32C-165 (6) GILLEN •KUHN• RIDDLE & GRAY INC.ARCHITECTS FIELD REPORT FORM 4' Project: Union Station, Northampton t+�S t Date: 4/9/86 tit Weather: Overcast Temperature: 510. Project No.: 84037 Time: 9:30 a.m. Work in progress: New concrete walls at Banquet Room area 95%, demolition work 75%, interior power cleaning of brick walls 60%, roof repair 40%, rough plumbing 20%. Present at meeting: C. Ragoza (M.L. Schmidt), Ziter Saloomey (Saloomey Const.), Owen Lococo, Lee Christenson (Depot Assoc.), Mike Brennan (GKRG) Observations: 1. Work progressing quickly, site clean. Information or action required: Items to verify: 1. Need structural information as to wall removal at kitchen and bar/lounge area. 2. Plan of Banquet Room restrooms at 1/4" scale to be prepared by 4/10/86. Report by: Mic�ael rennan WVG: IAW� cc: Depot Associates, Ted Tewhill Enclosures: None IN 26 South Prospect Street,Amherst,Massachusetts 01002 413.253.2528 ❑153 Milk Street,Boston,Massachusetts 02109 617.426.4993 GILLEN •KUHN• RIDDLE GRAY 26 So tit lh Prospect Street,Amherst,NlassaelmseIts 01002 413.253.2528 I NC.ARC IIITECTS Boston,Massachusetts April 10, 1986 1 r c Ai 4+ APR 15 6% L Mr. Edward Tewhill pl tip Btrs��si,y�INB�f Building Inspector 212 Main Street Northampton, MA 01060 Re: Union Station Job No. : 84037 Dear Ted: I was advised that you called this morning with questions regarding the electrical and mechanical plans for the Union Station project. I subsequently discovered that there are plans on the job site which have our firm name and my stamp on them which we did not prepare. I spoke with Lee Christenson who said that this was a mistake and that our name would be taken off the drawings. The engineer responsible for the drawings would be named and the appropriate professional engineer stamps put on the drawings. This is to advise you that Gillen, Kuhn, Riddle & Gray, Inc., is not respo rr- sible for the plumbing, heating, sprinkler or electrical engineering portions of the Union Station project. When I spoke with Lee Christenson, he said he would be in touch with you about this. Sincerely yours, W I[WZr L William V. Gillen /jha; 84037101.1 cc: Lee Christenson William V.Gillen,AIA,NCARB•John Wood KUhn,AIA,NCARB•Christopher E.Riddle,NCARB• Dennis J.Gray,ASIA,AIA,IFIM GILLEN KUHN RIDDLE ' ;) & GRAY INC.ARCffiTECTS x FIELD REPORT FORM 4 Project: Union Station Date: 4/16/86 Northampton, MA 01060 Weather: Overcast Temperature: 40 0 F Project No.: 84037 Time: 9:30 a.m. Workin progress: 1 electrician (M.L. Schmidt) starting rough wiring in Banquet Hall, Kitchen area, locating panels. 2 laborers patching marbel floor, main dining area. 3 roofers--roof repair/replacement. 2 laborers, cellar cleanout. Observations: 1. Demolition: 90% complete. 2. Formed concrete: 75% complete. 3. Roof repair/replacement: 40% complete. 4. Plumbing roughing: 35% complete. 5. Note: Purpose of this meeting was scheduled job meeting. Present: Job superintendent Saloomey Construction. Information or action required: Structural review of existing truss work at Banquet Room area for support of 3 HVAC units. Also, second floor ceiling joists to support HVAC units. Need contract cost breakdown from Depot Associates. Items to verify: Item verified: 2nd floor ceiling joists 2 x 6 at 20" o.c. , 21'-7" span. Report by: Mike Brennan WVG: IV(,t Ce:Depot Associates, Ted liewh Enclosures: None Jl 26 South Prospect Street,Amherst,Massachusetts 01002 413.253.2528 El 153 Milk Street,Boston,Massachusetts 02109 617.426.4993 GILLEN •KUHN- RIDDLE & GRAY INC.A I01 IITEI CTS f; " FIELD REPORT FORM Project: Union Station Date: 4/30/86 Northampton, MA �A F ; a P1►�Y 5 " It Weather: Clear DLPI,07 i?tlilDiNG Spl 0 r1S Temperature: 72°F Project No.: 84037 # Time: 9:30 a.m. Work in progress: Roofers completing flat roof membrane over banquet room. Carpentry work at banquet room area, floor framing over stairwell leading to tunnel and sample stud wall at northwesterly end of banquet room--satisfactory to all. Refinishing of ceiling at dining room 25%, good finish. Banquet room floor/slab 80%, underslab mechanicals 100%. Demolition 95%. Concrete forms for walls at southerly rear entry being placed for pour this week. Basement paint/whitewash 90%. Work progressing smoothly and according to plans and specifications. Observat ions: 1. Office 113, northeasterly rear corner, first floor to be changed to storage. 2. City of Northampton to start parking lot work and resurfacing next week. 3. Handicap ramp can be shortened due to raising of elevations in parking lot area. 4. Roof framing at southerly rear entry will follow lines of foundation versus circular. Information or action required: 1) Owners request parking lot drawing showing circular island, valet parking. Items to verity: Structural plans and information from John Brennan: 1. Detail of channel supports to footing. 2. Calcul�,ti�n.s o ba quet room roof structure and means of distributing weight of Report by: 'g - � HVAC units Michael G. Brennan William V. Gillen 1/V4L /; L CC: Depot Associates Enclosures: Ted Tewhill Tom Hill X 26 Sout It Prospect Street,Amherst,Massachusetts 01002 413•'253.2528 ❑ 15:3 Milk Street,,Boston,Massachusetts 02109 617.426.4993 GILHN KU RIDDLE & GRAY _ INC.ARCfnTECTS F-7 FIELD REPORT FORM Project: MAY 14 FA Date: 5/7/86 Union Station t; Weather: Rain Northampton, MA t. . Temperature: 55 Project No.: 84037 Time: 9:30 Work in progress: Roof @ banquet area now watertight, rough plumbing 90%, all underslab mechanicals 100%, rear entry @ parking lot, preparation for slab pour this week. Gas piping started. Electrical rough through panels. All work substantially in compliance with plans and specs. Observations: Present at meeting: Ziter Saloomey, Saloomey Construction C. Rogoza, M.L. Schmidt Owen Loccoco - Depot Assoc. M. Brennan - G.K.R.G. Information or action required: Need parking lot plan and load calculations of roof structure over banquet area in regards to HVAC units from J. Brennan Items to verify: Report by: CC: Michael Brennan Enclosures: willI Gillen Depot Assoc. Tewhill Z. Saloomey MB M.L. Schmidt 1126 South Prospect Street,Amherst,Massachusetts 01002 413.25:3.2528 0153 Milk Street,Boston,Massachusetts 02109 617.426.4993 3aC °lbSi GILLEN •KUHN- RIDDLE i�.GR'�Y FIELD REPORT FORM Project: Union Station Date: 5/15/86 Northampton, MA Weather: Clear Temperature: 700F ProjectNo.: 84037 Time: 9:45 a.m. Work in progress: Work by Saloomey Construction concentrated at cold food prep area, kitchen and bar lounge area, removing and opening up brick walls per plan by engineer J. Brennan. Walls in bar lounge area being sandblasted. Electrical roughing approx. 50% complete by M.L. Schmidt. Sprinkle system started by M.J. Moran. HVAC starting today, layout and placement of roof curbs by Astro Heating & Air Conditioning of W. Springfield. Saloomey Const. to reinforce cut areas in roof and to further reinforce roof structure Ober J. Brennan. Work is substantially in compliance with approved plans & specificati ns. servations: 1. Plan(s) HVAC contractor is using bears the GKRG title and W.V. Gillen's architect' stamp. NOTE: GKRG Architects axe:not responsible for the design, installation or inspection of HVAC system. 2. Roof beam, center horizontal in roof structure at kitchen storage, office area must be reinforced. Information or action required: Parking lot plan and roof structural information from J. Brennan. Remove Gillen, Kuhn, Riddle & Gray name and stamp from mechanical drawings immediately. Items to verifryy: Reportb • chael G. Brennan WVG: Cc: Depot Associates Enclosures: None. Ted Tewhill Saloomey Construction Tom Hill CJ26 South Prospect Street,Amherst,Massachusetts 01002 413.253.2528 0 153.Nlilk Street,Boston,Massachusetts 02109 617.426.4993