repairs - Dewey House 4 Neilson Drive Smith College Northampton, Massachusetts Prepared by: Laura Fitch, AIA, LEED AP BD&C Kraus-Fitch Architects, Inc. Summarized Program The following summarizes the main items of the recommended work for Dewey Hall. See the Scope of Work for more details. Accessibility: A variance application (supported by Laura Rauscher) is in process to allow for the following preferred direction for addressing accessibility. • Scheme A (recommended): Install a new wheelchair lift enclosed within a new addition west of the northern stair. Access to this addition would be from the corridor in the previously renovated north wing, which in turn is accessed from the existing sheltered ramp. The Lift would only connect the first and second floors in order to keep the tower below the historic eave of the back wing. Additional access work includes a redesign of second floor bathrooms, two second floor offices, and a kitchenette. A variance application for modification to door widths at the second and third levels is also in progress. Not only is it very expensive to widen door openings, but this work would be further complicated by the need to dispose of door casings with lead-based paint. Maintenance and System Upgrades: Repair of deferred maintenance and modernization of mechanical, plumbing and electrical systems are included in the proposed scope of work. Much of the mechanical and electrical work will require removals of sections of walls and ceilings. An inspection for asbestos, PCBs, and lead-based paint was contracted by Smith College with ATC Associates. Asbestos was found but is not extensive and was not detected within the plaster walls and ceilings. Areas requiring abatement are listed below in the Scope of Work and within the ATC report. PCBs sample results from caulking and glazings were less than 50 ppm, therefore the caulking is considered an “excluded PCB product” and not subject to regulation. Lead based paint was detected throughout the building and needs to be considered when disposing of demolished items. Page 2 Energy Conservation Measures: The architect recommends measures above and beyond those listed in the 2010 report by Richard White and Sons, including: • Insulating walls with dense packed cellulose –this may be affected by brick nogging (TBD) • Insulating old section: at attic floor or roof level (TBD) • Insulating newer section: at sloped roof (see below for more) Roof / Dormers: The entire roof (exclusive of the porch and one-story section at the first floor) is scheduled for replacement. To reduce additional snow loading and possible requirements for upgrading this, the Owner would like to consider replacing the slate with metal. An application to the Elm Street Historic Commission will be started soon. The architect recommends taking advantage of the opportunity of reroofing in two ways: 1. The replacement of the two “dog house” dormers on the west side with a shed dormer similar to the one on the Elm street (east) side. The chimney that used to penetrated the roof between them has been taken down below the roof, and the room within is very uncomfortable due to low ceiling heights. While these dormers may be original to this addition, many changes have been made to the structure over the years. Matching the style of the dormers on the other side seems appropriate. The reasons for this recommendation are: • To reduce the areas of roof wall flashings that can ultimately fail in the long run • To reduce the areas in which ice damming has occurred, and may continue to be problematic as they are hard to insulate and air seal • To reduce the hard to reach dormer side walls that require periodic painting • To significantly increase the head room in the middle office 2. The installation of 4 inches of rigid foam insulation over the existing roof sheathing prior to installation of new slate. The reasons for this recommendation are: • To increase the R-value of the roof • To decrease thermal bridging and air leakage at the structural members • To decrease ice damming, reducing damage to the roof and building over time Summary of Cost Estimate William Marr or Marr Engineering Services estimated the project at $3,093,072 of approximately $368 per square foot. Details can be found in the attached Appendix. Estimates for three alternates were given, as these are items that will likely need variances from the Massachusetts Architectural Access Board: • Alternate One: Widen all 2nd floor doors: $44,800 • Alternate Two: Add handrails to existing historic curved stairway: $4,500 • Alternate Three: Change Lift to Elevator: $88,000 Page 3 More Detailed Scope of Work Yellow highlighted items have long lead times, requiring early decisions and ordering. The likely Scope of Work is summarized below: • Alternates: o Widen all second floor doors (variance recommended) o Add second handrail to existing curved stair (custom wood) and raise height of existing rail (variance recommended) o Scheme B Elevator: Substitute elevator for lift, taller shaft, related roof work and machine room (add alternate), • Demolition: (see below for lead-based paint disposal recommendation) o All attic partitions and ceilings and access stair at previous dorm area of old section. Remove most of flooring retaining only catwalk through center o 3rd floor ceilings at newer wing, including dormer ceilings o Demo sections of walls for new electrical and telecommunications wiring o Bathrooms and kitchenette (core to stud), excluding relatively new ADA toilet. o MEP systems to be replaced (radiators and piping, window AC units, local exhaust systems) o Roofing (exclusive of new porch roof and first floor one story bump out roof) including skylights, o Demo two small dormers (to be replaced by single shed dormer) o Areas and doorways for minor renovations, including stair o Carpet and other finishes to be replaced • Hazardous materials abatement – Refer to ACT report, June 2011 for more information. o Asbestos – basement: Cellar window glazing 9 x 9 floor tile and Mastic (typing room area) o Asbestos – first floor: Entry hall sidelight glazing Hall and closet: linoleum Main Hall bathroom: linoleum o Asbestos – second floor: Kitchenette: linoleum and sink undercoating o Asbestos – third floor: Door window glazing Bathroom linoleum o Lead-based paint – any materials listed as containing lead in the above referenced report, shall be tested prior to disposal to determine if they require standard or hazardous waste disposal. Carpenters shall follow OSHA practices when working with lead materials. • Sitework o Excavation for lift addition o Landscape: Allowance only for misc. repairs • New Lift Addition: o Schemes A (lift): Servicing first and second floors (variance required for third floor access, based on historic status) includes recessed slab on grade and frost walls, framing, insulation, finishes, HVAC/electric, etc. Page 4 • Minor Structural improvements o Roof framing modifications for snow loading: Reinforce Purlins (both wings). Reinforce top chord of truss – older wing o Inspect roof framing after demolition of ceilings at third floor of newer wing. Work not currently listed will be considered a change order. o Inspect floor framing after demolition of bathrooms. Any required repairs for rot will be considered a change order. • Exterior Shell o New slate roof and copper flashings throughout excluding standing seam metal roofing at south porch and north 1-story section. See demo. Slate tiles. Cover existing sheathing with 4” nail base rigid insulation. Patch former skylight holes. Allow for 10% sheathing replacement (rough sawn boards) New copper roofing @ new and existing shed dormers (2). 30 lb single layer felt Copper standing seam strip at eaves Replace all damaged copper gutters (50% assumed). Retain existing downspouts. o Replace west-facing dormers with single shed dormer (see sketch) o Add additional trim at rake and eave to cover the exterior insulation (at newer wing only) o New windows and trim throughout. Windows to be aluminum clad wood (extruded, not roll stock). Double pane with simulated divided lites on single pane, low e, argon filled. Recessed pulls (to reduce maintenance). Window screens installed with SS screws. (Marvin or equal call Steve Pauquette at R&R Windows 527-7500 x117). o Minor repairs to clapboards (allow for 15% replacement) o Side porch repairs: new fiberglass columns on PT posts, new composite railings o Brick repointing at exposed foundation o Cap and repoint chimneys Painting: wash, scrape and paint full exterior including: clapboards, trim soffits, doors, windows, etc. o Thermal Envelope Foundation: No insulation to be added. Seal all penetrations in basement exterior walls. Walls: Dense pack cellulose blown into exterior walls, including patching of clapboards at holes. How is this effected by brick nogging Floor/Wall intersections: TBD dependent on balloon framing or not Ceiling at older wing: • See demo for removal of attic floor and stairs and retention of some catwalk areas, see structural repairs. Add attic hatch and ladder. • Remove insulation at second floor ceiling from attic • air seal all ceiling penetrations in plaster ceiling (existing and new for electrical plumbing, sprinklers, chimneys, etc.) • add new insulation (at ceiling level, not attic floor, R-60 loose fill cellulose). Ceiling at newer wing: • See demo for plaster ceiling removal, See other dormer items for new dormer and structural repairs • Insulate cavity with dense-packed cellulose. See roofing section for nail base rigid insulation recommendation. Page 5 • Interior Renovations o New 2-hour room in basement for electrical o First Floor modifications at elevator area o 2nd floor bathroom, office, and kitchenette renovations o New doors: 4-panel, solid wood, painted o New ADA hardware on doors throughout including non-custodial closets (excluding first floor newer wing which already complies) o Adjust 3 first floor wood thresholds to meet ADA requirements o Remove and reframe third floor stair, including new handrails (2) - note: new stair should not be required to meet code for tread and riser dimensions under IEBC o Misc. new enclosures for HVAC work: drywall surrounds, soffits, misc. patching o New ACT ceilings 2nd floor back halls (200-C, 200-B) and new bathrooms 3rd floor hall (300-A) o ACT ceiling at new areas of first floor: modifications for lift (all ceilings at first floor to otherwise remain, except where needed to hide new MEP) o New gypsum board ceilings at third floor (newer wing) o Refinish existing exposed hardwood floors in offices at all levels and front hall (100-A, 100-B) o Replace carpet @ common halls (100-C, 100-B, 200-A,B,C, 300-A, curved stair, and replacement stair) and first floor newer wing (103, 104, 105) o Repair cracks in plaster and paint all interior (except basement) with single coat finish paint o New ADA signage throughout o Furnishings: Replace window blinds in all offices (except 104, 105) • Mechanical, Electrical: For more detailed information about the recommended work, refer to Appendix A. New mechanical, piping and electrical systems are to be cut into existing walls. Vertical runs may be concealed within new chases. Some corridor work can be concealed in ACT drop ceilings o Sprinklers: Modify existing dry pipe sprinkler system: Replace the existing sprinkler air compressor Replace all existing sprinkler heads with new quick response heads Extend all sprinkler test connects from attic to ground floor and discharge to splash blocks or drywells. Revise existing sprinkler heads and piping to accommodate minor modifications to floor plan Install new stand pipe system in main stair tower with hose valves at each landing o Plumbing: Replace brass water piping with new copper. Revamp existing copper to serve the new bathroom configuration(s). Replace sanitary piping throughout (retain only section in good condition) Upgrade water service entrance piping, meter, PRV station and replace related brass piping Renovate existing toilet rooms to remain (1 at first floor, 1 at third floor), and plumb new toilet rooms (2nd floor) to include all new fixtures and related water and drain piping. Exclude newer ADA toilet room at first floor. Replace Gas Piping and reconnect gas dryers. Re-pipe gas to water heater. Page 6 Replace steam and condensate piping including pumps, traps, control valves, and pressure reducing station. o Heating and Ventilating(see details in appendix): Option1: two pipe heating utilizing Runtal style radiators and PEX-tubing system and new bathroom ventilation (not recommended) Option 2: two pipe fanned Coil System and new bathroom ventilation (recommended) Option 3: four pipe fan coil system and new bathroom ventilation (not recommended) Option 4: Mechanical Ventilation System (recommended) o Electrical Lighting • Remove and replace office lighting • Redesign and replace corridor lighting. Provide egress lighting. Provide occupancy and time clock controls for energy conservation • Replace all existing basement and stairway light fixtures • Replace bathroom lighting • Provide new LED exit lighting fixtures powered from emergency panel Telecommunications • provide new telephone and data cables from basement demarcation points to support additional outlets where required • provide data wiring and outlets in support of wireless access system • Rerouting existing cabling to run in wall and terminate at recess outlets. Wiring, Equipment, and Devices • Redesign and replace existing branch circuit wiring and devices throughout, including basement area. Install in-wall using a combination of baseboard removal and cutting and patching. • Replace existing branch circuit wiring and equipment in support of mechanical equipment throughout, including basement Distribution panels • Replace incoming service lateral conductors – 400A-3P 120/208V. Evaluate building service transformer • Replace existing service entry distribution equipment • Replace electrical distribution feeder conductors and subpanels throughout building. Reconnect to new service the existing panelboard installed to serve more recently removed space of building • Rework existing emergency service. 2 hour rated room is required. • Remove existing subpanels associated with emergency power. All loads shall be home runs to 2-hour rated room. Fire alarm • Install a new addressable Simplex Fire Alarm System to serve all public spaces. • Remove unrequired 120v smoke detection devices from all offices.