Loading...
Damon Rd Drainage Systemr Damon Road Drainage System Improvements Feasibility Report Northampton, Massachusetts Prepared for Massachusetts Department of Transportation Highway Division Boston, Massachusetts Prepared by Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts May 2010 LJ L. r r l l 1 Executive Summary 1 2 Introduction . 2 Existing Conditions 3 Geotechnical Investigation 6 Other Geotechnical and Bridge Information 7 8 Introduction. 8 Design Assumptions 9 Design Criteria 9 Alternatives ' 11 Project Decision Matrix 14 Environmental Issues. 15. Introduction 15 Anticipated Environmental. Impacts and Mitigation 15 Wetland Permits / Environmental Clearances 15 6 Conceptual Project Costs • 17 7 Conclusions 19 Introduction 19 Recommendations 19 Figures and Appendices Figure 1 - Locus Map Figure 2 - Existing Conditions Plan . Figure 3 - Alternative #1 Figure 4 - Alternative #2 Figure 5 - Alternative #3 Figure 6 - Bank Stabilization - Typical Section Alternatives Analysis Appendix A Appendix B Appendix C Appendix D City of Northampton -- Damon Road Drainage System Improvements Feasibility Report Table of Contents FI L J Executive Summary The Massachusetts Department of Transportation (MassDOT), acting through its Environmental Division and the District 2 office in Northampton, is planning major repairs to a portion of the Damon Road drainage system adjacent to the Norwottuck Rail Trail Bridge and the Connecticut River in Northampton, Massachusetts. For more than 10 years, the existing drainage system has been in a continual state of failure. The existing culvert beneath Water Street (abandoned) has collapsed and the downstream headwall has migrated down slope toward the Connecticut River. Major bank erosion is actively occurring and is approaching the western -most pier (Pier 9) of the Norwottuck Rail Trail Bridge. The repair alternatives included in this feasibility report contain approaches to repair the existing drainage system, improve the hydraulics, and reduce and repair bank erosion. Alternatives 1 & 2 include removal of the Water Street embankment and culvert to "daylight" the existing drainage ditch. Alternative 3 proposes hydraulic improvements to the system, and reconstructing the Water Street culvert and headwalls. On March 4, 2010, VHB met with representatives from MassDOT's Environmental Division and District 2 office, and a representative from the Department of Conservation and Recreation (DCR) to provide an update of the project and review the alternatives developed for the drainage system improvements. Based on input from all parties, Alternative 2 has been selected to be advanced into final design. VHB documented the decision - making process with the use of a Project Decision Matrix (included in Section 4) which shows that all three Alternatives achieve the required goals of the project. Alternative 2 was found to have more advantages, including greater wildlife habitat improvements and less maintenance costs. Executive Summary • n J' u ;.J r r7 Introduction The study area is located on the west bank of the Connecticut River, in the City of Northampton, Massachusetts (see Figure 1). The site is bound on the northeast by the Connecticut River, on the southwest by Damon Road, on the south and east by the Norwottuck Rail Trail and associated parking lot, and on the west by private property. The existing drainage system (see Figure 2) receives flows from a large drainage area. The drainage area includes a portion of Damon Road, a portion of Interstate 91 and an industrial park west of Interstate 91. Drainage ditches at the base of the Interstate 91 embankment flow to an open drainage ditch which enters a 40 -inch reinforced concrete pipe (RCP) culvert on the southwest side of Damon Road. The 40 -inch RCP culvert ends in an open drainage ditch on the northeast side of Damon Road where it collects a portion of the Damon Road runoff. The ditch remains open for approximately 140 feet where it enters a 48 -inch RCP culvert under Water Street. Water Street is an abandoned City roadway. Prior to failure of the system the culvert extended from a cement concrete headwall on the southwest side of the Water Street embankment to a headwall on the northeast side. Downstream of the 48 -inch culvert, the ditch extends approximately 100 feet where stormwater is discharged to the bank of the Connecticut River. Additionally, a 48 -inch drainage trunk line, originating in the industrial park to the west of Interstate 91, extends beneath the rail trail, west of Damon Road. The trunk line travels 120 feet from Damon Road and turns left at a 62 degree angle in a 16 feet deep drain manhole, 25 feet northwest of the rail trail bridge's west abutment. The trunk line then extends approximately 40 feet to the Water Street culvert. The industrial park drain line enters the Water Street culvert in a manhole at approximately a 90 degree angle. Two other major MassDOT projects are planned within the same area as the Damon Road Drainage Improvements discussed in this report. These projects include the Damon Road Transportation Improvement Project, which involves the widening of Damon Road (with minor vertical and horizontal realignment) to provide four foot shoulders and a sidewalk; and the Interstate 91 /Route 9 Introduction n J Interchange project, which involves construction of a new north -bound entrance ramp to I -91 from Damon Road. Introduction \ \Mawatr \ev\ 10829.00 \GIS\ project \NorthamptonDamonRoad\LocusMap larger.mxd oin9A4iu+rM+e fmnrM. T 0 250 500 Feet a Highway Source: MassGIS 2005 Site Location FIGURE 1 Site Location Map Drainage Improvements Damon Road Northampton, MA J T T I L f _J Alternatives - Analysis.. 3 Existing Conditions In 2005, the Water Street culvert began to collapse. The system has continued to deteriorate through a combination of factors, including continued drainage flows within the collapsed system and flooding of the Connecticut River. In addition, existing soil conditions and the age and condition of the system's components may have contributed to the initial collapse and continued deterioration of the system. The downstream headwall of the Water Street culvert has migrated down slope toward the Connecticut River, along with a portion of the culvert, downstream of the industrial park manhole connection. As far back as 1999, substantial bank erosion approaching the Norwottuck Rail Trail bridge pier, has been occurring. The failure of the culvert and downstream headwall appears to have resulted in significant additional slope erosion. Slope erosion is actively occurring and eroding the Water Street embankment. Slope erosion is also actively eroding the bank adjacent to the western most pier (Pier 9) of the Norwottuck Rail Trail Bridge. Several large and many smaller trees are being undercut and falling into the ditch. The downstream headwall has migrated down slope. Alternatives Analysis Erosion is occurring around the industrial park trunk line connection manhole at the Water Street culvert. The upstream headwall exhibits major concrete deterioration and extensive siltation of the Water Street culvert. The embankment, adjacent to the Norwottuck Rail Trail Bridge pier, at the Connecticut River, shows severe soil erosion. The open drainage ditch, upstream. from _ the Water Street embankment is experiencing moderate slope erosion. The downstream end of the Damon Road culvert is in satisfactory condition. 1 This culvert will be extended approximately twenty feet to facilitate the widening of Damon Road. 5 Alternatives Analysis The Water Street culvert has collapsed causing slope erosion and toppling vegetation into the drainage ditch. - Li ri In addition to the existing system failures described above, the existing industrial park trunk line may be experiencing significant energy losses due to severe bends in the 48inch line. The existing drain manholes may be sustaining severe wear internally due to major hydraulic impacts. It appears that a drainage easement is in place for the existing industrial park trunk line. No existing drainage easements have been identified for the existing open drainage ditch between Damon Road and Water Street. Geotechnical Investigation A geotechnical report was prepared for VHB by Nobis Engineering Inc., dated January 25, 2010, and is included as Appendix A. The geotechnical report was prepared in order to assess the structural and drainage characteristics of the site soils for supporting new headwalls, and how site soil conditions may have contributed to the failure of the existing drainage system. Conclusions of the Nobis Engineering Inc. report: Based on the conclusions listed above, it is our geotechnical consultant's opinion that the drainage structures at Damon Road failed due to the deteriorated condition of the downstream retaining wall, combined with a lack of drainage behind the retaining wall. The flooding that occurred_ during the flood of October 9, 2005 may have contributed to the eventual collapse, but was not the sole cause of the collapse. The soil laboratory analyses suggest that the soils underlying the drainage structures are over - consolidated clays which are less susceptible to settlement in comparison to normally consolidated clays. The evidence suggests that the downstream retaining wall was in a progressive state of collapse for a significant period of time. 7 Existing Conditions 1. The drainage system failed in a progressive manner, it was not the result of a single event (e.g. flood); 2. A'major flood event occurred in the area on October 9, 2005; however, there is insufficient data to link this flood event with the drainage system failure; 3. Based on the soil investigation and site reconnaissance, it is presumed that the existing retaining walls were backfilled with poorly drained soils, possibly contributing to the failure; 4 Subsurface conditions revealed significant depths of clay, extending to 72 feet below the surface; 5. Clay just below the surface fill is over- consolidated and is considered sensitive to disturbance since the natural moisture content is above the Liquid Limit. It is possible that the clay at greater depth is normally consolidated. Other Geotechnical and Bridge Information The Department of Conservation and Recreation (DCR) requested its consultant to inspect the ground conditions at the Norwottuck Rail Trail bridge and develop a scope of work for a full bridge inspection. A technical memorandum, prepared for the DCR by Simpson Gumpertz & Heger Inc., dated March 8, 2010, is included as Appendix B. Recommendations of the report included: weekly visual monitoring of the pier; immediate placement and monthly monitoring of survey points on the pier; subsurface investigation to determine nature of pier footing; coordination with drainage system repair to move the mouth of the channel further upstream of the pier; and the addition of rip rap revetment or other stabilization . measures on the banks at the north and east sides of the pier from the mudline to the top of the bank. The DCR [formerly Department of Environmental Management (DEM)] requested its consultant to perform a structural investigation of the Northampton Bikeway Bridge (Norwottuck Rail Trail bridge). A bridge report was prepared by BETA Engineering, Inc., titled "Connecticut River Greenway State Park, Massachusetts, Northampton Bikeway Bridge over the Connecticut River, Structural Evaluation", dated December, 1999, is included as Appendix C. The report indicates that erosion of the bank, adjacent to the bridge pier had been an issue in the area since December 1999. Recommendations of the report included stabilization of the bank adjacent to the pier with rip rap and /or a steel sheeting bulkhead to prevent further erosion. A subsurface investigation was performed at pier 9 of the Rail Trail Bridge, by GEI Consultants, Inc. for Simpson Gumpertz & Heger, Inc., DCR's consultant. The report, titled "Subsurface Exploration and Foundation Evaluation, Pier P9, Norwottuck Rail Trail Bridge, Over the Connecticut River ", dated May 2010, is included as Appendix D. The investigation was performed to determine subsurface conditions and evaluate the existing foundation of Pier 9. It was determined that the pier foundation consisted of a stepped stone foundation, underlain by wood piles or cribbing. Recommendations of the report include performing a scour analysis at the pier and provide design recommendations to stop erosion at this location. 1 I LJ In also our geotechnical consultant's opinion that since it appears that the former drainage structures failed due to age, - deteriorated condition, - and lack of . free _. draining backfill in the original design, it is considered possible to re- construct the existing structures in like kind, provided the replacement structures are engineered to current design standards. 8 Existing Conditions r r J Introduction The primary goal of any drainage system improvement alternative is stop erosion of the existing Water Street embankment and the bank of the Connecticut River downstream of the Water Street culvert, . and to reconstruct the drainage system in this area in a manner that provides long -term stability and ease of maintenance. An improvement to the existing hydraulic design is essential to prevent further erosion. Methods to reduce erosive velocities of concentrated runoff include plunge pools and drop manholes. Since any repair solution will require some degree of maintenance, access to the area by City of Northampton DPW staff is required. Due to the site's proximity to a popular outdoor family destination (the Norwottuck Rail Trail), safety and. security" of the site is essential. Overall aesthetics are also considered an important factor in selection of an alternative. An additional goal of this project is to assist MassDOT and DCR in establishing a plan of action for resolving the related erosion problems that are potentially destabilizing the adjacent Norwottuck Rail Trail bridge pier (Pier 9). Both rigid and flexible bank stabilization techniques have been explored for the drainage system improvement alternatives. One option considered is removing the headwalls and culvert under Water Street and opening the channel. Water Street is an abandoned City right of way. During a site visit in the Fall of 2009, DPW staff from the city of Northampton agreed that opening the channel was desirable. Construction activities will greatly change the aesthetics of the area, therefore final restoration will include a landscaping plan consisting of native vegetation such as grasses, groundcover and /or shrubs. All Alternatives include the extension of the existing Damon Road culvert to accommodate roadway widening and sidewalk construction proposed in the MassDOT Damon Road Transportation Improvement Project (MassDOT project No. 180525) Alternatives Analysis Alternatives Analysis Design Assumptions It is assumed that the existing culvert and trunk line sizes are adequate to convey existing flows; therefore, a full watershed analysis has not been performed as part of . this feasibility report. Design Criteria Goals Bank Stabilization The Norwottuck Rail Trail Bridge is owned and operated by the DCR. It is assumed that the DCR and its consultants are investigating repair alternatives in the vicinity of the bank erosion at the bridge pier. Final design of the Damon Road drainage repairs and bank stabilization must be closely coordinated with bridge pier bank stabilization. The proposed drainage improvements will be designed in accordance with the United States Department of Agriculture (USDA), Natural Resources Conservation Service, Engineering Field Handbook, December 1996; AASHTO Highway Drainage Guidelines, 1999; MA Department of Environmental Protection Stormwater Management Standards, 2008; Massachusetts Department of Transportation (MassDOT) Project Development and Design Guide, 2006. The major goals of this project are: > Bank Stabilization > Improved Hydraulics > Improved Stormwater Management > Safety > Maintenance > Aesthetics More information on each of these design goals are provided in the following sections. Among the repair alternatives deemed feasible, construction costs have been compared to determine the most cost - effective repair alternative. The primary goal of this project is to stabilize the river bank. Information on options for bank stabilization is provided in the USDA's Engineering Field Handbook. The options include stone or concrete revetment to the top of "stream forming flow" elevations and vegetative plantings below and above this elevation. 0 Alternatives Analysis r r Improved Hydraulics Compliance with. Wetlands Protection Act/ Stormwater Management Standards The proposed drainage improvement project is within wetland resources under the jurisdiction of the Massachusetts Wetland Protection Act. As such the project requires review by the Northampton Conservation Commission. MassDOT must demonstrate to the Commission that the alternative selected limits impact to wetland resources to the greatest extent practicable, provides appropriate compensation for affected wetland resources and comply with the DEP Stormwater Management Standards. Safety After consideration of site conditions, including soil types, extent of erosion and the steepness and condition of the existing ditch, VHB is proposing Vegetated Geogrids for the purpose of bank stabilization. This method of bank stabilization utilizes stone for the lower portion of the bank at up to a 1.5h:1v slope. Above this course, compacted soil wrapped in a geotextile fabric (Geogrids) is installed. This course may be at 2h:1v. slope. The Geogrids are interspersed with live cuttings, extending into the existing bank face. Above this middle course, the grade is sloped at 3h:lv or flatter, loamed and seeded and planted with native vegetation. The design of the existing drainage system is hydraulically inefficient. The existing 48 -inch drainage trunk line makes two very sharp bends within the system. The hydraulics could be improved by removing these two bends and straightening the trunk line. It is assumed that the industrial park drainage trunk line was designed to flow full during the design storm. These flows would be quite substantial and require some type of energy dissipation. This is achieved by a plunge pool at the outlet, or a drop manhole prior to outletting. With the abandonment of Water Street, the culvert beneath Water Street has become obsolete. The existing culvert shows . evidence of major siltation and is an obstruction to wildlife. The removal of the Water Street culvert and embankment would provide some degree of improvement to wildlife habitat. This change has been incorporated in Alternative 2 and 3. The proposed location of the project, adjacent to a Norwottuck Rail Trail and the trail parking area, requires that safety and security measures for the site be analyzed and incorporated into the project design. Access . to the project area during and after construction should be closed to the general public. The installation of fencing, to discourage access by the public, may help in maintaining safety in the area. Outlet pipes of 48inch may require safety bars to prevent unauthorized access. 11 Alternatives Analysis ■ Maintenance Aesthetics Alternatives Alternative 1 The existing system may have. benefitted from additional inspection and maintenance. In order for any drainage improvements to function properly over their expected lifecycle, adequate maintenance must be performed. Each alternative includes a stabilized surface to provide access to the drainage system components for City maintenance equipment. Access gates within the proposed fencing are proposed. Due to the project's location adjacent to the popular Norwottuck Rail Trail and on the bank of the Connecticut River, aesthetics are considered an important factor in the design of the drainage improvements. Natural materials, such as stone and vegetation, are incorporated wherever possible and appropriate. Vegetation would be native species such as grasses, groundcover and /or shrubs. Also, concrete liners, designed to provide an aesthetic appeal to concrete retaining walls could be incorporated. A landscaping plan will be developed to revegetate areas disturbed by project. The alternatives evaluated in this report are as follows:. > Alternative 1 (Figure 3): Remove Water St. embankment and culvert; provide outlet control for industrial park drainage, outlet toward ditch. > Alternative 2 (Figure .4): Remove Water St. embankment and culvert; provide drop manhole for industrial park drainage, outlet toward Connecticut River. > Alternative 3 (Figure 5): Replace Water St. culvert; straighten and extend industrial park drainage trunk line; provide single combined outlet structure. Depending on the alternative chosen, materials proposed in this report may be substituted with alternative materials, such as stone gabions in place of riprap. The following is a general discussion and comparison of the alternatives in terms of staging and aesthetics. A cost comparison for each alternative is included in the discussion of each alternative. Alternative 1 (Figure 3) generally involves the removal of the existing drainage system components (headwalls and manhole) under Water Street and reconstructing this area as an open charnel from Damon Road to the Connecticut River. The trunk line from the industrial park would be reconstructed and straightened (removal of the 90- degree bend within the manhole). This trunk line would discharge to a plunge 12 Alternatives Analysis r Alternative 2 pool with an overflow weir directing flow towards the open channel. Figure 3 shows specific elements of Alternative 1 including: 1. Extend Damon Road 42 -inch RCP culvert in preparation for. Damon Road widening 2. Install downstream headwall for 42 -inch Damon Road culvert 3. Remove existing 48" RCP culvert under Water Street embankment 4. Open drainage ditch through Water Street embankment 5. Create natural stream bed 6. Install slope protection at 1.5h:lv up to approximate elevation 115 7. Grade slope 2h:lv or flatter to meet existing 8. Straighten industrial park 48 -inch drainage trunk line 9. Outlet industrial park trunk line into rip rap plunge pool with overflow weir to ditch 10. Install stabilized surface to allow access for maintenance of plunge pool 11. Install safety fencing and gate along bike path 12. Install landscaping. These elements are identified by number on Figure 3. Similar to Alternative 1, Alternative 2 (Figure 4) involves the removal of existing drainage system components (headwalls and manhole) under Water Street and reconstructing this area as an open channel from Damon Road to the Connecticut River. The trunk line from the industrial park would be designed differently than Alternative 1. The existing manhole would be replaced with a deeper drop manhole to allow stormwater to exit the manhole at close to the same elevation as the Connecticut River. This alternative does not require a plunge pool to reduce stormwater velocity. Stormwater exits the manhole through a trunk line to an armored ditch prior to discharging to the Connecticut River. Figure 4 shows specific elements of Alternative 2 including: 1. Extend Damon Road 42 -inch RCP culvert in preparation for Damon Road widening 2. Install downstream headwall for 42 -inch Damon Road culvert 3. Remove existing 48 -inch RCP culvert under Water Street embankment 4. Open drainage ditch through Water Street embankment 5. Create natural stream bed 6. Install slope protection at 1.5h:1v up to approximate elevation 115 7. Grade slope 2h:lv or flatter to meet existing 8. Replace existing industrial park drain manhole with new drop manhole 9. Straighten industrial park 48 -inch drainage trunk line 10. Outlet industrial park trunk line through bank toward Connecticut River 11. Install stabilized surface for maintenance access to drop manhole 12. Install safety fencing and gate along bike path 13. Install landscaping. 13 Alternatives - Analysis f Alternative 3 These elements are identified by number on Figure 4. These elements are identified by number on Figure 5. 14 Alternatives Analysis Alternative 3 (Figure 5) represents the reconstruction of the Water Street culvert and. embankment. The downstream and upstream headwalls at Water Street and a new culvert would be constructed. The industrial park trunk line manhole would be replaced with a deeper drop manhole. An extension of the existing trunk line would convey the stormwater to a combined - outlet headwall. Figure 5 shows specific elements of Alternative 3 including: 1. Extend Damon Road 42 -inch RCP culvert in preparation for Damon widening 2. Install downstream headwall for 42 -inch Damon Road culvert 3. Replace existing upstream headwall at Water Street culvert 4. Replace existing. 48 -inch RCP culvert under Water Street embankment 5. Replace existing industrial park drain manhole with new drop manhole 6. Straighten and extend industrial park 48 -inch drainage trunk line 7. Replace existing downstream headwall with combined outlet headwall 8. Install slope protection at 1.5h:1v up to approximate elevation 115 9. Install maintenance drive to headwalls 10. Install safety fencing and gate along bike path 11: Install landscaping. Road Improvement Description Advantages Disadvantages • Provides Bank Stabilization Improves Hydraulics Improves Safety Maintenance Costs Improves Aesthetics Construction Costs Alternatives Do Nothing Allow existing drainage to continue to erode bank • No Cost • • Unsafe, poor hydraulics, Continued negative impact to bridge pier X X X X X None Alternative 1 Extend Damon Road Culvert, Remove Water • • Stops slope erosion Improved hydraulics • Large rock plunge pool not aesthetically pleasing Street Embankment and Stabilize Banks, Realign Industrial Park. Trunk Line, Stone Plunge Pool • • Improved safety Improved wildlife habitat along open channel Plunge pool provides pretreatment of stormwater • Greater maintenance costs than Alternative 2 Moderate Alternative 2 Extend Damon Road • Stops slope erosion • Slightly higher costs than Culvert, Remove Water • Improves hydraulics Alternatives 1 & 3 Street Embankment and • Improves safety • Stabilize Banks, Realign Industrial Park Trunk Line, Drop Manhole • • Greater landscaping opportunities Improved wildlife habitat along open channel 4 J+ 4 J+ . Al+ Moderate • Drop Manhole reduces stormwater velocities • Lower maintenance costs than Alternatives 1 & 3 Alternative 3 Extend Damon Road Culvert, Rebuild Water Street Culvert and • • • Stops slope erosion Improves hydraulics Improves safety • Fewer wildlife habitat improvements (no open channel) Headwalls, Realign • No pretreatment of stormwater Industrial Park Trunk Line • Greater construction costs associated with large headwalls Moderate • Greater maintenance costs than Alternatives 1 & 2 Project Decision Matrix J+ = Major Positive Impact/Yes = Positive Impact/Yes 15 Alternatives Analysis = No Impact /Maybe X = Negative Impact/No //PAW /, •. • Tiara C{;ntro/ \ p. 1 ti — Cabe 7e1 y kC an Ccnc: 1,Y 5.0 ``r' �` \ ' I� % ' 9P eyo '....,'''::"V:")"..; . //� _ \ N Poe lath Pea. Push Buttai and Signal 140 135- 130- 125- 120- 115- 110- 105- 100- I;T7 -397 \� O NUMBERS CORRESPOND TO ALTERNATIVE ELEMENTS LISTED IN SECTION 4 ALTERNATIVE 1 PROPOSED LOAM, SEED AND LANDSCAPING PROPOSED STONE SLOPE PROTECTION PROPOSED DRAINAGE DITCH BOTTOM PROPOSED MAINTENANCE DRIVE ter,, pe op ? �e C `SS � A 4/ E: \ 10829.08 \rep orts \Rgure —Color— Aits.dwg ��� • Troffic Centre/ �\ Gobbet \ �cf a; Conc. P.F.Ci f 33:0 ` @ \ G; °a va. / "'-`2' 4 \/ 4i ••.1 . // ACufm� O NUMBERS CORRESPOND TO ALTERNATIVE ELEMENTS LISTED IN SECTION 4 ALTERNATIVE 2 PROPOSED LOAM, SEED AND LANDSCAPING PROPOSED STONE SLOPE PROTECTION PROPOSED DRAINAGE DITCH BOTTOM E: \ 10829.08 \reporte \Rgure — Color— Alte.dwg f / d oss UP` ,3 NFIT / �.., Rol& Centro/ `\ --Gobbet oa Conc l.eut Pale RV/ Pea. Pvch Rattan and goo/ PROPOSED LOAM, SEED AND LANDSCAPING PROPOSED STONE SLOPE PROTECTION PROPOSED MAINTENANCE DRIVE E: \10829.08 \reports \Figure —Col or —AI ts. dwg P rI r.. ri 1 FT GEOGRIDS 4 125 3 FT /NATIVE PLANTINGS LOAM AND SEED 115 112 1.5 FT 109 1 FT 0 107 LOAM AND SEED GRAVEL FILTER FABRIC TYPICAL SECTION 104 +50 STREAMBANK STABILIZATION NOT TO SCALE 4 SCALE IN FEET TYPICAL OPEN CHANNEL SECTION PLANTING NOTES FOR STREAMBANK STABILIZATION: LOWER SLOPE — ELEVATIONS FROM 100.0 TO 112.0 THE LOWER EMBANKMENT WILL BE STABIUZED WITH RIPRAP FROM THE LOW FLOW ELEVATION TO 3 FEET ABOVE BANKFULL ELEVATION. DOGWOOD AND WILLOW LIVE STAKES SHALL BE A MINIMUM OF 5 FEET IN LENGTH AND PROTRUDE FROM THE RIPRAP A MINIMUM OF 6 INCHES. MIDDLE SLOPE — ELEVATIONS FROM 112.0 TO 115.0 THE MIDDLE EMBANKMENT SHALL BE STABILIZED WITH VEGETATED GEOGRIDS (SOIL LIFTS WRAPPED WITH GEOTEXTILE FABRIC) WITH A BRUSH LAYER PLANTED BELOW THE LOWER LIFT. GEOGRIDS SHALL CONSIST OF APPROXIMATELY ONE FOOT OF COMPACTED TOPSOIL PLACED ON A GEOTEXTILE. THE GEOTEXTILE SHALL BE WRAPPED OVER THE COMPACTED SOIL A BRUSH LAYER SHALL BE CONSTRUCTED, COMBINING A 6 INCH BED OF LOAM BORROW WITH AN EQUAL MIX OF 4 FOOT, 5 FOOT AND 6 FOOT DOGWOOD, WILLOW AND SPECKLED ALDER BARE ROOT STOCK. ROOTED ENDS SHALL TOUCH THE BACK OF THE EXCAVATED SLOPE. AND BRANCH TIPS WILL PROTRUDE APPROXIMATELY 6 INCHES OR LESS PERPENDICULAR TO STREAM FLOW. UPPER SLOPE — ELEVATIONS ABOVE 115.0 THE UPPER EMBANKMENT SHALL BE GRADED TO A SLOPE OF 3:1 WITH. APPROXIMATELY 6 INCHES OF LOAM BORROW. LOAM BORROW SHALL BE COVERED WITH EROSION CONTROL FABRIC —JUTE AND SEEDED. THE LOWER EDGE OF EROSION CONTROL FABRIC —JUTE SHALL BE ANCHORED TO THE UPPERMOST LAYER OF GEOTEXTILE FROM THE MIDDLE SLOPE. SHRUBS AND SAPLINGS SHALL BE PLANTED THROUGH THE EROSION CONTROL MAT. SHRUBS AND TREES SHALL BE MULCHED WITH HAY MULCH. 100 YEAR FLOOD ELEV = 125.00 TOP OF SLOPE ELEV = 115.00 BANK FULL ELEV = 109.00 MEAN LOW WATER ELEV = 100.00 PROP EROSION CONTROL FABRIC -JUTE BURLAP GEOTEXTILE FABRIC ORDINARY BORROW FIGURE 6 E: 10829.08 \reports \Rgure— Sectlon.dwg